Professional Documents
Culture Documents
MALAYSIA
BETWEEN
(1164231-M)
AND
BETWEEN
AND
1
[2020] 1 LNS 24 Legal Network Series
GROUNDS OF DECISION
Brief background
[1] In April 2016, the Government of Malaysia and the Sabah State
Government appointed BORNEO HIGHWAY PDP SDN BHD
(BORNEO HIGHWAY) as the Project Delivery Partner to carry
out the implementation of Phase 1 of the Pan Borneo Highway
Sabah project.
2
[2020] 1 LNS 24 Legal Network Series
Progress Claim No. 4 (the claim for tree cutting) which was not
certified or under-certified. For the said claim, the adjudicator
ordered BORNEO HIGHWAY to pay within 14 days the sum of
RM2,811,560.00, interest and costs.
[8] For good sense, both parties are ad idem that the setting
aside/stay application should be heard first followed by the
enforcement application as was done in the case of Skyworld
Development Sdn Bhd v. Zalam Corporation Sdn Bhd & Other
Cases [2019] 3 MLRH 143.
3
[2020] 1 LNS 24 Legal Network Series
(a) BORNEO HIGHWAY has not stated the full name of the
Adjudicator in the intitulement of their Originating
Summons for the setting aside/stay application. BORNEO
HIGHWAY only stated in the intitulement, the name of the
Adjudicator as “R. Jayasingam” instead of his full name,
“R. Jayasingam A/L Ratnasingam”; and
[11] I do not need to deal with the ground (d) of the preliminary
objects as counsel for INTAN MARUDU in his submission
informed that he is not pursuing on this ground in view of the
Federal Court decision in View Esteem Sdn Bhd v. Bina Puri
Holdings Bhd [2018] 1 MLRA 460. Federal Court in that case
decided that it is not improper for application to stay an
4
[2020] 1 LNS 24 Legal Network Series
[13] INTAN MARUDU was not alleging there were other payment
disputes adjudicated by different adjudicators whether on the
same or different dates and whether in the same adjudication
proceedings so as to render it confused and unable to ascertain
which adjudication decision and by which adjudicator this
setting/stay application is concerning.
[16] INTAN MARUDU was also not alleging that they are confused
as to what the application is about and misled in anyway. Thus, I
do not find the failure to state Order 69A of the Rules of Court,
2012 in the intitulement of the Originating Summons for the
5
[2020] 1 LNS 24 Legal Network Series
6
[2020] 1 LNS 24 Legal Network Series
7
[2020] 1 LNS 24 Legal Network Series
8
[2020] 1 LNS 24 Legal Network Series
[34] The strict timeline as provided under Section 12 (c) and 12(d) of
CIPAA for the adjudicator to deliver his/her decision shows the
legislative intention on the speed required of the adjudicator to
deliver his/her decision and to make such decision enforceable
in the interim for resolving the payment disputes of the parties
in a construction contract pending the final determination of the
payment disputes by arbitration, litigation or agreement.
[35] Given the strict and restrictive legislative timeline to deliver the
adjudication decision, the adjudicator cannot be expected to give
reasons for the adjudication decision with the
comprehensiveness as expected of judgment made by Court or
award of arbitrator.
9
[2020] 1 LNS 24 Legal Network Series
10
[2020] 1 LNS 24 Legal Network Series
[37] The principles that can be discerned from that case for
determination of the adequacy or sufficient of reasons given the
adjudicator are:
(c) The reasons given may be succinct and they are enough or
sufficient when they show that the adjudicator has dealt
with the very issues remitted to him/her and what his/her
conclusions are on those issues;
11
[2020] 1 LNS 24 Legal Network Series
[41] INTAN MARUDU’s case was that the claim for tree cutting as
the additional or variation works totalling RM2,811,560.00 was
calculated based on the rates as provided under item 5.2 of the
BQ for felling trees (provisional items). BORNEO HIGHWAY
had requested the claimant to transport these trees to the port
designated and obtained possession of them and thus, BORNEO
12
[2020] 1 LNS 24 Legal Network Series
[43] This was as defined under item 2.1.1.1 (Site Clearing) in Section
2 - Earthworks, the Standard Specification of the Contract of the
contract documents (page 351 of exhibit “MF-12” of the
Affidavit In Support of Muhammad Fadzil Bin Abdul Hamid
affirmed on 10-5-2019 [Encl.2]). BORNEO HIGHWAY
contended that they were not additional or variation works and
could not be claimed as such.
13
[2020] 1 LNS 24 Legal Network Series
14
[2020] 1 LNS 24 Legal Network Series
[51] The Adjudicator in this case identified four (4) issues he set out
(See: paragraph 47 therein) including Issue No.2 in respect of
the claim for tree cutting for his determination.
