A change has been proposed to the proj ect scope. Y ou have routed the change Answer: B
through the change control system as pl anned. Y ou need to exami ne cost, ti me, H i nt: I t al l works together.
qual i ty, human resources, communi cati ons, ri sks, and procurement when exami ni ng Ref erence: PM P Study Gui de, Chapter 4
the proposed change. Y our manager wants to know why al l of these areas must be Study Gui de Obj ecti ve: D evel op Change M anagement Pl an
exami ned. I n regard to the proposed change, what are you doi ng by exami ni ng each B i s correct. T hi s i s part of i ntegrated change control .
proj ect area? A i s i ncorrect because conf i gurati on management doesn’t f ul l y answer the
A. Conf i gurati on management questi on. C i s i ncorrect because scope change control i s part of i ntegrated change
B. I ntegrated change control control . I n thi s questi on, you are exami ni ng the i mpact of a change on al l
C. Scope change control knowl
Answer: edge
C areas. D i s i ncorrect because whi l e thi s may qual i f y as ef f ecti ve
A group of executi ves, subj ect matter experts, stakehol ders, and managers that
D . E f f ecti ve proj ect management proj ect management
H i nt: I t’s the death procedures, i ntegrated
of many potenti change control more f ul l y answers the
al proj ects.
convene to ask questi ons about a potenti al proj ect, i ts val ue, and l i kel i hood of
questi on. PM P Study Gui de, Chapter 4
Ref erence:
success to determi ne whi ch proj ects shoul d be i ni ti ated i s cal l ed what?
A. A change control board Study Gui de Obj ecti ve: Conduct Proj ect Sel ecti on M ethods

B. A proj ect steeri ng commi ttee C i s correct. M urder boards are a method that management can use to determi ne

C. A murder board whi ch proj ect i s most l i kel y to succeed.

D . A techni cal revi ew board A i s i ncorrect because a change control board eval uates proposed changes to an
exi sti ng proj ect. B i s i ncorrect because a proj ect steeri ng commi ttee may be used
to hel p C
Answer: the proj ect manager make deci si ons wi thi n an exi sti ng proj ect. D i s
A maj or component of proj ect pl anni ng and management i s the proj ect’s work iHncorrect
i nt: N o because a techni cal revi ew board, si mi l ar to a change control board,
rakes needed.
breakdown structure. T he smal l est i tem i n the WBS i s cal l ed what? revi erence:
Ref ews techni
PMcal changes
P Study Guito
de,anChapter
exi sti ng5proj ect.
A. A l eaf obj ect Study Gui de Obj ecti ve: Create the WBS
B. A task C i s correct. T he smal l est i tem i n the WBS i s cal l ed the work package.
C. A work package A i s i ncorrect because thi s i s not a val i d term. B i s i ncorrect because a task i s the
D . A del i verabl e actual work, not the smal l est i tem i n the WBS. D i s i ncorrect because a
del i verabl e does not accuratel y def i ne what the smal l est i tem i n the WBS i s.

A proj ect has j ust f i ni shed the f i nal work packages. M anagement has deemed that Answer: B
thi s proj ect i s a f ai l ure because the proj ect came i n l ate and over budget. H i nt: N ot a l esson.
M anagement wants to know why the proj ect has f ai l ed. Whi ch cl osi ng process can Ref erence: PM P Study Gui de, Chapter 4
answer management’s questi on? Study Gui de Obj ecti ve: Obtai n F i nanci al , Legal , and Admi ni strati ve Cl osure
A. Scope veri f i cati on B i s correct because admi ni strati ve cl osure does i ncl ude anal yz i ng proj ect
B. Admi ni strati ve cl osure success and f ai l ure.
C. Lessons Learned A i s i ncorrect because scope veri f i cati on veri f i es the proj ect del i verabl es. C i s
D . Contract cl oseout i ncorrect because l essons l earned i s part of admi ni strati ve cl osure, whi ch answers

A proj ect manager i s compl eti ng a proj ect to bui l d a new condo. H e needs to thi s questi
Answer: C on more compl etel y. D i s i ncorrect because there’s no evi dence that a
conf i rm that any f i el d drawi ngs by the archi tect match the of f i ce drawi ngs that contract
H i nt: Go was
confeven used i n thi s proj ect. I n addi ti on, A answers the questi on.
i gure.
wi l l go i nto the proj ect archi ves. Whi ch proj ect management system ensures that Ref erence: PM P Study Gui de, Chapter 5
changes to the proj ect scope and the product scope are thoroughl y consi dered Study Gui de Obj ecti ve: D evel op Change M anagement Pl an
and documented? C i s correct. T he conf i gurati on management system ensures that requested changes
A. T he change control system to the proj ect scope and the product scope are thoroughl y consi dered and
B. T he i ntegrated change control process documented.
C. T he conf i gurati on management system A i s i ncorrect because i t does not f ul l y answer the questi on. B i s i ncorrect
D . T he communi cati on management system because
Answer: Cthe conf i gurati on management system processes happen bef ore i ntegrated
A proj ect team compri sed of peopl e that spend l i ttl e or no ti me meeti ng f ace to change
H i nt: Vicontrol
rtual l y.possi
D i s bl
i ncorrect
e. because thi s term i s not appl i cabl e to thi s scenari o.
f ace i s known as what? Ref erence: PM P Study Gui de, Chapter 9
A. A dysf uncti onal proj ect team Study Gui de Obj ecti ve: M anage Resource Al l ocati on
B. A non-col l ocated proj ect team C i s correct because vi rtual teams are compri sed of peopl e that don’t spend much
C. A vi rtual proj ect team ti me worki ng f ace to f ace wi th other proj ect team members.
D . An E -team A and D are i ncorrect because these terms are not val i d. B i s i ncorrect because
thi s descri bes a proj ect team that i s not al l l ocated i n one l ocal e.

A proj ect team has j ust compl eted the f i nal work packages f or a proj ect. T he Answer: A

proj ect manager needs to f i nd the f i nal CPI f or the proj ect. T he BAC was H i nt: T he proj ect work i s 100 percent compl ete.

$250,000, but the actual costs came i n at $286,000. What’s the f i nal CPI ? Ref erence: PM P Study Gui de, Chapters 4 and 7

A. .87 Study Gui de Obj ecti ve: Obtai n F i nanci al , Legal , and Admi ni strati ve Cl osure

B. $286,000 A i s correct because the CPI i s f ound through the f ormul a E V/AC. I n thi s i nstance,

C. -$36,000 the E V i s $250,000, whi ch i s 100 percent of the BAC because the proj ect i s

D . T he earned val ue i nf ormati on i s needed to answer thi s questi on. compl ete.
B i s i ncorrect because thi s i s the f i nal AC f or the proj ect. C i s i ncorrect because

A vendor has proposed a change to the work you’ve contracted them to do f or your thi s i s the
Answer: D cost vari ance f or the proj ect. D i s i ncorrect because the E V i nf ormati on
proj ect. T he vendor says i t i s because of the hardware i nstal l ed on your company’s i sisuppl
H nt: Add i edi t.i n the questi on.

server. Y our hardware techni ci an says thi s i s not true, that the hardware Ref erence: PM P Study Gui de, Chapter 4
i nstal l ati on i s accurate and there i s no need f or the change. What shoul d you do Study Gui de Obj ecti ve: Veri f y and M anage Changes to the Proj ect
wi th the proposed change? D i s correct because thi s i s a proposed change. I t shoul d be documented and
A. D i scard the change request and ask the vendor to conti nue as pl anned. revi ewed f or consi derati on. Just because the change i s consi dered doesn’t mean
B. Accept the vendor’s proposed change because i t’s thei r contract to compl ete that i t wi l l necessari l y be i mpl emented.
the work. A i s i ncorrect because di scardi ng the change of f ers no documentati on i n case the
C. E nter the change request i nto the SOW update f or consi derati on. change i s actual l y needed. B i s i ncorrect because the change shoul d be added
PMP Exam Practice Test And Study Guide
Study this set o nline at: https://www.cram.co m/flashcards/pmp-exam-practice-test-
and-study-guide-56 32748
Answer: D
Al l of the f ol l owi ng are accompl i shed duri ng the proj ect ki ck-of f meeti ng except H i nt: N ot yet.
f or whi ch one? Ref erence: PM P Study Gui de, Chapter 1
A. T he proj ect organi z ati on i s expl ai ned. Study Gui de Obj ecti ve: Conduct Ki ck-Of f M eeti ng
B. T he proj ect goal s are def i ned. D i s correct because ri sk does not happen unti l l ater i n the proj ect pl anni ng
C. T he proj ect obj ecti ves are i denti f i ed. process.
D . T he proj ect ri sks are exami ned. A, B, and C are i ncorrect because al l of these are true statements about the
proj ect ki ck-of f meeti ng.

Al l of the f ol l owi ng are desi red outcomes of the proj ect ki ck-of f meeti ng except Answer: D
f or whi ch one? H i nt: N o naggi ng.
A. Provi de cl ari f i cati ons on the proj ect goal s and obj ecti ves. Ref erence: PM P Study Gui de, Chapter 1
B. Al l ow the team and stakehol ders to know the poi nts of contact wi thi n the Study Gui de Obj ecti ve: Conduct Ki ck-Of f M eeti ng
proj ect team. D i s correct because the ki ck-of f meeti ng i s not the pl ace f or thi s di scussi on.
C. Learn how the current proj ect may i nteract wi th other proj ects. A, B, and C are i ncorrect because al l of these are desi red outcomes of the proj ect
D . Al l ow the proj ect team to voi ce concerns and obj ecti ons about the proj ect ki ck-of f meeti ng
scope.

Al l of the f ol l owi ng are true statements about the staf f i ng management pl an Answer: D
except f or whi ch one? H i nt: I sn’t there another pl an f or thi s one?Ref erence: PM P Study Gui de, Chapter
A. T he staf f i ng management pl an provi des i nf ormati on about when proj ect team 9Study Gui de Obj ecti ve: I mprove T eam Perf ormance
members may be rel eased f rom the proj ect team. D i s correct because thi s i s a f al se statement about the staf f i ng management pl an.
B. T he staf f i ng management pl an provi des i nf ormati on about staf f acqui si ti on. T he qual i ty management pl an def i nes qual i ty expectati ons.
C. T he staf f i ng management pl an provi des i nf ormati on about proj ect saf ety. A, B, and C are i ncorrect because each i s a true statement about the staf f i ng
D . T he staf f i ng management pl an provi des i nf ormati on about proj ect qual i ty. management pl an.

Answer: A
Al l of the f ol l owi ng statements are f al se about the proj ect ki ck-of f meeti ng
H i nt: T he team i s there.
except f or whi ch one?
Ref erence: PM P Study Gui de, Chapter 1
A. T he proj ect ki ck-of f meeti ng i s a team-bui l di ng exerci se.
Study Gui de Obj ecti ve: Conduct Ki ck-Of f M eeti ng
B. Onl y the proj ect team members shoul d attend the proj ect ki ck-of f meeti ng.
A i s correct because thi s i s a true statement about the proj ect ki ck-of f meeti ng.
C. T he proj ect ki ck-of f meeti ng i s l ed by the proj ect sponsor.
B, C, and D are i ncorrect because al l of these are f al se statements about the
D . T he proj ect ki ck-of f meeti ng i s hel d duri ng scope veri f i cati on.
proj ect ki ck-of f meeti ng.

Al l proj ect managers shoul d set expectati ons f or the qual i ty of the proj ect. T hese Answer: D

expectati ons shoul d be cl earl y def i ned as part of the qual i ty management pl an. H i nt: N ot Spock!

Al l of the f ol l owi ng are qual i ty pl anni ng tool s except f or whi ch one? Ref erence: PM P Study Gui de, Chapter 8

A. F orce f i el d anal ysi s Study Gui de Obj ecti ve: E nsure Proj ect D el i verabl es Conf orm to Qual i ty

B. F l owcharts Standards

C. Brai nstormi ng D i s correct because i nspecti on i s a qual i ty control tool , not a qual i ty pl anni ng

D . I nspecti on tool . Y ou’l l i nspect the resul ts of the proj ect work wel l af ter the qual i ty pl anni ng
occurs.
A i s i ncorrect
Answer: C because thi s i s an exampl e of a qual i ty pl anni ng tool . B i s i ncorrect
because
H i nt: I t’s not iasthreshol
thi s an exampl
d.e of a qual i ty pl anni ng tool . C i s i ncorrect because thi s
An organi z ati on’s wi l l i ngness to accept ri sk i s known as what?
iRef
s an examplPM
erence: e ofP aStudy
qual iGui
ty pl
de,anni ng tool11
Chapter .
A. T he entrepreneuri al spi ri t
B. An autocrati c bel i ef Study Gui de Obj ecti ve: M oni tor Al l Ri sks

C. T he uti l i ty f uncti on C i s correct because the uti l i ty f uncti on i s the term used to descri be an

D . Ri sk threshol d organi z ati on’s wi l l i ngness to accept ri sk.


A i s i ncorrect because thi s term i s not val i d. B i s i ncorrect because thi s descri bes
proj ect management l eadershi p, not ri sk. D i s i ncorrect because the term

As a PM P candi date, you shoul d recogni z e the di f f erent methods an organi z ati on descri bes a condi ti on that a ri sk event i s pendi ng or has come to f rui ti on.
Answer: D
can use to sel ect proj ects. Benef i ts compari son i s the most common approach to H i nt: I t’s a mathemati cal model .
sel ect proj ects, but constrai ned opti mi z ati on, a more speci al i z ed approach to Ref erence: PM P Study Gui de, Chapter 4
proj ect sel ecti on, i s al so used by organi z ati ons. Whi ch one of the f ol l owi ng i s an Study Gui de Obj ecti ve: Conduct Proj ect Sel ecti on M ethods
exampl e of constrai ned opti mi z ati on? D i s correct. Li near programmi ng i s a mathemati cal model —an exampl e of
A. N et present val ue constrai ned opti mi z ati on.
B. F uture val ue A, B, and C are i ncorrect. T hey are exampl es of benef i t compari sons.
C. Benef i t/cost rati os
D . Li near programmi ng
As a proj ect manager, you have to document the constrai nts wi thi n your proj ect Answer: A
team. Al l proj ects have the T ri pl e Constrai nts of Proj ect M anagement, whi ch i s H i nt: I t’s the I ron T ri angl e of proj ect management.
made up of whi ch three f actors? Ref erence: PM P Study Gui de, Chapter 1
A. T i me, cost, and scope Study Gui de Obj ecti ve: D ocument Proj ect Ri sks, Assumpti ons, and Constrai nts
B. T i me, cost, and qual i ty A i s correct. T i me cost and scope are the T ri pl e Constrai nts of Proj ect
C. Cost, schedul e, and stakehol ders M anagement.
D . T i me, scope, and qual i ty B, C, and D are i ncorrect because none of these def i ne the T ri pl e Constrai nts.
PMP Exam Practice Test And Study Guide
Study this set o nline at: https://www.cram.co m/flashcards/pmp-exam-practice-test-
and-study-guide-56 32748
As a proj ect manager, you may rel y on organi z ati onal theori es to hel p you better Answer: C

manage the proj ect team. Whi ch organi z ati onal theory bel i eves that an absence H i nt: N ot an ouchi e.Ref erence: PM P Study Gui de, Chapter 9Study Gui de

of hygi ene agents wi l l demoti vate a proj ect team? Obj ecti ve: I mprove T eam Perf ormance

A. M asl ow’s H i erarchy of N eeds C i s correct because H erz berg’s T heory of M oti vati on states that hygi ene agents,

B. Ouchi ’s T heory Z such as a paycheck, won’t moti vate peopl e, but thei r absence wi l l demoti vate.

C. H erz berg’s T heory of M oti vati on A i s i ncorrect because M asl ow’s H i erarchy of N eeds i denti f i es the seven needs

D . M cGregor’s X and Y we al l pursue. B i s i ncorrect because Ouchi ’s T heory Z i s based on the Japanese
management styl e. D i s i ncorrect because M cGregor’s X and Y i s a descri pti on of

As part of your constructi on proj ect, there are several standards and regul ati ons management’s
Answer: D vi ew of i ts empl oyees. T he X bel i eve that proj ect team members

that you must accommodate i n the proj ect work. What i s the di f f erence between a must
H i nt: D on’t go to j ai l . T he Y bel i eve that proj ect team members can be sel f -l ed.
be mi cromanaged.

standard and a regul ati on? Ref erence: PM P Study Gui de, Chapter 1
A. Standards and regul ati ons are essenti al l y the same. Study Gui de Obj ecti ve: E nsure Proj ect D el i verabl es Conf orm to Qual i ty
B. Standards are determi ned by the Organi z ati on f or I nternati onal Standards, whi l e Standards
regul ati ons are speci f i c to each i ndustry. D i s correct because standards are gui del i nes, whi ch are opti onal , whi l e
C. Standards are opti onal , whi l e regul ati ons vary by i ndustry. regul ati ons are never opti onal .
D . Standards are opti onal , whi l e regul ati ons are not. A, B, and C are i ncorrect because each i s a f al se statement about regul ati ons and
standards.
Answer: C
Assumpti ons must be i denti f i ed and documented as part of proj ect pl anni ng.
Whi ch one of the f ol l owi ng i s an assumpti on? H i nt: Wai t f or the sunshi ne.

A. T he proj ect must be compl eted by N ovember 1. Ref erence: PM P Study Gui de, Chapter 6

B. T he proj ect must cost l ess than $250,000. Study Gui de Obj ecti ve: D ef i ne and Record Requi rements, Constrai nts, and

C. T he proj ect must be compl eted i n the summer because the weather i s better. Assumpti ons

D . T he proj ect must be compl eted by the end of the year because of a new C i s the best choi ce because weather i s a typi cal exampl e of an assumpti on.

regul ati on. A i s i ncorrect because thi s i s an exampl e of a ti me constrai nt. B i s i ncorrect
because thi s i s an exampl e of a cost constrai nt. D i s i ncorrect because thi s i s an
external
Answer: Bconstrai nt.
Based on the f ol l owi ng tabl e, what i s the H i nt: Y ou don’t get i t al l .
needed conti ngency reserve? Ref erence: PM P Study Gui de, Chapter 11
A. -11,600 Study Gui de Obj ecti ve: M oni tor Al l Ri sks
B. 11,600 B i s correct because the conti ngency reserve i s f ound by mul ti pl yi ng the
C. 4000 probabi l i ty ti mes the i mpact. T he sum of the expected monetary val ue equates, i n
D . 120 percent of the proj ect budget posi ti ve numbers, to the amount of the conti ngency reserve.
A i s i ncorrect because thi s i s a negati ve number. T he conti ngency reserve i s a
posi ti veBnumber. C i s i ncorrect because thi s i s an i ncorrect cal cul ati on f or the
Answer:
Because change can have a si gni f i cant i mpact on a proj ect’s success, there must
conti
H i nt:ngency reserve. D i s i ncorrect because thi s statement i s f al se.
N ot ri sk.
be a documented approach to change management f or the proj ect scope. Whi ch
pl an documents the proj ect scope change control system? Ref erence: PM P Study Gui de, Chapter 5

A. T he proj ect management pl an Study Gui de Obj ecti ve: D evel op Change M anagement Pl an

B. T he proj ect scope management pl an B i s correct. T he Proj ect scope management pl an documents the proj ect scope

C. T he change control system change control system.

D . T he ri sk response pl an A i s i ncorrect because i t i s too broad and does not answer the questi on as
compl etel y as B. C i s i ncorrect because thi s i s the system f or managi ng changes. D

Benj ami n’s proj ect i s to bui l d a new bri dge over a smal l creek. T he government iAnswer:
s i ncorrect
C because thi s documents ri sk responses.
l eaders want the bri dge to be compl eted as soon as possi bl e because of the H i nt: T hey are not ri sky.
economi c i mpact the constructi on wi l l have on the busi nesses i n the communi ty. An Ref erence: PM P Study Gui de, Chapter 5
envi ronmental group, however, has concerns that the bri dge wi l l di srupt the nature Study Gui de Obj ecti ve: I denti f y and Perf orm Stakehol der Anal ysi s
and ecol ogi cal f actors surroundi ng the creek. T he envi ronmental group i s C i s correct. T he envi ronmental group i s a negati ve stakehol der because thei r
demandi ng addi ti onal testi ng, surveys, and anal ysi s bef ore the proj ect can concerns may i mpede the success and progress of Benj ami n’s proj ect.
conti nue. T he envi ronmental group i s whi ch one of the f ol l owi ng i n thi s i nstance? A i s i ncorrect because i t i s too vague. A stakehol der i s anyone who has an i nterest
A. Stakehol der i n the proj ect’s outcome and may be af f ected by the proj ect work. B i s i ncorrect
B.
BethPosi
i stiave stakehol
proj der f or her organi z ati on and she’s j ust been assi gned a new
ect manager because
Answer: Da posi ti ve stakehol der wants the proj ect to move f orward as qui ckl y as
C.
proj ect. T hi s proj ect der
N egati ve stakehol has a deadl i ne of M ay 15 and a budget of $250,000. A possi
H i nt:bl
I t e. D i scts.
restri i ncorrect because a ri sk owner i s a person that owns and i s
D . Ri
proj sk wi
ect owner
th a budget that must not exceed $250,000 i s an exampl e of whi ch one responsi
Ref bl ePM
erence: f orPa Study
proj ectGui
ri sk.
de, Chapter 5
of the f ol l owi ng? Study Gui de Obj ecti ve: D ocument Proj ect Ri sks, Assumpti ons, and Constrai nts
A. Assumpti on D i s correct. A constrai nt i s anythi ng that l i mi ts the team’s opti ons. N ote that the
B. Ri sk deadl i ne of M ay 15 i s al so an exampl e of a constrai nt.
C. M anagement di screti on A i s i ncorrect because an assumpti on i s anythi ng bel i eved to be true, but not
D . Constrai nt proven to be true. B i s i ncorrect because ri sk i s a potenti al event that has a
posi ti veBor negati ve ef f ect on the proj ect’s outcome. C i s i ncorrect because thi s
Answer:
Betsy i s the proj ect manager of the JGB Proj ect f or her organi z ati on. She woul d
team
H i nt: iHs ow
not much?
appl i cabl e.
l i ke to sol i ci t seven vendors f or a pri ce to suppl y 1000 f i xtures f or her proj ect.
What type of a document woul d Betsy i ssue to the vendors i n thi s scenari o? Ref erence: PM P Study Gui de, Chapter 12

