TRUNKLINE FROM WP-A TO GIFT FOR PETRONAS CARIGALI IRQA HOLDING B.V.
TENDER NO.: PCIHBV/2019/PD&T/2429
TECHNICAL PROPOSAL
TECHNICAL PROPOSAL
Table of Content
T14.1.1 Preface...................................................................................................................................... 3
TECHNICAL PROPOSAL
T14.1.1 Preface
T14.1.1.1 Introduction
The prime objective of this Quality Assurance and Quality Control (QA/QC) Plan provided by
CONTRACTOR is to demonstrate, that CONTRACTOR intends to completely satisfy the
requirements of the contract with regard to fitness for use, performance, safety and reliability of the
plant and the services of the project to be supplied to PCIHBV through the implementation of an
efficient quality management system (QMS), as described in this QA/QC Plan.
T14.1.1.2 Definition & Abbreviations
PROJECT/WORK: PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND
COMMISSIONING (EPCC) OF OIL TRUNKLINE FROM WP-A TO GIFT FOR
PETRONAS CARIGALI IRAQ HOLDING B.V. GARRAF OPERATION
PCIHBV: PETRONAS CARIGALI IRAQ HOLDING B.V.’s, GARRAF OPERATIONS
CONTRACTOR: Grand Energy Development ltd.
Quality: definitions and terms are specified in ISO 9001:2015, ISO-TS 29001 and ISO
9000:2015 'Quality management systems - Fundamentals and vocabulary.
QA/QC: Quality Assurance and Quality Control
HSE: Health, safety and environment
QMS: Quality management system
ITB: Invitation to bidding
NCR: Non-Conformity Report
NDT: Non-Destructive testing
T14.1.1.3 Reference
This quality assurance and quality control plan outlined herewith is based on the following
documents:
ISO 9001-2000 Quality Management System
PCIHBV ITB reference documents
CONTRACTOR Enterprise Quality Manual
T14.1.1.4 Control of Quality Plan
Quality Plan Description
The quality plan identifies the quality policy, quality objectives, project quality management
organization, duties and limits of authority, resource allocation, process control, quality
requirements, quality management system evaluation and sustained improvement of the quality
management system that will be implemented in the Project for the realization of the realization of
the WORK as described in the Contract. It is a guideline to CONTRACTOR and project office on
quality management activities, control of quality management process and achievement of quality
objective. In addition, it also demonstrates CONTRACTOR’s ability to continually deliver
products/services, which meet PCIHBV’s requirements and relevant regulatory requirements.
Management of the Quality Plan
The quality plan will be prepared under the organization of project quality management department,
and reviewed by project manager. After the joint review by relevant departments, it will be
submitted to manager in charge (or his authorized) for approval and issuance for implementation.
The project document control department will make the distribution list to define the distribution
T14.1 Quality Management System Page 3 of 28
PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) OFOIL
TRUNKLINE FROM WP-A TO GIFT FOR PETRONAS CARIGALI IRQA HOLDING B.V.
TENDER NO.: PCIHBV/2019/PD&T/2429
TECHNICAL PROPOSAL
scope of the quality plan, which shall be approved by the project manager. The quality plan will be
stamped with “CONTROLLED” “VALID” and then distributed to the internal project departments.
The distribution shall be numbered, recorded for filing.
Validity Term of the Quality Plan
This project plan shall be executed from the issuance date and shall be valid until the handover
date of the project.
All the project departments shall seriously and strictly follow and implement the quality plan, and
the project quality management department will organize the surveillance and inspection over its
implementation.
The project quality management department is responsible for the interpretation of this plan.
TECHNICAL PROPOSAL
Level III may be approved by Project Manager or Deputy Project Manager in charge.
Distribution of QMS Documents
Project Manager shall decide distribution scope of QMS documents.
Document of Level I or Level II shall be distributed by Document Control Group in
Administration Department.
Document of Level III may be distributed by the functional Department. A copy shall be
filed in Document Control Group of Administration Department.
Control of Technical Document
Scope of the Technical Document Shall Be as Follows:
Engineering documents such as drawings, design change order, specifications
Standard and Code
Pre-commissioning and commissioning plan;
Operation Manual
Distribution of Construction Drawings:
All original copies of approved engineering and other technical documents shall be kept by
Administration Department and controlled copies distributed to all other concerned
departments/ parties for their information or action.
A distribution matrix shall be prepared by Document Controller Superintendent and approved
by Project Manager. All project drawings shall be distributed as per the matrix. The recipient of
document shall sign his / her name on a distribution log.
The document controller in each department and the subcontractor shall be responsible for
controlling the drawings received. After completion of the project, all project drawings shall be
returned to the Administration Department or destroyed. As-built drawing shall be submitted to
the PCIHBV /CONTRACTOR as per the project subcontract.
