You are on page 1of 1

3.20 3.00 3.15 3.00 3.00 3.00 3.15 3.00 3.

20

GB1 GB1 GB1 GB1 GB1 GB1 GB1 GB1 GB1


C1 C1 C1 C1 C1 C1 C1 C1 2.30

F-1 F-1 F-1 F-1 F-1 F-1 F-1 F-1 F-2


C2

2.45
GB1 GB1 GB1 GB1 GB1 GB1 GB1 GB1 GB1

GB1 GB1 GB1 GB1 GB1 GB1 GB1 GB1 GB1


F-SAH

1.65
150 MM thk. CONCRETE SLAB
ON GRADE w/ 12mm RSB

CONSTRUCTION AND SUPPLY


SPACED @ 0.20m O.C.
C1 150 MM thk. CONCRETE SLAB
ON GRADE w/ 12mm RSB C1

3.60
SPACED @ 0.20m O.C.

F-1 F-1
C2

7.30

2.40
GB1 GB1 GB1 GB1 GB1 GB1 GB1 GB1 GB1 F-2

1.65
GB1
GB1 GB1 GB1 GB1 GB1 GB1 GB1 GB1
C1
C1 C1 C1 C1 C1 C1 C1 C1 C2
F-1 F-2
F-1 F-1 F-1 F-1 F-1 F-1 F-1 F-1
GB1 GB1 GB1 GB1 GB1 GB1 GB1 GB1

2.45
2.45
GB1 2.60

GB1 GB1 GB1 GB1 GB1 GB1 GB1 GB1


C1 C1
GENERAL CONSTRUCTION NOTES
F-1 F-1
1.0 STANDARDS AND REFERENCES
THE FOLLOWING SHALL GOVERN THE DESIGN FABRICATION AND CONSTRUCTION OF 3.00 3.00 3.15 3.00 3.20
THE PROJECT. 1.1 NATIONAL STRUCTURAL CODE OF THE PHILIPPINES (N.S.C.P 2015) VOL. 1, SEVENTH EDITION. 3.20 3.00 3.15 3.00
2.0 DESIGN CRITERIA
2.1 LOADINGS
A. DEAD LOAD
CONCRETE 23.56kN/m³
STEEL 76.97kN/m³
150mm THK. CHB WALL 2.73 kPa
100mm THK. CHB WALL 2.11 kPa
B. LIVE LOAD

C.
FLOOR AREA

WIND LOAD
BUILDING CATEGORY = 4 ( NON ESSENTIAL FACILITIES )
EXPOSURE = D (FLAT, UNOBSTRUCTED AREAS AND WATER SURFACES)
1.90 KPA
NOTES ON CONCRETE MIXES & PLACING
1. ALL CONCRETE SHALL DEVELOP A MIN. COMPRSSIVE STRENGTH AT THE END OF TWENTY EIGHT (28) DAYS
W/ CORRESPONDING MAXIMUM SIZE AGGREGATE & SLUMP AS FOLLOWS
SWIMMING POOL
MAXIMUM WIND VELOCITY, V = 250 KPH
MAX. SIZE OF
P = qh [(GCpf) - (GCpi)] ( DESIGN WIND PRESSURE) LOCATION 28 DAYS STRENGTH AGGREGATE MAX SLUMP

AMAIA STEPS
D. SEISMIC LOAD
WHERE: qh = VELOCITY PRESSURE (kPa)

V=Cvl
RT W
GCpf = EXTERNAL PRESSURE COEFFICIENT
GCpf = INTERNAL PRESSURE COEFFICIENT

V=2.50Cal
RT W
(DESIGN BASE SHEAR)
V=0.11 CalW
V=0.80ZNVLW (ZONE 4)
ALL OTHERS, INCLUDING
SUSPENDED SLABS
COLUMNS
BEAMS, SLABS
SLAB ON FILL

2. MAINTAIN MINIMUM CONCRETE COVER FOR REINFORCING STEEL AS FOLLOWS.


SUSPENDED SLABS
3000 PSI (21 MPa)

