From To
Sri.M. Vannur Swamy, M.Tech, The Deputy Executive Engineer,
Assistant Executive Engineer, (R&B)Sub - Division,
(R&B) Section,Puttaparthy. Dharmavaram.
Sub: - (R&B) Department – Strengthening of PHC at Krishnapuram (V) & Bukkapatnam (M)
in Anantapuramu District– Extention of Time (EOT) proposal submitted - Approval
requested - Reg
It is to inform that, the subject work is awarded to M/s Sri J.Ram Mohan Reddy,
Gunipally with 4.58 % excess over ECV of Rs. 3805287 /- prepared with SSR 2019-20. The
Agreement was concluded vide ref 1st cited with a stipulated period of completion in 6
months by 18.05.2021.
2.Labour couldn’t turn up to work at these PHC’s as these PHC’s became COVID
Centers.
In view of the reasons reported by the Contractor, proposals for EOT upto
30.09.2021 without LDs are herewith submitted with a recommendation to obtain approval
from the Competent Authority for the same so as to complete the rest of work in full
shape.
From To
Sri.G.Venkata Subbaiah, M.Tech, The Executive Engineer,
Deputy Executive Engineer, (R&B) Division,
(R&B) Sub-division,Dharmavaram. Dharmavaram.
Sub: - (R&B) Department – Strengthening of PHC at Krishnapuram (V) & Bukkapatnam (M)
in Anantapuramu District– Extention of Time (EOT) proposal submitted - Approval
requested - Reg
Ref:- 1. CR Agreement No. 34 /2020-21 Dated.13-11-2020 of SE(R&B) Circle, Anantapuram
2. Lr.No. 1111/Building work/AEE(R&B)/PTP/2020-21,Dt.1.05.2021 of
AEE/R&B/Puttaparthy
3. Contractor’s letter date.
<><><><>
It is to inform that, the subject work is awarded to M/s Sri J.Ram Mohan Reddy,
Gunipally with 4.58 % excess over ECV of Rs. 3805287 /- prepared with SSR 2019-20. The
Agreement was concluded vide ref 1st cited with a stipulated period of completion in 6
months by 18.05.2021.
2.Labour couldn’t turn up to work at these PHC’s as these PHC’s became COVID
Centers.
In view of the above, I request to kindly grant EOT upto 30.09.2021 without LDs to
complete the rest of work in full shape.
Yours faithfully,
8 Tender percentage :: 4.58 % excess over E.C.V framed with S.S.R. 2019-20