Professional Documents
Culture Documents
https://www.issmge.org/publications/online-library
C.C. Kao
Department of Rapid Transit Systems, Taipei City Government, Taipei, Taiwan
ABSTRACT: In this paper, the heaving of an airport runway in Taipei due to shield tunneling for the construction of Taipei
Rapid Transit Systems (TRTS) was reported. The runway heaving incident, its emergency treatment, and the causes of this
incident were introduced. It was found that, the mud injection pressure at the face, and backfill grouting pressure were
significantly greater than the limiting values assumed for construction. The material ejected to the ground surface was found to be the
same as the mud injected at the face. The excess fluid pressure in the ground caused an upward flow, and an upward thrust on the
runway pavement, causing the runway heaving.
RÉSUMÉ : Dans cet article, on a signalé le soulèvement d'une piste d'aéroport à Taipei en raison de la construction de tunnels
bouclier pour la construction des systèmes de transport rapide de Taipei (TRTS). L'incident du soulèvement de la piste, son traitement
d'urgence et la cause de cet incident ont été introduits. On a constaté que la pression d'injection de la boue au niveau du visage,
la pression d'injection du remblai et la pression d'injection secondaire étaient significativement supérieures aux valeurs limites prises
pour la construction. On a trouvé que le matériau éjecté à la surface du terrain était le même que la boue injectée au niveau du visage.
L'excès de pression de fluide dans le terrain a provoqué un écoulement vers le haut, et une poussée vers le haut sur les couches de sol
au-dessus et du soulèvement de la piste.
KEYWORDS: backfill grouting, face pressure, heave, mud injection, runway, shield, tunnel.
- 1683 -
Proceedings of the 19th International Conference on Soil Mechanics and Geotechnical Engineering, Seoul 2017
2 .4 Backfill grouting
For the excavation of down-track tunnel, the outside diameter
of the shield was 6.15 m, and the outside diameter of lining
segments was 6.0 m. When the lining ring left the protection of
the steel shield, a 75 mm-thick tail void was generated between
the segment and excavated ground. Backfill grouting was
conducted to fill the tail void. For straight-line tunneling, the
controlled backfill injection rate was 150%, and the grouting
pressure range applied was 100 ~ 200 kPa higher than the
ground water pressure. Backfill grout was injected through the
grouting holes on the lining segments.
2 .5 Secondary grouting
Figure 2. Geological profile and tunnel location. For tunneling under the airport, the extra protection measure of
secondary grouting was taken to fill the ground loss and reduce
2.1.1 Surface fill ground stettlement. Two layers of chemical-grout injection,
The brown silty clay was about 2.0~2.9 m-thick, with a water each 0.5 m-thick, formed a 1.0 m-thick fan grout zone above
content of 36.5%, and SPT-N values of about 5. the tunnel.
- 1684 -
Technical Committee 204 & Joint Technical Committee 2 / Comité technique 204 & Comité technique conjoint 2
Based on equations (2) and (3), the limiting values of face 4 HEAVING OF RUNWAY
pressure ranged from 244 to 379 kN/m2.
The Civil Aeronatics Administration of Taiwan required, the 4 .1 The incident
warning and action values of surface settlement due to
tunneling in the airport was 20 and 25 mm, respectively. To On January 9th of 2004, the down-track shield tunnel was
reduce the amount of ground settlement due to construction, Ko driving under the Taipei Songshan Airport. When surface
coefficirnt in equation (1) was increased to 0.8. The lower and settlement measurement was carried out on the shutdown
upper bound of face pressure was increased to 318 and 486 runway at 02:00 a.m., a 1.5 m x 3.8 m heaving area above ring
kN/m2, respectively. 316 was observed with a maximum heave of 65 mm, as shown
in Figure 3 and 4. Mud materials injected at the face seeped out
3 .2 Mud injection pressure management under the pavement at the nearby edge of the runway. When
heaving was observed, the shield machine had excavated about
To maintain the plastic flow of soils in the earth chamber, mud 10 m into the runway zone. Shield tunneling operation was
was injected to the face through three injection holes on the stopped right after the heaving occurred.
cutter disc. The actual amount of mud injected ranged from 5 to
14% of the volume of excavated ground. The measured 4 .2 Emergency treatments
injection pressure varied from 491 to 589 kN/m2, which was
much higher than facce pressure. For ring 281, located at the The heaving area was located on the main runway of the airport.
depth of 28.3 m, assuming t = 17.7 kN/m3 and Ko = 0.6, the If any accident happened on the runway during landing on take
earth pressure at-rest po acting at the center of the cutter disc off of an aircraft, the results would be unbearable . The airport
would be 300 kN/m2. The measured mud injection pressure △p must reopen in the early morning and emergency treatments
almost doubled the po value. The high mud injection pressure were necessary. After evaluation and discussion by the DORTS
behaved like high grouting pressure, which could cause and the contractor, the 10 m x10 m x 120 mm-thick asphalt
hydraulic fracture in the cohesive soil layer. concrete (AC) pavement was removed as shown in Figure 3.
During the scraping of AC, seeping of face mud was observed.
3 .3 Backfill grouting pressure management Then new asphalt concrete was backfilled and compacted with a
drum compactor as shown in Figure 5. The airport reopen in the
For design, the backfill grouting rate of 150% was suggested. morning on time.
The backfill grouting pressure was recommended to be the
hydrostatic pressure of 196 to 284 kN/m2, plus the extra
pressure of 98 to 196 kN/m2 as management values. The
specification of the Department of Rapid Transit Systems
(DORTS) of Taipei suggested that, the maximum backfill
grouting pressure should not exceed 353 kN/m2.
However, since the overburden was quite thick, following the
DORTS specification, the amount of backfill injected would be
limited, and excessive ground settlement became possible. For
Lot CB420, 300 mm-thick lining segments and significant
amount of reinforcement steel were used. Without damaging the
lining segments, and to reduce the amount of ground settlement,
the measured backfill grouting ranged from 383 to 579 kN/m2.
The recorded grouting rate varied from 120 to 160%.
- 1685 -
Proceedings of the 19th International Conference on Soil Mechanics and Geotechnical Engineering, Seoul 2017
- 1686 -