The Administration Department shall register, file and distribute project specification and
standards.
The technical documents prepared by each department or the third party shall be jointly
reviewed by related departments and distributed by Administration Department after approval
by Project Manager.
The As-built technical documents and data shall be controlled as “As-Built Drawing Procedure”
Correspondence:
A letter, when issuing from CONTRACTOR for an approval, certificate, consent,
determinations, notice and for request, shall be type-written, printed or electronically made
and signed by Project Manager or his authorized representative. The letter number shall be
assigned by Administration Department.
A transmittal is used to convey technical documents and drawings. All transmittal shall be
numbered and prepared by using approved transmittal coversheet. The transmittal number is
assigned by Administration Department. The Numbering system of letter and transmittal shall
be as per project Document and Data Control Procedure.
Each department shall keep their own “Register of Quality System Documentation”.
Document shall be distributed by use of “Documents Distribution Record”, if so required.
Changes to documents and data should be reviewed and approved by the same function/
authority that perform the original review and approval. The invalid and/or obsolete document
shall be promptly removed from all points of issue or use, or otherwise assured against
unintended use.
T14.1 Quality Management System Page 5 of 28
PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) OFOIL
TRUNKLINE FROM WP-A TO GIFT FOR PETRONAS CARIGALI IRQA HOLDING B.V.
TENDER NO.: PCIHBV/2019/PD&T/2429
TECHNICAL PROPOSAL
CONTRACTOR shall establish “Document and Data Control” Procedure and relevant internal
regulations to control project documents.
Control of Quality Document
The project document control department is the main department in charge of the quality
management system document.
The scope of quality system document includes the CONTROLLED quality system document
issued by CONTRACTOR, project quality plan, operation record of quality system, project quality
inspection document, project operation guidance manual (including management system and
management practice), sample of quality record, project contract document, procurement
document, written management documents and internal communication documents concerning
quality.
The project document control department is responsible for establishing “List of Controlled Quality
System Document” and “Issuance Record of Controlled Document”, and for recording the issuance
of the document.
Document Management
To ensure the quality management system documents under controlled state, the project office
shall follow strictly Document Control Procedure which clearly specifies followings to be controlled.
Any documents shall be approved before issuance to ensure the fullness and fit-for-
purpose of the documents.
If necessary, the documents shall be reviewed and updated, and obtain re-approval.
Identify the revision and current revision status of the document.
Ensure valid revision of document is issued and used.
Ensure the text of the document is clear and legible.
Any external document shall be marked and its issuance shall be under control.
To avoid the non-intended reference of obsolete document, any obsolete document shall
be appropriately marked if the document is to be retained. The types of document include
drawing, calculation sheet, data sheet and instruction manual, etc., and the format of
document includes hard copy and electronic copy.
T14.1.2.3 Control of Records
General Requirement
The records required by the project management system include the quality system operation
record and project products record.
The project quality control department is responsible for controlling quality system management
record, organizing the final inspection and test records for construction process, filling, collecting,
collating, cataloguing and managing project record, which in detail includes control over quality
system document and data, construction process inspection and testing status, nonconformance
product control, control of surveillance and measurement devices, as well as filling, collecting,
collating and reporting of records for corrective and preventive measures.
The project engineering department is responsible for filling, collecting, collating and reporting the
records for project design control, project design nonconformance product control and technical
documents and data control.
The project procurement department is responsible for the management of project
materials/equipment procurement, identification of incoming materials/equipment, inspection and
testing status of incoming materials/equipment, and filling, collecting, collating, reporting and the
management of the records for incoming material/equipment certificates.
T14.1 Quality Management System Page 6 of 28
PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) OFOIL
TRUNKLINE FROM WP-A TO GIFT FOR PETRONAS CARIGALI IRQA HOLDING B.V.
TENDER NO.: PCIHBV/2019/PD&T/2429
TECHNICAL PROPOSAL
The project construction technology department is responsible for filling, collecting, collating,
cataloguing, shelving and management of the records in the course of project execution, as well as
the filling, collecting, collating and reporting of the records for equipment operation and
maintenance.
The project document control department is responsible for filling, collecting, collating, and
cataloguing the records within the department.
Control Scope of the Records
The quality management system record includes following: quality system supervision and
inspection record, internal quality system audit record, management examination and evaluation
report, contract review record, engineering supplier record, engineering examination and evaluation
record for critical items, material/equipment supplier record, documents and data control record,
material/equipment procurement and receiving inspection record, equipment running, repairing and
maintenance record, special process control record, product identification and mark transferring
record, nonconformance product control record, identification for inspection and testing status,
inspection, measurement and test equipment record, corrective and preventive measures record,
staff training and qualification test record, record for quality questionnaire, after-sale service record.
It also includes the quality management system records from engineering supplier, project
material/equipment supplier and project subcontractor.