[53] In respect of the claim for tree cutting (Issue No.3) and after
setting out the summary of the rival contentions of the parties
(paragraphs 55 and 56 therein), the adjudicator then stated in
paragraph 57 of the Adjudication Decision, that:
15
[2020] 1 LNS 24 Legal Network Series
16
[2020] 1 LNS 24 Legal Network Series
[60] The Adjudicator had indeed stated that he was not persuaded by
the BORNEO HIGHWAY’s interpretation of item 5.2 of the BQ
nor the alternative calculations it provided in the Adjudication
Response. It is apparently that he preferred INTAN MARUDU’s
version of the case and their interpretation of the related items
of BQ and reasoning or found them more probable.
17
[2020] 1 LNS 24 Legal Network Series
[65] In SKS Pavillion Sdn Bhd v. Tasoon Injection Pile Sdn Bhd
[2019] MLJU 1051, similarly, the adjudicator had preferred and
accepted the defendant’s version of the case in respect of an
item of claim for loss and expense under a construction contract.
The plaintiff in case also sought to set aside the adjudication
decision on the ground that the reasons given by the adjudicator
were incoherent and unintelligible. The Court held the
plaintiff’s grounds to be without substance and that the
plaintiff’s should not be allowed to vent its dissatisfaction on
the pretext that the adjudicator’s reasons were unintelligible.
18
[2020] 1 LNS 24 Legal Network Series
19
[2020] 1 LNS 24 Legal Network Series
20
[2020] 1 LNS 24 Legal Network Series
[76] That being the case, I do not find any substance in BORNEO
HIGHWAY’s grounds that there were a denial of natural justice
under Section 15 (b) and/or that the Adjudicator has acted in
excess of his jurisdiction under Section 15(d) of CIPAA 2012 to
sustain BORNEO HIGHWAY’s application to set aside the
Adjudication Decision.
21
[2020] 1 LNS 24 Legal Network Series
[79] In View Esteem Sdn. Bhd. v. Bina Puri Holdings Bhd [2019] 5
CLJ 479, the Federal Court held that it is not right to restrict
exercise of the statutory power to stay Adjudication Decision by
confining consideration on the financial status of the other
party.
[81] Federal Court also accepted that a stay of the adjudication award
ought not to be given readily and caution must be exercised
when doing so.
22
[2020] 1 LNS 24 Legal Network Series
23
[2020] 1 LNS 24 Legal Network Series
24
[2020] 1 LNS 24 Legal Network Series
25
[2020] 1 LNS 24 Legal Network Series
26
[2020] 1 LNS 24 Legal Network Series
27
[2020] 1 LNS 24 Legal Network Series
High Court
Kota Kinabalu
COUNSEL:
For the defendant - Norbert Yapp; M/s Norbert Yapp & Associates
Advocates & Solicitors
Kota Kinabalu
View Esteem Sdn Bhd v. Bina Puri Holdings Bhd [2018] 1 MLRA 460
28
[2020] 1 LNS 24 Legal Network Series
Bouygues (UK) Ltd v. Dahl-Jensen (UK) Ltd. [2000] EWCA Civ. 507
Engineering & Construction Sdn. Bhd. v. Esstar Vision Sdn. Bhd &
anor. [2016] 1 LNS 1522
Econpile (M) Sdn. Bhd. v. IRDK Ventures Sdn. Bhd. & anor [2016] 5
CLJ 882
Ranhill E & C Sdn Bhd v. Tioxide (Malaysia) Sdn Bhd & Other Cases
[2016] 5 MLRH 472
SKS Pavillion Sdn Bhd v. Tasoon Injection Pile Sdn Bhd [2019] MLJU
1051
View Esteem Sdn. Bhd. v. Bina Puri Holdings Bhd [2019] 5 CLJ 479
United Asian Bank Bhd. v. Hong Huat Realty (M) Sdn. Bhd [1986] 2
MLRH 61
United Asian Bank Bhd. v. Hong Huat Realty (M) Sdn. Bhd [1986] 2
MLRH 61
Mecomb Malaysia Sdn Bhd v. VST M&E Sdn Bhd [2018] 8 CLJ 380
Econpile (M) Sdn Bhd v. LRDK Ventures Sdn Bhd [2016] 1 LNS 581
29
[2020] 1 LNS 24 Legal Network Series
Subang Skypark Sdn Bhd v. Arcradius Sdn Bhd [2015] 10 CLJ 801
Econpile (M) Sdn Bhd v. LRDK Ventures Sdn Bhd [2016] 1 LNS 581
Subang Skypark Sdn Bhd v. Arcradius Sdn Bhd [2015] 10 CLJ 801
30