A. A request f or proposal Study Gui de Obj ecti ve: I mpl ement the Procurement of Proj ect Resources

B. A request f or quote B i s correct because a request f or quote onl y wants a f ee f or the procured goods or

C. A request f or i nf ormati on servi ces.

D . An i nvi tati on f or a bi dders’ conf erence A i s i ncorrect because a request f or proposal wants i deas and suggesti ons on how
to compl ete the work. C i s i ncorrect because a request f or i nf ormati on i s aski ng
the vendor to provi de i nf ormati on on thei r goods or servi ces. D i s i ncorrect because
PMP Exam Practice Test And Study Guide
Study this set o nline at: https://www.cram.co m/flashcards/pmp-exam-practice-test-
and-study-guide-56 32748
Bob i s a proj ect manager i n a f uncti onal organi z ati on. H e di sagrees wi th the Answer: A
proj ect sponsor on how some acti vi ti es of the proj ect shoul d commence. T he H i nt: N o f un f or the proj ect manager.Ref erence: PM P Study Gui de, Chapter
proj ect sponsor, however, i nsi sts that Bob have the proj ect team begi n worki ng on 2Study Gui de Obj ecti ve: I mpl ement Approved Acti ons and Workarounds
the proj ect. What shoul d Bob do? A i s correct because the proj ect sponsor i s i n charge i n a f uncti onal organi z ati on.
A. I nstruct the proj ect team to begi n worki ng on the proj ect. I n addi ti on, i t’s permi ssi bl e to have di sagreements regardi ng the proj ect work as
B. Obj ect to the proj ect sponsor’s manager. l ong as the di sagreements don’t hi nder the proj ect f rom movi ng f orward.
C. D ocument the di sagreements i n a f ormal report f or l essons l earned when the B i s i ncorrect because Bob i s operati ng i n a f uncti onal organi z ati on. C i s i ncorrect
proj ect f ai l s. because there’s no reason f or Bob to document the i ssues i n a f ormal report. I n
D . I nstruct
Charl es, thethe proj ect fteam
carpenter or thetoXH
work onlect,
G proj y on cri
hastimade
cal path acti vito
a change ti es.
the wood f l oor addi
Answer:ti on,
B thi s answer i mpl i es that the proj ect wi l l f ai l whi l e the questi on does
he’s i nstal l i ng. H e deci ded that the f l oor shoul d be i nstal l ed at an angl e not
H i nt: I t’s the
stress not magni
good.tude of the probl em or di sagreement. D i s i ncorrect because
because of a doorway i n the l i vi ng room. Y ou i nspect the i nstal l ed wood f l oor and the proj ect PM
Ref erence: team shoul dGui
P Study work
de,on the acti
Chapter 4 vi ti es as pl anned, not onl y the acti vi ti es
agree wi th hi s deci si on. T hi s i s an exampl e of whi ch one of the f ol l owi ng? on the Gui
Study cri tide
calObj
path.
ecti ve: Veri f y and M anage Changes to the Proj ect
A. E xpert j udgment B i s correct because the change was made by Charl es on hi s own accord. T he
B. I nef f ecti ve change control change control system was not f ol l owed.
C. Correcti ve acti on A i s i ncorrect because expert j udgment i s usi ng an expert to hel p make the best
D . Sel f -l ed teams deci si on. N o consul tati on was done on the change. C i s i ncorrect because

Congratul ati ons! Y ou’ve f i ni shed the proj ect work and are perf ormi ng qual i ty correcti
Answer: C ve acti on i s correcti ng a probl em to get the proj ect work back i nto scope.

control . Y ou are about to enter scope veri f i cati on and management woul d f i rst D i s i ncorrect because
H i nt: Y ou better Charl es di d not consul t, document, or i nvol ve the proj ect
have both.
l i ke to exami ne al l of the changes that have been requested and thei r status. team
Ref i n hi s PM
erence: deci
P siStudy
on. Gui de, Chapter 4

M anagement wants to see whi ch changes have been approved and decl i ned. Where Study Gui de Obj ecti ve: I mpl ement Approved Changes
can you f i nd al l of thi s i nf ormati on? C i s correct because the Conf i gurati on M anagement System i ncl uded the process
A. Y ou wi l l onl y have records of the change requests that have been approved as f or submi tti ng, tracki ng, revi ewi ng, and approvi ng proposed changes.
decl i ned change requests are di scarded. A and B are i ncorrect because you wi l l keep decl i ned and approved change
B. Y ou wi l l onl y have records of the change requests that have been decl i ned requests. D i s i ncorrect because thi s i s not rel evant wi th change request tracki ng.
because al l approved
D uri ng scope changes
def i ni ti on, Robert,arethe
i ncorporated i nto theder,
CE O and stakehol projdemands
ect scopethat
and the
the Answer: A
ti meect
proj andobtai
cost nbasel
customeri nes sati
are updated.
sf acti on to be successf ul . What i s the danger i n thi s H i nt: T ry to measure customer sati sf acti on f i rst.
C. T he Conf i gurati on M anagement System
request? Ref erence: PM P Study Gui de, Chapter 5
D . T he Ri sk sati
A. Customer Regisfster
acti on i s not quanti f i abl e. Study Gui de Obj ecti ve: D ef i ne Scope
B. Customer sati sf acti on i s not known unti l the proj ect has been pai d f or. A i s correct. I t’s the best choi ce because customer sati sf acti on i s not a
C. Customer sati sf acti on i s onl y achi eved through measurabl e qual i ty control quanti f i abl e metri c.
metri cs. B i s i ncorrect because customer sati sf acti on i s a goal of every proj ect. H owever,
D . Customer sati sf acti on i s never achi eved through proj ects, but through customer sati sf acti on i s not a quanti f i abl e goal f or the proj ect. C i s i ncorrect
operati
D ons. i ni ti al proj ect team meeti ng, the proj ect manager and the proj ect team
uri ng the becauseCthe metri cs i n themsel ves don’t achi eve customer sati sf acti on. D i s
Answer:
establ i shed ground rul es f or how proj ect team meeti ngs woul d operate. T i na, a iHncorrect as customer
i nt: E veryone pl ays. sati sf acti on can be achi eved through successf ul proj ect
proj ect team member, i s not obeyi ng the proj ect rul es. Who has the responsi bi l i ty iRef
mplerence:
ementati
PMons. Consi der
P Study Gui organi z ati ons9 that compl ete proj ects f or others, such as
de, Chapter
to enf orce the rul es? carpenters and archi tects.
Study Gui de Obj ecti ve: E nsure Common Understandi ng and Set E xpectati ons
A. T he proj ect manager C i s correct because al l proj ect team members share the responsi bi l i ty to enf orce
B. T he proj ect sponsor the rul es.
C. T he proj ect team A i s i ncorrect because thi s does not answer the questi on f ul l y. T he proj ect
D . T he human resources department manager may l ead the enf orcement, but the questi on asks who has the

E ri c i s the proj ect manager f or hi s organi z ati on and he’s been worki ng on draf ti ng responsi
Answer: C bi l i ty—and i t’s the enti re proj ect team. B i s i ncorrect because the

the proj ect charter. Beth Ann, a proj ect team member, asks why E ri c needs to proj ect team
H i nt: Y ou can’thashave
the responsi
a proj ectbiwi
l i ty. D ias icharter.
thout ncorrect because the proj ect team has

create the charter at al l i f everyone al ready knows thi s proj ect i s goi ng to happen. the responsiPM
Ref erence: bi lPi ty. I t may,
Study Guiide,
n some i nstances,
Chapter 3 be up to the proj ect manager to

What i s the purpose of the proj ect charter? escal ate


Study Guithe i ssue
de Obj through
ecti the op
ve: D evel projProj
ectect
sponsor to human resources.
Charter
A. I t al l ows the proj ect manager to assi gn the proj ect team to work. C i s correct. T he proj ect charter authori z es the proj ect. E ven i n scenari os where
B. I t assi gns authori ty to the proj ect manager. the proj ect i s goi ng to happen, a proj ect charter i s needed to name the proj ect
C. I t authori z es the proj ect. manager, authori z e the proj ect manager to use the proj ect resources, and
D . I t i denti f i es the constrai nts and autonomy of the proj ect manager. communi cate the backi ng and support of the proj ect sponsor.
A i s i ncorrect.
Answer: B T he work authori z ati on system al l ows the proj ect manager to assi gn
E ri c i s the proj ect manager f or hi s organi z ati on and he’s been worki ng on draf ti ng
the
H i nt: I t’s not the to
proj ect team work. B i s not the best choi ce f or the questi on. Whi l e the
champ.
the proj ect charter. I n thi s case, E ri c needs to def i ne who wi l l i ssue the proj ect
projerence:
Ref ect manager
PM P does
Studyrecei ve authori
Gui de, Chapterty 4
over some of the proj ect resources, the best
charter si nce he’s the person wri ti ng i t. Who i ssues the proj ect charter?
choi
StudyceGui
i s that theecti
de Obj projve:
ectD ievel
s authori z ed
op Proj ecttoCharter
exi st i n the organi z ati on. D i s an
A. T he proj ect manager
iBncorrect statement
i s correct becauseabout theect
the proj projsponsor
ect charter.
i ssues the charter. T he proj ect charter i s
B. T he proj ect sponsor
C. T he proj ect customer si gned and i ssued by an enti ty i n the organi z ati on that has the power to authori z e

D . T he proj ect champi on the proj ect manager to uti l i z e the needed resources f or the proj ect to be
successf ul .
A i s i ncorrect.
Answer: B T he proj ect manager doesn’t i ssue the proj ect charter. T he proj ect
E xami ne the exhi bi t. H ow l ong wi l l the manager doesn’t, i n most cases, have authori ty over al l of the resources (peopl e,
H i nt: T here i s a change.
proj ect take i f Acti vi ty C i n the exhi bi t fRef
acierence:
l i ti es, equi
PM Ppment)
Study the
Gui proj
de, ect wi l l 6need. C i s i ncorrect because the customer
Chapter
i ncreases by f our days? may demand the proj ect, but they don’t i ssue thei charter.
Study Gui de Obj ecti ve: E xecute T asks D ef i ned n Proj ectDPl
i san
not a val i d opti on.
A. 22 T
B he
i s proj ect because
correct champi onthei s apath
stakehol
ACF Hder
I i sthat
the may
cri tibe
cal“cheeri
path, andng”wi
the
thproj
f ourect onward,
B. 26 but oftiten
addi onalthidays
s person i sn’tthe
of work thedurati
proj ect sponsor.
on of the proj ect wi l l i ncrease to 26 days.
C. 16
A i s i ncorrect because thi s i s the proj ect durati on bef ore the change i n durati on
D . N o change because there i s f l oat
f or Acti vi ty C. C i s i ncorrect because thi s i s not val i d. D i s i ncorrect because the
durati on of the proj ect has i ncreased regardl ess of the f l oat
PMP Exam Practice Test And Study Guide
Study this set o nline at: https://www.cram.co m/flashcards/pmp-exam-practice-test-
and-study-guide-56 32748
Answer: B
E xami ne the exhi bi t. What i s the
H i nt: N ot Si gma.
hi ghl i ghted area i n the f ol l owi ng chart
Ref erence: PM P Study Gui de, Chapter 8
cal l ed?
Study Gui de Obj ecti ve: E nsure Proj ect D el i verabl es Conf orm to Qual i ty
A. T he mean
Standards
B. T he Rul e of Seven
B i s correct because whenever there are seven measurements i n a row al l on one si de
C. T he control l i mi t
of the mean, thi s i s cal l ed the Rul e of Seven. I t i s an assi gnabl e cause.
D . Si x Si gma
A i s i ncorrect because the mean i s represented by the sol i d bar i n the mi ddl e of
the
Answer:control
C chart. C i s i ncorrect because the control l i mi ts are the top and bottom
E xami ne the exhi bi t. Y ou are the proj ect lHi nes
i nt: F ithe
i n control
nd the chart.
l ongest D ito
path s icompl
ncorrect
eti because
on. Si x Si gma i s a qual i ty assurance
manager f or your organi z ati on. Y ou’re program i nvented by M otorol a. Chapter 6
Ref erence: PM P Study Gui de,
worki ng wi th your proj ect team to hel p
Study Gui de Obj ecti ve: E xecute T asks D ef i ned i n Proj ect Pl an
them understand the concept of the
C i s correct. T he cri ti cal path i s the l ongest path of durati on f rom the proj ect
cri ti cal path i n a proj ect. I f the exhi bi t
start to i ts compl eti on. I n thi s exampl e, the cri ti cal path i s the sum of durati on f or
represents your proj ect, what i s the
tasks ACF H I at 22 days.
cri ti cal path?
A i s i ncorrect. T he path of ABE I i s onl y 13 days. B i s i ncorrect. T he path of ABD GI
A. ABE I
H arry i s the manager of a sof tware devel iAnswer:
s 21 days.
D D i s i ncorrect. T o f i nd the cri ti cal path, add up the durati on of the
B. opment
ABD GI proj ect f or hi s company. I n thi s
proj ect, H arry i s uti l i z i ng an i ssue l og. path movi ng del
f orward, not backward.
C.What
ACF Hshoul
I d H arry do wi th the i ssue l og H i nt: D on’t ete anythi ng.
when i ssues have been resol ved? D . I GD BA Ref erence: PM P Study Gui de, Chapter 13
A. D el ete the i ssue l og. Study Gui de Obj ecti ve: M anage Stakehol der E ngagement
B. D el ete the resol ved i ssues f rom the l og. D i s correct. When an i ssue has been resol ved, H arry shoul d update the i ssue l og
C. Update the proj ect ri sk regi ster because the i ssue i s no l onger rel evant to the to ref l ect the status of the i ssue as resol ved.
proj ect success. A i s i ncorrect. T he i ssue l og shoul d not be del eted because i t wi l l become part
D . Update the i ssue l og. of the organi z ati onal process assets. B i s i ncorrect because the i ssue shoul d be
marked
Answer: C as resol ved, not del eted. C i s i ncorrect because the i ssue l og i s separate
H arry i s the proj ect manager of the H QQ Proj ect. M anagement has asked hi m to
f rom
H i nt:the ri skthe
Read regiquesti
ster. on bef ore you change your answer.
report on the proj ect executi on and i ts outcomes. Whi ch one of the f ol l owi ng i s an
output of proj ect executi on? Ref erence: PM P Study Gui de, Chapter 4

A. T he proj ect charter Study Gui de Obj ecti ve: E xecute T asks D ef i ned i n Proj ect Pl an

B. T he cost basel i ne C i s correct because change requests are outputs of proj ect executi on.

C. Change requests A i s i ncorrect because the proj ect charter i s not an output of proj ect executi on. B

D . Qual i ty control mechani sms i s i ncorrect because the cost basel i ne has been establ i shed based on your cost
esti mates and the cost budgeti ng acti vi ti es. D i s i ncorrect because thi s i s not a

H ol l y Ann i s the proj ect manager of the GVF Proj ect, whi ch i s si mi l ar to the H GF val i d answer.
Answer: D
Proj ect she j ust compl eted. She and the proj ect team are about to begi n creati ng H i nt: I t’s l i ke a cooki e cutter.
the WBS f or the GVF Proj ect and she woul d l i ke to use the WBS f rom the H GF Ref erence: PM P Study Gui de, Chapter 5
Proj ect to create the current WBS. T hi s i s an exampl e of whi ch one of the Study Gui de Obj ecti ve: Create the WBS
f ol l owi ng? D i s correct because when H ol l y uses a previ ous proj ect’s WBS to create the
A. T op-down esti mati ng current proj ect’s WBS, she i s usi ng a templ ate.
B. H i stori cal i nf ormati on A i s i ncorrect because she i s not esti mati ng at thi s poi nt i n the proj ect. B i s
C. Poor proj ect management i ncorrect because whi l e thi s may be a l oose exampl e of hi stori cal i nf ormati on,
D
H .olWBS
l y i s templ ateect manager of the UI M Proj ect f or her company. A new change
the proj WBS
Answer:templ
A ate answers the questi on more accuratel y. C i s i ncorrect because thi s i s
request has moved through the change control board and i t was approved. N ow not
H i nt: N ot theebi
an exampl ofgpoor
one. proj ect management.
H ol l y needs to i ncorporate the change i nto the proj ect to ref l ect the addi ti onal Ref erence: PM P Study Gui de, Chapter 5
scope requi rements. Al l of the f ol l owi ng are resul ts of approved changes except Study Gui de Obj ecti ve: I mpl ement Approved Changes
f or whi ch one? A i s correct because the charter i s not updated as a resul t of an approved change
A. Proj ect charter updates request.
B. Proj ect scope updates B i s i ncorrect because the scope may be updated as a resul t of an approved
C. WBS updates change request. C i s i ncorrect because the scope may be updated as a resul t of an
D . WBS di cti onary updates approved
Answer: A change request. D i s i ncorrect because the scope may be updated as a
I n most proj ects, change i s i nevi tabl e. Change f or ti me, cost, scope, and even
resul
H i nt:t Read
of an approved
the questichange
on. request.
contracts must be captured, anal yz ed, and i ncorporated i nto the proj ect pl an.
What system control s changes wi thi n a proj ect? Ref erence: PM P Study Gui de, Chapter 4

A. Change control system Study Gui de Obj ecti ve: D evel op Change M anagement Pl an

B. Change control board A i s correct. T he change control system control s changes to the proj ect.

C. Cost change control system B i s i ncorrect because the change control board may be used as part of the change

D . Change approval system control system. C i s i ncorrect because costs may be af f ected by the changes, but
there i s no cost change control system. D i s i ncorrect because thi s term i s not
val i d. A
Answer:
I n the earl y stages of a proj ect, thi s event i s easy to accept. Later i n the proj ect i t H i nt: T he f urther the proj ect i s f rom compl eti ng, the hi gher the ri sk and
i s di f f i cul t to accept. What i s the event? uncertai nty.
A. Change Ref erence: PM P Study Gui de, Chapter 2
B. Ri sk Study Gui de Obj ecti ve: Veri f y and M anage Changes to the Proj ect
C. T eam devel opment A i s correct. Change i s easi l y accepted i n the begi nni ng of a proj ect. As the
D . Scope veri f i cati on proj ect moves toward compl eti on, change i s harder to i ncorporate.
B i s i ncorrect. Ri sk i s onl y accepted based on i ts i mpact of the proj ect and the
perf ormi ng organi z ati on’s uti l i ty f uncti on. Recal l that the uti l i ty f uncti on i s an
PMP Exam Practice Test And Study Guide
Study this set o nline at: https://www.cram.co m/flashcards/pmp-exam-practice-test-
and-study-guide-56 32748
I t i s i mportant f or the proj ect manager to i denti f y the organi z ati onal structure she Answer: A

i s operati ng wi thi n to better pl an the proj ect. Whi ch organi z ati onal structure H i nt: I t’s no “f un” f or the proj ect manager.

provi des the l east amount of power f or the proj ect manager? Ref erence: PM P Study Gui de, Chapter 9

A. F uncti onal Study Gui de Obj ecti ve: I denti f y Proj ect T eam and D ef i ne Rol es and

B. Weak M atri x Responsi bi l i ti es

C. Strong M atri x A i s correct because the F uncti onal structure provi des the l east amount of

D . Proj ecti z ed authori ty f or the proj ect manager.


B i s i ncorrect because the Weak M atri x provi des more power than the F uncti onal

I t’s di f f i cul t to capture and anal yz e al l ri sks that may af f ect the proj ect Structure, but sti l l l i mi ts the proj ect manager’s authori ty. C i s i ncorrect because
Answer: B
obj ecti ves. One approach i s usi ng the ri sk regi ster. What exactl y i s the ri sk the Strong M atri x provi des the proj ect manager more power than the f uncti onal
H i nt: Keep i t si mpl e.
regi ster? manager. D i s i ncorrect because the Proj ecti z ed structure provi des the most power
Ref erence: PM P Study Gui de, Chapter 11
A. I t’s a central database f or al l ri sks wi thi n an organi z ati on. f or the proj ect manager.
Study Gui de Obj ecti ve: I denti f y Ri sks and D ef i ne Ri sk Strategi es
B. I t’s a l i sti ng of al l ri sks that have been i denti f i ed wi thi n a proj ect. B i s correct because the ri sk regi ster i s si mpl y a l i st of i denti f i ed ri sks wi thi n a
C. I t’s a l i sti ng of al l ri sks that have been i denti f i ed and responded to wi thi n an proj ect.
organi z ati on. A, C, and D are i ncorrect because these statements are not true.
D . I t’s a l i sti ng of al l ri sks that must be mi ti gated wi thi n a proj ect.