Project products record includes all kinds of inspection and test record, quality certificate for project
product or raw material, engineering review and confirmation record, engineering requirement
clarification record, record for drawing review by multi-party, engineering revision, review &
approval, confirmation and tracing record, record for all kinds of work order, commissioning and
testing record, handover and acceptance certificate, etc. It also includes the project product records
from material/equipment supplier and project subcontractor.
T14.1.2.4 Record Management Responsibilities
Project quality control department is the major department responsible for the quality record. It will
supervise, inspect and control the implementation of the quality record.
Every record management department of the project office shall, as per its responsibility, establish
“record list” for usage by itself and collect, collate and take care of the records.
T14.1.2.5 Management of Records
The main activities of record control include: filling in of record, identification of record, shelving of
record, retrieval of record (including cataloguing, filing and lending), protection of record, “shelf life”
of record and disposal of record.
The medium format of the record includes written, hardcopy or soft copy. The records shall be kept
clear and identifiable, stipulating the control requirement in terms of identification, shelving,
protection, retrieval, “shelf life” and disposal of the records.
Every responsible department shall establish its own record list (general list). The quality record in
the quality system operation will be collected, collated and catalogued by each responsible
department and project office, who will report to higher level the associated records. The project
product record will be collected, collated as per classification and catalogued by each department
of the project office, and the project document control office is responsible for the management.
The record cataloguing method will be as per the Project Archive Management Practice. The
management of records related to final documentation and filing will be as per the contract and
CONTRACTOR’s regulation.
The management of other aspects of project records shall be as per Record Control Procedure.
T14.1 Quality Management System Page 7 of 28
PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) OFOIL
TRUNKLINE FROM WP-A TO GIFT FOR PETRONAS CARIGALI IRQA HOLDING B.V.
TENDER NO.: PCIHBV/2019/PD&T/2429
TECHNICAL PROPOSAL
TECHNICAL PROPOSAL
T14.1.4 Planning
T14.1.4.1 Contents of Quality Objective
To ensure the normal operation of the quality management system established as per ISO9001
standard, the effective control of project quality, the documents and data are full and complete, the
quality activities records are complete and reliable, and to ensure the quality system can be
continuously improved.
Any project undertaken by CONTRACTOR is reasonable design and advanced in technology.
T14.1.4.2 Planning Frequency of Quality Objective
The project quality objective shall be initiated by quality control department, approved by project
manager, and then submitted to CONTRACTOR manager in charge for approval and issuance for
implementation in the form of project office document. The project objective shall be assigned
annually based on the progress of project, and shall be examined and evaluated at least once a
year. Suggestion on improvement shall be raised as per examination and evaluation result, and the
quality objective for next year will be determined accordingly.
T14.1.4.3 Requirements for Establishing Quality Objective
The project quality object shall be maintained consistent with CONTRACTOR quality policy and
annual quality objective. The sub-objective of each project office department shall, together with the
main project objective, compose a network system, and shall be consistent between top level and
lower level, concerted between same levels, thus making up the objective management system of
the project.
T14.1.4.4 Breakdown and Fulfillment of Quality Objective
QA/QC Department shall develop Quality Management System (QMS) Procedure Manual. After
approval by Project Manager, this manual shall be carried out by all CONTRACTOR staff as a
guideline for implementation and improvement of the project QMS.
All functional departments shall establish their quality objectives and establish their department
procedures / work instructions to ensure the fulfillment of their objectives.
The integrity of the quality management system shall be maintained no matter whatever changes to
the quality management system.
T14.1.4.5 Planning of Quality Management System
The quality management system shall be planned in compliance with ISO 9001-2000,
CONTRACTOR quality system document, and PCIHBV’s requirements (contract clause) on the
product.
The project manager will organize the project management to plan the quality management system,
i.e. to plan the resource and process required for implementing quality policy and for establishing
quality objective, thus establishing the quality management system via written document and
improving continuously its effectiveness to meet the requirements of project quality objective.
Result of Quality Management System Planning
The outcome of planning at the time of establishing quality management system is the
formation of project quality management system documents in which the process
(including subcontracting) resource required by the project management system is
determined, and the duties, limits of authority and their relations, as well as function
allocation of the quality management system are defined.
The outcome of sustained quality improvement planning is the origination of requirements
for sustained improvement, and the decision making through internal quality audit and the
T14.1 Quality Management System Page 9 of 28
PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) OFOIL
TRUNKLINE FROM WP-A TO GIFT FOR PETRONAS CARIGALI IRQA HOLDING B.V.
TENDER NO.: PCIHBV/2019/PD&T/2429
TECHNICAL PROPOSAL
TECHNICAL PROPOSAL
TECHNICAL PROPOSAL
TECHNICAL PROPOSAL
TECHNICAL PROPOSAL
Administration Department shall develop “Document Control Procedure” and “Human Resource
Provision & Training Plan”.