3000 PSI (21 MPa)


3000 PSI (21 MPa)
2500 PSI (17.5 MPa)
20mm

20mm
20mm
20mm
100mm

100mm
100mm
100mm

20mm
1 FOUNDATION PLAN JUNCTION
S 1
R

SCALE
SLAB ON GRADE 40mm
WHERE: W = TOTAL DEAD LOAD
T = NATURAL PERIOD = Ct (h)
WHERE: C = NUMERICAL COEFFICIENT
WALLS ABOVE THE GRADE
BEAM STIRRUPS AND COLUMN TIES
25mm 1:80 MTS
h = BUILDING HEIGHT WHERE CONCRETE IS EXPOSED TO 40mm
I = IMPORTANCE FACTOR = 1.00 EARTH BUT POURED AGAINST FORMS
R = NUMERICAL FCACTOR = 8.50 WHERE CONCRETE IS DEPOSITED 50mm
SEISMIC COEFFICIENT Cv = 0.42 Nv DIRECTLY AGAINST EARTH 75mm
Ca = 0.64 Nv
NEAR SOURCE FACTOR (15km) Nv = 1.0 3. CONCRETE SHALL BE DEPOSITED IN ITS FINAL POSITION WITHOUT SEGREGATION. RE-HANDLING
Na = 1.0
OR PLACING SHALL BE DONE PREFERABLY WITH BUGGIES, BUCKETS OR WHEELBARROWS.
Z = SEISMIC ZONE = 0.40 (ZONE 4)
S = SOIL TYPE = D NO CHUTES WILL BE ALLOWED EXCEPT TO TRANSFER CONCRETE FROM HOPPERS TO BUGGIES,
WHEELBARROWS OR BUCKETS IN WHICH CASE THEY SHALL NOT EXCEED SIX (6) METERS
2.2 DESIGN STRESSES IN AGGREGATE LENGTH.
A. CONCRETE COMPRESSIVE STRENGTH @ 28 DAYS:
a. FOOTINGS, COLUMNS, BEAMS AND SLABS fc = 21MPa (3,000 psi) 4. NO DEPOSITING OF CONCRETE SHALL BE ALLOWED WITHOUT THE USE OF VIBRATORS UNLESS
AUTHORIZED IN WRITING BY THE DESIGNER AND ONLY FOR UNUSUAL CONDITIONS WHERE VIBRATIONS
b. SLAB ON FILL

B. REINFORCING STEEL BARS


fc = 17.5MPa (2,500 psi)
ARE EXTREMELY DIFFICULT TO ACCOMPLISH.
5. ALL ANCHOR BOLTS, DOWELS, AND OTHER INSERTS SHALL BE PROPERLY POSITIONED & SECURED
NOVALICHES QUEZON CITY

COLUMN SCHEDULE
a. FOR BARS 16mm AND GREATER (STRUCTURAL GRADE DEFORMED BAR) fy = 275 MPa (40,000 psi) IN PLACE PRIOR TO PLACING OF CONCRETE.
b. FOR BARS LESS THAN 16mm (STRUCTURAL GRADE DEFORMED BAR) fy = 275 MPa (40,000 psi)
6. ALL CONCRETE SHALL BE KEPT MOST FOR A MINIMUM OF SEVEN CONSECUTIVE DAYS IMMEDIATELY
C. STRUCTURAL STEEL ASTM-A36 AFTER POURING BY THE USE
FOR TRUSSES, BRACINGS & STRUTS fy = 248 MPa (36,000 psi) 7. STRIPPING OF FORMS AND SHORES:
FOUNDATION 24 HOURS
D. PURLINS
COLD FORMED LIGHT fy = 248 MPa (36,000 psi)
SUSPENDED SLAB EXCEPT WHEN
ADDITIONAL LOADS ARE IMPOSED
8 DAYS
TIE BAR 2 LEGS
E. MASONRY UNIT (CHB) WALLS 21 DAYS
BEAMS 14 DAYS

F.
NON-LOADING BEARING CHB WALLS

WELDS
fm' = 2.07MPa (300 psi)

E - 60XX ELECTRODE
COLUMNS 21 DAYS
8. THE CONTRACTOR OR PROJECT IN-CHARGE SHALL SUBMIT THE SCHEDULE OF POURING OF CONCRETE JOINTS
NAME SECTION NAME SECTION NAME
G. STRUCTURAL BOLTS ASTM A-307 a. Ft = 96.60 mPa (14,000 psi) TO THE STRUCTURAL ENGINEER AT LEAST (4) DAYS PRIOR TO THE POURING FOR APPROVAL.
b. Fv = 69.00 mPa (10,000 psi) 9. THE CONTRACTOR SHALL FURNISH AND MAINTAIN ADEQUATE FORMS AND SHORINGS UNTIL THE C-1 C-2 C-2

