You are on page 1of 23

MS Ref No.

:
PROJECT: ZARA-ENOVA-ALEM-MSS-
ZARA MECH-0003
Rev: 00
STORAGE
Date: 21 October 2023
CREATION
Page 1 of 23
METHOD STATEMENT FOR FLUSHING & CHEMICAL CLEANING OF CHILLED WATER SYSTEM

METHOD STATEMENT
STATEMENT
METHOD

FOR
TITLE

FLUSHING & CHEMICAL CLEANING OF


CHILLED WATER SYSTEM

Rev Date Document Status Prepared By Reviewed by Approved by

Sathiyamoorthy
00 21-10-2023 Issued for Approval Ajeesh Vijayan Henry Ungerer
Meyyappan

CONTRACTOR: ALEMCO ELECTROMECHANICAL CONTRACTING LLC


MS Ref No.:
ZARA-ENOVA-ALEM-MSS-
PROJECT: MECH-0003
ZARA STORAGE Rev: 00
CREATION Date: 21 October 2023
Page 2 of 23
METHOD STATEMENT FOR FLUSHING & CHEMICAL CLEANING OF CHILLED WATER SYSTEM

CONTENT

1. INTRODUCTION:.......................................................................................................................................3
2. SCOPE OF WORK:.....................................................................................................................................3
3. DEFINITIONS & ABBREVATIONS:........................................................................................................3
4. ROLES AND RESPONSIBILIITIES...........................................................................................................4
5. WORKING ACCESS:..................................................................................................................................9
6. LIGHTING:..................................................................................................................................................9
7. PLANT & EQUIPMENT:............................................................................................................................9
8. MATERIALS:............................................................................................................................................10
9. WORK SEQUENCE:.................................................................................................................................11
10. PROGRAMME...........................................................................................................................................15
11. RISKS & CONTROLS...............................................................................................................................15
12. EMERGENCY ARRANGEMENTS..........................................................................................................16
13. TRAINING.................................................................................................................................................16
14. SUPERVISION..........................................................................................................................................16
15. WORKING HOURS..................................................................................................................................16
16. HOUSEKEEPING......................................................................................................................................17
17. ATTACHMENTS.......................................................................................................................................17

CONTRACTOR AUTHORIZED SIGNATORY

Ajeesh Vijayan Sreesankar Sathiyamoorthy Meyyappan


QAQC ENGINEER Construction Risk Coordinator CONSTRUCTION MANAGER

CONTRACTOR: ALEMCO ELECTROMECHANICAL CONTRACTING LLC


MS Ref No.:
ZARA-ENOVA-ALEM-MSS-
PROJECT: MECH-0003
ZARA STORAGE Rev: 00
CREATION Date: 21 October 2023
Page 3 of 23
METHOD STATEMENT FOR FLUSHING & CHEMICAL CLEANING OF CHILLED WATER SYSTEM

1. INTRODUCTION:
This Method Statement describes the comprehensive requirements and procedures for the crucial phase of Flushing and
Chemical Cleaning of the Chilled Water System within the newly constructed Zara storage facility at the Mall of the Emirates,
Dubai. This meticulous process is pivotal to ensuring the optimal performance, longevity, and efficiency of the Chilled Water
System, comprising FCUs (Fan Coil Units), FAHUs (Fresh Air Handling Units), and related CHW pipe modifications in and
around the location.
2. SCOPE OF WORK:

The scope of this method statement is to define the procedure for Flushing and chemical cleaning of chilled water piping
system in accordance with the Specification Sections 15120.

3. DEFINITIONS & ABBREVATIONS:


Client Majid Al Futtaim / ENOVA
Tenant Zara
Consultant Mott Macdonald / WSP
Contractor Alemco Electromechanical Contracting L.L.C
PM Alemco Project Manager
CM Alemco Construction Manager
QCM Alemco QA/QC Manager
QCE Alemco Quality Control Engineer
SE Site Engineer
CRM Alemco Construction Risk Manager
ITP Inspection and Test Plan
MSS Method Statement Submittal
MS Material Submittal
SD Shop Drawing
CD Contract Drawing issued for Construction
CL Check List
RA Risk Assessment
MS Material Submittal
MRS Material Reference Schedule
IR Inspection Request
PSSP Project Safety Security Plan
MC Mobile Crane / Man Lift
MIM Manufacturer Instruction Manual
HSE Health, Safety & Environment
HSEMS Health, Safety & Environment Management System
GI Galvanized Iron
CHWP Chilled Water Pipes

CONTRACTOR: ALEMCO ELECTROMECHANICAL CONTRACTING LLC


MS Ref No.:
ZARA-ENOVA-ALEM-MSS-
PROJECT: MECH-0003
ZARA STORAGE Rev: 00
CREATION Date: 21 October 2023
Page 4 of 23
METHOD STATEMENT FOR FLUSHING & CHEMICAL CLEANING OF CHILLED WATER SYSTEM