HSE Department shall develop “Healthy Safety Environment and Security Manual” for this project.
All documents developed by project functional departments based on the project realization plan
shall be consistent with each other and constitutes QMS level III document action.
T14.1.7.2 PCIHBV Related Processes
Determination of the PCIHBV’s requirement, CONTRACTOR shall review PCIHBV related
process in the following aspects:
Requirement specified by PCIHBV, including the requirement for delivery and post-
delivery.
Requirement not stated by PCIHBV but necessary for specified or intended use.
Statutory and regulatory requirement related to the project.
Any additional requirements necessitated by the project.
After project contract review, CONTRACTOR shall ensure that:
CONTRACTOR has an ability to meet the defined contract requirements;
Contract requirements differing from those previously expressed are resolved;
Contract requirements are clearly known by all department staff within their scope of work.
Contract Department is responsible to assist Project Manager for project routine contract control. It
shall be in charge of collecting contract information including contract change and claim and
interface with insurance PCIHBV.
Contract Department shall carefully study related law, rules and statutory regulations, and review
contract change status and report to Project Manager.
Any PCIHBV’s requirement shall be through formal contractual document, and confirmed by
CONTRACTOR before acceptance.
Process for contract change
Where project requirements are changed and approved by PCIHBV, CONTRACTOR shall ensure
that relevant documents are amended and that relevant personnel are notified accordingly.
No matter whether changes to the contract are initiated by PCIHBV or by CONTRACTOR, the
changes shall be made available to every relevant department to study. Only agreement between
CONTRACTOR to PCIHBV is made, than the “changes to the subcontract” can be documented
and distributed to relevant departments for action. If the Subcontract changes negatively affect the
project function, quality, cost and completion date, the Project Manager shall report to
CONTRACTOR Head Office for instruction.
Communication with PCIHBV
The contract department is responsible for identifying the requirements associated with the product,
organizing the construction technology department, planning and control department and document
control department, etc to identify PCIHBV’s requirements based on the documents like bidding
document, contract protocol, change order and written agreement. The requirements include the
requirement made clear by PCIHBV, the implied requirement from PCIHBV, law and regulation
requirement, and additional requirements decided by CONTRACTOR.
All contract issues during those shall be carefully kept and copied to Contract Department for
information.
The contractual information includes but not limit to the following:
TECHNICAL PROPOSAL
Project Status.
Inquiries on subcontracts or PCIHBV’s instruction including amendments.
Explanation to PCIHBV’s feedback, including their complaints.
T14.1.7.3 Purchasing
Purchasing process
The purpose of control over the purchasing process is to ensure that the purchasing product,
including Sub-contract service, conforms to specified purchase requirement.
CONTRACTOR shall establish criteria for selection, evaluation and re-evaluation of suppliers. It
shall evaluate and select suppliers based on their ability to supply product or service in accordance
with the project requirement.
Procurement Department, Construction Department and Contract Department are respectively
responsible for the purchase process related to their own work.
Procurement Department and Contract Department shall develop “Procurement Manual” and “Sub-
Contract Control Procedure” respectively to define criteria of selection, evaluation and re-evaluation
of suppliers, based on the following aspects:
Evaluation of supplier about qualification, capability, history, reputation, financial status.
Product supplied quality status and experience of suppliers
Supplier’s quality management system and its assurance ability.
Degree of customer ‘s satisfaction
Service and support ability after delivery by supplier.
After evaluation Procurement Department and Contract Department shall establish a list for pre-
qualified suppliers
Contract Department shall prepare regulatory and statutory terms and conditions of purchasing
document according to the PCIHBV’s requirements.
All evaluation records shall be maintained.
Purchasing information
Procurement Department shall define technical and commercial requirements in a purchase order
of material quantity, price, quality, acceptance, and delivery.
The adequacy of purchase order shall be confirmed and approved by Project Manager and
PCIHBV, if so required, prior to communication to supplier.
Verification of purchased product
QC team in Procurement Department shall be responsible for quality control in all processes of
material being purchased. They shall develop product inspection and test plan/ procedure, which
shall be approved by PCIHBV, and conduct verification to the material produced by vendor.
Procurement Department QC team shall review procurement documents related to quality control
and ensure they are suitable, adequate and effective.
Procurement Department QC team shall also perform inspection for delivered material and
equipment to ensure they are in conformance with purchase order.
For the important material, QC team shall prepare inspection plan. After approved by PCIHBV, QC
team shall perform inspection at the supplier’s premises for verification.
All material and service verification records shall be maintained.
TECHNICAL PROPOSAL
TECHNICAL PROPOSAL
In order to preclude from confusion or misuse during the project realization and achieve the
purpose of status traceability of material or construction stage, a suitable means shall be taken to
identify their status and a unique identification system for traceability shall be established.
