Professional Documents
Culture Documents
ABSTRACT: During the construction of Cairo Metro Line 3 Phase 2, ground investigations
highlighted the presence of unexpected swelling clay at the tunnel elevation around Cairo Fair
station. In order to control this event, investigations were ordered so as to understand why an initially
stable clay layer could swell in such large proportions in case of excavation below the water table.
Considering the very high potential swelling behavior and the associated time dependent effect on
the next 100 years, a specific design was then developed and implemented on site. On the Cut &
Cover station, a fuse layer (up to 60 cm thick) made with a specific polystyrene material was
installed below the raft level. On the bored tunnel section, several sections were investigated and
iterative calculations were then performed so as to estimate the clay strain amount in the influenced
swelling clay layer. The conclusion was that the swelling effect had no impact on the tunnel lining
design.
1 INTRODUCTION behavior of the considered clay layer. The
design of the fuse layer below raft level of the
When the Egyptian-French Joint Venture, with station will then be described in detail. Finally,
VINCI Construction Grands Projets as leader, tunnel behavior in the presence of swelling clay
was awarded the Phase 2 of the Cairo Metro will be presented.
Line 3 in June 2009, the knowledge of the
anticipated ground conditions was not
sufficiently detailed. 2 CAIRO METRO LINE PHASE 2
Ground investigations performed for the
purpose of the bid around Cairo Fair station
highlighted clay layers just below the raft, but 2.1 Project location
swelling behavior was not suspected. Ground In contrast to most completed tunnels projects in
investigations for the detailed design later Cairo, Cairo Metro Line 3 Phase 2 is not located
showed that this clay layer had a very high in the lower Nile valley, but on East Cairo's hills
swelling behavior. (see figure 1) where no major tunneling projects
As a consequence, dedicated soil have ever been completed prior, to the
investigations were decided and executed. A execution of Phase 2.
specific study followed with the aim of
managing the problems caused by this swelling Phase 2 project consists in:
behavior of the soil below the raft of Cairo Fair - Building five 150 meters long Cut & Cover
station. On the TBM tunnel section, detailed stations with diaphragm wall technology,
investigations and calculations showed that the - Boring an 8.35 meters inner diameter tunnel
swelling behavior was not affecting the segment with one slurry TBM and one EPB TBM
reinforcement design. over a length of about 7.1 km,
After a brief description of the Cairo Metro - Excavating seven circular Evacuation Shafts
line 3 Phase 2, this paper details the swelling located between stations.
1
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
2
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
3
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
with what is usually used on settlement design. 4 SWELLING BEHAVIOR BELOW THE
Note also that load effect is taken into account STATION
in the formula so as to follow as much as
possible the reality measured in the tests.
Finally, it is worth highlighting that the 4.1 Swelling generation
proposed formula deals with thin samples, As previously stated, there is a swelling clay
where the delay effect related to the water layer below the raft base that is below the water
diffusion is quite limited. table on Cairo Fair station. Constructing the
station requires excavation down to this clay
3.5 Swelling rate speed estimation layer, creating a sudden decrease of the total
vertical stress of the clay.
As it is usually done in cases of settlement Contrary to settlement issues on the soft clay
design, it is then necessary to estimate a layer, the excavation will induce (via this
swelling rate speed. As defined in ASTM 4546, unloading) a sudden decrease of the pore water
this means that a boundary (called t100) between pressure. At the same time, the vertical effective
primary swell and secondary swell needs to be stress will slowly reduce so as to reach an
estimated based on the loading stages of the equilibrium state. Figure 6 below presents the
performed tests (see figure 5). typical evolution of stress of this clay layer with
respect to time:
800 kPa
400 kPa
200 kPa
100 kPa
t50
50 kPa
t100
change in this clay layer after the excavation. It durability and behavior have already been
will then induce some swelling into this clay checked and tested,
layer, which needs to be controlled and - It is a controlled material,
managed over the years. - It is a material which perfectly suits
requirements because it is an elastic quasi
perfect plastic material with the typical
4.2 Mitigation proposal strategy stress-strain curve presented in figure 7:
In order to mitigate the anticipated swelling
effects on the raft design for the next 100 years
(station lifetime), several strategies were
successively considered:
- Designing a raft able to support the full
swelling pressure. This would mean that the
raft should be able to support a 900 kPa load,
which is too large. Because of the
consequences on the raft design, this solution
was disregarded.