BEAM SCHEDULE
CONCRETE MEMBERS HAVE ATTAINED THEIR WORKING CONDITION AND STRENGTH.
3.0 IN THE INTERPRETATION OF THE DRAWING, INDICATED DIMENSIONS SHALL
10. THE CONTRACTOR OR PROJECT IN-CHARGE SHALL MAINTAIN CONCRETE POUR CARD
FOUNDATION FOUNDATION FFL
AMAIA LAND CORP.
GOVERN.DISTANCES AND SIZES SHALL NOT BE SCALED FOR CONSTRUCTIONS PURPOSES.
INSPECTION CHECKLIST, CONCRETE POUR MAP FOR EACH SCHEDULED POURING.
4.0 IN REFERENCES TO THE OTHER DRAWINGS, SEE ARCHITECTURAL DRAWINGS FOR
DEPRESSIONS IN FLOOR SLABS, OPENINGS IN THE WALLS AND SLABS, INTERIOR
PARTITIONS, LOCATIONS OF DRAINS ETC.
NOTES ON FOOTINGS: TO TO TO
1. FOOTINGS ARE DESIGNED FOR AN ALLOWANCE SOIL BEARING PRESSURE OF 150 KPa.
5.0 IN CASE OF DISCREPANCIES AS TO THE LAYOUT, DIMENSIONS, AND ELEVATIONS
BETWEEN THE STRUCTURAL PLANS AND ARCHITECTURAL DRAWINGS, THE CONTRACTOR
CONTRACTOR SHALL REPORT TO THE ENGINEER, IN WRITING, THE ACTUAL SOIL CONDITIONS
UNCOVERED AND CONFIRM ACTUAL BEARING CAPACITY OF SOIL BEFORE DEPOSITING CONCRETE.
FFL FFL ROOF BEAM
SHALL NOTIFY BOTH THE STRUCTURAL ENGINEER AND ARCHITECTS. 2. FOOTING SHALL REST AT LEAST 2000mm BELOW NATURAL GRADE LINE UNLESS OTHERWISE
INDICATED IN PLANS. NO FOOTING SHALL REST ON FILL.
6.0 ALL CONCRETE WORKS AND CONCRETE REINFORCEMENTS SHALL BE DONE IN 3. MINIMUM CONCRETE PROTECTION FOR REINFORCEMENT SHALL BE 75mm CLEAR FOR CONCRETE
ACCORDANCE WITH THE ACI.318 95 BUILDING CODE REQUIREMENT AND ALL
STRUCTURAL STEEL WORKS ACCORDING WITH THE AISC SPECIFICATION (9TH EDITION)
DEPOSITED THE GROUND AND 50mm FOR CONCRETE DEPOSITED AGAINST A FRAMEWORK.
4. IN CASES WHERE THE SOIL CONDITION IS SUCH THAT THE MINIMUM ALLOWABLE SOIL PRESSURE NAME AT SUPPORTS AT MIDSPAN
IN SO FAR AS THEY DO NOT CONFLICT WITH THE LOCAL BUILDING CODE OF 96KPa (2000 psi) CAN NOT BE ATTAINED AT A PRACTICAL DEPTHS THE USE OF MICROPILES,
REQUIREMENT. BORED PILES, OR DRIVEN PILES MAY BE ADOPTED IN LIEU OF STANDARD ISOLATED FOOTINGS.

