C1 & C2 Labour Report - Station Finishing Work(QBPL) DATE :- 09-12-2023

Minimum Available As
SR. No Contractor Name Balance Short fall (%)
Required on 09.12.23
1 Tapovan station 50 53 -3 -6
2 PDPU station 50 62 -12 -24
QBPL
3 GNLU station 50 36 14 28
4 Gift City 50 32 18 36

1 Sector-1 50 30 20 40
2 Infocity 50 36 14 28
3 QBPL Dholakuva 50 30 20 40
4 Randesan 50 31 19 38
5 Raysan 50 28 22 44
Total 450 338 112