Jerry i s the proj ect manager of the N H Q Proj ect f or hi s company. H e’s worki ng Answer: D
wi th the proj ect sponsor to def i ne the hi gh-l evel scope statement of the proj ect. H i nt: Y ou work on thi s document once the proj ect i s i n moti on.
T he proj ect scope statement def i nes many thi ngs, i ncl udi ng al l of the f ol l owi ng Ref erence: PM P Study Gui de, Chapter 5
except f or whi ch one? Study Gui de Obj ecti ve: D ef i ne Scope
A. Proj ect boundari es D i s correct. Lessons l earned are not i ncl uded i n the proj ect scope statement.
B. Product acceptance cri teri a Lessons l earned are created throughout the proj ect to ref l ect what has, and has
C. Proj ect assumpti ons not, worked wel l i n the proj ect.
D . Lessons l earned A i s i ncorrect because proj ect boundari es are i ncl uded i n the proj ect scope

Ji m i s the proj ect manager of the BH Q Proj ect f or hi s company. T hi s proj ect i s a statement.
Answer: A B i s i ncorrect because the product acceptance cri teri a are i ncl uded i n
manuf acturi ng proj ect f or a new cl i ent. Beth, the proj ect sponsor, has asked Ji m to the
H proj
i nt: Onect scope
your statement. C i s al so i ncorrect because proj ect assumpti ons are
mark...
create a chart that wi l l hel p the stakehol ders see the hi story of the proj ect work iRef
nclerence:
uded i nPM
theP proj ectGui
Study scope
de, statement.
Chapter 8
and any vari ati ons to the proj ect mean. T hi s chart, however, must be measured Study Gui de Obj ecti ve: E nsure Proj ect D el i verabl es Conf orm to Qual i ty
agai nst a ti mel i ne. Whi ch type of qual i ty control chart shows the hi story and Standards
pattern of vari ati on? A i s correct. Run charts show the hi story and pattern of vari ati on.
A. A run chart B i s i ncorrect because a f l owchart shows the f l ow of work or processes wi thi n a
B. A f l owchart system. C i s i ncorrect because a Pareto chart i s a hi stogram that shows categori es
C. A Pareto chart of f ai l ure.
Answer: C D i s i ncorrect because a network di agram chart demonstrates the f l ow
John i s the proj ect manager of the BH Q Proj ect. T hi s proj ect i s to create new
D . A network di agram chart of
H i acti vi tiwork.
nt: I t’s es wi thi n a proj ect.
sof tware f or a cl i ent. John i nsi sts on a documented approach to qual i ty control f or
the sof tware del i verabl e. Qual i ty control f ocuses on what acti vi ty? Ref erence: PM P Study Gui de, Chapter 8

A. Qual i ty assurance Study Gui de Obj ecti ve: E nsure Proj ect D el i verabl es Conf orm to Qual i ty

B. Qual i ty management Standards

C. I nspecti on C i s correct because qual i ty control f ocuses on preventi on and i nspecti on.

D . Acceptance A i s i ncorrect because qual i ty assurance i s a management process to ensure that


the proj ect empl oys al l processes to meet requi rements. B i s i ncorrect because

June i s the proj ect manager of her proj ect and wants to recogni z e team members thi s term
Answer: C i s not val i d. D i s i ncorrect because thi s term appl i es to scope
that have contri buted to the proj ect work i n a si gni f i cant way each month. June veri
H i nt: I t’s on.
f i cati not good f or everyone.Ref erence: PM P Study Gui de, Chapter 9Study
deci des that she’l l award one team member the ti tl e of “T eam M ember of the Gui de Obj ecti ve: I mprove T eam Perf ormance
M onth.” T hi s person wi l l get to park i n a reserved parki ng space and wi l l recei ve C i s correct because thi s i s an exampl e of a z ero sum reward. Onl y one team
one pai d day of f f rom the proj ect. What i s the danger i n June’s pl an f or rewards member can be awarded the ti tl e.
and recogni ti on? A i s i ncorrect because thi s i s an exampl e of a z ero sum reward. B i s i ncorrect
A. T here i s no danger. T hi s i s an exampl e of a reward and recogni ti on system. because i t doesn’t f ul l y answer the questi on. D i s i ncorrect because thi s i s not
B. Onl y proj ect team members that have acti vi ti es duri ng the month can be the i ssue of the reward. Regardl ess of who chooses the reward, onl y one team
awarded the ti tl e. member
Answer: Ccan recei ve the award.
C.anagement
M Onl y one team
has asked
memberyou
can
tobe
create
awarded
a projthe
ecttiki
tlck-of
e per fmonth.
meeti ng f or the GH B H i nt: T he pl an i s needed.
D . Tect.
Proj he proj
When
ect shoul
manager
d the
chooses
proj ectthe
ki ck-of
team fmember,
meeti ngnot
happen?
the proj ect team. Ref erence: PM P Study Gui de, Chapter 1
A. When the proj ect manager has the proj ect team assembl ed f or the f i rst ti me. Study Gui de Obj ecti ve: Conduct Ki ck-Of f M eeti ng
B. When the proj ect manager has approved the proj ect pl an. C i s correct. T he proj ect ki ck-of f meeti ng happens af ter the i ni ti al proj ect pl an
C. When management has approved the i ni ti al proj ect pl an. has been approved.
D . At the start of scope veri f i cati on. A i s i ncorrect because thi s does not answer the questi on as wel l as C. B i s
i ncorrect because the proj ect manager does not necessari l y approve the proj ect

M anagement has asked you, the proj ect manager of the KJU Proj ect, to provi de an pl an—management
Answer: A does. D i s i ncorrect because thi s i s not a val i d statement.

esti mate of the proj ect costs. T hei r deci si on to move f orward wi th the proj ect H i nt: I t’s rough.
wi l l be based on your i ni ti al esti mate. Y ou have j ust started the proj ect so what Ref erence: PM P Study Gui de, Chapter 7
esti mate type wi l l you l i kel y provi de? Study Gui de Obj ecti ve: Obtai n Pl an Approval
A. Rough order of magni tude A i s correct because thi s earl y esti mate i s the rough order of magni tude esti mate.
B. D ef i ni ti ve B i s i ncorrect because the def i ni ti ve can be provi ded once the WBS has been
C. Budget created. C i s i ncorrect because the budget i s provi ded once the scope statement
D . Bottom-up has been created. D i s i ncorrect because the bottom-up i s created once the WBS
has been created.
PMP Exam Practice Test And Study Guide
Study this set o nline at: https://www.cram.co m/flashcards/pmp-exam-practice-test-
and-study-guide-56 32748
M anagement has compared your proj ect to a si mi l ar proj ect that’s j ust been Answer: A
compl eted i n your organi z ati on. T hi s f i ni shed proj ect was deemed successf ul . H i nt: N ot the proj ect managers.
T hi s i s benchmarki ng. What i s the goal of thi s compari son? Ref erence: PM P Study Gui de, Chapter 8
A. T o provi de a basi s by whi ch management may measure perf ormance of your Study Gui de Obj ecti ve: M easure Proj ect Perf ormance
proj ect. A i s correct because management wants to determi ne how your proj ect i s f ai ri ng i n
B. T o provi de a basi s by whi ch management may measure al l proj ects. compari son to a compl eted proj ect that they’ve al ready deemed successf ul .
C. T o provi de a basi s by whi ch management may measure the compl eted proj ect. B i s i ncorrect because benchmarki ng i s most usef ul f or si mi l ar proj ects, though i t
D . T o provi de a basi s by whi ch management may measure proj ect managers. i s possi bl e to benchmark proj ects that are not i n the same di sci pl i ne. C i s
iAnswer:
ncorrectC because management has al ready deemed the f i ni shed proj ect as
M anagement wants a hi stogram that demonstrates the number of def ects that were
successf ul . D i s i ncorrect because the goal i s to measure your proj ect, not you.
H i nt: 80/20.
caused by equi pment f ai l ure, sof tware errors, human errors, and dri ve conf l i cts.
What type of hi stogram i s management aski ng f or? Ref erence: PM P Study Gui de, Chapter 8

A. A cause-and-ef f ect di agram Study Gui de Obj ecti ve: E nsure Proj ect D el i verabl es Conf orm to Qual i ty

B. A control chart Standards

C. A Pareto chart C i s correct because a Pareto chart i s a hi stogram that shows categori es of

D . A f l owchart f ai l ure.
A i s i ncorrect because a cause and ef f ect di agram seeks to i denti f y why the
fAnswer:
ai l uresAhappened, whi l e a Pareto chart onl y wants to i denti f y the categori es of
M anagement wants you, the proj ect manager, to create a matri x to qui ckl y show fHaii nt:
l ure. B ican
Y ou s i ncorrect because
create these a control
f or qual chart
i tati ve andtracks
quantisuccess
tati ve riand f ai lysi
sk anal uress. as a
the probabi l i ty of each ri sk i n your proj ect. What i s management aski ng f or? wholerence:
Ref e—not PMby Pi ndi vi dual
Study Guierrors. D i s i ncorrect
de, Chapter 11 because a f l owchart shows the
A. A probabi l i ty-i mpact matri x fStudy
l ow ofGui
work
de or
Objprocesses
ecti ve: M wioni
thitor
n aAlsystem.
l Ri sks
B. A ri sk rati ng matri x A i s correct because thi s matri x i denti f i es the probabi l i ty, i mpact, and overal l
C. An RAG rati ng matri x ri sk score f or the proj ect.
D . A ri sk owner’s matri x B and D are i ncorrect because nei ther term i s val i d. C i s i ncorrect because an RAG
rati ng i s represented by a red-amber-green rati ng f or ri sk i denti f i cati on or ri sk
acti vi ty.C
Answer:
M anagement woul d l i ke f or you to i denti f y each del i verabl e wi thi n the WBS
wi th a number. T he numberi ng system you shoul d use wi th your WBS i s cal l ed H i nt: I t’s not a secret.

what? Ref erence: PM P Study Gui de, Chapter 5

A. Chart of accounts Study Gui de Obj ecti ve: Create the WBS

B. Bi l l of materi al s C i s correct. T he code of accounts i s used to provi de a hi erarchi cal structure f or

C. Code of accounts the del i verabl es i denti f i ed i n the WBS.

D . WBS di cti onary A i s i ncorrect because the chart of accounts i s an accounti ng tool f or assi gni ng
predef i ned costs f or del i verabl es such as cost per square f oot, cost per hour, or
cost perBuni t. B i s i ncorrect because a bi l l of materi al s i denti f i es al l of the
Answer:
M anagement woul d l i ke you, the proj ect manager, to create a chart showi ng when
materi
H i nt: Nalots needed
H enry. to create the thi ngs i denti f i ed i n the WBS. D i s i ncorrect
resources wi l l be uti l i z ed on your proj ect. What chart i s management aski ng you
because
Ref erence:the
PMWBS di ctiGui
P Study onary
de,def i nes what
Chapter 9 each work package i n the WBS i s and
to create?
iStudy
ts associ ated ti me and cost esti mate.
Gui de Obj ecti ve: M anage Resource Al l ocati on
A. A Gantt chart
B. A resource hi stogram B i s correct because a resource hi stogram i s a bar chart that shows uti l i z ati on of

C. A network di agram resources across ti me.

D . A Pareto chart A i s i ncorrect because a Gantt chart, f rom H enry Gantt, i s a schedul i ng tool that
shows proj ect acti vi ti es across a ti mel i ne or cal endar. C i s i ncorrect because a

M arci wants to know the di f f erence between scope veri f i cati on and qual i ty network
Answer: Ddi agram shows the f l ow of acti vi ti es. D i s i ncorrect because a Pareto
control . What’s the di f f erence? chart
H i nt: iRead
s typicaref
cal l yulused
l y. i n qual i ty control acti vi ti es and shows categori es of
A. QC i s concerned wi th i nspecti on, whi l e scope veri f i cati on i s concerned wi th the fRef
ai lerence:
ure wi thi
PM n aP proj ect.Gui de, Chapter 5
Study
qual i ty. Study Gui de Obj ecti ve: Obtai n F i nal Acceptance f or the Proj ect
B. QC i s concerned wi th the correctness of the del i verabl es, whi l e scope D i s correct because scope veri f i cati on i s concerned wi th the acceptance of the
veri f i cati on i s concerned wi th the acceptance of the proj ect scope. proj ect del i verabl es.
C. QC and scope veri f i cati on are the same. A i s i ncorrect because thi s i s not a true statement about scope veri f i cati on. B i s
D . QC i s concerned wi th the correctness of the del i verabl es, whi l e scope i ncorrect because thi s i s not a true statement about scope veri f i cati on. C i s
veri f i cati on i s concerned wi th the acceptance of the proj ect del i verabl es. iAnswer:
ncorrectD because whi l e QC and scope veri f i cati on both rel y on i nspecti on, they
M ari , the proj ect manager, has al l otted two weeks f or travel del ays wi thi n her are notY the
H i nt: sameprove
ou can’t thi ng.i t.
QC happens wi thout the proj ect customers, whi l e scope
proj ect. She has no proof that travel days wi l l happen. T hi s i s an exampl e of what? veri erence:
Ref f i cati onPM
happens wi Gui
P Study th them.
de, Chapter 5
A. Change control Study Gui de Obj ecti ve: D ef i ne and Record Requi rements, Constrai nts, and
B. Constrai nt Assumpti ons
C. I nef f ecti ve proj ect management D i s correct. M ari has made an assumpti on that there wi l l be travel del ays wi thi n
D . Assumpti on her proj ect. Assumpti ons must be tested f or thei r correctness. An assumpti on that
proves f al se can become a ri sk f or the proj ect success.
A i s i ncorrect
Answer: C because thi s i s not an exampl e of change control . B i s i ncorrect
M ary i s the proj ect manager of the GH Q Proj ect. H er proj ect i s part of a program
because
H i nt: I t’sconstrai nts
not a sol are thi
o acti ngs that l i mi t the proj ect team’s opti ons. C i s i ncorrect
vi ty.
i n her organi z ati on. T homas i s the program manager,
because thiPM
Ref erence: s i sPan exampl
Study Guiede,
of ef f ecti ve5proj ect management.
Chapter
whi l e Joan i s the proj ect sponsor. Who creates the WBS?
A. T he proj ect manager Study Gui de Obj ecti ve: Create the WBS

B. T he proj ect sponsor C i s correct. T he proj ect team creates the WBS.

C. T he proj ect team A i s i ncorrect because the proj ect manager doesn’t compl ete the WBS al one. B i s

D . T he program manager i ncorrect because the proj ect sponsor doesn’t compl ete the WBS. D i s i ncorrect
because the program manager doesn’t create the WBS f or the i ndi vi dual proj ects
wi thi n the program. T he WBS creati on i s the responsi bi l i ty of the proj ect manager
PMP Exam Practice Test And Study Guide
Study this set o nline at: https://www.cram.co m/flashcards/pmp-exam-practice-test-
and-study-guide-56 32748
M cCl el l and’s T heory of N eeds states that there are three needs that we al l have. Answer: B

T he needs are devel oped over ti me and through l i f e experi ences. What i s the H i nt: T i t f or T AT .Ref erence: PM P Study Gui de, Chapter 9Study Gui de Obj ecti ve:

name of the anal ysi s whi ch determi nes an i ndi vi dual ’s dri vi ng need? I mprove T eam Perf ormance

A. T he M yers-Bri gg test B i s correct. T he T hemati c Appercepti on T est (T AT ) can determi ne i f power,

B. T he T hemati c Appercepti on T est achi evement, or af f i l i ati on dri ves an i ndi vi dual .

C. T he Bi g F i ve Personal i ty T est A i s i ncorrect. T he M yers-Bri gg test i s based on the work of Carl Jung, not

D . T he Accurate Personal i ty T est M cCl el l and. C i s i ncorrect. T he Bi g F i ve Personal i ty T est was devel oped by Paul
Costa and Robert M cCrae. D i s i ncorrect because thi s i s not a val i d test f or

N ot al l ri sks are negati ve, and some negati ve ri sks are worth accepti ng i nto the determi
Answer: Ani ng dri vi ng needs.
proj ect based on the i mpact, the possi bl e outcomes, and the percei ved benef i ts H i nt: I t’s based on Bernoul l i ’s curves.
that the ri sk may bri ng. What terms descri bes a person’s or organi z ati on’s Ref erence: PM P Study Gui de, Chapter 11
wi l l i ngness to accept ri sk? Study Gui de Obj ecti ve: I denti f y Ri sks and D ef i ne Ri sk Strategi es
A. Uti l i ty f uncti on A i s correct. Uti l i ty f uncti on i s a term used to descri be a person’s or organi z ati on’s
B. Ri sk exposure wi l l i ngness to accept ri sk. T he l ower the uti l i ty f uncti on, the more ri sk response
C. M i ti gati on pl anni ng i s needed.
D . Ri sk probabi l i ty B i s i ncorrect because ri sk exposure i s based on each proj ect. C i s i ncorrect
because
Answer: Cmi ti gati on i s one response to a ri sk event. D i s i ncorrect because ri sk
One of the most i mportant processes of ri sk management i s ri sk i denti f i cati on. probabi
H i nt: I t laii ty
n’tdescri besl the
over unti i t’sl iover.
kel i hood of a ri sk event actual l y happeni ng.
When does the ri sk i denti f i cati on concl ude? Ref erence: PM P Study Gui de, Chapter 11
A. Wi th the pl anni ng process group Study Gui de Obj ecti ve: I denti f y Ri sks and D ef i ne Ri sk Strategi es
B. Wi th the executi on process group C i s correct because ri sk i denti f i cati on happens throughout the proj ect l i f e
C. Wi th the cl osi ng process group cycl e.
D . When the proj ect customer deems al l the ri sks have been i denti f i ed. A i s i ncorrect because ri sk i denti f i cati on happens throughout the proj ect. B i s
i ncorrect because ri sk i denti f i cati on i s i terati ve and happens throughout the
proj ect.DD i s al so i ncorrect. T he proj ect customer may not know enough about the
Answer:
Pi i s the proj ect manager f or her organi z ati on. M anagement has asked her to
proj
H ect’s
i nt: di zsci
Organi atiplon-wi
i ne to understand when al l of the ri sks have been i denti f i ed.
de.
i denti f y the qual i ty control tool s she’l l use i n the proj ect. Al l of the f ol l owi ng
Ri
Refskerence:
i dentiPM
f i cati on i s iGui
P Study terati
de,veChapter
and happens
8 throughout the proj ect.
are exampl es of qual i ty control tool s except f or whi ch one?
A. I nspecti on Study Gui de Obj ecti ve: E nsure Proj ect D el i verabl es Conf orm to Qual i ty

B. D ef ect repai r revi ew Standards

C. Stati sti cal sampl i ng D i s correct because qual i ty audi ts are a tool used f or qual i ty assurance.

D . Qual i ty audi ts A i s i ncorrect because i nspecti on i s a QC tool . B i s i ncorrect because def ect
repai r revi ew i s a QC tool . C i s i ncorrect because stati sti cal sampl i ng i s a QC

Proj ect management requi res cost control , whi ch can mean tradeof f s and tool . C
Answer:
addi ti onal f unds f or changes. Currentl y, your proj ect i s runni ng over on costs due to H i nt: Onl y f or emergenci es.Ref erence: PM P Study Gui de, Chapter 7Study Gui de
unknown unknowns. What can you do? Obj ecti ve: I mpl ement Approved Acti ons and Workarounds
A. N othi ng because unknown unknowns are ri sks. C i s correct because the management conti ngency reserve i s an amount of f unds set
B. Propose to management to obtai n more f unds to counteract the unknown asi de f or unpl anned events that consume the proj ect budget.
unknowns. A i s i ncorrect because whi l e unknowns may be ri sks, thi s i s not the best response. B
C. Propose to management to uti l i z e the management conti ngency reserve. i s i ncorrect because i t does not answer the questi on as compl etel y as C. D i s
D . Prepare an assessment of why the proj ect has f ai l ed due to the unknown i ncorrect because the proj ect has not f ai l ed at thi s poi nt.
unknowns.
Proj ect managers may need to work wi th uni on l abor as part of the proj ect Answer: B
executi on. T hi s requi res pl anni ng and consi derati on of al l the uni on agreements, H i nt: M ore than j ust a stakehol der.
rul es, and restri cti ons. A contract between the perf ormi ng organi z ati on and a uni on Ref erence: PM P Study Gui de, Chapter 9
i s an exampl e of whi ch one of the f ol l owi ng? Study Gui de Obj ecti ve: I denti f y Proj ect T eam and D ef i ne Rol es and
A. Stakehol der Responsi bi l i ti es
B. Col l ecti ve bargai ni ng agreement B i s correct because the contract between the perf ormi ng organi z ati on and the
C. Assumpti on uni on i s cal l ed a col l ecti ve bargai ni ng agreement.
D . M anagement A i s i ncorrect because the uni on i s a stakehol der i f they’re i nvol ved wi th the
proj ect Abut thei r contract i s not. C i s i ncorrect because the contract may l i st
Answer:
Proj ects are compl eted by peopl e and requi re ground rul es to establ i sh cl ear
constrai nts,thi
H i nt: T wo but not assumpti ons. D i s i ncorrect because management i s not a val i d
ngs.
expectati ons. Why must the proj ect team commi t to cl ear gui del i nes on thei r
answer.
Ref erence: PM P Study Gui de, Chapter 9
behavi or and proj ect parti ci pati on earl y i n the proj ect?
A. I t decreases mi sunderstandi ngs and i ncreases producti vi ty. Study Gui de Obj ecti ve: E nsure Common Understandi ng and Set E xpectati ons

B. I t i ncreases the proj ect’s l i kel i hood of success. A i s correct because earl y commi tment to cl ear gui del i nes decreases

C. I t decreases stormi ng among the proj ect team members. mi sunderstandi ngs and i ncreases producti vi ty f or the proj ect team.