7.0 ACI REFERS TO AMERICAN CONCRETE INSTITUTE, AISC REFERS TO AMERICAN


NOTES ON REINFORCEMENT:
GB1
INSTITUTE OF STEEL CONSTRUCTION AND ASTM REFERS TO AMERICAN SOCIETY FOR
TESTING MATERIALS.
(200 x 300 ) (150 x 250 ) (150 x 250 )
1. UNLESS OTHERWISE NOTED IN PLANS, THE YIELD STRENGTH OF REINFORCING BARS SHALL BE:
A. FOOTINGS, FOOTING BEAMS AND GIRDERS
8.0 CONSTRUCTION NOTES AND TYPICAL DETAILS APPLY TO ALL DRAWINGS UNLESS
OTHERWISE SHOWN OR NOTED. MODIFY TYPICAL DETAILS AS DIRECTED TO MEET
B. COLUMNS AND SHEAR WALLS
C. BEAMS AND GIRDER
MAIN BAR-1 4-D16 MAIN BAR-1 4-D16 MAIN BAR-1
SPECIAL CONDITIONS. D. NON-LOAD BEARING WALL PARTITIONS, BEDDED SLABS, FLOOR & ROOF SLABS,
9.0 SHOP DRAWING WITH ERECTION AND PLACING DIAGRAMS OF ALL STRUCTURAL
STEELS, MISCELLANEOUS IRON, PRE-CAST CONCRETE, ETC. SHALL BE SUBMITTED FOR
PARAPETS, CATCH BASIN, SIDE WALK MAIN BAR-2 2-D12 MAIN BAR-2 2-D12 MAIN BAR-2
2. ALL REINFORCING BARS SIZE 10mm OR LARGER SHALL BE DEFORMED IN ACCORDANCE WITH THE ASTM
ENGINEERS APPROVAL BEFORE FABRICATION.

10. CONTRACTOR SHALL NOTE AND PROVIDE ALL MISCELLANEOUS CURBS, SILLS,
A-706 BARS SMALLER THAN 10mm MAY BE PLAIN.
3. SPLICES SHALL BE SECURELY WIRED TOGETHER & SHALL LAP OR EXTEND IN ACCORDANCE w/ TABLE B
MAIN BAR-3 - MAIN BAR-3 - MAIN BAR-3
(TABLE OF LAP SPLICE & ANCHORAGE LENGTH) UNLESS OTHERWISE SHOWN ON DRAWINGS, SPLICES SHALL
STOOLS EQUIPMENT AND MECHANICAL BASES THAT ARE REQUIRED BY THE
ARCHITECTURAL, ELECTRICAL AND MECHANICAL DRAWNGS. BE STAGGERED WHENEVER POSSIBLE.
4. FABRICATOR SHALL SUBMIT BAR BENDING & CUTTING SCHEDULE FOR APPROVAL BY THE ENGINEER AND
TIE (MID) D10@150 TIE (MID) D10@150 TIE (MID)
OWNER PRIOR TO BENDING & CUTTING.
11. ALL RESULTS OF THE MATERIAL TESTING FOR CONCRETE, REINFORCING BARS &
TIE (END) TIE (END) TIE (END)
STRUCTURAL STEEL MUST BE NOTED & APPROVED BY THE MATERIALS ENGINEER/
1@50, 10@75 1@50, 10@75
STRUCTURAL DESIGNER.
(200x400)
TIE BAR 2 LEGS TIE BAR TOP BAR 2-d12 2-d16
NOTES ON CONCRETE SLABS:
1. ALL SLAB REINFORCEMENTS SHALL BE 20mm CLEAR MINIMUM FROM BOTTOM AND FROM THE TOP OF SLAB.
BOT BAR 4-d12 2-d16
CONF. REINF.

2. UNLESS OTHERWISE SHOWN, REINFORCEMENT IN OCNTINUOUS ELEVATED SLAB SHALL BE CUT AS FOLLOWS:
JOINT HOOP SPACE @ "2Sh" WHEN
BENT BAR THERE ARE BEAMS HAVING WIDTH OF
STIRRUP D10 1@ 50, 10@75 D10@150
CONF. REINF. D

L1 L2 AT LEAST ONE-HALF THE COLUMN


WIDTH & DEPTHS NOT LESS THAN
THREE QUARTERS OF THE DEEPEST
L 1/4 L 1/4 L 2/4
TOP BAR BEAM THAT FRAME INTO FOUR
SKIN BAR
SIDES OF THE COLUMN. ALL OTHER

FOOTING SCHEDULE SCHEDULE OF SLAB


D

CONDITIONS USE HOOPS @ "Sh" CENTERS.


CONF. REINF.

