4 June 2018

Introduction
81,300 kWh Approximate output of the solar system(year 1)
Indigo Energy (also known as “IE”) is pleased
to offer a rooftop solar PV project to Khin
Maung Nyunt Manufacturing Co., Ltd (also
known as “KMN” or “Khin Maung Nyunt”).

Technical Data Summary


This proposal was based around the following
technical assumptions.

Site Location
The site is located at No.(506-508), Mogoke
Street, Industrial Zone(1),South Dagon Township, Yangon, Myanmar. (with
GPS coordinates of 16.828794, 96.224459 ).

60 kWp / 50 kWac 362 m2 30%


Proposed solar system Solar percentage of
Roof area required
capacity total energy

~10 lakhs MMK 10-12 3 weeks


Saving per month
weeks Construction period
Shipping time

356 661 1,017 lakhs 81,300 kWh


lakhs lakhs
MMK Approximate output
MMK MMK of the solar system
Total System Cost (year 1)
Price to KMN RBF

Since this project will connect with the diesel generator, IE must do a proper power
monitoring study after KMN selects IE for this project. The precise sizing of the
load must be determined by installing a power meter and recording data for a
minimum of one week. Additionally, the existing diesel generator size must be
analyzed to insure that it can run properly with the solar system. A generator
should not run less than 30% of its capacity.

KMN Rooftop Solar Preliminary Proposal Page 2