Warehouse keeper shall maintain the vendor’s original identification mark with warehouse material
system number, if so required, on purchased material and equipment for his material control. The
record of material identification shall be registered.
Construction personnel shall check the identification number before withdrawing material from
warehouse for confirmation.
Construction Department may give a further Construction ID mark to identify their products during
construction activity as per Construction Procedure.
QA/QC personnel shall be responsible for marking inspection and test status on project product,
e.g. hold, acceptance, reject, valid, invalid etc.
Before a material is separated or covered, Procurement Department or Construction Department
shall transfer the identification mark, if so required, to ensure a truly material traceability is kept. QC
inspector shall monitor ID mark transfer.
Customer (PCIHBV) property
The project procurement department will be responsible for the management of PCIHBV supplied
project equipment and piping material, and document control department for the management of
drawing provided by PCIHBV.
Upon the arrival of PCIHBV supplied material/equipment, receiving inspection shall be carried out
as per inspection process, and the record for such inspection shall be taken. Unacceptable
material/equipment will be segregated, marked, recorded and stored at designated place. The
procurement department will gather the record for any shortage, damage and inadequacy of the
material/equipment, and inform the PCIHBV in writing and discuss with PCIHBV for solution.
The storage, custody and maintenance of PCIHBV supplied equipment will be as PCIHBV’s
requirements:
All equipment and material shall be carefully handled and stored at SITE, either inside
covered stores or inside fenced material yard, depending upon the type of equipment or material.
Handling, preservation and storage of equipment and material shall be carried out in
conformance with Vendor’s instructions, in addition to PCIHBV requirements and specifications.
Fragile equipment, Instrumentation and electronic items etc. which are sensitive to weather
conditions, if required, shall be stored in an air conditioned enclosed storage.
Liquids such as chemicals, lubricants etc. if any shall be stored on hard standings with shed and
proper facility for spillage and drainage control.
Preservation of product
Warehouse will be set up at the construction site to effect the warehouse storage management of
material/equipment required. Scientific management will be implemented at the warehouse area.
The warehouse areas shall be tidy and clean; roads in the area shall be passable;
material/equipment shall be stored orderly; identifications are complete and fire-fighting facilities
are in good conditions.
The procurement department will, based on the nature of the material/equipment and stipulation on
material/equipment storage, take precautionary measures against the material/equipment from
firing, moisture, explosion, rust, damage and contamination. Mixed storage of equipment of
different material and specification shall be strictly prohibited. Welding consumables shall be stored
separately, maintaining drafty and dry storage conditions. The paint and flammable chemical
T14.1 Quality Management System Page 17 of 28
PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) OFOIL
TRUNKLINE FROM WP-A TO GIFT FOR PETRONAS CARIGALI IRQA HOLDING B.V.
TENDER NO.: PCIHBV/2019/PD&T/2429
TECHNICAL PROPOSAL
material shall be stored at drafty and dry conditions and shall be kept away from fire source.
Cement shall not be stockpiled in the open air and measures shall be taken against water, moisture.
Cement beyond expiry date shall not be used. Motors and instrument device shall be stored in
room, putting in order.
For the material/equipment stored outdoor, proper support and cover shall be provided, and shall
be put in order and marked clearly with clear identification. During the storage of valve, non-
standard vessel, non-standard equipment, pumps and motors, the inlet and outlet flanges shall be
covered to prevent the damage to the flange faces or ingression of foreign materials. Thermal
insulation material, fire proof material and cable terminator shall be sealed and covered to prevent
exposing to rain, water ingression and getting most. The material/equipment in stock shall be
handled with care. Large and heavy equipment and valve shall be lifted using crane, chain block,
fork truck and trailer, taking care not to damage and scratch to the equipment.
Protection during Construction Process
Fabricated items shall be identified and stored as per classification. The fabricated piping spool
shall be internally inspected to ensure free of foreign material. The ends shall be sealed with screw
plug, blind plate or plastic sheet. Being installed instrument and electrical equipment shall be
protected carefully. Any stamping on the equipment or hanging of object is not allowed to
equipment/part which is liable to damage and deformation. The electrical and instrument boxes and
panels after installation shall be locked timely, on which no walking and operating is allowed. Care
shall be taken to protect the identifications during sand blasting and painting and to protect the
painted structural surface from any scratches and damage to the painting.
Strict protective measures shall be taken on every kind of pipe and equipment during transportation
and lifting. Care shall be taken to protect the identification area from damage, and to protect the
pipes or equipment from scratching, deforming and bumping. Reinforcing measure shall be taken if
necessary.
In case damage is found to material/equipment and project product during storage, the warehouse
supervisor, construction personnel or construction subcontractor shall inform timely the responsible
department. The material/equipment and project product will be disposed of as per stipulation after
double checking and confirming by project quality department.