D . I t i ncreases the proj ect’s ri sk mi ni mi z ati on. B i s i ncorrect. Whi l e thi s may be true, i t i s not as accurate as A. Ri sks, l ack of
qual i ty, and other i nf l uencers coul d sti l l cause the proj ect to f ai l . C i s i ncorrect
because stormi ng happens as part of team devel opment. D i s i ncorrect because
Qual i ty control and qual i ty assurance are needed i n every proj ect. Whi ch one of thi s i s notAnswer:
a val i dDstatement.
the f ol l owi ng i s an exampl e of qual i ty assurance? H i nt: Started at M otorol a.
A. A Pareto chart Ref erence: PM P Study Gui de, Chapter 8
B. A control chart Study Gui de Obj ecti ve: I mpl ement Qual i ty M anagement Pl an
C. I nspecti on D i s correct because Si x Si gma i s a qual i ty assurance program.
D . A Si x Si gma program A, B, and C are i ncorrect because each i s a qual i ty control tool .
PMP Exam Practice Test And Study Guide
Study this set o nline at: https://www.cram.co m/flashcards/pmp-exam-practice-test-
and-study-guide-56 32748
Qual i ty control i s managed by T erry, a qual i ty engi neer on your proj ect. T erry Answer: B
reports that she’l l need some ti me and resources to compl ete qual i ty control on H i nt: N o changes.Ref erence: PM P Study Gui de, Chapter 8Study Gui de Obj ecti ve:
the proj ect del i verabl es. T erry al so reports the tool s she’l l use as part of the I mpl ement Approved Acti ons and Workarounds
qual i ty control acti vi ti es. Al l of the f ol l owi ng are qual i ty control tool s T erry B i s correct because thi s i s not a qual i ty control tool . A basel i ne update ref l ects
coul d use except f or whi ch one? changes to the proj ect’s scope, cost, or schedul e basel i ne.
A. Control charts A i s i ncorrect because thi s i s a qual i ty control tool . Control charts show
B. Basel i ne updates f l uctuati ons f rom the proj ect’s mean. C i s i ncorrect because thi s i s a qual i ty
C. F l owcharti ng control tool . F l owcharts show the f l ow of work, i nf ormati on, or data through a
D
Ri.sk
I nspecti
anal ysion
s i s an i terati ve process wi thi n any proj ect. I t someti mes hel ps to def i nedCsystem. D i s i ncorrect because thi s i s a qual i ty control tool . I nspecti on i s
Answer:
cl assi f y and break down the ri sk events to provi de a deeper understandi ng of the priI mary
H i nt: qual iritysk.
t’s about control tool T erry wi l l use.

them. Whi ch structure l i sts the categori es and subcategori es f or ri sks wi thi n a Ref erence: PM P Study Gui de, Chapter 11
proj ect? Study Gui de Obj ecti ve: I denti f y Ri sks and D ef i ne Ri sk Strategi es
A. T he work breakdown structure C i s correct. A ri sk breakdown structure i l l ustrates the ri sk categori es wi thi n a
B. T he organi z ati onal breakdown structure proj ect.
C. T he ri sk breakdown structure A i s i ncorrect because the WBS shows the decomposi ti on of the proj ect scope. B
D . T he bi l l of materi al s structure i s i ncorrect because the OBS shows the structure of an organi z ati on, not the ri sks

Ri sk i denti f i cati on and anal ysi s i ncl udes caref ul consi derati on of proj ect wi thi n the organi z ati on. D i s al so i ncorrect because the BOM descri bes the
Answer: C
requi rements, scope obj ecti ves, the nature of the proj ect work, and the proj ect materi al s needed i n order to bui l d the proj ect scope.
H i nt: Assumpti ons.
documentati on. Based on thi s i nf ormati on, whi ch one of the f ol l owi ng statements Ref erence: PM P Study Gui de, Chapter 11
must be exami ned f or ri sk? Study Gui de Obj ecti ve: I denti f y Ri sks and D ef i ne Ri sk Strategi es
A. T he product requi res a f oi l stamp of .32 mi l l i meters. C i s correct because al l assumpti ons must be tested.
B. T he product requi res oak beams. A i s i ncorrect because thi s i s not an assumpti on, but a requi rement. Both B and D
C. T he product must be constructed duri ng the summer months due to the are i ncorrect because these are proj ect requi rements.
expected good weather.
D . T hethe
Sarah, product must be
CI O, wants to approved
know why by
youahave
bui lrequested
di ng i nspector bef ore
so many August
meeti ngs wi th the Answer: B
users of the sof tware your proj ect i s creati ng. Whi l e she acknowl edges that the H i nt: T hi nk customer buy-i n.
users are stakehol ders, she doesn’t understand why you bel i eve these Ref erence: PM P Study Gui de, Chapter 13
stakehol ders shoul d be i nvol ved so much duri ng the i ni ti ati on phase of the Study Gui de Obj ecti ve: I denti f y and Perf orm Stakehol der Anal ysi s
proj ect. Why shoul d the stakehol ders be i nvol ved now? B i s correct. I nvol vi ng the stakehol ders and customers wi l l i ncrease the
A. I nvol vi ng the customers and other stakehol ders i mproves proj ect perf ormance. probabi l i ty of shared ownershi p, del i verabl e acceptance, and sati sf acti on. T hi s
B. I nvol vi ng the customers and other stakehol ders i s part of stakehol der i s an ongoi ng component of stakehol der engagement and i t ai ds i n mai ntai ni ng
engagement. i nterest and support of the proj ect.
C. I nvol vi
Several ng ect
proj the team
customers and want
members otherto
stakehol
schedulders reduces
e vacati proj iect
on days ri y,
n Jul sk.but you A i s i ncorrect
Answer: A because there i s no guarantee that i t wi l l i mprove proj ect
D . I nvol
need to vi ng the
conf i rm icustomers and other
f Jane, a network stakehol
engi ders
neer, has i s needed
al ready to obtai
schedul ed hernvacati
proj ecton. perf ormance.
H i nt: Jane’s aCresource.
i s i ncorrect because stakehol der parti ci pati on wi l l not reduce
sponsorshi
Whi ch calp.
endar wi l l tel l you, the proj ect manager, i f Jane i s avai l abl e on Jul y proj ect ri sk.PM
Ref erence: D Pi sStudy
i ncorrect
Gui because stakehol
de, Chapter 6 der parti ci pati on duri ng i ni ti ati on i s

17? not needed f or proj ect sponsorshi p.


Study Gui de Obj ecti ve: M anage Resource Al l ocati on
A. T he resource cal endar A i s correct because Jane i s a resource and resource cal endars are speci f i c to each
B. T he proj ect cal endar resource on the proj ect.
C. T he proj ect schedul e B i s i ncorrect because the proj ect cal endar determi nes when proj ect work i s
D . T he H R cal endar al l owed. C i s i ncorrect because the proj ect schedul e shows the mappi ng of the

Stephen i s the proj ect manager of a constructi on proj ect. H e has wri tten i nto hi s proj ect B
Answer: work. D i s i ncorrect because thi s term i s not val i d.

proj ect pl an that the proj ect work be compl eted duri ng the summer months H i nt: Can you prove i t?
because the weather i s typi cal l y better f or constructi on than i n wi nter months. Ref erence: PM P Study Gui de, Chapters 3 and 5
T hi s deci si on i s an exampl e of whi ch one of the f ol l owi ng? Study Gui de Obj ecti ve: D ocument Proj ect Ri sks, Assumpti ons, and Constrai nts
A. M anagement reserve B i s correct. An assumpti on i s somethi ng that you cannot prove to be true, such as
B. Assumpti on the summer weather, but you bel i eve i t to be true.
C. Constrai nt A i s i ncorrect because management reserve descri bes a porti on of ti me al l otted f or
D . Proj ect ri sk schedul e overruns wi thi n the proj ect work. C i s i ncorrect because a constrai nt

T he conf i gurati on management system accompl i shes al l of the f ol l owi ng except l i mi ts the proj ect team’s opti ons. D i s i ncorrect because a proj ect ri sk i s an
Answer: D
f or whi ch one? uncertai n event that may have a negati ve or posi ti ve i mpact on the proj ect’s
H i nt: Al l of these al ready exi st.
A. Provi des opportuni ti es to val i date and i mprove the proj ect by consi deri ng the outcome.
Ref erence: PM P Study Gui de, Chapter 4
i mpact of each change Study Gui de Obj ecti ve: D evel op Change M anagement Pl an
B. Provi des opportuni ti es f or the proj ect management team to communi cate al l D i s correct because the conf i gurati on management system does not provi de a
changes to the stakehol ders method f or proj ect management processes to be removed or added to the proj ect.
C. Provi des a method to i denti f y and request changes to establ i shed basel i nes A, B, and C are i ncorrect because al l of these statements are true.
D . Provi des a method f or proj ect management processes to be removed or added
to the
T he diproj ect between what was pl anned and what was experi enced i n the
f f erence Answer: B
proj ect i s cal l ed a proj ect vari ance. Proj ect vari ances are of ten compared agai nst H i nt: E quates to the scope.
the proj ect basel i nes, such as ti me, cost, and scope. What document serves as the Ref erence: PM P Study Gui de, Chapter 5
scope basel i ne? (Choose the best answer.) Study Gui de Obj ecti ve: Create the WBS
A. T he summati on of the cost and ti me basel i nes B i s correct. T he WBS i s the scope basel i ne. T echni cal l y, the WBS, the WBS
B. T he WBS di cti onary, and the detai l ed proj ect scope are the scope basel i ne.
C. T he proj ect charter A i s i ncorrect because the ti me and cost basel i nes do not ref l ect the scope. C i s
D . T he proj ect scope i ncorrect because the proj ect charter does not capture al l the del i verabl es the
proj ect wi l l create. D i s i ncorrect because the proj ect scope i s decomposed i nto
PMP Exam Practice Test And Study Guide
Study this set o nline at: https://www.cram.co m/flashcards/pmp-exam-practice-test-
and-study-guide-56 32748
Answer: C
T he l argest ri sk i n your proj ect has j ust occurred. T hi s ri sk event has depl eted H i nt: F i nd the probl em f i rst.
nearl y al l of your ri sk conti ngency reserve. What must happen next? Ref erence: PM P Study Gui de, Chapter 11
A. T he proj ect must be scrapped. Study Gui de Obj ecti ve: M oni tor Al l Ri sks
B. T he proj ect must be revi ewed f or addi ti onal ri sks. C i s correct because when a ri sk depl etes the conti ngency reserve, i t cal l s f or
C. T he proj ect manager and the proj ect team must compl ete reserve anal ysi s. reserve anal ysi s i n rel ati on to the amount of remai ni ng ri sks wi thi n the proj ect.
D . T he proj ect manager must ask f or addi ti onal f unds. A i s i ncorrect because the proj ect l i kel y won’t need to cancel ed because of the
ri sk event.B i s i ncorrect because thi s event i s i terati ve. D i s i ncorrect because
there’s
Answer: no
A evi dence yet i f addi ti onal f unds are needed.

T he process of breaki ng down the proj ect scope i nto the WBS i s cal l ed what? H i nt: N o surf i ng.

A. Progressi ve el aborati on Ref erence: PM P Study Gui de, Chapter 1

B. Rol l i ng wave pl anni ng Study Gui de Obj ecti ve: Create the WBS

C. WBS composi ti on A i s correct because progressi ve el aborati on means devel opi ng i n steps and

D . Work structure conti nui ng i n i ncrements, as i n the WBS creati on.


B i s i ncorrect because rol l i ng wave pl anni ng al l ows f or ebb and f l ow i n pl anni ng. C
and D are i ncorrect because both of these terms are not val i d.

Answer: D

T he proj ect charter must def i ne whi ch one of the f ol l owi ng? H i nt: N ot QA.

A. T he ri sk exposure f rom not compl eti ng the proj ect Ref erence: PM P Study Gui de, Chapter 4

B. T he qual i ty assurance program the proj ect manager must operate under Study Gui de Obj ecti ve: E nsure Common Understandi ng and Set E xpectati ons

C. T he work authori z ati on system the proj ect must use D i s correct because the charter must def i ne the requi rements f or customer

D . Requi rements f or customer sati sf acti on sati sf acti on.


A, B, and C are i ncorrect because these are not val i d components of the proj ect
charter.

Answer: D
T he proj ect charter shoul d al ways address al l of the f ol l owi ng except f or whi ch H i nt: I t doesn’t exi st j ust yet.
one? Ref erence: PM P Study Gui de, Chapter 4
A. T he proj ect purpose Study Gui de Obj ecti ve: D evel op Proj ect Charter
B. T he assi gned proj ect manager and authori ty l evel D i s correct. Proj ect team members are not i denti f i ed i n the proj ect charter.
C. T he summary budget A i s i ncorrect because the proj ect charter does i denti f y the proj ect purpose. B i s
D . Proj ect team members i ncorrect because the proj ect does i denti f y the proj ect manager and the authori ty
l evel . C i s i ncorrect because the summary budget i s i denti f i ed.

T he proj ect management team i s creati ng the proj ect charter and they are rel yi ng Answer: A
on several tool s to hel p them. T hey want the proj ect charter to be accurate to H i nt: N ot the thi ng.
ensure i ts approval . Whi ch one of the f ol l owi ng i s not a tool or techni que that Ref erence: PM P Study Gui de, Chapter 4
shoul d be used when creati ng the proj ect charter? Study Gui de Obj ecti ve: Obtai n Proj ect Charter Approval
A. Proj ect product anal ysi s A i s correct because product anal ysi s i s not a tool or techni que f or the proj ect
B. Proj ect sel ecti on methods charter devel opment.
C. Proj ect management methodol ogy B i s i ncorrect because proj ect sel ecti on methods are acceptabl e tool s. C i s
D . E xpert j udgment i ncorrect because proj ect management methodol ogy i s an acceptabl e tool . D i s
iAnswer:
ncorrectB because expert j udgment i s an acceptabl e tool .
T he proj ect scope statement i ncl udes constrai nts, assumpti ons, and requi rements.
Al l of the f ol l owi ng are exampl es of constrai nts except f or whi ch one? H i nt: I t’s not a requi rement.

A. A preset proj ect budget Ref erence: PM P Study Gui de, Chapter 7

B. A proj ect that has been compl eted bef ore Study Gui de Obj ecti ve: D ef i ne and Record Requi rements, Constrai nts, and

C. A proj ect due date as def i ned by management Assumpti ons

D . A proj ect that requi res a mechani cal engi neer f or the month of B i s the best choi ce because thi s descri bes hi stori cal i nf ormati on rather than a

January constrai nt.


A i s i ncorrect because a preset proj ect budget descri bes a proj ect constrai nt. C i s
iAnswer:
ncorrectD because a due date i s an exampl e of a proj ect constrai nt. D i s i ncorrect
T he proj ect team has compl eted some of the proj ect work i ncorrectl y. Y ou’ve because i t descri
H i nt: M ake bes a resource
sure everythi constrai nt
ng i s correct.Ref f or the
erence: PMmechani
P StudycalGui
engi
de,neer.
Chapter
i nstructed the proj ect team to redo the work. What must happen next? 8Study Gui de Obj ecti ve: I mpl ement Approved Acti ons and Workarounds
A. Conduct an anal ysi s of the del ay because of the rework. D i s correct because the repai r must be revi ewed f or accuracy.
B. Conduct an anal ysi s of the cost i ncrease because of the rework. A i s i ncorrect because the repai r must be correct bef ore the proj ect can move
C. Revi ew each proj ect team member’s perf ormance. f orward. I f the repai r i s assumed to be correct, then the revi ew of the ti me del ay
D . Revi ew the def ect repai r. may be i naccurate because of f uture rework, waste, or a seri es of f ai l ures because
of the i naccurate rework. B i s i ncorrect because the repai r must be revi ewed f or
accuracy
Answer: B f i rst. C i s i ncorrect because thi s i s not the most pressi ng i ssue at thi s
T he proj ect team i s obvi ousl y struggl i ng over who wi l l be l eadi ng the proj ect. poi
H nt Boomers.
i nt: i n the proj ect.
T hi s happens i n whi ch phase of team devel opment? Ref erence: PM P Study Gui de, Chapter 9
A. F ormi ng Study Gui de Obj ecti ve: I mprove T eam Perf ormance
B. Stormi ng B i s correct because stormi ng i s when the proj ect team moves through power
C. N ormi ng struggl es about who’s i n charge of the proj ect.
D . Perf ormi ng A i s i ncorrect because f ormi ng happens when the team f i rst meets. C i s i ncorrect
because thi s happens once the proj ect team settl es i nto thei r rol es. D i s i ncorrect
because thi s happens once the proj ect team f ocuses on getti ng the proj ect work
PMP Exam Practice Test And Study Guide
Study this set o nline at: https://www.cram.co m/flashcards/pmp-exam-practice-test-
and-study-guide-56 32748
T he proj ect vendor you sel ected to provi de materi al s f or your proj ect cannot Answer: A
del i ver. Y ou need the materi al s by the end of the week. T he change control board H i nt: I t’s not pl anned.Ref erence: PM P Study Gui de, Chapter 11Study Gui de
agrees that you shoul d cal l another vendor that has sl i ghtl y hi gher pri ces but can Obj ecti ve: I mpl ement Approved Acti ons and Workarounds
del i ver as needed. T hi s i s an exampl e of whi ch one of the f ol l owi ng? A i s correct because thi s i s an exampl e of a workaround.
A. A workaround B i s i ncorrect because a conti ngency pl an i s pre-pl anned, whereas a workaround i s
B. A conti ngency pl an a response to an i mmedi ate ri sk. C i s i ncorrect because transf erence transf ers the
C. A transf erence ri sks to another party. D i s i ncorrect because mi ti gati on i s a pl anned attempt to
D . M i ti gati on reduce or el i mi nate the i mpact of a known ri sk. I n thi s i nstance, the ri sk was not
known.
Answer: D
T here’s a ri sk that a new l aw wi l l cause your proj ect to f ai l . What ri sk response
H i nt: T here’s nothi ng you can do about i t.
can you use f or thi s possi bl e l aw?
Ref erence: PM P Study Gui de, Chapter 11
A. M i ti gati on
Study Gui de Obj ecti ve: I denti f y Ri sks and D ef i ne Ri sk Strategi es
B. T ransf erence
D i s correct because the onl y response you can do i s to accept the ri sk.
C. E xpl oi t
A i s i ncorrect because you cannot mi ti gate the ri sk. B i s i ncorrect because you
D . Acceptance
cannot transf er the ri sk. C i s i ncorrect because you cannot accept the ri sk.

Answer: A
What shoul d be i mpl emented when determi ni ng how detai l ed the decomposi ti on H i nt: I t i s a heuri sti c.
of the del i verabl es i n the WBS shoul d be? Ref erence: PM P Study Gui de, Chapter 5
A. T he 8/80 rul e Study Gui de Obj ecti ve: Create the WBS
B. T he l aw of di mi ni shi ng returns A i s correct because the 8/80 rul e states that the work package shoul d not
C. T he pri ori ty of the proj ect equate to l ess than ei ght hours of l abor to create and no more than 80 hours of
D . T he ti metabl e to create the WBS l abor to create.
B i s i ncorrect because the l aw of di mi ni shi ng returns descri bes the ef f ect of
added
Answer: lBabor and the return f or that l abor. C i s i ncorrect because the pri ori ty of
Where wi l l a proj ect manager f i nd i nf ormati on on how the proj ect’s product the
H proj
i nt: ect doesn’t
D on’t af f ect the decomposi ti on of the proj ect. D i s i ncorrect
be bored.
characteri sti cs can be changed? because the
Ref erence: PMti metabl
P StudyeGui
to create the WBS
de, Chapter 4 does not di ctate the l evel of detai l
A. T he proj ect charter requi red f or decomposi ti on
Study Gui de Obj ecti ve: I mpl ement Approved Changes
B. T he Conf i gurati on M anagement System B i s correct because that’s what the Conf i gurati on M anagement System does.
C. T he proj ect scope A i s i ncorrect because the proj ect charter authori z es the proj ect work. C i s
D . T he change control board i ncorrect because the proj ect scope def i nes the proj ect work. D i s i ncorrect
because the CCB may approve or decl i ne changes based on the change control
system the
Answer: A proj ect i s usi ng.
Whi ch one of the f ol l owi ng statements about changes to the proj ect scope i s H i nt: Ask yoursel f , “D o al l changes requi re thi s?”
correct? Ref erence: PM P Study Gui de, Chapter 11
A. Al l changes shoul d be f ormal l y documented. Study Gui de Obj ecti ve: Veri f y and M anage Changes to the Proj ect
B. Al l changes requi re addi ti onal proj ect ti me. A i s correct because al l changes, approved or otherwi se, shoul d be f ormal l y
C. Al l changes requi re addi ti onal proj ect f undi ng. documented.
D . Al l changes f ol l ow the rul es of the change control system. B i s i ncorrect because not al l changes requi re addi ti onal ti me. C i s i ncorrect
because not al l changes requi re addi ti onal f undi ng. D i s i ncorrect because not
al l changes,
Answer: D unf ortunatel y, f ol l ow the change control system. Some changes are
unauthori z ed, but they
H i nt: N ot an ouchi e.Refoccur
erence: anyway.
PM P Study Gui de, Chapter 9Study Gui de
Whi ch organi z ati on theory bel i eves that proj ect teams can be sel f -l ed?
A. M asl ow’s H i erarchy of N eeds Obj ecti ve: I mprove T eam Perf ormance

B. Ouchi ’s T heory Z D i s correct because M cGregor’s X and Y i s a descri pti on of management’s vi ew of

C. H erz berg’s T heory of M oti vati on i ts empl oyees. T he X managers bel i eve that proj ect team members must be

D . M cGregor’s X and Y mi cromanaged. T he Y managers bel i eve that proj ect team members can be sel f -
l ed.
C i s i ncorrect because H erz berg’s T heory of M oti vati on states that hygi ene
agents,
Answer: such
D as a paycheck, won’t moti vate peopl e, but thei r absence wi l l
Whi ch system i s responsi bl e f or i denti f yi ng and documenti ng the f uncti onal and demoti vate. A i s i ncorrect because M asl ow’s H i erarchy of N eeds i denti f i es the
H i nt: I t i s a system.
physi cal characteri sti cs of a product or component that a proj ect i s creati ng? seven
Ref needsPM
erence: wePalStudy
l pursue.
GuiBde,i s Chapter
i ncorrect4because Ouchi ’s T heory Z i s based on
A. T he requi rements gatheri ng process the Japanese
Study Gui de management
Obj ecti ve: Dstyl
evele.op Change M anagement Pl an
B. Stakehol der anal ysi s D i s correct. T he conf i gurati on management system i s responsi bl e f or i denti f yi ng
C. T he pl anni ng process group and documenti ng the f uncti onal and physi cal characteri sti cs of a product or
D . T he conf i gurati on management system component that a proj ect i s creati ng.
A i s i ncorrect because the requi rements gatheri ng process does not f ul l y answer the

Whi l e i t’s not a proj ect i ni ti ati on acti vi ty, most proj ects can benef i t f rom a questi
Answer:on. C B i s i ncorrect because stakehol der anal ysi s does not compl ete thi s
proj ect ki ckof f meeti ng. What’s the goal of the proj ect ki ckof f meeti ng? f uncti
H i nt: Yon.
ouCwant
i s i ncorrect because the pl anni ng process group i s too broad to f ul l y
thi s f i rst.
A. I t i ntroduces the proj ect goal . answer the questi
Ref erence: on. Gui de, Chapter 1
PM P Study
B. I t al l ows the proj ect manager, the proj ect team, and the key stakehol ders to Study Gui de Obj ecti ve: Conduct Ki ck-Of f M eeti ng
meet one another. C i s correct because the goal of the ki ck-of f meeti ng i s to gai n everyone’s
C. I t al l ows the proj ect manager to gai n commi tment f rom the proj ect team and key commi tment to the proj ect.
stakehol ders f or the proj ect. A i s i ncorrect because the proj ect goal i s establ i shed bef ore the ki ck-of f
D . I t al l ows the proj ect manager to f aci l i tate thei r expert power. meeti ng. B i s i ncorrect because the proj ect manager has l i kel y al ready met the
proj ect team. I n addi ti on, thi s i s not the goal of the meeti ng. D i s i ncorrect
PMP Exam Practice Test And Study Guide
Study this set o nline at: https://www.cram.co m/flashcards/pmp-exam-practice-test-
and-study-guide-56 32748
Whi l e proj ect management pl anni ng i s essenti al , pl anni ng cannot conti nue Answer: D
i ndef i ni tel y. At some poi nt, the proj ect management team must move i nto proj ect H i nt: T hi s doesn’t have to happen.
executi on. Al l of the f ol l owi ng acti ons are requi red to execute the proj ect Ref erence: PM P Study Gui de, Chapter 4
management pl an except f or whi ch one? Study Gui de Obj ecti ve: E xecute T asks D ef i ned i n Proj ect Pl an
A. Perf orm acti vi ti es to accompl i sh proj ect obj ecti ves. D i s correct because you, the proj ect manager, do not al ways have to i nteract wi th
B. Staf f , trai n, and manage the proj ect team. other proj ect managers to compl ete the proj ect work. Y ou do al ways have to
C. M anage ri sks and i mpl ement ri sk response acti vi ti es. compl ete choi ces A, B, and C.
D . I nteract wi th other proj ect managers. A, B, and C are i ncorrect because al l of these are val i d statements.