COMMENT
D

Sh

BOTTOM BAR
COLUMN TIES AS
PER SCHEDULE

3. IF SLABS ARE REINFORCED BOTHWAYS BARS ALONG THE SHORTER SPAN SHALL BE PLACED
BELOW THOSE ALONG THE LONG SPAN AT THE CENTER AND ABOVE THE LONGER SPAN FOR
FOR COL. BAR SPACES SEE TABLE
NAME AT SUPPORTS AT MIDSPAN
REINFORCING BARS NEAR THE SUPPORTS. THE SPACING OF THE BARS AT THE COLUMN STRIPS

TYPE "A"
OF MIN. LAP SPACE LENGTH OF

TYPE "A"
CONF. REINF.

SHALL NOT BE MORE THAN ONE (1) SLAB THICKNESS. COLUMN REINFORCEMENT

4. TEMPERATURE BARS FOR SLAB SHALL BE GENERALLY PLACED NEAR THE FACE IN TENSION AND
Ly GB2
CONF. REINF. D

SHALL NOT BE LESS THAN 0.0025 X GROSS-SECTIONAL AREA (Ag) OF THE SLAB.
Sh

(SEE SCHEDULE BELOW)

E.Q E.Q Ly
D

SCHEDULE OF MINIMUM SLAB REINFORCEMENT NOTE:


CONF. REINF.

ALL CONCRETE REINF. DETAIL SHOULD


MINIMUM TEMPERATURE BARS BE DONE IN ACCORDANCE WITH ACI
Lx/4 Ly-Lx/2 Lx/4
D

DETAILING MANUAL (LATEST EDITION)

AS SHOWN
100 mm 10 mm Ø @ 250mm EACH WAY
125 mm 10 mm Ø @ 250mm EACH WAY
150 mm
175 mm
10 mm Ø @ 250mm EACH WAY
10 mm Ø @ 250mm EACH WAY
X1
D

TYPICAL COLUMN ELEV. SHOWING


200 mm 10 mm Ø @ 250mm EACH WAY
DOWELS AND TIES SPACING Cy Y1
E.Q

5. UNLESS OTHERWISE NOTED IN THE PLANS ALL BEDDED SLABS SHALL BE REINFORCED WITH 10mm Ø
LAP SPLICE LENGTH:
AT 25mm O.C EACH WAY TO CENTER OF SLAB AND CONSTRUCTION JOINTS FOR SAME SHALL
Lx/4

AT ANY LEVEL NO MORE THAN


NOT BE LESS THAN 3.65 METER APART. ALTERNATE BARS SHOULD BE

6. PROVIDE EXTRA REINFORCEMENTS FOR CORNER SLAB ( TWO ADJACENT DISCONTINUOUS EDGES)
AS SHOWN BELOW.
SPLICED MIN. DISTANCE BET.
TWO ADJACENT BARS SPLICES
SHALL BE 600mm.
(150x400)
7. CONCRETE SLAB REINFORCEMENT BE PROPERLY SUPPORTE4D WITH 10mm. STEEL CHAIR Y2
OR APPROVED EQUIVALENT SPACED AT 1.0 METER ON CENTER BOTHWAYS. C
L Y1 TOP BAR 2-d12 2-d16
Cx
Lx
0.37
X2
Lx/2

IMPORTANT: THESE DRAWINGS AS INSTRUMENTS


DOWN INTO EDGE BEAM. EXTENDED

TYPE "B"
Lx

4-12Ø @ 1800 LONG TOP BARS BEND Ø12 X 1000 LONG AT


BARS MIN. OF 1,200 (4'-0") INTO BARS. L

4-d12 2-d16
MID-DEPTH OF SLAB

BOT BAR
4 - 12Ø BOTT. BARS
AT EACH CORNER
H (CLEAR HEIGHT OF COL.)

1-12Ø TOP & BOTT. BARS


WITHIN CENTER

Y3
OF SERVICE, ARE THE PROPERTY AND
HALF OF "H"

0.
60
SLAB
38mm
0.25L SPLICE

Y1
G.L STIRRUP D10 1@ 50, 10@75 D10@150
60

E.Q

OPENING
Lx/4

TOP BARS @ SUPPORT (CONT.)


0.