T14.1.7.5 Surveillance and Measurement Device Control
The project quality department will initiate the setting up plan for surveillance and measurement
device. The plan will be reviewed and approved by project manager for device balancing or
procuring by construction and procurement departments. The accuracy and precision of the device
shall meet the project metering requirements and shall be suitable for using under the climate at
project working site. The surveillance and measurement device used by project subcontractor will
be provided as per the project requirement by the subcontractor itself.
The surveillance and measurement device used by project office and by project subcontractor shall,
prior to usage, be tested and calibrated in accordance with the requirement of international or state
measurement standards, and shall be calibrated at the frequency specified. In case of non-
availability of above standards, calibration method shall be prepared, and the calibration record
shall be made. Only those devices passing the test and calibration shall be used. The quality
department will specify the test and calibration frequency, and carry out the control and
management of the surveillance and measurement device required by the project. The surveillance
and measurement device list and calibration record shall be established to ensure the device usage
before the expiry of calibration.
In the course of use of the calibrated surveillance and measurement device, timely adjust and
manage the device as per the inspection standard from superior level or as per document self-
T14.1 Quality Management System Page 18 of 28
PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) OFOIL
TRUNKLINE FROM WP-A TO GIFT FOR PETRONAS CARIGALI IRQA HOLDING B.V.
TENDER NO.: PCIHBV/2019/PD&T/2429
TECHNICAL PROPOSAL
prepared, and make re-adjustment if deemed necessary, to prevent accuracy loss. Effective
measures shall be taken during handling, service and storage of the device to avoid any damage
and accuracy loss. Meanwhile, the device in using shall be calibrated to avoid possible accuracy
loss.
During the routine management of the device, it shall be identified to show its calibration status.
When the device is found of deviation to the calibration status, and not meeting requirements, then
the validity of the previous measurement shall be evaluated and recorded, and appropriate
measures shall be taken to the device and any products impacted by such device. At the same time,
the calibration and verification result record shall be taken
Prior to commencement of construction, each subcontractor shall submit its surveillance and
measurement device list to project quality department for review. The quality department will carry
out once every quarter supervisory inspection on the procurement of new device, usage and
calibration of existing devices, and record such inspections.
The control and execution of surveillance and measurement device shall be as per Control
Procedure for Surveillance and Measurement Device.
TECHNICAL PROPOSAL
data, as well as their collection method and process monitoring and measuring method.
Every project subcontractor and functional department shall implement the process monitoring and
measuring involved as per its own quality system operation plan, and the project quality department
will organize the supervisory check on the above once every quarter, formulating the supervisory
check record.
The project quality department shall analyze the information and data collected, and in case
nonconformance is found through surveillance, measurement and analysis, take timely corrective
measures to ensure the project product meeting the specified requirements, enhancing the level of
satisfaction by customer.
The process supervising and measuring shall be as per Control Process for Process and Product
Supervising and Measuring.
Product Supervising and Measuring
The project quality department is responsible for preparing Incoming Material/Equipment Inspection
Plan, conducting the inspection to all incoming material/equipment after the approval of the plan by
project manager.
The project procurement department is responsible for supervising and measuring the control over
the incoming material/equipment, organizing the inspection of the material/equipment. The
warehouse keeper from the procurement department will carry out the visual inspection of the
material/equipment, inspections of material, specifications, document supplied, spare parts,
package, quantity, dimension and weight, then formulate inspection record. If the above inspections
meet requirements, inform the project quality department for double check, and the project quality
department will, as per the Incoming Material/Equipment Inspection Plan, inform PCIHBV for
inspection. If accepted by PCIHBV, the warehouse will complete the formality for stocking, hence
formulating the Material/Equipment Receiving Inspection Record for filing.
In case of emergent releasing of material/equipment due to the urgent needs of the project, the
construction subcontractor will submit the application which will be reviewed by procurement
department and approved by project manager, and filed by project quality department. Such
material/equipment shall be identified by procurement as per stipulation, and record for such
releasing shall be taken. The emergent releasing is applicable to recoverable material/equipment
only.
The project quality department shall be responsible for the supervising and measuring control over
process and final product, organizing the preparation of the supervising and measuring procedures
like Quality Inspection Plan and Quality Inspection Process, which specify the hold point, witness
point, surveillance point and review point of the construction process, and list detailed requirements
for the inspection of special process.
The project quality department will, as per the stipulation on Quality Inspection Plan, organize the
process quality inspection. The subcontractor will conduct self-check and cross check on the
process quality. If accepted, inform project discipline engineer for inspection, and then request
PCIHBV’s supervisor for inspection, if necessary, formulating the inspection report signed by the
supervisor before proceeding with next process. Special supervision shall be conducted to critical
process, exercising 100% inspection.