Y ou and the proj ect sponsor are worki ng together to create a proj ect scope Answer: A
statement. T he proj ect sponsor has concerns about the demand f or saf ety f or the H i nt: Shocki ng.
el ectri cal requi rements f or the proj ect work. T he concerns about saf ety shoul d be Ref erence: PM P Study Gui de, Chapter 5
documented as whi ch one of the f ol l owi ng? Study Gui de Obj ecti ve: D ocument Proj ect Ri sks, Assumpti ons, and Constrai nts
A. I ni ti al ri sk A i s correct. T he concerns surroundi ng the el ectri cal work descri be a ri sk. T hi s i s
B. Cost of qual i ty an exampl e of a pure ri sk because thi s dangerous acti vi ty can onl y have negati ve
C. Product requi rement outcomes i f someone i s i nj ured. An i nvestment, such as purchasi ng f aster computer
D . Assumpti on equi pment, i s a busi ness ri sk because i t can have a posi ti ve or negati ve outcome.
B i s i ncorrect
Answer: A because the cost of qual i ty descri bes the expense to ascertai n the
Y ou are a proj ect manager and you want to perf orm some anal ysi s of def ects and
expected
H i nt: F i shy. i ty. C i s i ncorrect because a product requi rement descri bes the
qual
probl ems that have been di scovered i n the proj ect. Whi ch chart can reveal f actors
requi
Ref rements
erence: PMthe proj ectGui
P Study must
de,adhere
Chapter to.
8 D i s i ncorrect because an assumpti on i s
that mi ght be l i nked to potenti al probl ems wi thi n your proj ect?
when
Studysomethi
Gui de ng
Obji secti
assumed but
ve: I mpl not proven.
ement Qual i tyAssumpti ons can
M anagement Plbecome
an ri sks, but thi s
A. An I shi kawa di agram
iAsinot the best
s correct answeran
because i nI thi
shi skawa
scenari o.
di agram, al so cal l ed a cause-and-ef f ect
B. A control chart
C. A Pareto chart di agram, reveal s potenti al probl ems that contri bute to ef f ects.

D . A f l owchart B i s i ncorrect because control charts show i f a proj ect i s stabl e and predi ctabl e.
C i s i ncorrect because Pareto charts show categori es of f ai l ure. D i s i ncorrect
because f l owcharts hel p anal yz e how probl ems occur.
Y ou are a proj ect manager consul tant f or a new proj ect that wi l l uti l i z e a vi rtual
Answer: D
team. Vi rtual teams make al l of the f ol l owi ng possi bl e except f or whi ch one?
H i nt: Y ou sti l l have thi s.
A. I ncl udi ng peopl e wi th mobi l i ty handi caps
Ref erence: PM P Study Gui de, Chapter 9
B. I ncl udi ng peopl e that work f rom home of f i ces
Study Gui de Obj ecti ve: M anage Resource Al l ocati on
C. Al l owi ng proj ects to progress that otherwi se woul d have been cut due to travel
D i s correct because thi s i s a f al se statement about vi rtual teams.
expenses
A, B, and C are i ncorrect because each i s a true statement about vi rtual teams.
D . Reduci ng the amount of ti me dedi cated to meeti ngs and communi cati ons

Y ou are a proj ect manager f or your organi z ati on. Y our proj ect has a BAC of Answer: D
$250,000 and i s expected to l ast ten months. Currentl y the proj ect i s i n month si x H i nt: D oubl e-check your work.
and i s 40 percent compl ete, but the proj ect was expected to be 60 percent Ref erence: PM P Study Gui de, Chapter 7
compl ete by thi s ti me. Y ou have spent $125,000 to compl ete the work. What i s Study Gui de Obj ecti ve: M easure Proj ect Perf ormance
the cost perf ormance i ndex of the proj ect? D i s correct. T he cost perf ormance i ndex i s cal cul ated by di vi di ng the earned
A. 80 val ue by the actual costs. I n thi s i nstance, the f ormul a i s CPI = 100,000/125,000.
B. 1.25 T hi s resul ts i n .80.
C. $125,000 A i s i ncorrect. T he CPI i s .80, not 80. B i s i ncorrect because thi s i s not the ri ght
D . .80
Y ou are a proj ect manager f or your organi z ati on. Y our proj ect has a BAC of val ue. CBi s i ncorrect. T he CPI i s not a dol l ar amount, so thi s val ue i s i ncorrect.
Answer:
$250,000 and i s expected to l ast ten months. Currentl y the proj ect i s i n month si x H i nt: N ot a dol l ar amount.
and i s 40 percent compl ete, but the proj ect was expected to be 60 percent Ref erence: PM P Study Gui de, Chapter 7
compl ete by thi s ti me. Y ou have spent $125,000 to compl ete the work. What i s Study Gui de Obj ecti ve: M easure Proj ect Perf ormance
the schedul e perf ormance i ndex of the proj ect? B i s correct. T he schedul e perf ormance i ndex (SPI ) i s cal cul ated by di vi di ng the
A. .80 earned val ue by the pl anned val ue. I n thi s i nstance, the f ormul a i s
B. .67 $100,000/150,000 = .67.
C. $67,000 A i s i ncorrect. T hi s i s the val ue of the cost perf ormance i ndex. C and D are
D . $80,000
Y ou are a proj ect manager f or your organi z ati on. Y our proj ect has a BAC of iAnswer:
ncorrectD because the SPI i s not a dol l ar amount.

$400,000 and i s expected to l ast one year. T he proj ect work i s schedul ed to be H i nt: F i nd out how much shoul d have been spent.
compl eted i n equal amounts each month. Currentl y the proj ect i s i n month three Ref erence: PM P Study Gui de, Chapter 7Study Gui de Obj ecti ve: M easure Proj ect
but i s onl y 20 percent compl ete. Y ou have spent $35,000 to compl ete the work. Perf ormance
What i s the pl anned val ue f or thi s proj ect? D i s correct. T he pl anned val ue i s the amount the proj ect shoul d have spent to
A. $20,000 reach thi s poi nt i n the schedul e. Because the proj ect i s schedul e to l ast one year
B. $35,000 wi th the work compl eted i n part each month, month three represents 25 percent of
C. $80,000 the proj ect, or $100,000.
D . $100,000
Y ou are a proj ect manager f or your organi z ati on. Y our proj ect has a BAC of A i s i ncorrect
Answer: B because $20,000 i s not the pl anned val ue. B i s i ncorrect because

$400,000 and i s expected to l ast one year. T he proj ect work i s schedul ed to be $35,000
H i s the
i nt: F i nd the actual
percentcost.
complCete.
i s i ncorrect because $80,000 i s the earned val ue.

compl eted i n equal amounts each month. Currentl y, the proj ect i s i n month three Ref erence: PM P Study Gui de, Chapter 7Study Gui de Obj ecti ve: M easure Proj ect
but i s onl y 20 percent compl ete. Y ou have spent $35,000 to compl ete the work. Perf ormance
What i s the earned val ue f or thi s proj ect? B i s correct. T he earned val ue f or thi s proj ect i s 20 percent compl ete. T he f ormul a
A. N egati ve $20,000 i s E V= % compl ete × BAC.
B. $80,000 A i s i ncorrect. T he E V i s not a negati ve number because i t i s 20 percent compl ete.
C. $100,000 C i s i ncorrect because $100,000 i s the pl anned val ue amount. D i s i ncorrect. T here
D . N ot enough i nf ormati on to know i s enough i nf ormati on to cal cul ate the f ormul a.
PMP Exam Practice Test And Study Guide
Study this set o nline at: https://www.cram.co m/flashcards/pmp-exam-practice-test-
and-study-guide-56 32748
Y ou are compl eti ng a proj ect to bui l d a park i n a communi ty. T he communi ty i s Answer: C
hosti ng a meeti ng where resi dents can ask you questi ons and cl ari f y the park’s H i nt: I t’s about peopl e.
goal s and f eatures. Y ou i nsi st that the proj ect team attend thi s meeti ng. Why Ref erence: PM P Study Gui de, Chapter 1
shoul d the proj ect team attend? Study Gui de Obj ecti ve: E nsure Common Understandi ng and Set E xpectati ons
A. T he team i s needed to show the publ i c the expert that you have empl oyed to C i s correct because the proj ect team needs to see the i mpact of thei r proj ect on
bui l d an excel l ent park f or them. the communi ty and how the communi ty may af f ect the proj ect outcome.
B. T he team may have answers to some of the questi ons the publ i c may ask. A i s i ncorrect because thi s i s not a val i d reason f or havi ng the team present. B i s
C. T he team needs to understand how the proj ect wi l l af f ect the peopl e and vi ce i ncorrect because the proj ect manager wi l l be answeri ng the questi ons f rom the
versa.
Y ou are hi ri ng another organi z ati on to compl ete a proj ect f or your organi z ati on. communi
Answer: Dty. Whi l e the proj ect team may f i el d some questi ons, thi s i s not the best
D . Tch
Whi he document
team i s needed
woul dto see
i ncl thei nf
ude i mpact
ormatiof
onthe projperf
about ectormance
on the communi ty.
reporti ng reason
H i nt: Tfhere’s
or theino
r i nvol vement.
contract yetD i s i ncorrect because thi s does not answer the
requi rements, operati on transf er i ssues, and post-proj ect support of the questi on asPM
Ref erence: compl etel yGui
P Study as choi ce C. 12
de, Chapter
del i verabl e? Study Gui de Obj ecti ve: Obtai n Pl an Approval
A. Proposal D i s correct because the SOW provi des al l these el ements.
B. Request f or proposal A i s i ncorrect because the proposal does not provi de these el ements but f ocuses
C. Bi d on how the sol uti on can be i mpl emented. B i s i ncorrect because the RF P asks the
D . Statement of Work vendor to provi de a proposal . C i s i ncorrect because thi s document comes f rom the
vendor
Answer:to
D the buyer and i s f ocused on pri ce onl y.
Y ou are managi ng a proj ect i n a matri x-structured organi z ati on. Y ou woul d l i ke to
create a chart that depi cts each department’s contri buti ons to the proj ect. H i nt: I t organi z es the work.

Whi ch one of the f ol l owi ng can best accompl i sh thi s goal ? Ref erence: PM P Study Gui de, Chapter 9

A. Work breakdown structure Study Gui de Obj ecti ve: I denti f y Proj ect T eam and D ef i ne Rol es and

B. Proj ect network di agram Responsi bi l i ti es

C. T ext-ori ented organi z ati on chart D i s correct because the organi z ati onal breakdown structure shows the hi erarchy

D . Organi z ati onal breakdown structure of the organi z ati on and l i sts each department’s contri buti ons to the proj ect.
A i s i ncorrect because the WBS l i sts the del i verabl es of the proj ect, not whi ch
department
Answer: D wi l l contri bute to the creati on of the WBS del i verabl es. B i s
Y ou are prepari ng f or stakehol der engagement i n your proj ect. Al l of the f ol l owi ng i ncorrect
H i nt: N otbecause
ri sky. the proj ect network di agram shows the workf l ow of acti vi ti es
i tems wi l l be needed as part of stakehol der engagement except f or whi ch one? wi
Refthi n the proj
erence: PM ect. C i sGui
P Study i ncorrect because
de, Chapter 13 a text-ori ented organi z ati on chart does
A. T he proj ect management pl an not
Study Gui de Obj ecti ve: M anage Stakeholbuti
show department-by-department contri der Eons to the proj ect work.
ngagement
B. T he i ssue l og D i s correct because the ri sk management pl an i s not an i nput to the control
C. Work perf ormance data stakehol der engagement process. T here are f our i nputs to thi s process: the proj ect
D . T he ri sk management pl an management pl an, i ssue l ogs, proj ect documents, and work perf ormance data.
A i s i ncorrect because the proj ect management pl an i s an i nput to the control

Y ou are the proj ect manager f or a new constructi on proj ect. T here are several stakeholBder engagement process. B i s i ncorrect because the i ssue l og i s an i nput
Answer:
bui l di ng codes that your proj ect team must adhere to duri ng the desi gn and to
H i the
nt: Ycontrol
ou muststakehol
adhere der engagement
to the codes. process. C i s i ncorrect because work
constructi on phases of your proj ect. T he bui l di ng codes are exampl es of whi ch perf ormancePM
Ref erence: data i s an iGui
P Study nputde,
toChapters
the control stakehol
1 and 5 der engagement process.

one of the f ol l owi ng? Study Gui de Obj ecti ve: D ef i ne and Record Requi rements, Constrai nts, and
A. Standards Assumpti ons
B. Government-i mposed requi rement B i s the best choi ce because bui l di ng codes are an exampl e of a government-
C. Qual i ty management concern i mposed requi rement.
D . Scope A i s i ncorrect. Standards are opti onal , regul ati ons are not. C i s i ncorrect. Whi l e

Y ou are the proj ect manager f or a new sof tware devel opment proj ect f or a cl i ent. qual i tyCmay be af f ected by adherence to the bui l di ng code, B
Answer:
Y ou are expl ai ni ng to the cl i ent the approach you’l l use to i denti f y, pl an, and answers theand
H i nt: Over questi
over.on more accuratel y. D i s i ncorrect because scope does not
manage the ri sks wi thi n the proj ect. Whi ch best descri bes when ri sk answer the questi
Ref erence: on
PM P Study Gui de, Chapter 11
i denti f i cati on occurs? Study Gui de Obj ecti ve: M oni tor Al l Ri sks
A. E arl y i n the proj ect C i s correct because ri sk i denti f i cati on i s an i terati ve process. T he proj ect team
B. D uri ng proj ect i ni ti ati on must proacti vel y l ook f or ri sks.
C. I terati vel y A i s i ncorrect because ri sk doesn’t happen onl y earl y i n the proj ect, but throughout
D . As schedul ed by the ri sk management pl an the proj ect. B i s i ncorrect because ri sk i denti f i cati on doesn’t happen i n

Y ou are the proj ect manager f or an organi z ati on compl eti ng a proj ect f or your iAnswer:
ni ti ati on,
C but i terati vel y throughout the proj ect. D i s i ncorrect because ri sk
customer. Y our boss approaches you and asks that you add a f ew f eatures to the iHdenti f i
i nt: I t’scati
noton happens
your sans schedul
del i verabl e. e, as needed.

del i verabl e your proj ect team i s creati ng as part of the proj ect. What shoul d you Ref erence: PM P Study Gui de, Chapter 4
do next? Study Gui de Obj ecti ve: Veri f y and M anage Changes to the Proj ect
A. I nstruct the team to add the f eatures. C i s correct because the customer must approve any changes to the proj ect
B. Consul t wi th the customer about the f eatures your proj ect team i s addi ng to del i verabl e.
the proj ect scope. A i s i ncorrect because the customer must f i rst approve proposed changes. B i s
C. Ask the customer i f they woul d l i ke the f eatures as part of the del i verabl e. i ncorrect because the proj ect manager must gai n approval f rom the customer i n
D . Add
Y ou are the
the fproj
eatures but document
ect manager f or thethem
creatii non
anofapproved change request.
a new warehouse i n Knoxvi l l e, order
Answer: toBmake the changes. D i s i ncorrect because i t ci rcumvents the change

T ennessee. Y ou and the proj ect team are creati ng the scope statement and are management
H i nt: Y ou’reprocess.
exami ni ng the del i verabl e.
eval uati ng the f uncti on, purpose, and acti vi ti es that wi l l take pl ace wi thi n the Ref erence: PM P Study Gui de, Chapter 5
warehouse to hel p the proj ect customer gather al l of the requi rements f or the Study Gui de Obj ecti ve: D ef i ne Scope
scope. T hi s process i s an exampl e of whi ch one of the f ol l owi ng? B i s correct. Product anal ysi s consi sts of product breakdown and f uncti onal
A. E xpert j udgment anal ysi s.
B. Product anal ysi s A i s i ncorrect because expert j udgment rel i es on experts to devel op a porti on of
C. Work breakdown structure creati on the detai l ed proj ect scope statement. C i s i ncorrect because thi s i s not an
D . Scope change control exampl e of the WBS creati on. D i s i ncorrect because the scope has not been
PMP Exam Practice Test And Study Guide
Study this set o nline at: https://www.cram.co m/flashcards/pmp-exam-practice-test-
and-study-guide-56 32748
Y ou are the proj ect manager f or your organi z ati on and you’re exami ni ng several Answer: C

proj ects you’re managi ng f or your company. I n your anal ysi s, you’ve noti ced that one H i nt: CPI i s the cost perf ormance i ndex. Ref erence: PM P Study Gui de, Chapter 7

of your proj ects has a CPI of .98. A proj ect that has a CPI of .98 means what? Study Gui de Obj ecti ve: M easure Proj ect Perf ormance

A. T he proj ect i s l ate. C i s correct. A proj ect wi th a CPI of .98 has to spend one dol l ar f or every 98 cents

B. T he proj ect i s maki ng money. worth of work i t recei ves.

C. T he proj ect has to spend one dol l ar f or every 98 cents worth of work i t recei ves. A i s i ncorrect. T here i s no evi dence that the proj ect i s l ate. B i s i ncorrect because

D . T he proj ect i s 98 percent compl ete. the proj ect i s actual l y l osi ng money wi th thi s CPI , not maki ng i t. D i s i ncorrect
because a CPI of .98 does not mean the proj ect i s 98 percent compl ete.

Y ou are the proj ect manager f or your organi z ati on and you’re exami ni ng several Answer: A

proj ects you’re managi ng f or your company. I n your anal ysi s, you’ve noti ced that one H i nt: SPI i s the schedul e perf ormance i ndex.

of your proj ects has an SPI of .80. A proj ect wi th an SPI of .80 means what? Ref erence: PM P Study Gui de, Chapter 7

A. T he proj ect i s behi nd schedul e. Study Gui de Obj ecti ve: M easure Proj ect Perf ormance

B. T he proj ect i s ahead of schedul e. A i s correct. A schedul e perf ormance i ndex of .80 means the proj ect i s behi nd

C. T he proj ect i s l osi ng money. schedul e. T he cl oser to “1” the SPI i s, the better the proj ect.

D . T he proj ect i s 80 percent compl ete. B i s i ncorrect. An SPI of .80 means the proj ect i s behi nd schedul e, not ahead. C i s
i ncorrect. Whi l e the proj ect l i kel y wi l l resul t i n bei ng over budget due to the

Y ou are the proj ect manager f or your organi z ati on and you’re worki ng wi th lAnswer:
abor demands
B to compl ete the proj ect, the SPI deal s wi th the proj ect schedul e.

management and several subj ect matter experts to create the proj ect scope D
H i nt: Understand.SPI does not ref l ect the percent compl ete of the proj ect.
i s i ncorrect. An

statement. Once the statement i s compl ete, you menti on that the key proj ect Ref erence: PM P Study Gui de, Chapter 5
stakehol ders shoul d recei ve a copy of the proj ect scope statement. Why shoul d Study Gui de Obj ecti ve: E nsure Common Understandi ng and Set E xpectati ons
the key stakehol ders recei ve a copy of the proj ect scope statement? B i s correct because the proj ect scope expl ai ns what the proj ect wi l l accompl i sh.
A. T o ensure that al l of the key stakehol ders have been i denti f i ed. A i s i ncorrect because thi s i s part of communi cati ons management. C i s i ncorrect
B. T o ensure that al l of the key stakehol ders have a common understandi ng of the because thi s i s part of human resources management. D i s i ncorrect because thi s i s
proj ect. accompl i shed i n the proj ect charter.
C.
Y ouT oare
ensure thatect
the proj al lmanager
of the proj
f or ect
yourteam
organimembers are you’re
z ati on and accounted
workifng
or among the
wi th the Answer: C
f uncti
proj ectonal managers.
team to def i ne the change control system. Y ou want to capture the correct H i nt: Revi ew i t.
D
i nf. ormati
T o ensure that changes
on when the proj ect manager i sand
are presented i denti
analf iyz
ed.
ed f or your proj ect. Whi ch one Ref erence: PM P Study Gui de, Chapter 4
of the f ol l owi ng must be compl eted f or each change that i s proposed f or a Study Gui de Obj ecti ve: Veri f y and M anage Changes to the Proj ect
proj ect? C i s correct because i ntegrated change control cal l s f or al l of the knowl edge
A. T he proj ect charter must be exami ned. areas, i ncl udi ng ri sks, to be revi ewed f or the i mpact of the proposed change.
B. T he proj ect l i f e cycl e costs must be revi ewed. A i s i ncorrect because the charter does not have to be exami ned. B i s i ncorrect
C. T he change must be revi ewed f or any associ ated ri sks. because the l i f e cycl e costs concern the cost of the proj ect’s del i verabl e once
Dou
Y . T are
he benef i t/cost
the proj rati o must
ect manager be revi
f or your ewed.
organi z ati on and you’re worki ng wi th your i t’s i n producti
Answer: C on. I n some i nstances, l i f e-cycl e costi ng may be appropri ate, but

supervi sor to def i ne the di f f erence between proj ects and operati ons. Y ou expl ai n not i nProj
H i nt: everyects
i nstance of a change request. D i s i ncorrect because benef i t/cost
are temporary.
that proj ects are uni que whi l e operati ons are the core busi ness. Proj ects are rati
Ref os are aPM
erence: method f or sel
P Study Guiecti
de, ng proj ects,
Chapter 1 not eval uati ng change requests.
typi cal l y i ni ti ated f or al l of the f ol l owi ng reasons except f or whi ch one? Study Gui de Obj ecti ve: Conduct Proj ect Sel ecti on M ethods
A. M arket demand C i s correct. I t descri bes operati ons—an ongoi ng f uncti on of an organi z ati on.
B. Organi z ati onal need Proj ects have a def i ni te endi ng, whi l e operati ons wi l l conti nue l onger than the
C. Ongoi ng manuf acturi ng of equi pment proj ect’s durati on.
D . Legal requi rements A, B, and D are i ncorrect because they are l egi ti mate reasons f or proj ects to be

Y ou are the proj ect manager f or your organi z ati on and you’ve i denti f i ed several iAnswer:
ni ti ated.
B
mi stakes i n the proj ect del i verabl es. Y ou’d l i ke to i nvesti gate the i ssue more H i nt: H ooked you.
cl osel y and your proj ect sponsor recommends you create an I shi kawa di agram. Ref erence: PM P Study Gui de, Chapter 8
What i s an I shi kawa di agram? Study Gui de Obj ecti ve: E nsure Proj ect D el i verabl es Conf orm to Qual i ty
A. A control chart Standards
B. A f i shbone di agram B i s correct because an I shi kawa di agram i s al so cal l ed a f i shbone di agram. I t’s
C. A scatter di agram al so known as a cause-and-ef f ect di agram.
D . A Pareto chart A i s i ncorrect because a control chart i s used to predi ct perf ormance. C i s

Y ou are the proj ect manager f or your organi z ati on and you’ve tol d management that iAnswer:
ncorrectC because a scatter di agram shows the pattern of rel ati onshi p between two

you’l l be usi ng the cri ti cal chai n method f or thi s proj ect. M anagement i s unaware vari abl
H i nt: Nes. D i s i. ncorrect because a Pareto chart shows categori es of f ai l ure.
ot CPM
of thi s approach and they want to know more about i t. What i s the cri ti cal chai n Ref erence: PM P Study Gui de, Chapter 6
method? Study Gui de Obj ecti ve: M anage Resource Al l ocati on
A. I t uti l i z es j ust-i n-ti me orderi ng. C i s correct because the cri ti cal chai n method accounts f or l i mi ted resources. F or
B. I t f i nds the l ongest path to proj ect compl eti on and al l ows f l oat on the other exampl e, a structural engi neer may be needed on two concurrent acti vi ti es, but she
acti vi ti es i n the proj ect. can onl y work on one acti vi ty at a ti me.
C. I t i s a schedul e network anal ysi s that accounts f or l i mi ted resources. A i s i ncorrect because thi s schedul i ng method i s not appl i cabl e to thi s scenari o.
D . I t i s a proj ect network di agram wi th the proj ect f l oat exposed. B i s i ncorrect
Answer: C because thi s descri bes the cri ti cal path method. D i s i ncorrect
Y ou are the proj ect manager f or your organi z ati on whi ch wi l l uti l i z e contract
because
Ref erence:thiPM
s i sPthe cri tiGui
Study calde,
path method.
Chapter 9
l abor on your proj ect. T he l abor wi l l be part of a uni on workf orce. Whi ch pl an
def i nes uni on contracts? H i nt: N ot ri sky.Study Gui de Obj ecti ve: I mprove T eam Perf ormance

A. T he proj ect pl an C i s correct because the staf f i ng management pl an does def i ne compl i ance i ssues

B. T he procurement management pl an wi th uni on contracts.

C. T he staf f i ng management pl an A i s i ncorrect because thi s i s too broad an answer. B i s i ncorrect because thi s pl an

D . T he ri sk management pl an def i nes the procurement pol i ci es of the organi z ati on. D i s i ncorrect because thi s
pl an def i nes ri sk management f or the proj ect.
PMP Exam Practice Test And Study Guide
Study this set o nline at: https://www.cram.co m/flashcards/pmp-exam-practice-test-
and-study-guide-56 32748
Y ou are the proj ect manager f or your organi z ati on. Y our management team i s
determi ni ng whi ch proj ect shoul d be i ni ti ated based on the present val ue of two Answer: A

proj ects. Proj ect A wi l l be worth $750,000 i n three years. Proj ect B wi l l be worth H i nt: Present val ue needs di vi si on.

