This progress report summarizes the fabrication, sandblasting/painting, and erection progress of members for two phases of construction. For Phase 1, 93 members have been fabricated, 41 sandblasted and painted, and 24 erected. Beam and bracing members are ahead of schedule while column members are slightly behind. Phase 2 involves 102 members but fabrication is only 29% complete so far. Overall, construction is on track with over half of members fabricated and a quarter erected.
This progress report summarizes the fabrication, sandblasting/painting, and erection progress of members for two phases of construction. For Phase 1, 93 members have been fabricated, 41 sandblasted and painted, and 24 erected. Beam and bracing members are ahead of schedule while column members are slightly behind. Phase 2 involves 102 members but fabrication is only 29% complete so far. Overall, construction is on track with over half of members fabricated and a quarter erected.
This progress report summarizes the fabrication, sandblasting/painting, and erection progress of members for two phases of construction. For Phase 1, 93 members have been fabricated, 41 sandblasted and painted, and 24 erected. Beam and bracing members are ahead of schedule while column members are slightly behind. Phase 2 involves 102 members but fabrication is only 29% complete so far. Overall, construction is on track with over half of members fabricated and a quarter erected.