After inspection and acceptance of underground facilities, hydro-test and air pressure test,
tightness test, motor test, and system pre-commissioning inspection, PCIHBV or supervisor shall
be requested for inspection and confirmation as per specified procedure, after which the inspection
record shall be signed off.
Upon completion of the project, the construction subcontractor shall apply for completion certificate.
T14.1 Quality Management System Page 20 of 28
PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) OFOIL
TRUNKLINE FROM WP-A TO GIFT FOR PETRONAS CARIGALI IRQA HOLDING B.V.
TENDER NO.: PCIHBV/2019/PD&T/2429
TECHNICAL PROPOSAL
The project construction department will organize the completion inspection first, then after
acceptance of the inspection, write to PCIHBV or supervisor for applying mechanical completion
certificate. Upon the completion of joint inspection and acceptance by project office and PCIHBV or
supervisor, the mechanical completion certificate will be signed, and at the same time punch list
shall be issued to construction subcontractor for clearing item by item.
Exceptional release will be applied by construction subcontractor, approved by technical deputy
general manager, and then reported to project quality department for recording. Such
material/equipment shall be identified. The project quality department shall conduct timely the
tracing inspection, and recover back the material/equipment immediately in case non-conformance
is found.
The unacceptable process shall be handled as per the stipulation on non-conformance product,
and re-submission of request for inspection after correction is done as per specified inspection
procedure.
Inspection, measurement and test device shall be calibrated and managed as per Control
Procedure for Surveillance and Measurement Device.
The project procurement department and construction subcontractor shall report monthly the
surveillance and measurement information to project quality department. Other works for project
product surveillance and measurement shall be carried out as per Control Procedure for Process
and Product Surveillance and Measurement.
T14.1.8.2 Control of Non-conformance Product
The project procurement department is responsible for the management of non-conforming
incoming material/equipment. It carries out the supervisory inspection to the non-conforming
incoming products by establishing “non-conforming incoming products record”. The project quality
department is responsible for the management of non-conforming project products. It carries out
the supervisory inspection to the non-conformance product by establishing “non-conforming
products record”.
The nonconforming incoming material/equipment inspection shall be conducted at the time of
material receiving. The procurement department shall be noticed through “non-conforming product
notification” of any non-conforming product found by quality department. The procurement
department will identify and store separately the product as per CONTRACTOR related control
procedure. The scheme to dispose of the non-conforming incoming products includes: rejection,
replacement, scrapping and claim.
The project discipline engineer shall record the non-conforming construction product in relevant
inspection record, and inform the construction subcontractor of such nonconformance through
“non-conformance product notification”. The quality inspector of the subcontractor shall analyze the
reason for the nonconformance, propose corrective measures and fill in the “non-conformance
product notification”. The correction will be carried out after approving the proposal by project
discipline engineer.
The seriousness of the non-conforming construction product is classified as three levels: slight,
normal and serous. The non-conforming product shall be re-inspected and re-tested after
modification as per requirement. Based on the actual seriousness of the non-conforming product, it
will be handled via reworking, using on less critical location/structure after repairing, requesting for
waiver, or scrapping, etc.
The detailed control and management of non-conforming project product and non-conforming
incoming material/equipment shall be as per CONTRACTOR enterprise Non-conforming Product
control procedure.
T14.1 Quality Management System Page 21 of 28
PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) OFOIL
TRUNKLINE FROM WP-A TO GIFT FOR PETRONAS CARIGALI IRQA HOLDING B.V.
TENDER NO.: PCIHBV/2019/PD&T/2429
TECHNICAL PROPOSAL
TECHNICAL PROPOSAL
Corrective Measures
Corrective measures to the following shall be taken: Non-conformance occurred during quality
system operation, serious non-conformance happening during construction; normal but repeated
non-conformance; slight but continuously happening non-conformance; PCIHBV’s complaint or
dissatisfaction.
The corrective measures for the non-conformance in quality system operation shall be prepared by
project quality department together with the department in which such non-conformance happens.
The corrective measures shall be approved by the deputy general manager in charge of quality
work, and implemented by the non-conformance sourcing department. The quality department will
be responsible for the verification work of such correction.
The corrective measures for non-conformance in material procurement shall be prepared and
implemented by procurement department, and the corrective measures shall be approved by
procurement manager. The quality department will be responsible for the verification of such
correction.
The quality department will organize the construction subcontractor to analyze the reason for the
non-conformance which happens continuously during construction, and prepare the corrective
measures which shall be approved for fulfillment by the man responsible for technique. The project
quality department will trace and verify such correction.
The quality department will organize discipline engineers to analyze the reason for the serious non-
conformance happening during construction, and prepare the corrective measures which shall be
approved by project manager. Such correction shall be traced by project quality department and
verified by project manager or technical deputy general manager.