$478,000 i n two years. What i s the present val ue of Proj ect A i f the i nterest rate i s Ref erence: PM P Study Gui de, Chapter 4

6 percent? Study Gui de Obj ecti ve: Conduct Proj ect Sel ecti on M ethods

A. $630,000 A i s correct. I t uses the f ormul a of F V/(1.06)3 to f i nd the present val ue.

B. $45,000 B, C, and D are al l i ncorrect cal cul ati ons f or the present val ue.

C. $710,000
D . Z ero Answer: C
Y ou are the proj ect manager i n a proj ecti z ed organi z ati on. Y ou bel i eve i n the
E xpectancy T heory. Whi ch one of the f ol l owi ng mechani sms wi l l promote and H i nt: Oh goody!

rei nf orce desi red behavi or f rom your proj ect team? Ref erence: PM P Study Gui de, Chapter 9

A. E xpert j udgment Study Gui de Obj ecti ve: M anage Resource Al l ocati on

B. Lectures and moti vati onal speeches C i s correct because rewards and recogni ti on are i deal methods f or promoti ng

C. Rewards desi red behavi or.

D . Puni shments f or poor proj ect perf ormance A i s i ncorrect because expert j udgment won’t rei nf orce desi red behavi or f rom the
proj ect team. B i s i ncorrect because l ectures and moti vati onal speeches are not as

Y ou are the proj ect manager of a constructi on proj ect f or a new cl i ent. T he cl i ent ef f ecti ve
Answer: C as rewards and recogni ti on systems. D i s i ncorrect because there’s no
has asked that you i ncl ude an outdoor deck as part of the proj ect—somethi ng iHncenti
i nt: N ot to
ve dosiwel
the l , onl ynecessari
gnature, an i ncenti
l y.ve to not do poorl y.
your company doesn’t normal l y do, but you agree to take on thi s proj ect component Ref erence: PM P Study Gui de, Chapter 12
usi ng a contractor to bui l d the seati ng deck. F or thi s porti on of the proj ect, you Study Gui de Obj ecti ve: I mpl ement the Procurement of Proj ect Resources
woul d l i ke to use a ti me and materi al s contract. What must thi s contract type C i s correct because a T &M contract must have a not-to-exceed (N T E ) cl ause,
have? otherwi se the cost can spi n out of control .
A. T he si gnature of the purchasi ng agent A i s i ncorrect because whi l e a si gnature i s needed on most contracts, a T &M
B. An end date f or the procured work demands an N T E cl ause... or el se. B i s i ncorrect because not al l T &M contracts
C.
Y ouA not-to-exceed
are the proj ect cl ause of a home constructi on proj ect. Y ou are i ntervi ewi ng
manager requi
Answer:re Dan end date. D i s i ncorrect because changes can spur new contracts, be
D . Addendums
the homeownersf toor each change
determi i nrthe
ne thei projand
wants ect needs
work f or the home constructi on. Y ou covered
H i nt: Y oubycannot
the exido
stithi
ng sTal
&M contract, or have addendums.
one.
are di scussi ng, room by room, what they’d l i ke i n thei r home. T hi s l ong process i s Ref erence: PM P Study Gui de, Chapter 5
cal l ed what? Study Gui de Obj ecti ve: I denti f y and Perf orm Stakehol der Anal ysi s
A. Ri sk anal ysi s D i s correct because the questi on descri bes stakehol der anal ysi s. I ntervi ewi ng
B. Qual i ty determi nati on the proj ect stakehol ders i s a common stakehol der anal ysi s acti vi ty to promote
C. Scope creati on stakehol der engagement.
D . Stakehol der anal ysi s A i s i ncorrect because ri sk anal ysi s i nvol ves determi ni ng the i mpact of the ri sk

Y ou are the proj ect manager of a l arge i nternati onal proj ect. Y our proj ect team events. B
Answer: A i s i ncorrect because thi s term i s not appl i cabl e to the questi on. C i s
wi l l be travel i ng to f our di f f erent countri es to compl ete the proj ect work. Y ou iHncorrect
i nt: I t’sbecause
not aboutstakehol
ri sk. der anal ysi s contri butes to scope creati on, but i t i s not
have requi red the proj ect team to compl ete trai ni ng regardi ng the customs, l aws, scope creatiPM
Ref erence: onPofStudy
i tsel fGui
. de, Chapter 1

and l anguages f or each country they wi l l be travel i ng to. What theory bel i eves Study Gui de Obj ecti ve: E nsure Common Understandi ng and Set E xpectati ons
that an understandi ng of the cul ture, l ocal l anguage, and col l oqui al i sms al l ows A i s correct. T he Sapi r-Whorf hypothesi s states that an understandi ng of the
peopl e to have a better understandi ng of the country they’re worki ng i n? cul ture, l ocal l anguage, and col l oqui al i sms al l ows peopl e to have a better
A. T he Sapi r-Whorf hypothesi s understandi ng of the country they’re worki ng i n.
B. E thnocentri sm B i s i ncorrect because ethnocentri sm i s when an i ndi vi dual measures another
C. Cul ture shock cul
Answer:ture C
by thei r own cul ture. C i s i ncorrect because cul ture shock descri bes the
Y ou are the proj ect manager of a l arge proj ect f or your organi z ati on. M anagement
D . Uti l i ty f uncti on iHnii ti
nt: N ot sori
al di entati on peopl e f eel when they f i rst arri ve i n a f orei gn cul ture. D i s
money.
has j ust cal l ed to l et you know that they wi l l be parti ci pati ng i n a new ri sk audi t
iRef
ncorrect because
erence: thi s descri
PM P Study Gui de,bes a person’s
Chapter 11 wi l l i ngness to accept ri sk.
that wi l l begi n next week. What i s a ri sk audi t?
A. I t i s a process to see what ri sks are wi thi n a proj ect. Study Gui de Obj ecti ve: M oni tor Al l Ri sks

B. I t i s a process to determi ne the ri sk exposure f or a proj ect. C i s correct because a ri sk audi t determi nes the ef f ecti veness of ri sk responses.

C. I t i s a process to determi ne the ef f ecti veness of the ri sk responses. A i s i ncorrect because thi s answer descri bes the ri sk i denti f i cati on process. B i s

D . I t i s a process to determi ne the costs of ri sks. i ncorrect because thi s answer descri bes the ri sk anal ysi s process. D i s i ncorrect
because thi s answer descri bes the expected monetary val ue perf ormed i n

Y ou are the proj ect manager of a l arge proj ect that spans the Uni ted States. Y our quanti
Answer:tati
A ve ri sk anal ysi s
proj ect team i s non-col l ocated so your communi cati on and travel demands are H i nt: Poor Scotty.
hi gh. Y ou’ve made i t known that no changes can enter the proj ect unl ess the Ref erence: PM P Study Gui de, Chapter 3
stakehol der wanti ng the change compl etes a change request through your web- Study Gui de Obj ecti ve: I mpl ement Approved Changes
based change request f orm. I t has come to your attenti on that Scotty, a devel oper A i s correct because you want to i mpl ement correcti ve acti ons to prevent the
i n Phoeni x, has been al l owi ng stakehol ders to request changes to hi s work. What probl em f rom happeni ng agai n.
must you do i n thi s scenari o? B i s i ncorrect because you are not f ol l owi ng the change control system or
A. I mpl ement correcti ve acti on so Scotty won’t al l ow any more changes to the preventi ng the probl em f rom happeni ng agai n. C i s i ncorrect because you are
proj
Y ouect
are work wi thout
the proj usi ng the
ect manager of change
a l arge control
proj ect system.
to i nstal l 10,000 f i xtures across a Scotty’s
Answer: Dsupervi sor when i t comes to proj ect di sci pl i ne. D i s i ncorrect. Whi l e thi s
B. I nspect
campus. theproj
Y our changes thathas
ect team have entered
been thethei
l ate on projr ect
assiand
gnedthen have
work and you f ear the choi
H i nt:ce seems
E VM . appropri ate, not al l of the proj ect team members or the stakehol ders
Scotty
proj ectreverse any
wi l l be changes
l ate. youone
Whi ch doofnotthe
approve ofng
f ol l owi . provi des f orecasti ng f or the are
Ref ci rcumventi
erence: PM PngStudy
the change
Gui de,control
Chaptersystem—j
4 ust Scotty i n thi s i nstance. As the
C. M eet
proj ect? wi th Scotty and hi s supervi sor to di scuss what di sci pl i ne i s most proj ect manager, you need to address the probl
Study Gui de Obj ecti ve: E xecute T asks D ef i nedemi ndiProj
rectl y. IPl
ect n addi
an ti on, the
appropri ate. eval uati on and revi ew techni que
A. T he program questi on states
D i s correct that al
because l ofearned
the the proj
valect team members
ue management and a—esti
f ormul stakehol dersatare
mate
D . TMhe
B. eetgraphi
wi thcal
youreval
projuati
ect on
team
andmembers and key
revi ew techni questakehol ders i n l ocated
compl etithroughout the des
on (E AC)—provi Uni ted States,
f orecasti ngnot
f orjthe
ust proj
i n Phoeni x.
ect success.
Phoeni
C. Ri skxanal
and ysi
disscuss i n detai l the change management processes you’ve A i s i ncorrect because the program eval uati on and revi ew techni que (PE RT )
establ i shed.
D . T he esti mate at compl eti on provi des ti me esti mates, not f orecasti ng. B i s i ncorrect because the graphi cal
eval uati on and revi ew techni que (GE RT ) provi des branchi ng and l oopbacks i n
PMP Exam Practice Test And Study Guide
Study this set o nline at: https://www.cram.co m/flashcards/pmp-exam-practice-test-
and-study-guide-56 32748
Y ou are the proj ect manager of a new home constructi on proj ect. Y ou are Answer: B

i nspecti ng the home as part of qual i ty control . Y ou’ve noti ced f aul ty work duri ng H i nt: F i x i t.

one of your qual i ty control i nspecti ons. What i s needed? Ref erence: PM P Study Gui de, Chapter 4

A. Proj ect scope change control f or the new work Study Gui de Obj ecti ve: D evel op Change M anagement Pl an

B. Recommended def ect repai r f or the i ncorrect work B i s correct. Y ou typi cal l y f i nd f aul ty work duri ng qual i ty control i nspecti ons and

C. Change request f or the addi ti onal work then you make recommendati ons to f i x the probl ems.

D . Recommended correcti ve acti ons A i s i ncorrect because you are not changi ng the proj ect scope. C i s i ncorrect
because you are not requesti ng f or the proj ect scope to change wi th addi ti onal

Y ou are the proj ect manager of a proj ect that has a preset budget and must be work.
Answer: D Di s i ncorrect because you are not maki ng acti ons to bri ng f uture resul ts

compl eted wi thi n si x months. Y ou’ve compl eted the f i rst phase of your proj ect. back
H i nt: iDnto
o i al
t rii gnment
ght. wi th the proj ect pl an. Y ou are f i xi ng errors—thus, thi s i s

T he stakehol der, however, wants to know why one of the changes you and he def
Ref ect repai
erence: PMr. P Study Gui de, Chapter 8

di scussed was not i mpl emented i nto the del i verabl e. D uri ng the ori gi nal Study Gui de Obj ecti ve: Veri f y and M anage Changes to the Proj ect
conversati on about the change, the stakehol der wanted to perf orm a cost-benef i ts D i s correct because i n the change control system al l changes shoul d be f ormal l y
anal ysi s, whi ch he reported the resul ts of to you. What’s your response? documented. Undocumented change requests shoul d not be processed or
A. T he change was not needed. i mpl emented.
B. T he change woul d have cost too much. A i s i ncorrect because the change may have been needed but the f ai l ure to f ol l ow
C.
Y ouT he
arechange
the projwoul
ect dmanager
have taken
of a too
proj lect
ongthat
to del i ver.
must operate by your organi z ati on’s the change
Answer: C control system prevents the change f rom enteri ng the proj ect scope. B i s
D . T he change request was never documented
qual i ty pol i cy. M anagement has deci ded to examif or the
ne change
your projcontrol system. to
ect’s processes iHncorrect because
i nt: Looki there’s
ng f or proof of no menti
compl on of how much the change woul d cost the
i ance.
determi ne i f you are f ol l owi ng the qual i ty pol i cy. T hi s revi ew process i s known as projerence:
Ref ect. C iPM
s i ncorrect
P Studybecause there’s no
Gui de, Chapter 8 menti on of how much addi ti onal ti me
what? the change
Study woul
Gui de Objdecti
requi
ve:re.
I mpl ement Qual i ty M anagement Pl an
A. Qual i ty control C i s correct because a qual i ty audi t exami nes a proj ect to determi ne i f the
B. Qual i ty assurance proj ect i s compl yi ng wi th an organi z ati on’s qual i ty pol i ci es.
C. Qual i ty audi t A i s i ncorrect because QC exami nes the proj ect work to determi ne the qual i ty of
D . Qual i ty pl anni ng the proj ect del i verabl es. B i s i ncorrect because QA i s the company qual i ty pol i cy.

Y ou are the proj ect manager of a proj ect to i nstal l new l i ght f i xtures throughout D i s i ncorrect
Answer: B because qual i ty pl anni ng consti tutes those acti vi ti es that

several f actori es. T he proj ect i s expected to l ast one year and has a BAC of determi
H i nt: CPIne =how the proj ect wi l l adhere to the qual i ty demands of the
E V/AC
$750,000. T he proj ect i s now i n month f our and has a CPI of .89. Whi ch one of the organi z ati on.
Ref erence: PM P Study Gui de, Chapter 7
f ol l owi ng statements i s true about thi s proj ect? Study Gui de Obj ecti ve: M easure Proj ect Perf ormance
A. T he proj ect i s perf ormi ng wel l . B i s correct. T he proj ect wi th a CPI of .89 i s not doi ng too wel l . F or every dol l ar
B. T he proj ect spends one dol l ar f or 89 cents of work. the proj ect spends, i t l oses 11 cents.
C. T he proj ect wi l l l i kel y f i ni sh under budget. A i s i ncorrect. T he proj ect i s not perf ormi ng wel l . C i s i ncorrect. T he proj ect wi l l
D . T he proj ect wi l l l i kel y f i ni sh i n al i gnment wi th the cost basel i ne. l i kel y f i ni sh over budget. D i s i ncorrect. T he probabl y won’t be i n al i gnment wi th

Y ou are the proj ect manager of a sof tware devel opment proj ect. I n thi s proj ect, the costDbasel i ne.
Answer:
you wi l l approve or decl i ne proposed changes bef ore they are i ncorporated i nto H i nt: I t’s about change.
the proj ect pl an. Y ou have recentl y approved a change that wi l l i ncrease the Ref erence: PM P Study Gui de, Chapter 4
proj ect’s costs. What must you do next? Study Gui de Obj ecti ve: Veri f y and M anage Changes to the Proj ect
A. Prepare a cost vari ance report. D i s correct because the proj ect’s basel i nes must be changed to ref l ect the
B. E xami ne the overal l i mpact of the change request on the proj ect. added change.
C. E xami ne the di rect costs of the change. A i s i ncorrect because there’s no reasons to create a vari ance report; i t’s a change
D . Change the proj ect’s cost basel i ne to ref l ect the added change. not a cost overrun. B i s i ncorrect because thi s i s part of the process to approve the
change
Answer: request.
A T he change request has al ready been approved i n thi s i nstance. C
Y ou are the proj ect manager of the BD S Proj ect. Y our proj ect must be compl eted
iHsiint:
ncorrect because
Y ou must. thi s i s part of the process to approve the change request. T he
by October 13 and cannot exceed $250,000. October 13 i s an exampl e of whi ch
change request
Ref erence: PM Phas al ready
Study been
Gui de, approved
Chapter 3 i n thi s i nstance.
one of the f ol l owi ng?
A. A constrai nt Study Gui de Obj ecti ve: D ef i ne and Record Requi rements, Constrai nts, and

B. An earl y f i ni sh f or the proj ect Assumpti ons

C. A schedul ed compl eti on date A i s correct. T he proj ect must be compl eted by October 13th, so thi s date

D . An assumpti on ref l ects a constrai nt on the proj ect.


B i s i ncorrect because the proj ect may be abl e to f i ni sh earl i er than October 13.

Y ou are the proj ect manager of the BH Q M anuf acturi ng Proj ect. I n thi s proj ect, We do not
Answer: D have enough i nf ormati on to determi ne i f thi s i s the earl i est the proj ect
you have uti l i z ed a control chart to measure proj ect perf ormance of repeatabl e can
H i nt: F i x the eted.
be compl C i s i ncorrect because the proj ect coul d be schedul ed to
probl em.
acti vi ti es. Y ou are exami ni ng a control chart. When shoul d processes be f i ni erence:
Ref sh earl i PM
er than
P StudyOctober 13. Chapter
Gui de, T he constrai
8 nt i s that the proj ect be f i ni shed by
adj usted? October
Study Gui13. deDObj i s ecti
i ncorrect because
ve: E nsure Proj an
ectassumpti on i sessomethi
D el i verabl ngto
Conf orm bel i eved
Qual i ty to be
A. When the control chart’s mean i s too l ow. true, but not proven to be true.
Standards
B. When the control chart’s mean i s too hi gh. D i s correct because processes outsi de of acceptabl e l i mi ts shoul d be adj usted
C. When the process i s wi thi n acceptabl e l i mi ts. to bri ng the process i nto acceptabl e l i mi ts.
D . When the process i s outsi de of acceptabl e l i mi ts. A i s i ncorrect because the mean represents the average or predi cted average f or the

Y ou are the proj ect manager of the GH Q Proj ect f or your company. resul ts. AB i s i ncorrect because the mean represents the average or predi cted
Answer:
As part of proj ect i ni ti ati on, you need to i denti f y and anal yz e the proj ect average
H f or thepower,
i nt: T here’s resul ts.
butC not
i s i incorrect
mpact. because processes wi thi n acceptabl e l i mi ts
stakehol ders. M anagement recommends that you uti l i z e a sal i ence model as part shoul d not be
Ref erence: PMadj usted.
P Study Gui de, Chapter 13
of thi s acti vi ty. What three components are measured i n a sal i ence model ? Study Gui de Obj ecti ve: Obtai n Proj ect Charter Approval
A. Power, urgency, and l egi ti macy A i s correct. T he sal i ence model typi cal l y uses three ci rcl es to map out
B. Power, i nterest, and l egi ti macy stakehol ders’ power, urgency, and l egi ti macy i n the proj ect.
C. Power, i mpact, and l egi ti macy B i s i ncorrect because the sal i ence model onl y uses the characteri sti cs of power,
D . Power, urgency, and i mpact urgency, and l egi ti macy over the proj ect deci si ons and obj ecti ves. C i s i ncorrect
because the sal i ence model onl y uses the characteri sti cs of power, urgency, and
PMP Exam Practice Test And Study Guide
Study this set o nline at: https://www.cram.co m/flashcards/pmp-exam-practice-test-
and-study-guide-56 32748
Y ou are the proj ect manager of the H H A Proj ect f or your company. M anagement has Answer: A

asked you to present your approach to proj ect executi on. Whi ch of the f ol l owi ng H i nt: N ot a person.

def i nes how the proj ect i s executed? Ref erence: PM P Study Gui de, Chapter 4

A. T he proj ect management pl an Study Gui de Obj ecti ve: E xecute T asks D ef i ned i n Proj ect Pl an

B. T he work authori z ati on system A i s correct because the proj ect management pl an def i nes how the proj ect i s

C. T he proj ect executi on process group executed, moni tored and control l ed, and cl osed.

D . T he proj ect manager B i s i ncorrect because the work authori z ati on system tracks compl eted work and
al l ows schedul ed work to begi n. C i s i ncorrect because thi s statement i s not
val i d f or
Answer: B thi s questi on. D i s i ncorrect because the proj ect manager doesn’t sol el y
Y ou are the proj ect manager of the H N N Proj ect. Y our team needs saf ety trai ni ng
def i ne how the
H i nt: T he trai ni proj
ng i sect i s executed,
needed i n orderthe proj ect
to compl eteteam
the and expert j udgment may
proj ect.
i n order to i nstal l several of the components i n your proj ect. T he cost of thi s
al
Refsoerence:
contri bute.
PM P Study Gui de, Chapter 8
trai ni ng i s known as whi ch one of the f ol l owi ng?
A. T eam devel opment Study Gui de Obj ecti ve: E nsure Proj ect D el i verabl es Conf orm to Qual i ty

