Professional Documents
Culture Documents
Landscaping / Unit - -
1. Job scope - 26 units bungalow. Job scope - 46 units bungalow. - Based on economics of scale, Phase J17 would be more expensive
2. Type of units Type of units - Phase J3 would be less expensive due to the types having more 3
2 storey bungalow. 3 storey bungalow - 31 units. storey houses than 2 storey houses as in Phase J17.
2 storey bungalow - 15 units. - 3 storey would be cheaper in terms of cost per FS.
3. No. of tenders - 5 Tenderers. No. of tenders - 8 Tenderers. - Competitiveness of tender for Phase J3.
(b) Preparing precast RC pile head was (b) Preparing precast RC pile head was Reasonable rate is between
priced at RM 21.00 / NO priced at RM 5.44 / NO RM15 - RM25/NO. depend on
size of piles.
(b) 6mm thick sandblast glass was priced (b) 6mm thick frosted glass; light green
at RM 109.00 / M2. tinted was priced at RM 58.36 / M2. Tinted glass normally more
expensive than normal glass.
(d) 1.5mm thick powder coated (d) 1.2mm thick powder coated (b) Difference in specifications. The cost difference between
aluminium frame louvres. aluminium frame louvres. 1.2mm and 1.5mm thick
@ Cost / m² = RM 448.00 / M2 @ Cost / m² = RM 267.00 / M2 approximately between 20% -
30%.
ECA/DIFF_J17_J3/Page 2
APPENDIX A
DIFFERENCES IN BUILDING COST PER SF BETWEEN BUNGALOW AT PHASE J17 AND PHASE J3
PHASE J17 PHASE J3
Item Remarks
Building cost / FS CPA = RM 211/FS Building cost / FS CPA = RM 177/FS
(e) 1.5mm thick powder coated (e) 1.4mm thick powder coated
aluminium door frame. aluminium door frame.
(f) Glass door type is folding, sliding, (f) Glass door type is swing doors and Folding glass door is the most
swing, slide & hide doors. sliding doors. expensive doors compared to
sliding glass door and swing
(g) Floor, Wall & Ceiling Finishes. (g) Floor, Wall & Ceiling Finishes. glass door.
1. Porcelain wall and floor tiles. 1. Porcelain wall and floor tiles.
2. Plasterboard ceiling. 2. Plasterboard ceiling.
ECA/DIFF_J17_J3/Page 3
BUNGALOWS AT DENAI ALAM.
GENERAL
Notes to Tenderers
Specifications
GENERAL ITEM
Piling Record
C Submit piling records as specified in triplicate, duly
signed by the contractor and the engineer and
deliver to the Architect / S.O. as the work proceed.
Item 3,150.00 1,088.80
As-Built Drawing
D Upon completion of the piling works, the contractor
shall submit an as-built drawing on the pile position
certified by a License Land Surveyor and deliver the
same to the Architect / S.O..
Item 12,867.75 3,810.80
WORKING PILES
Testing
Carry out initial static load test on precast reinforced
concrete piles to 2 times the working load; including
bring to site for testing purposes all calibrated
instrument, equipment, kentledge, labour and
materials and remove the same on completion.
Collection Page
BQ/piling/1 - -
Landscaping / Unit - -
Landscaping / Unit - -
Landscaping / Unit - -
Provisional Sum - -
Landscaping / Unit - -
Total Building cost only excluding M&E 21,485,097.30 174.52 33,460,854.98 149.97
PROPOSED 46 UNITS 2 & 3 STOREY BUNGALOW AT PHASE J3, DENAI ALAM
SUMMARY
2 Frame 46,677.96 326,745.72 54,316.28 1,194,958.16 46,933.16 703,997.40 46,138.12 45,606.28 2,317,445.68
3 Upper floor 29,852.32 208,966.24 28,569.50 628,529.00 21,950.17 329,252.55 27,634.73 31,386.84 1,225,769.36
4 Roof and rainwater goods
4.1 : Roof structure 18,973.20 132,812.40 21,813.10 479,888.20 21,115.74 316,736.10 18,987.20 22,616.39 971,040.29
4.2 : Roof finishes 31,215.48 218,508.36 37,529.84 825,656.48 50,500.98 757,514.70 40,196.26 35,393.52 1,877,269.32
4.3 : Rainwater plumbing 2,996.15 20,973.05 3,899.79 85,795.38 4,099.01 61,485.15 4,062.00 2,068.57 174,384.15
5 Staircase
5.1 : Staircase structure 5,381.49 37,670.43 6,310.29 138,826.38 2,852.54 42,788.10 5,667.29 5,381.49 230,333.69
5.2 : Staircase finishes 2,551.12 17,857.84 3,032.32 66,711.04 0.00 0.00 3,000.96 2,551.12 90,120.96
5.3 : Staircase railings 7,011.90 49,083.30 9,015.30 198,336.60 6,010.20 90,153.00 7,011.90 7,011.90 351,596.70
6 External walls
6.1 : External walls 30,756.91 215,298.37 31,573.72 694,621.84 43,283.32 649,249.80 27,865.03 34,329.03 1,621,364.07
6.2 : External railings 15,177.94 106,245.58 8,928.20 196,420.40 2,678.46 40,176.90 15,177.94 8,928.20 366,949.02
7 Windows And Vents 42,614.58 298,302.06 58,658.20 1,290,480.40 65,420.90 981,313.50 38,950.98 42,373.78 2,651,420.72
8 Doors And Ironmongeries 46,727.26 327,090.82 37,461.43 824,151.46 42,443.17 636,647.55 51,546.32 45,609.17 1,885,045.32
9 Internal walls
9.1 : Internal walls 13,311.03 93,177.21 14,207.31 312,560.82 15,128.35 226,925.25 12,966.30 13,821.69 659,451.27
9.2 : Internal railings 2,003.40 14,023.80 5,509.35 121,205.70 4,507.65 67,614.75 0.00 2,003.40 204,847.65
10 Internal wall finishes 50,535.70 353,749.90 57,404.63 1,262,901.86 52,105.12 781,576.80 48,994.24 54,108.79 2,501,331.59
11 Internal floor finishes 23,176.30 162,234.10 23,108.49 508,386.78 24,405.68 366,085.20 22,447.29 23,176.30 1,082,329.67
12 Internal ceiling finishes 8,590.41 60,132.87 8,943.16 196,749.52 8,075.16 121,127.40 8,348.26 8,590.41 394,948.46
13 External finishes 35,796.30 250,574.10 42,688.92 939,156.24 34,164.66 512,469.90 78,755.55 69,692.37 1,850,648.16
14 Sanitarywares and Fittings 31,432.33 220,026.31 27,755.45 610,619.90 27,755.45 416,331.75 31,402.93 31,402.93 1,309,783.82
15 Builder's Work In Connection With Services 1,766.66 12,366.62 1,761.22 38,746.84 1,761.22 26,418.30 1,777.55 1,777.55 81,086.86
16 External Works Within lot boundary 101,482.40 710,376.80 79,608.28 1,751,382.16 73,107.04 1,096,605.60 104,918.74 121,217.73 3,784,501.03
BQ/BLDG/5.2(a)/SUM/14/Add2
PROPOSED 46 UNITS 2 & 3 STOREY BUNGALOW AT PHASE J3, DENAI ALAM
SUMMARY
BQ/BLDG/5.2(a)/SUM/15/Add2