- Allow a free swelling of the clay without
any stresses below the raft. This means that
the raft should be designed as a slab resting Figure 7: typical polystyrene behavior
on the diaphragm walls. However, because
the swelling increases when the vertical For typical polystyrene material, εmax is
effective stress decreases, calculations have usually more than 50% while σel and σmax
shown that this solution would have required usually depend on polystyrene density. After
too much void thickness (that is to say over- having performed a series of laboratory tests on
excavation) between the base of the raft and polystyrene samples (see figure 8), a
the top of the clay. Consequently, such a polystyrene with 24-25 kg/m3 density was
solution was also disregarded. selected as most suitable.
- Allowing a maximum and controlled
effective stress of the clay layer, so as to
reduce the swelling effect as much as
possible while keeping the upward stress
below the raft at reasonable levels. Finally,
this solution was developed.
6
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
When using this consolidation formula, it is Finally, the following swelling curve
then possible to estimate the thickness of the presented in figure 10 has been obtained, with
ground influenced by swelling with respect to the main swelling results:
time, and consequently the swelling value for a - 5 cm after 5 years
considered time t and a total clay height equal to - 8 cm after 10 years
H: - 14 cm after 10 years
t - 28 cm after 100 years
swelling value delta h j t j ,
j 0
4.6 Polystyrene fuse thickness estimation
4.5 Swelling estimation below the raft Based on sensitivity analysis made on clay
thickness, swelling speed and effective stress, it
Calculations were made considering a 6 meter was finally decided to install a 60 cm thick
thick clay layer with an average effective stress polystyrene layer below the station raft. Figure
within the clay below the raft equal to 50 kPa as 9 shows the placing of the polystyrene layer
given by the polystyrene layer. This value was before the pouring of the raft lean concrete.
resulted of mechanical characteristics of the
selected 24-25 kg/m3 polystyrene:
- Elastic stress σel of the polystyrene is
superior to the raft concrete dead load and
the on-site water pressure plus some safety
factor. Indeed, we do not want any
polystyrene crush because of concrete load or
water pressure.
- εmax>50% is considered for fuse purpose,
- A maximum allowable stress equal 200 kPa,
based on engineering judgment.
0.25
0.20
Swelling value (meters)
0.15
0.10
0.05
0.00
0 10 20 30 40 50 60 70 80 90 100
Time (years)
As stated by Serratrice & Soyez in 1996, Figure 11: FEM analysis so to define sensitive
swelling phenomena in clay material is usually swelling zone
initiated by water pressure changes during or
after the works: Obviously, it was possible to show that the
- It can be generated by negative pore pressure most sensitive zone to total stress change
generation during the works in relation with corresponds to a clay layer located in the lower
deep excavation. Such should occur around a part of the tunnel. Indeed, whatever the
tunnel if the total stress change is in practice considered thickness in the lower part of the
superior to the initial water pressure (see tunnel, models show that mean total stress is
figure 6). reduced by more than 70 kPa on the first 2.6
- It can be generated by water pressure meters below the bottom of the tunnel. Such a
changes in line with hydraulic boundary 70 kPa in fact falls within a typical range of
conditions related to the associated works. water head at the tunnel axis in the vicinity of
Cairo Fair station.
A detailed analysis of the mean total stress
5.2 Critical swelling zone around a tunnel change results then allowed defining the area
In a first stage, a sensitivity analysis was prone to potential swelling behavior, as shown
performed in order to estimate the location of in figure 12.
the most critical zone regarding total stress
change for a clay layer. A FEM analysis was
performed, considering a typical tunnel section
where clay layer thickness and location around
the tunnel is changed depending on the
investigated case (see figure 11).
8
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
6 CONCLUSION REFERENCES
On Cairo Metro Line 3 Phase 2, although a ASTM D 4546-03: Standard Test Methods for One-
swelling clay layer as shown on figure 15 was Dimensional Swell or Settlement Potential of
Cohesive Soils
not expected along the project alignment; Serratrice, J.F and Soyez, B. 1996. Les essais de
detailed investigations highlighted its presence, gonflement in Bulletin des laboratoires des Ponts
with potential risks for the structures to be &Chaussées
constructed. Dedicated tests were then
implemented, which showed that either the
swelling pressure could be up to 900 kPa or free
swelling could be up to 200%.
ACKNOWLEDGEMENTS