B. Cost of qual i ty Standards

C. Cost of nonconf ormance B i s correct because the cost of trai ni ng i s consi dered a cost of qual i ty.

D . Vari abl e costs A i s i ncorrect because trai ni ng i s one method of team devel opment, but the cost of
trai ni ng i s not. C i s i ncorrect because the cost of nonconf ormance to qual i ty i s the

Y ou are the proj ect manager of the H i ghway Automati on Proj ect and are costs that wi l l occur i f qual i ty i s not obtai ned. D i s i ncorrect because vari abl e

f aci l i tati ng the ri sk i denti f i cati on process wi th your proj ect team and other key costs
Answer:
descri
C bes costs that f l uctuate wi thi n a proj ect.

stakehol ders. Y ou have encouraged the parti ci pants to i denti f y as many proj ect H i nt: T hi s happens l ater.

ri sks as possi bl e. Al l of the f ol l owi ng are acceptabl e ri sk i denti f i cati on Ref erence: PM P Study Gui de, Chapter 11

techni ques except whi ch one? Study Gui de Obj ecti ve: I denti f y Ri sks and D ef i ne Ri sk Strategi es

A. T he D el phi T echni que C i s correct. Qual i tati ve anal ysi s happens af ter ri sk i denti f i cati on.

B. SWOT anal ysi s A, B, and D are i ncorrect because al l of these are ri sk i denti f i cati on methods.

C. Qual i tati ve anal ysi s


D . Root
Y ou cause
are the projanal
ectysi s
manager of the H ome Automati on Proj ect. Y ou are uncertai n Answer: D
what the f ee wi l l be f or wi ri ng the home wi th bundl ed cabl e so you hi re a vendor H i nt: Woul da-coul da.
to exami ne the home and create an esti mate f or the SOW you’ve prepared. Y ou’l l Ref erence: PM P Study Gui de, Chapter 12
use thi s esti mate f rom the vendor to measure al l other esti mates f rom vendors that Study Gui de Obj ecti ve: I mpl ement the Procurement of Proj ect Resources
want to bi d on the i nstal l ati on of the bundl ed cabl e. What i s thi s esti mate D i s correct because a shoul d-cost esti mate, al so known as an i ndependent
cal l ed? esti mate, i s prepared i n-house or by a thi rd party. T hi s esti mate then measures al l
A. Budget esti mate other esti mates agai nst i t.
B. D ef i ni ti ve esti mate A i s i ncorrect because thi s def i nes the mi d-stage esti mate f or the enti re proj ect.
C.ou
Y Good f ai th
are the esti
proj ectmate
manager of the KH Y Proj ect. T hi s proj ect i nvol ves 45 proj ect B i s i ncorrect because thi s i s the most-detai l ed esti mate based on the WBS f or
D . Shoul
team d-costf rom
members estiacross
mate your matri x-structured organi z ati on and wi l l l ast f or 18 the entiAnswer:
re proj C
ect. C i s i ncorrect because thi s i s not a val i d term.

months. Y ou have requested a central meeti ng room f or communi cati ons, proj ect H i nt: Y ou don’t decl are i t.

i nf ormati on, testi ng equi pment, and other proj ect-rel ated acti vi ti es. T hi s room i s Ref erence: PM P Study Gui de, Chapter 9

cal l ed what? Study Gui de Obj ecti ve: M anage Resource Al l ocati on

A. A resource request C i s correct because a war room i s a meeti ng room f or proj ect support.

B. A f aci l i ty resource request A, B, and D are i ncorrect because these terms are not val i d.

C. A war room
D . T he
Y ou areproj
theect
projheadquarters
ect manager of the KJP Proj ect. Y ou, the proj ect team, and the Answer: D
proj ect sponsor are worki ng together to compl ete qual i ty management pl anni ng. H i nt: Compari sons.
T he stakehol der has compared your current proj ect scope to a recentl y compl eted Ref erence: PM P Study Gui de, Chapter 8
proj ect that uti l i z ed Si x Si gma techni ques i n thei r proj ect. T hi s i s cal l ed what? Study Gui de Obj ecti ve: I mpl ement Qual i ty M anagement Pl an
A. Qual i ty assurance D i s correct because benchmarki ng i s when one proj ect i s compared to another.
B. Qual i ty control A i s i ncorrect because QA i s the organi z ati on-wi de program f or qual i ty. B i s
C. Stati sti cal anal ysi s i ncorrect because QC i s an i nspecti on to determi ne the exi stence of qual i ty. C i s
D . Benchmarki ng i ncorrect because stati sti cal anal ysi s i s the exami nati on of stati sti cs and
producti
Answer: Bon.
Y ou are the proj ect manager of the N GBB Proj ect. Y our proj ect team has f ai l ed
to compl ete the work as the proj ect management pl an demanded. What acti on H i nt: F i x i t.

wi l l the proj ect team now have to perf orm wi th your gui dance? Ref erence: PM P Study Gui de, Chapter 4

A. Qual i ty control Study Gui de Obj ecti ve: E xecute T asks D ef i ned i n Proj ect Pl an

B. D ef ect repai r B i s correct because the proj ect team wi l l have to f i x the def ects i n thei r work.

C. Peer revi ew A i s i ncorrect because QC i s based on i nspecti on. T he errors have al ready been

D . E xi t i ntervi ew i denti f i ed so the proj ect team must f i x the errors. C i s i ncorrect because peer
revi ew i s an exampl e of QC. T he proj ect team must f i x the probl ems. D i s i ncorrect

Y ou are the proj ect manager of the N H B Proj ect. Y ou’ve j ust l earned that the because
Answer: B thi s statement i s not appl i cabl e to the si tuati on. Sorry, but you don’t get
cost of materi al s wi l l i ncrease by 10 percent due to a hurri cane al ong the Gul f toi nt:
H f i reI t’s
your proj ect team members.
money.
Coast. Y ou woul d l i ke to update the cost basel i ne to ref l ect these Ref erence: PM P Study Gui de, Chapter 7
unanti ci pated changes. What system wi l l al l ow you to make these changes? Study Gui de Obj ecti ve: Veri f y and M anage Changes to the Proj ect
A. T he change control system B i s correct because procedures on how to change the cost basel i ne are
B. T he cost change control system documented i n the cost change control system.
C. T he change control board A i s i ncorrect because thi s does not answer the questi on as compl etel y as B. C i s
D . T he cost management system i ncorrect because the CCB may be part of the change control system, but B answers
the questi on compl etel y. D i s i ncorrect because thi s term i s not val i d.
PMP Exam Practice Test And Study Guide
Study this set o nline at: https://www.cram.co m/flashcards/pmp-exam-practice-test-
and-study-guide-56 32748
Y ou are the proj ect manager of the N H G Proj ect. Y our proj ect i s to create 8453 Answer: A
custom doorknobs f or a hotel . Y our proj ect team has compl eted the work, the H i nt: D one i s done.
customer has agreed to the proj ect del i verabl es, and has si gned of f on the Ref erence: PM P Study Gui de, Chapter 5
proj ect work. T he customer, however, asks you to drop of f the doorknobs to the Study Gui de Obj ecti ve: Obtai n F i nal Acceptance f or the Proj ect
next proj ect team that wi l l i nstal l the work. Y ou agree to do thi s. When you A i s correct because the proj ect i s done.
del i ver the doorknobs to the next proj ect team, thei r proj ect manager asks when B i s i ncorrect because, regardl ess of the team’s status, the proj ect has been
your team wi l l arri ve to hel p i nstal l the doorknobs. What shoul d you do? compl eted. C i s i ncorrect because there’s no need to do a change request—the
A. N othi ng. Y our proj ect i s done. proj ect i s compl eted. D i s i ncorrect because your proj ect i s done. I t’s up to the
B. N othi
Y ou ng. Y
are the ourect
proj projmanager
ect team
of has
themoved ontoect
N H H Proj other
andproj
areects.
worki ng wi th your proj ect proj ect B
Answer: manager of the i nstal l ati on proj ect to request f or addi ti onal l abor i f he
C. Compl ete a change request f or the i nstal l ati
team to create the WBS. One porti on of the WBS cannot be on of the doorknobs.
decomposed unti l fHeel s i t’s needed.
i nt: Surf ’s up!
D . Consul
l ater t wi
i n the thect.
proj the customer
Y ou have to seeded
deci i f they’d
to wai lt iunti
ke you to hel
l more p i nstal
detai l the
l s become Ref erence: PM P Study Gui de, Chapter 5
doorknobs—f
avai l abl e aboutor a the
f ee.el ement and to decompose the del i verabl e at that poi nt. Study Gui de Obj ecti ve: Create the WBS
T hi s i s someti mes cal l ed what? B i s correct. T hi s approach i s someti mes cal l ed rol l i ng wave pl anni ng.
A. T he WBS templ ate A i s i ncorrect because thi s i s not an exampl e of a WBS templ ate. C i s i ncorrect
B. Rol l i ng wave pl anni ng because thi s term i s not val i d. D i s i ncorrect because thi s i s not an exampl e of
C. I terati ve WBS creati on scope creep.
D . Scope
Y ou creep
are the proj ect manager of the N H Q Proj ect f or your company. Y ou are worki ng Answer: C
wi th your proj ect team and the proj ect sponsor to create a stakehol der H i nt: Y ou’re executi ng a pl an.
management strategy. Y ou want to determi ne the needed l evel of i nteracti on Ref erence: PM P Study Gui de, Chapter 13
among the proj ect stakehol der. What document wi l l best hel p you compl ete thi s Study Gui de Obj ecti ve: M anage Stakehol der E ngagement
task? C i s correct. T he stakehol der management pl an i s an i nput to management
A. T he proj ect charter stakehol der engagements. T hi s pl an def i nes the needed l evel s of i nteracti ons of
B. T he stakehol der regi stry the proj ect stakehol ders.
C. T he stakehol der management pl an A i s i ncorrect. T he proj ect charter authori z es the proj ect and the proj ect manager,
D . T he proj ect management pl an but
Answer:i t doesn’t
C def i ne the i nteracti ons among the proj ect stakehol ders. B i s
Y ou are the proj ect manager of the N JQ i ncorrect. T heout.
stakehol der regi stry def i nes the proj ect stakehol ders, thei r
H i nt: I t’s not
Proj ect and you have created a chart as i n communi cati onPpref erences, andChapter
proj ect 8concerns. D i s i ncorrect. T he stakehol der
Ref erence: PM Study Gui de,
the exhi bi t. What i s the area hi ghl i ghted management
Study Gui de Obj ecti ve: I mpl ementect’s
pl an i s part of the proj Qual management pl an,Plbut
i ty M anagement an thi s i sn’t the best
i n the chart cal l ed? answer f or the questi on
C i s correct because thebecause
resul t ofthe stakehol
seven der management
measurements i n a row pl
onan i s si
one most
de of the
A. Out of control speci if n
i c.
mean a control chart i s cal l ed the “Rul e of Seven.” T hi s i s an assi gnabl e cause.
B. Wi thi n control
A i s i ncorrect because out of control means one measurement exceeds the control
C. Rul e of Seven
l i mi ts. B i s i ncorrect because i n control means that the resul t of one measurement
D . I mprovement of qual i ty
stayed wi
Answer: C thi n the control l i mi ts. D i s i ncorrect because the Rul e of Seven doesn’t
Y ou are the proj ect manager of the XH G Proj ect. Y our manager has determi ned
al
H iways si gnal
nt: Start at qual i ty i mprovement. I t coul d, i n some i nstances, si gnal that the
the end.
that the proj ect must be compl eted by January 31. I n order to meet thi s constrai nt,
mean i s set PM
Ref erence: tooPl ow f or the
Study Gui proj
de, ect.
Chapter 3
what wi l l you and the proj ect team l i kel y need to do?
A. Work overti me Study Gui de Obj ecti ve: D ef i ne and Record Requi rements, Constrai nts, and

B. Add more proj ect team members Assumpti ons

C. Schedul e backward f rom the compl eti on date C i s the best answer. An i mposed compl eti on date wi l l l i kel y requi re you and the

D . Requi re addi ti onal f unds proj ect team to schedul e f rom the compl eti on date.
A i s i ncorrect. T here’s no evi dence you must work overti me to compl ete the proj ect.

Y ou are tryi ng to determi ne i f you shoul d make or buy a pi ece of sof tware. I f you B i s i ncorrect
Answer: B because there’s no evi dence you wi l l need addi ti onal l abor to

create the sof tware, i t’l l cost your organi z ati on $45,000 to create i t and $3,400 compl ete the proj ect onthl
H i nt: (Bui l d-buy)/(M by they fschedul e date. I n addi ti on, the work may not be
ee di f f erence)
each month to support i t. A vendor, however, can create the sof tware f or $12,000 af
Reff ected
erence:byPM
the
P added l abor
Study Gui de,(consi dered
Chapter 12 acti vi ti es of f i xed durati on). D i s
and wi l l charge you $0.17 per transacti on, per month. Accordi ng to your i ncorrect.
Study T heObj
Gui de schedul edI mpl
ecti ve: compl eti on
ement date
the doesn’t necessari
Procurement l y correl
of Proj ect ate to more
Resources
cal cul ati ons, you’l l have 31,400 transacti ons each month. What shoul d you do? fBunds to compl
i s correct ete thethe
because proj ect.
sof tware wi l l “pay f or i tsel f ” i f i t i s used 17 months or
A. H i re the vendor i f the sof tware wi l l be kept l onger than 17 months. l onger. T hi s can be cal cul ated by f i ndi ng the di f f erence of the bui l d and buy,
B. H i re the vendor i f the sof tware wi l l be repl aced wi thi n 17 months. whi ch i s $33,000. T hen, you f i nd the di f f erence of the monthl y f ees, whi ch i s
C. H i re the vendor i f the transacti ons wi l l be l ess than 30,000 per month. $1,938. D i vi de the $33,000 by $1,938 and thi s tel l s you how l ong the vendor’s
D . Mare
Y ou akeworki
the sof
ng tware and reduce on
wi th management your monthl
the y expenses
proj ect pl anni ngby payi ng the
processes. vendor
T hey wantf or
to sol uti onBwi l l be val i d. I f the sof tware i s to be kept l onger than 17 months, i t
Answer:
the transacti ons.
know why you’re spendi ng ti me on ri sk management pl anni ng so earl y i n the proj ect woul
H i nt:dPlbe more
anni ng icost ef f ecti
s i terati ve. ve to bui l d the sof tware than to buy i t.
pl anni ng. Whi ch one of the f ol l owi ng i s the best response to management’s A i serence:
Ref i ncorrect
PMbecause
P Studyaf terde,
Gui 17Chapter
months the
11 bui l d sol uti on i s a better choi ce. C i s
concern? iStudy
ncorrect
Guibecause theve:
de Obj ecti questi
Obtaionnal
Plready expl ai ns that the permonth transacti on wi l l
an Approval
A. Al l proj ects have ri sks. be
B i smore thanbecause
correct 30,000. D i smanagement
ri sk i ncorrect because thidoes
pl anni ng s i s not a val i d
i ncrease choi
the cebi
possi (especi
l i ty ofal l y
B. Ri sk management pl anni ng i ncreases the probabi l i ty of success f or the other fsuccess
or the vendor).
f or the ri sk management processes.
ri sk management processes. A i s i ncorrect because ri sk management pl anni ng i s not about ri sk i denti f i cati on,
C. Ri sk management pl anni ng must happen bef ore any other pl anni ng acti vi ti es. but rather how to approach and conduct ri sk management acti vi ti es. C i s i ncorrect
D . Y ou
Y ou arefworki
eel , asngthe proj
wi th ectproj
your manager, that
ect team tothe projthe
create ect proj
has ect
too scope
many rifsks
or ato be
web- because
Answer: Cthi s statement i s not true. D i s i ncorrect because thi s concern centers on
successf
based ul . i cati on to gather i nf ormati on on cl i ents. H enry says the web
appl ri sk
H i nt:i denti f i cati
T here’s on andhere.
no storm response, not the approach to ri sk management.

appl i cati on can be created wi th JAVA programmi ng. Ref erence: PM P Study Gui de, Chapter 5
M arsha agrees, but i nsi sts the appl i cati on can al so be created wi th ASP Study Gui de Obj ecti ve: D ef i ne Scope
technol ogy. T hi s i s an exampl e of whi ch one of the f ol l owi ng? C i s correct. H enry and M arsha are proposi ng di f f erent approaches to compl eti ng
A. F orci ng the proj ect.
B. E xpert j udgment A i s i ncorrect because f orci ng means one person i s f orci ng the deci si on i n thei r
C. Al ternati ve i denti f i cati on f avor. B i s i ncorrect because M arsha and H enry are contri buti ng i deas, not rel yi ng
D . T eam stormi ng on someone el se to make the deci si on. D i s i ncorrect because M arsha and H enry
PMP Exam Practice Test And Study Guide
Study this set o nline at: https://www.cram.co m/flashcards/pmp-exam-practice-test-
and-study-guide-56 32748
Answer: B
Y ou f ear that your proj ect team i s bl oati ng thei r ti me esti mates f or thei r assi gned H i nt: Work expands.
acti vi ti es. What l aw addresses bl oated esti mates? Ref erence: PM P Study Gui de, Chapter 6
A. T he l aw of di mi ni shi ng returns Study Gui de Obj ecti ve: E xecute T asks D ef i ned i n Proj ect Pl an
B. Parki nson’s Law B i s correct because Parki nson’s Law states that work wi l l expand to f i l l the
C. T he Pareto pri nci pl e amount of ti me al l otted to i t.
D . T he conti ngency reserve A i s i ncorrect. T he l aw of di mi ni shi ng returns states that i ncreased l abor doesn’t
al ways guarantee an i ncrease i n the yi el d, and can even di mi ni sh an organi z ati on’s

Y ou have a proj ect that must be f i ni shed by Jul y 30 or your organi z ati on wi l l have overal
Answer:l prof
D i t. (See the PM P Study Gui de, Chapter 6 f or more detai l s.) C i s
to pay f i nes and penal ti es. M anagement i s adamant that you do not exceed more iHncorrect
i nt: Losebecause
the f at.the Pareto pri nci pl e i s the 80/20 rul e—f or exampl e, 80 percent
than $125,000 f or the proj ect budget. T he proj ect i s neari ng compl eti on but you of
Refyour busiPM
erence: nessP comes
Study fGui
romde,20 percent
Chapterof 4 your customers. D i s i ncorrect because
wi l l l i kel y mi ss the target end date. What can you do to meet the proj ect end the conti
Study Guingency
de Objreserve
ecti ve:i sI mpl
the ement
ti me alApproved
l otted f or schedul e sl i ppage. (See the PM P
Changes
date wi thout spendi ng more dol l ars on the proj ect? Study Gui de,because
D i s correct Chapterwhi
6.) l e i t does assume there are thi ngs to tri m i n the proj ect

A. N othi ng. Y ou wi l l have to spend more money to compl ete on ti me because you scope, i t i s the onl y opti on that won’t i ncrease costs and compl ete the proj ect by
wi l l need to buy more l abor. the schedul ed end date.
B. Crash the proj ect. A i s i ncorrect because thi s statement i s not true. B i s i ncorrect because crashi ng
C.
Y ouAdd
havel ag to the proj
created the ect.
proj ect schedul e and management has asked to revi ew the the projD
Answer: ect means you’l l be addi ng l abor, whi ch wi l l dri ve costs. C i s i ncorrect
D
schedul e. T hey havescope
. T ri m the proj ect of everythi
concerns ng lthat
that your abori sesti
notmates
af f ected by the
may be too faggressi
i nes andve. I f because l ag i s posi
H i nt: Resource l eveltii ve
ng ti
f l me (or wai
attens thetiresources.
ng ti me), so
Refthi s wi l lPM
erence: actual l y cause
P Study the
Gui de,
penal ti es. recommends resource l evel i ng, what wi l l l i kel y happen to your proj ect
management proj ect to
Chapter be l ate.
6 Study Gui de Obj ecti ve: Obtai n Pl an Approval
schedul e? D i s correct because resource l evel i ng wi l l typi cal l y requi re the proj ect durati on
A. N othi ng. Onl y more l abor wi l l be added. to i ncrease.
B. N othi ng. Onl y more costs wi l l be added. A i s i ncorrect because there i s no evi dence that more l abor i s avai l abl e, approved,
C. T he schedul e wi l l take l onger to compl ete. or al l owed. B i s i ncorrect because there’s no evi dence that more f unds wi l l be
D . T he proj ect durati on wi l l i ncrease. needed to compl ete the proj ect work. C i s i ncorrect because the creati on of the

Y ou have hi red a vendor to compl ete a proj ect f or your organi z ati on. T he vendor schedul
Answer: Ce wi l l not necessari l y take l onger to create. T he compl eti on of the proj ect
presents the proj ect as compl ete but you di sagree wi th the compl eteness of the wiilnt:
H l lA
i kel y take
deal l onger,
’s a deal . however.
proj ect. What shoul d you do? Ref erence: PM P Study Gui de, Chapter 12
A. Create a change request f or the vendor. Study Gui de Obj ecti ve: Obtai n F i nanci al , Legal , and Admi ni strati ve Cl osure
B. Consul t the proj ect sponsor f or advi ce. C i s correct because the contract sti pul ates the terms f or proj ect acceptance.
C. Ref erence the detai l s of the contract f or the acceptance of the proj ect A i s i ncorrect because a change request i sn’t needed unl ess you are addi ng
del i verabl es. del i verabl es to the proj ect scope. B i s i ncorrect because the proj ect sponsor may
D . Ref erence the detai l s of the l ocal l aw f or processes of arbi trati on. need to be i ncl uded i n the di scussi on, but the best choi ce i s to consul t the
contractDf i rst. D i s i ncorrect because the contract shoul d be consul ted bef ore any
Answer:
Y ou have hi red another company to compl ete a proj ect f or you. Y ou woul d l i ke to
opti
H i nt:ons of arbithe
Control trati on.ect scope f i rst.
proj
change some detai l s i n the proj ect scope whi ch wi l l af f ect the contract between
you and the vendor. Whi ch system woul d manage these changes? Ref erence: PM P Study Gui de, Chapter 5

A. T he schedul e change control system Study Gui de Obj ecti ve: D evel op Change M anagement Pl an

B. T he cost change control system D i s correct. E ven changes to the contracted work must f l ow through the scope

C. T he procurement management system change control system.

D . T he scope change control system A i s i ncorrect because the schedul e change control system i s i nvoked i f there are
changes to the schedul e. T he questi on does not def i ne i f the changes wi l l af f ect
the schedul
Answer: D e or not. B i s i ncorrect because the cost change control system i s
Y ou have i denti f i ed a ri sk that may cause saf ety concerns f or the workers
iHnvoked i f there
i nt: Someone i sare
doichanges
ng the rito
skythe cost.
work. RefTerence:
he questi
PMon
P does
Studynot def
Gui i ne
de, i f the 11
Chapter
compl eti ng the task. Y ou’ve deci ded to hi re a thi rd party to compl ete thi s work
changes
Study Gui wide
l l af
Objf ect
ectithe
ve:costs
M oni or
tornot.
Al l C
Riisks
s i ncorrect because i t does not f ul l y
because the ri sk i s too great to accept i nternal l y. Whi ch ri sk response i s thi s?
answer
D the questi
i s correct becauseon. transf erence i s when someone el se owns the ri sk—usual l y f or a
A. M i ti gati on
B. Acceptance f ee. T he ri sk doesn’t go away.