CLEAR

REQ'D BOTT. BARS @ SUPPORT


SKIN BAR DOCUMENTS OF THE ARCHITECT. IT SHALL BE
H
JT. REINF.
CONF. REINF. TIES LAT. TIES

IN TWO WAY SLAB EXTEND


BARS UP TO BEAM SUPPORT
0.

OMIT TRIMMER BARS WHERE


COMMENT
60

TYPICAL CORNER SLAB DETAIL


OPENING IS FRAMED BY BEAM

TYPICAL SLAB
X1 X1
UNLAWFUL FOR ANY PERSON WITHOUT THE
D

BOTTOM BARS
0.12
OPENING DET.
Y1
0.165L SPLICE

WRITTEN CONSENT OF THE ARCHITECT OF


AT MID SPAN
0.22L
EXTRA TOP BARS
X1 X3
NOTES ON COLUMNS @ SUPPORT

1. PROVIDE EXTRA SETS OF TIES AT 100 O.C FOR TIED COLUMN REINFORCEMENT ABOVE
AND BELOW BEAM-COLUMN CONNECTIONS FOR A DISTANCE FROM FACE OF CONNECTION TYPICAL DETAIL OF COL. LAP SPLICE
SPLICE = 1:3Ld
TOP BAR AUTHORS OF SAID DOCUMENTS, TO DUPLICATE
EQUAL TO GREATER OF THE OVERALL THICKNESS OF COLUMN, 61 THE CLEAR HEIGHT OF & EXT. GIRDER TO COL. CONNECT.
COLUMN OR 450mm.
2. COLUMN TIES SHALL BE PROTECTED EVERYWHERE BY A COVERING OF CONCRETE CAST
MONOLITHICALLY WITH THE CORE WITH A MINIMUM THICKNESS OF 40mm AND NOT LESS
BOTTOM BAR OR COPY SAID INSTRUMENTS
NOTES ON BEAMS AND GIRDERS
THAN 40 TIMES THE MAXIMUM SIZE OF COARSE AGGREGATE IN MILLIMETERS.
3. WHERE COLUMNS CHANGE IN SIZE, VERTICAL REINFORCEMENT SHALL BE OFFSET AT A 1. UNLESS OTHERWISE NOTED IN PLANS, CAMBER ALL BEAMS AND GIRDER AT FOOTING COLUMN REBAR
SLOPE MONOLITHICALLY WITH THE CORE WITH MINIMUM THICKNESS OF 40mm AND
LEAST 6mm FOR EVERY 4.50M OF SPAN, EXCEPT CANTILEVERS FOR WHICH
SOIL
NOT LESS THAN 40 TIMES THE MAXIMUM SIZE COARSE AGGREGATE IN MILLIMETERS.
THE CAMBER SHALL BE AS NOTED IN PLANS OR AS ORDERED BY THE ENGINEER
BUT IN NO CASE LESS THAN 20mm FOR EVERY 3.0M OF FREE SPAN. NAME TYP. CAPA. REMARK SHORT DIRECTION ( X ) LONG DIRECTION ( Y )
2. TYPICAL BARS BENDING AND CUTTING DETAILS FOR BEAMS SHALL BE AS
4. UNLESS OTHERWISE INDICATED IN THE PLANS, LAP SPLICES FOR VERTICAL COLUMN
SHOWN IN FIG. B-1 THK. Lx Ly Cx Cy X1 Y1 X2 Y2
REINFORCEMENT SHALL BE MADE WITHIN THE CENTER HALF OF COLUMN HEIGHT, AND
THE SPLICE LENGTH SHALL BE LESS THAN 40 BAR DIAMETERS. NAME TYPE THK.
H
L1 L2 D16 D16 X1 X2 X3 Y1 Y2 Y3
L1 31 L1 31 L2 31 L2 13 F-1 B 300 1200 1200 200 300 @200 @200 150 H=VARIES
350mm. MAX.

D12 D12 d12 d12 d12 d12 d12 d12


S-1 A 150
10

F-2 B 300 900 900 150 250 @150 @150 150 H=900 @200 @200 @200 @200 @200 @200
d

S-01
H

L1 51 L1 51 L2 51 L2 51
m
in
.

2 - 12mmØ SIDE BARS TOP BARS WEB BARS


BOTTOM BARS

FIGURE B-1

You might also like