GOVERNMENT OF ANDHRA PRADESH

ROADS AND BUILDINGS DEPARTMENT

From To
Sri.M. Vannur Swamy, M.Tech, The Deputy Executive Engineer,
Assistant Executive Engineer, (R&B)Sub - Division,
(R&B) Section,Puttaparthy. Dharmavaram.

Lr.No.1111 /Building work/AEE(R&B)/PTP/2020-21 ,Dt.01.05.2021


Sir,

Sub: - (R&B) Department – Strengthening of PHC at Krishnapuram (V) & Bukkapatnam (M)
in Anantapuramu District– Extention of Time (EOT) proposal submitted - Approval
requested - Reg

Ref:- 1. CR Agreement No. 38 /2020-21 Dated.19-11-2020 of SE(R&B) Circle, Anantapuram


2. Contractor’s letter date.
<><><><>

It is to inform that, the subject work is awarded to M/s Sri J.Ram Mohan Reddy,
Gunipally with 4.58 % excess over ECV of Rs. 3805287 /- prepared with SSR 2019-20. The
Agreement was concluded vide ref 1st cited with a stipulated period of completion in 6
months by 18.05.2021.

However, only 65 % of physical progress is achieved within the agreement Period by


completing the Electrical works,Roof repairs, plinth protection, CC pavement,
Flooring/toilets and Water supply and sanitary items. However Joinery works,
compound wall gate,plinth protection couldn’t be completed within the agreement
period and hence vide ref 2 nd cited, the Contractor has submitted EOT proposals
upto 30.09.2021 without LDs with following reasons for not completing the work
within the agreement period:

1.Difficulty in procuring sand

2.Labour couldn’t turn up to work at these PHC’s as these PHC’s became COVID
Centers.

In view of the reasons reported by the Contractor, proposals for EOT upto
30.09.2021 without LDs are herewith submitted with a recommendation to obtain approval
from the Competent Authority for the same so as to complete the rest of work in full
shape.

Encl: EOT Proposals along with Contractor’s


Representation in original
Yours faithfully,

Assistant Executive Engineer,


(R&B)Section, Puttaparthy.
GOVERNMENT OF ANDHRA PRADESH
ROADS AND BUILDINGS DEPARTMENT

From To
Sri.G.Venkata Subbaiah, M.Tech, The Executive Engineer,
Deputy Executive Engineer, (R&B) Division,
(R&B) Sub-division,Dharmavaram. Dharmavaram.

Lr.No. /Building work/DEE(R&B)/DMM/2020-21 ,Dt.2.05.2021


Sir,

Sub: - (R&B) Department – Strengthening of PHC at Krishnapuram (V) & Bukkapatnam (M)
in Anantapuramu District– Extention of Time (EOT) proposal submitted - Approval
requested - Reg
Ref:- 1. CR Agreement No. 34 /2020-21 Dated.13-11-2020 of SE(R&B) Circle, Anantapuram
2. Lr.No. 1111/Building work/AEE(R&B)/PTP/2020-21,Dt.1.05.2021 of
AEE/R&B/Puttaparthy
3. Contractor’s letter date.
<><><><>

It is to inform that, the subject work is awarded to M/s Sri J.Ram Mohan Reddy,
Gunipally with 4.58 % excess over ECV of Rs. 3805287 /- prepared with SSR 2019-20. The
Agreement was concluded vide ref 1st cited with a stipulated period of completion in 6
months by 18.05.2021.

However, only 65 % of physical progress is achieved within the agreement Period by


completing the Electrical works,Roof repairs, plinth protection, CC pavement,
Flooring/toilets and Water supply and sanitary items. However Joinery works, compound
wall gate,plinth protection couldn’t be completed within the agreement period and hence
vide ref 2 nd cited, the Contractor has submitted EOT proposals upto 30.09.2021
without LDs with following reasons for not completing the work within the agreement
period:

1.Difficult of difficulty in procuring sand

2.Labour couldn’t turn up to work at these PHC’s as these PHC’s became COVID
Centers.

In view of the above, I request to kindly grant EOT upto 30.09.2021 without LDs to
complete the rest of work in full shape.

Thank you sir,


Encl: EOT Proposals along with Contractor’s
Representation in original

Yours faithfully,

Deputy Executive Engineer,


(R&B) Sub-division, Dharmavaram.
PROFORMA TO ACCOMPANY THE PROPOSAL FOR EXTENSION OF TIME AS PER CHIEF
ENGINEER (R&B) CIRCULAR MEMO NO 114043-CONTR(1) 74 DATED 16-06-1974

1 Name of work :: Strengthening of PHC at Krishnapuram


(V),Bukkapatnam (M) in Anantapuramu District

2 Estmate amount and Number :: 59.62 Lakshs


Sub Estimate amount
3 Head of Account to which the :: 4210-02-110-11-04-530/531
expenditure is chargeable

4 Agreement NO.and amount :: 38/2020-21, Rs. 3979569.00


5 Name and address of the contractor :: M/s Sri J.Ram Mohan Reddy
Gunipalli (V),Anantapur District.
6 The Division in which the work is :: Dharmavaram
situated
7 Tender approving authority :: Superintending Engineer ,(R&B) Circle, Anantapuramu
Lr.No. 482/Building work/SE(R&B)ATP/ 2020-21, Dated
: 19-11-2020

8 Tender percentage :: 4.58 % excess over E.C.V framed with S.S.R. 2019-20

9 Date of handing over site to the :: 19-11-2020


contractor

10 Date fixed for completion of work as per :: 18-05-2021


agreement

11 Value of work done up to the agreement :: 65%, (Rs. 2604357.00)


date (which percentage)
12 Extension of time granted previously :: No

13 The value of work done during the :: No


extended period
14 value of work yet to be done :: Rs. 1375212

15 provisions made in the estimate :: PHC Krishnapuram :


1) Flooring/Toilets
2) Joinery
3) Roof Repairs
4) Plinth Protection
5 )Painting
6 )Compound wall
7) CC Pavements and Internal roads
8) Wter supply and sanitary items
9) Electrical Items
16 physical stage of work :: Electrical works,Roof repairs,CC road,Flooring,
Compound wall, Water supply and sanitary works
completed.Joinery works,Gravel filling ,compond wall
gate provision and biomedical waste pit construction
under progress
17 Details of penalties.if any levied so far :: NIL

18 If no penal action was taken, reasons :: No


for not taking such action so far

19 The date up to which the extension of :: 30-09-2021


time is applied for by the contractor

20 Extension of time upto which it is :: 30-09-2021


necessary in the opinion of the EE

21 General Remarks of the Executive ::


Engineer (R&B) Dharmavaram

Asst. Executive Engineer, Deputy Executive Engineer,


(R&B) Section, Puttaparthy (R&B) Sub Division, Dharmavaram.