C. Avoi dance A i s i ncorrect because mi ti gati on i s any ef f ort to reduce or el i mi nate the ri sk. B i s

D . T ransf erence i ncorrect because acceptance means j ust that—the ri sk has been accepted. C i s
i ncorrect because avoi dance i s changi ng the proj ect management pl an to avoi d the

Y ou have i denti f i ed a ri sk wi thi n your proj ect deal i ng wi th the i nstal l ati on of ri sk al together.
Answer: A
the el ectri cal system i n a bui l di ng expansi on. Y ou have hi red a l i censed H i nt: Choose the best answer, or get someone el se to do i t.
el ectri ci an to compl ete thi s porti on of the proj ect. T hi s i s what type of ri sk Ref erence: PM P Study Gui de, Chapter 11
response? Study Gui de Obj ecti ve: I denti f y Ri sks and D ef i ne Ri sk Strategi es
A. T ransf erence A i s correct because whenever you hi re someone el se to own a ri sk, you are
B. M i ti gati on parti ci pati ng i n ri sk transf erence.
C. Procurement B i s i ncorrect. M i ti gati on i s an ef f ort to reduce the probabi l i ty or i mpact of a ri sk
D . Avoi dance event. C i s i ncorrect because thi s term i s not val i d f or thi s scenari o. D i s i ncorrect

Y ou have i nvi ted seven vendors to create proposal s f or a porti on of your proj ect because
Answer: Cyou are not avoi di ng the ri sk, you’re transf erri ng i t.
work. As part of the i nvi tati on, however, the vendor must have a mechani cal H i nt: N ot a constrai nt.
engi neer on thei r proj ect team or they cannot of f er a proposal . T he mechani cal Ref erence: PM P Study Gui de, Chapter 12
engi neer requi rement i s an exampl e of whi ch one of the f ol l owi ng? Study Gui de Obj ecti ve: I mpl ement the Procurement of Proj ect Resources
A. Resource constrai nt C i s correct because the requi rement to have the mechani cal engi neer “screens
B. Resource requi rement out” the vendors that do not qual i f y.
C. Screeni ng system A, B, and D are al l i ncorrect because i n thi s i nstance the mechani cal engi neer i s
D . Proj ect requi rement needed to of f er a proposal . T he questi on does not say the proj ect requi res the
mechani cal engi neer at al l —onl y to submi t a proposal .
PMP Exam Practice Test And Study Guide
Study this set o nline at: https://www.cram.co m/flashcards/pmp-exam-practice-test-
and-study-guide-56 32748
Y ou have schedul ed your proj ect team to work f ul l -ti me on the proj ect work of Answer: A
bui l di ng a bri ck wal l duri ng the week of August 16. Y ou have al l otted si x hours H i nt: I t’s your bel i ef .
of l abor per worker f or each day of the week. T he si x hours of l abor i s consi dered Ref erence: PM P Study Gui de, Chapter 6
what? Study Gui de Obj ecti ve: D ef i ne and Record Requi rements, Constrai nts, and
A. An assumpti on because you bel i eve the proj ect team wi l l onl y contri bute si x Assumpti ons
hours of l abor each day to the constructi on. A i s correct because you bel i eve the proj ect team wi l l onl y contri bute si x hours,
B. An assumpti on because the l abor uni on wi l l al l ow the proj ect team members to but you haven’t proven thi s to be true. T he proj ect team coul d work more, or l ess,
work onl y si x hours each day. than si x hours per day.
C. An assumpti on because you have hi stori cal i nf ormati on to base your esti mate on. B i s not Da val i d choi ce because i f i t’s true that the l abor uni on wi l l onl y al l ow
Answer:
Dou
Y . Anmust
assumpti
i denti
onf ybecause
and perfyou
ormknow
stakehol
the der
bui anal
l di ng
ysii s.
nspector
Key proj
wiect
l l be
stakehol
onsi teders
f or two si x hours
H i nt: Y ouofdon’t
work,althen
waysi thave
woulone
d be
of athese.
constrai nt. C i s i ncorrect because i f you have
hours
al wayseach
i ncl ude
work al
day.
l of the f ol l owi ng except f or whi ch one? hi
Refstori cal iPM
erence: nf ormati on to
P Study base
Gui de, your ti me5esti mate on, then i t’s f actual rather than
Chapter
A. Proj ect manager an assumpti
Study on.Obj
Gui de D ecti
i s i ncorrect because
ve: I denti i f you
f y and Perf know
orm the bui
Stakehol derl di ng ysi
Anal i nspector
s wi l l be
B. Customer/user onsi
D i ste f or two
correct hours each
because proj day,
ects thi s i salaways
don’t constrai
havent.vendors. T hi s i s a good exampl e
C. Perf ormi ng organi z ati on of a test questi on that doesn’t seem f ai r. Vendors can be key stakehol ders i n the
D . Vendor proj ect, but you may not al ways have a vendor. Y ou wi l l al ways have a proj ect
manager, a customer or user of the proj ect’s outcome, and a perf ormi ng

Y ou need a vendor to shi p a pi ece of sof tware f or your proj ect i mmedi atel y so your organi
Answer:z ati
C on. By process of el i mi nati on, the onl y stakehol der you won’t al ways
proj ect team can i nstal l the sof tware over the hol i day weekend. Because of the have i s a vendor.
H i nt: T here’s Watch out
no error.Ref f or these
erence: PM Ptypes
StudyofGui
questi ons on your
de, Chapter PM P exam.
11Study Gui de
hol i day weekend, however, no one wi l l be abl e to accept the package when the A i s ecti
Obj i ncorrect because
ve: I mpl the proj ect
ement Approved manager
Acti ons andi sWorkarounds
al ways a key stakehol der. B i s

del i very company attempts to del i ver the package. Whi ch one of the f ol l owi ng i s iCncorrect because
i s correct becausethethi
customer/user
s workaround ial
s al ways
l ows a key
the projstakehol
ect teamder. C i s ito
member ncorrect
recei ve
an exampl e of an appropri ate workaround? because the perf
the sof tware ormithe
bef ore ng organi z ati
proj ect i s on i s al ways
schedul a key
ed to stakehol der.
start.
A. D on’t start the proj ect work acti vi ti es unti l af ter the hol i day when the A i s i ncorrect because thi s wi l l del ay the proj ect. B i s i ncorrect because thi s
mai l room can accept the package. workaround wi l l i ncrease costs and woul d be a waste of ti me. D i s i ncorrect
B. F l y to the vendor’s l ocati on to pi ck up the package i n person. because there i s no error wi th the shi ppi ng. A di scount woul d not get the sof tware
C. H ave the vendor del i ver the sof tware to one of the team member’s homes so to the proj
Answer: A ect team member’s home as needed.
they
Y ou woul
havedthe
l i ke
softo
tware
create
delai vered
matri xdi
chart
rectlthat
y to shows
them. each team member’s H i nt: Race to the f i ni sh.
iDnvol
. D vement
emand awidi
thscount
each acti
f romvithe
ty. What
vendori sbecause
thi s chart
of known
the shias?
ppi ng error. Ref erence: PM P Study Gui de, Chapter 9
A. T he RACI chart Study Gui de Obj ecti ve: I denti f y Proj ect T eam and D ef i ne Rol es and
B. T he Pareto chart Responsi bi l i ti es
C. T he Rol es and Responsi bi l i ty M atri x A i s correct because a RACI chart depi cts the rol es of each team member as
D . T he H R I nteracti on chart Responsi bl e, Accountabl e, Consul t, and I nf orm.
B i s i ncorrect because a Pareto chart shows categori es of f ai l ure and i s used wi th
qual i tyCcontrol measures. C and D are i ncorrect because both of these terms are
Answer:
Y ou woul d l i ke to use a si mul ati on to predi ct a proj ect’s success based on the not appl
H i nt: i cabl
I t’s not ae.gambl e.
number of i denti f i ed ri sks and thei r overal l i mpact. What method coul d you use? Ref erence: PM P Study Gui de, Chapter 11
A. PE RT Study Gui de Obj ecti ve: M oni tor Al l Ri sks
B. GE RT C i s correct because a M onte Carl o Si mul ati on can be used to determi ne the
C. A M onte Carl o Si mul ati on l i kel i hood of a proj ect’s success.
D . A ri sk si mul ati on A i s i ncorrect because PE RT i s a ti me-esti mati ng f ormul a. B i s i ncorrect because
GE RT i s a network di agrammi ng techni que. D i s i ncorrect because thi s answer i s
not val i d
Answer: A f or thi s questi on.
Y our f uncti onal manager asks you to add f eatures to the proj ect scope to consume
the remai ni ng dol l ars i n the proj ect budget. T hi s i s an exampl e of whi ch one of H i nt: Sounds ni ce, but i t’s not.

the f ol l owi ng? Ref erence: PM P Study Gui de, Chapter 4

A. Gol d pl ati ng Study Gui de Obj ecti ve: Veri f y and M anage Changes to the Proj ect

B. Change control A i s correct because addi ng f eatures to the proj ect scope j ust to consume the

C. F uncti onal management proj ect budget i s cal l ed gol d pl ati ng.

D . Cost of qual i ty B i s i ncorrect because thi s does not answer the questi on as compl etel y as A. C i s
i ncorrect because the organi z ati onal structure does not change that thi s i s gol d
pl ati ng.CD i s i ncorrect because thi s answer i s not rel evant to thi s questi on
Answer:
Y our organi z ati on compl etes proj ects f or others. Whi ch one of the f ol l owi ng H i nt: Y ou’re a vendor.
documents serves as i nput to proj ect charter creati on and approval ? Ref erence: PM P Study Gui de, Chapter 4
A. Proj ect cal endar Study Gui de Obj ecti ve: Obtai n Proj ect Charter Approval
B. Proj ect constrai nts C i s the best answer because contracts are needed when you’re compl eti ng
C. Contract proj ects f or other organi z ati ons. Contracts, al so cal l ed agreements f or i nternal
D . Ri sk matri x proj ects, shoul d def i ne al l of the expectati ons f or al l parti es i nvol ved i n the
contracted proj ect work. T here are f i ve i nputs to consi der f or a proj ect charter:
proj ect Astatement of work, busi ness case, agreements, enterpri se envi ronmental
Answer:
Y our organi z ati on has tasked you wi th busi ness devel opment. Speci f i cal l y, they’d
f actors,
H andSunday.
i nt: E very organi z ati onal process assets.
l i ke to bi d on government-based contracts. Where wi l l you l i kel y f i nd i nf ormati on
A
Refi serence:
i ncorrect
PMbecause
P StudycalGuiendars are not12
de, Chapter an i nput to the proj ect charter. B i s
on government contracts that your organi z ati on coul d bi d on?
iStudy
ncorrect because constrai nts are not an i nput to the proj
Gui de Obj ecti ve: I mpl ement the Procurement ect ect
of Proj charter. D i s i ncorrect
Resources
A. N ewspapers
as
A i the ri sk matri
s correct x hasyou’l
because l i kellyof
not been
ten f i ndcreated yet.
adverti sements i n the newspaper of pendi ng
B. H i stori cal i nf ormati on
C. Sal es channel s government contracts.

D . Ci ty hal l B i s i ncorrect because hi stori cal i nf ormati on i s acti vi ty that has al ready been
compl eted. C i s i ncorrect because thi s i s too vague of an answer. D i s i ncorrect
because not al l government contracts are avai l abl e through ci ty hal l ; consi der
PMP Exam Practice Test And Study Guide
Study this set o nline at: https://www.cram.co m/flashcards/pmp-exam-practice-test-
and-study-guide-56 32748
Y our organi z ati on i s operati ng i n a f uncti onal structure and you’re the proj ect Answer: D

manager of a newl y i ni ti ated proj ect. Who has the power on a proj ect team i n a H i nt: I t’s not f un f or the proj ect manager.

f uncti onal organi z ati on? Ref erence: PM P Study Gui de, Chapter 2

A. T he proj ect manager Study Gui de Obj ecti ve: E nsure Common Understandi ng and Set E xpectati ons

B. T he proj ect sponsor D i s correct. T he f uncti onal managers have the power i n a f uncti onal organi z ati on.

C. T he proj ect team A i s i ncorrect because the proj ect manager has l i ttl e or no authori ty i n a f uncti onal

D . T he f uncti onal manager organi z ati on. B i s i ncorrect because i t’s the f uncti onal manager wi th the power,
not the proj ect sponsor. C i s i ncorrect because the proj ect team does not have the
power
Answer:i nCa f uncti onal structure.
Y our organi z ati on i s partneri ng wi th a competi ng f i rm i n order to compl ete a l arge
constructi on proj ect. Y ou wi l l serve as the proj ect manager i n thi s partnershi p. H i nt: Y ou’re on a temporary, contractual team.

What i s thi s rel ati onshi p cal l ed? Ref erence: PM P Study Gui de, Chapter 2

A. D ual -enti ty proj ect management Study Gui de Obj ecti ve: Conduct Ki ck-Of f M eeti ng

B. D ual f uncti onal structure C i s correct. When two competi ng enti ti es partner together to compl ete a proj ect

C. T eami ng agreement through a contractual rel ati onshi p, i t i s cal l ed a team agreement.

D . F uncti onal team agreement A, B, and D are i ncorrect because none of these are val i d proj ect management
terms.

Y our organi z ati on needs to procure trai ni ng cl asses. T here are many trai ni ng Answer: C

compani es that you can hi re, but you pref er to work wi th one parti cul ar vendor. H i nt: I t’s not the tri cky one.

T hi s i s an exampl e of whi ch market condi ti on? Ref erence: PM P Study Gui de, Chapter 12

A. Ol i gopol y Study Gui de Obj ecti ve: I mpl ement the Procurement of Proj ect Resources

B. Sol e source C i s correct because a si ngl e-source market means they pref er to work wi th one

C. Si ngl e source parti cul ar vendor.

D . Qual i f i ed sel l er l i st A i s i ncorrect because an ol i gopol y descri bes a market condi ti on where the
acti ons of one vendor af f ects al l of the others (f or exampl e, oi l , ai rf are, and

Y our proj ect conti nues to stal l because of addi ti onal changes to the proj ect sof tware).
Answer: A B i s i ncorrect because a sol e source means there i s onl y one vendor
scope. Y ou’ve asked that al l changes to the proj ect scope stop unl ess the changes avai
H i nt:l abl e. D i s i Change
I ntegrated ncorrect Control
because . thi s i s si mpl y a l i st of vendors that your
are trul y needed f or the success of the proj ect scope as i t was approved. organi z ati on
Ref erence: PMalPl ows youGui
Study to do
de,busi ness wi
Chapter 4 th.
M anagement, however, has demanded a change to the proj ect. What must be Study Gui de Obj ecti ve: I mpl ement Approved Changes
exami ned? A i s correct because the change may af f ect al l or some of the knowl edge areas:
A. T he change request and i ts i mpact on the enti re proj ect ti me, cost, qual i ty, communi cati ons, ri sk, human resources, procurement.
B. T he change request and the cost to i mpl ement the change B i s i ncorrect because i t onl y addresses cost. C i s i ncorrect because i t onl y
C. T he change request and the ti me to i mpl ement the change addresses ti me. D i s i ncorrect because i t onl y addresses the change request.
D . T he change request and the purpose f or the change Answer: B
Y our proj ect i s sl i ppi ng and you woul d l i ke to add more l abor to compl ete ef f ort- H i nt: Kaboom!
dri ven acti vi ti es sooner. What i s thi s cal l ed? Ref erence: PM P Study Gui de, Chapter 6
A. Cost i ncrease Study Gui de Obj ecti ve: M anage Resource Al l ocati on
B. Crashi ng B i s correct because crashi ng means that the proj ect manager adds resources i n
C. Ri sk i ncrease ef f orts to compl ete acti vi ti es f aster.
D . F ast tracki ng A i s i ncorrect because thi s i s a typi cal ef f ect of crashi ng. C i s i ncorrect because
thi s i s a typi cal ef f ect of f ast tracki ng. D i s i ncorrect because f ast tracki ng
al l ows phases
Answer: C to overl ap.
Y our proj ect j ust got cancel ed. Y ou were nearl y 60 percent done. What shoul d H i nt: D on’t qui t.
happen next? Ref erence: PM P Study Gui de, Chapter 5
A. Bi l l f or 60 percent of the contracted f ee. Study Gui de Obj ecti ve: Obtai n F i nal Acceptance f or the Proj ect
B. D etermi ne why the proj ect has f ai l ed. C i s correct because even though the proj ect’s been cancel ed, you need to
C. Compl ete scope veri f i cati on. compl ete scope veri f i cati on.
D . Of f er your resi gnati on. A i s i ncorrect because the contract f or the proj ect wi l l determi ne what wi l l
happen i n thi s scenari o. I n addi ti on, i nternal proj ects may have no contract. B i s

Y our proj ect sponsor has asked you to revi ew some of the ri sks of the proj ect wi th iAnswer:
ncorrectD because there’s no evi dence that the proj ect has f ai l ed. T here coul d be

hi m. I n parti cul ar, the proj ect sponsor wants to def i ne some of the root causes of other
H i nt: reasons why the proj ect has been cancel ed, such as advancements i n
N ot a person.
ri sks. Whi ch component wi l l hel p you, the proj ect manager, i denti f y the root technol
Ref ogy PM
erence: or aPshi f t i nGui
Study thede,
market. D i s11
Chapter i ncorrect because thi s i sn’t val i d. I t may

causes of ri sk? fStudy


eel val i d,de
Gui but
Obji t’s not
ecti ve:the best
M oni torchoi ce.sks
Al l Ri
A. T he proj ect team D i s correct because the ri sk regi ster i ncl udes the root causes of ri sk.
B. E xpert j udgment A i s i ncorrect because the proj ect team may contri bute to the root cause anal ysi s,
C. Proj ect scope but the ri sk regi ster i s the component that stores the root cause of i denti f i ed ri sk.
D . Ri sk regi ster B i s i ncorrect because experts may contri bute to the root cause anal ysi s, but the
ri sk regiAster i s the component that stores the root cause of i denti f i ed ri sk. C i s
Answer:
Y our proj ect team does not know how to i nstal l the new materi al s you’l l be usi ng
i ncorrect
H i nt: Got because
to do i t,the
or elproj
se.ect scope does not contri bute to or suppl y the root
i n your proj ect. Y ou hi re a trai ner to teach the team how to i nstal l the proj ect.
cause of ri sks.
Ref erence: PM P Study Gui de, Chapter 8
T he costs of the trai ner are descri bed as what?
A. T he cost of conf ormance to qual i ty Study Gui de Obj ecti ve: I mpl ement Qual i ty M anagement Pl an

B. Sunk costs A i s correct because trai ni ng i s an exampl e of the cost of conf ormance to qual i ty.

C. T eam devel opment I f you don’t trai n the proj ect team, then qual i ty wi l l suf f er.

D . T he cost of doi ng busi ness B i s i ncorrect because sunk costs descri bes moni es spent on proj ect work that has
f ai l ed and that cannot typi cal l y be recovered. C i s i ncorrect because team
devel opment i nvol ves acti vi ti es to f aci l i tate team cohesi on. T he costs, i n thi s
PMP Exam Practice Test And Study Guide
Study this set o nline at: https://www.cram.co m/flashcards/pmp-exam-practice-test-
and-study-guide-56 32748
Y our proj ect team has i ncorporated some mi nor changes i nto thei r proj ect work as Answer: D

di rected by the customer. Y ou agree that these changes are needed. What i s thi s H i nt: I t’s not good.

an exampl e of ? Ref erence: PM P Study Gui de, Chapter 5

A. F l ui d change control Study Gui de Obj ecti ve: I mpl ement Approved Changes

B. I ntegrated change control D i s correct because uncontrol l ed changes are cal l ed scope creep.

C. E xpert j udgment A i s i ncorrect because thi s term i s not val i d. B i s i ncorrect because i ntegrated

D . Scope creep change control requi res documented changes to f ol l ow a set of rul es of revi ewi ng
and approvi ng change requests. C i s i ncorrect because expert j udgment i s when an
expert
Answer:helA ps you, the proj ect manager, make the best deci si on. I n thi s i nstance, no
Y ou’ve i denti f i ed a ri sk wi th your proj ect team that may cause maj or del ays i n
one hel ped wi thyou
H i nt: N ot much thecan
deci
do.si on, i t was j ust i mpl emented wi thout any revi ew or
your proj ect. T here’s nothi ng you can do about the ri sk, however, because of the
consi deratiPM
Ref erence: on. P Study Gui de, Chapter 11
nature of the proj ect work. Whi ch ri sk response wi l l you l i kel y choose?
A. Acceptance Study Gui de Obj ecti ve: M oni tor Al l Ri sks

B. Avoi dance A i s correct because you are f orced to accept the ri sk.

C. E xpl oi t B i s i ncorrect because avoi dance i mpl i es that the ri sk can be taken out of the

D . M i ti gate proj ect, but i n thi s i nstance i t cannot because the ri sk i s i nherent to the proj ect
work. C i s i ncorrect because expl oi t i s a ri sk response when the ri sk i s i denti f i ed
as a posi ti ve ri sk or opportuni ty. D i s i ncorrect because mi ti gate i s a response to
l ower or el i mi nate the ri sk i mpact. I n thi s i nstance, there’s nothi ng that can be
done about the ri sk.