Material Supply Requisition
ALBROUJ VILLAS
Project Name: MSR No: 499
PARCEL 1.3.1
Exhaust Fan
20 عدد 1
50 LPS of air flow, and 0.100 kPa
22 6 ألنكيه عدد 2
2:- Quantity according to BOQ 7:- (6)+(7) is not greater than (5) 3- All transferred materials will be 50% discounted
3:- Quantity according to QS from T.O. 8:- MSR should be issued before 14 days from the required date on site 4- Inventory dept. to provide its feedback within 1 or 2 working days , then PM approval and to Purchasing to proceed
4:- Waste according to latest approved budget 9:- Final quantity for purchasing to proceed 5- PM should reapprove this form especially if there is a suggested Equivalent materials
5:- Total Project Planned Quantity including waste = (2 or 3) + 4