Lead time 9 days

D 6000 per month 500 per month


c 20 $
h 4.2 $
K (setup cost) 115 $
working days 300 days
Shortage cost 0 $ Lưu ý đồ thị đề cho là Basic EOQ Model

EOQ
573.2115061477

BASIC EOQ MODEL MIN TC AND TVC


Total Reorder point 147.9452055
Acquisition cost 120000

Setup cost 1203.744155


Holding cost 1203.744163

TC 122407.4883
TVC 2407.488318

PLANNED SHORTAGE MIN TVC AND TC

EOQ Total acquisition cost 120000


715.94093970078 Total setup cost 963.7666485
Total holding cost 617.7991344
p 7.5 Total shortage cost 345.9675152
Shortage 257.0044399
TC 121927.5333
TVC 1927.533298

BASIC EOQ PLANNED SHORTAGE


Q 573.2115061 715.9409397
S* 0 257.0044399

MAX INVT 573.2115061 458.9364998