Design Scope : FLAT GLASS DESIGNING
Design Starting Date : DD/MM/YYYY
Design Completion Date : DD/MM/YYYY

Internal &
Responsibilt External
Sr. No. Activity Nature & ComplexityTime Required y Resources Planned Actual

Customer
drawings/requir
ements,
National or
Design and development International DD/MM/
1 inputs High 5 Days HOD-Design standards etc. YYYY DD/MM/YYYY

Design and development


controls (Review, Verification Prototype DD/MM/
2 & Validation activities) High 20 Days HOD-Design developed etc. YYYY DD/MM/YYYY
Design and development Drawings/ DD/MM/
3 outputs High 6 Days HOD-Design designs made YYYY DD/MM/YYYY
Design and development Delivered DD/MM/
4 changes High 15 Days HOD-Design products etc. YYYY DD/MM/YYYY