When non-conformance happens, the project quality department shall notify, via non-conformance
notification, the party from which the non-conformance generates, who will organize the correction
of such nonconformance, formulating the “corrective measure record”.
Preventive Measures
The project office will analyze the information on quality; find out any problems to define the
measures for implementation, thus eliminating the possibility for potential non-conformance,
preventing the occurrence of non-conformance.
The project office will conduct monthly meeting to analyze the operation status of project quality
system, the status of project product quality and make the decision on taking corrective and
preventive measures.
The project quality department will inform, through “non-conformance notification”, the
department/subcontractor of the potential non-conformance, who will organize as per requirement
the analysis on the reasons for such non-conformance, and establish preventive measures. The
measures will be carried out after approval by technical deputy general manager, and the project
quality department will verify the fulfillment of the measures, and take “preventive measure record”
after verification. Such record shall be kept by quality department for filing purpose.
In the course of establishing the measures to be taken, following requirements and responsibilities
shall be made clear:
To define the potential nonconformance and analyze its causes;
To evaluate the feasibility of the measures preventing the occurrence of the non-
conformance.;
To define and carry out the measures necessary;
To record the result after taking the measures;
TECHNICAL PROPOSAL
T14.1.9 Attachments
Attachment 1: List of Procedures (parts)
Attachment 2: QA/QC Management Certificate
TECHNICAL PROPOSAL
CONTRACTOR-QA-
1 01 QUALITY PLAN
CONTRACTOR-QA-
2 02 GENERAL PROVISION OF INSPECTION AND TEST PLAN
CONTRACTOR-QA-
3 03 DOCUMENT AND DATA CONTROL
CONTRACTOR-QC-
4 01 CIVIL INSPECTION AND TEST PLAN
CONTRACTOR -QC-
5 02 PIPING QUALITY CONTROL PLAN
CONTRACTOR -QC-
6 03 STEEL STRUCTURE QUALITY CONTROL PLAN
CONTRACTOR -QC-
7 04 STATIC EQUIPMENT INSPECTION AND TEST PLAN
CONTRACTOR -QC-
8 05 ROTAING EQUIPMENT INSPECTION AND TEST PLAN
CONTRACTOR -QC-
9 06 ELECTRICAL QUALITY CONTROL PLAN
CONTRACTOR -QC-
10 07 INSPECTION AND TEST PLAN OF INSTRUMENT
CONTRACTOR -QC-
11 08 INSPECTION AND TEST PLAN FOR BLASTING AND PAINTING
CONTRACTOR -QC-
12 09 INSULATION INSPECTION AND TEST PLAN
CONTRACTOR -
13 WLD-01 WELDING CONSUMABLE CONTROL
CONTRACTOR -
14 WLD-02 WELDING PROCEDURE AND QUALITY CONTROL
TECHNICAL PROPOSAL
WLD-03
CONTRACTOR-
16 WLD-04 WELD EXAMINATION PROCEDURE
CONTRACTOR-
17 WLD-05 WELD REPAIR PROCEDURE
CONTRACTOR-
18 WLD-07 PIPING WELDING PROCEDURE
CONTRACTOR-
19 WLD-09 HOT TAPPING PROCEDURE
CONTRACTOR-PP-
PROCUREMENT MANUAL
20 01
CONTRACTOR-PP-
21 02 PURCHASING
CONTRACTOR-PP-
22 03 EXPEDITING
CONTRACTOR-PP-
23 04 INSPECTION
CONTRACTOR-PP-
24 05 TRAFFIC
CONTRACTOR-PP-
25 06 MATERIAL CONTROL
CONTRACTOR-
26 CTRU-01 PROGRESS MEASUREMENT PROCEDURE-ENGINEERING
CONTRACTOR-
27 CTRU-02 PROGRESS MEASUREMENT PROCEDURE-PROCUREMENT
CONTRACTOR-
28 CTRU-03 PROGRESS MEASUREMENT PROCEDURE-CONSTRUCTION
CONTRACTOR-
29 CTRU-04 WORK BREAKDOWN STRUCTURE
CONTRACTOR-
30 CTRU-05 COMMISSIONING PROCEDURE
CONTRACTOR-
31 CTRU-06 OPERATING AND MAINTANCE MANUAL
CONTRACTOR-
32 CTRU-07 COMMISSIONING PROCEDURE
T14.1 Quality Management System Page 26 of 28
PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) OFOIL
TRUNKLINE FROM WP-A TO GIFT FOR PETRONAS CARIGALI IRQA HOLDING B.V.
TENDER NO.: PCIHBV/2019/PD&T/2429
TECHNICAL PROPOSAL
CONTRACTOR-
33 CTRU-08 OPERATING AND MAINTENANCE MANUAL
TECHNICAL PROPOSAL