PT Pressure Test
VCD Volume Control Damper
4. ROLES AND RESPONSIBILIITIES
 Construction Manager
The construction manager will be responsible for following activities:
 Ensure high standard of quality workmanship on site.
 Ensure total Human Resource Management on site.
 Contract improvement actions
 Safeguard and promote Alemco interests when dealing with suppliers:
 Ensure contract programme deadlines are met and exceeded where possible:
 Materials and storage management:
 Site Administration
 Quality Manager:
The quality manager will be responsible for following activities:
 Plan, Organize and Manage the QA QC team for the implementation of project quality management system.
 Develop and implement the Project Quality Plan.
 Develop and implement Internal and External Audit schedule and conduct /organize audits as per the schedule.
 Coordinate with third party laboratories for initial testing activities and material testing. Verify the test reports for the
compliance to specification and submit to consultant.
 Develop and establish a comprehensive schedule of all planned material submittals based on the project schedule.
 Prepare Review and ensure the detailed material submittal schedule follows project schedule.
 Coordinate with team and Consultants - to ensure the progress of material submittals is as per schedule.
 Establish and Implement the Material and work Inspection procedure for the project. Monitor inspection status,
analysis status reports and trend analysis, implement corrective actions for the variations of plan.
 Ensure the non-conforming materials are tagged and removed from site and provide the rejected material inspection
report to commercial and procurement for corrective actions.
 Organize/Manage offsite inspections in coordination with team, Consultant and /supplier / manufacturer.
 Establish and Implement procedures for monitoring and controlling quality of work including site surveillance,
recording the deficiencies and continuous follow up with construction tea for closing the recorded deficiencies.
 Close Site Instructions/non-conformance reports from consultant within 14 days of receipt and conduct the review of
the Site instruction/corrective action to verify the scope for a potential claim.
 Coordinate with team and consultant for implementing the corrective actions and closing the site instruction /NCR.
 Coordinate with team for the timely submission of material submittals, test reports and O & M manual for the project.

CONTRACTOR: ALEMCO ELECTROMECHANICAL CONTRACTING LLC


MS Ref No.:
ZARA-ENOVA-ALEM-MSS-
PROJECT: MECH-0003
ZARA STORAGE Rev: 00
CREATION Date: 21 October 2023
Page 5 of 23
METHOD STATEMENT FOR FLUSHING & CHEMICAL CLEANING OF CHILLED WATER SYSTEM

 Prepare the closeout documentation requirements for the project and manage the Preparation / compilation and
submission of project closeout documents to consultant.
 Coordinate with consultant for testing and commissioning inspections.
 Establish and implement the procedures for snagging /de-snagging at project site. Coordinate with Consultant to
complete the snagging and de-snagging inspections as per project schedule.
 Provide accurate progress updates of material submittals to planning department weekly and monthly.
 Provide accurate status of material inspections to planning department weekly.
 Present weekly material submittal status, weekly look ahead, status of site instructions to management and implement
the actions decided for any variations from plan.
 Report to commercial department regarding the poor performance of team in quality or any other concerns, which
needs to be taken contractually.
 Organize trainings on special systems/new procedures introduced in the project.
 Lead, motivate, Train and develop QA QC team.
 Design Manager:
The design manager will be responsible for following activities:
 Understand the conditions of the contract with the client.
 Liaise with client to determine factors affecting planning of the interior architecture, such as budget, architectural
preferences, purpose and function.
 Prepare detailed drawings and design specifications and submit these for approval by relevant planning authorities.
 Carry out a thorough site survey to determine site characteristics and to assess likely problems.
 Advise client on interior design factors such as space planning, layout and utilization of furnishings or equipment, and
colour coordination.
 Ensure all fit out work is carried out to the specific requirements of the client.
 Coordinate with other professionals, such as contractors, architects, Engineers, and planners, to ensure that work is
completed to the highest standards and that the highest quality product is delivered to the client.
 Oversee all the tasks of the design team and to provide motivation and support for the team.
 Review and detail shop drawings for construction plans.
 Formulate environmental plan to be practical, aesthetic, and conducive to intended purposes, such as raising
productivity or selling merchandise.
 Select or design, and purchase furnishings, art works, and accessories.
 Render design ideas in form of paste-ups or drawings.
 Use computer-aided drafting (CAD) and related software to produce construction documents.

CONTRACTOR: ALEMCO ELECTROMECHANICAL CONTRACTING LLC


MS Ref No.:
ZARA-ENOVA-ALEM-MSS-
PROJECT: MECH-0003
ZARA STORAGE Rev: 00
CREATION Date: 21 October 2023
Page 6 of 23
METHOD STATEMENT FOR FLUSHING & CHEMICAL CLEANING OF CHILLED WATER SYSTEM

 Maintain an awareness of developments in the field of architecture so that up-to-date and accurate advice can be given
to clients.
 Ensure all work is completed in compliance with the site HSE plan.
 Coordinate with the local authorities where necessary
 CRM Advisor / Safety Manager:
The CRM Manager will be responsible for the following activities:
 Will train construction personnel in safe work practices on the job site.
 Will prepare report as required by the Project Leader.
 Will monitor, inspect, and report on unusual and/or serious accidents which may occur on the job sit.
 Will submit written evaluation and recommendations direct to the Project Leader.
 Will be based on site and manage the SAFETY performance of all project team personnel and operative.
 Will assist the managers in overseeing SAFETY related activities that are associated with any of Alemco Sub-
contractor personnel, who are working on the project.
 Will coordinate and supervise safety advisors and site clinic.
 Will assist to prepare ‘lifting operations’ plan, ‘Fire and emergency’ plan and coordinate for its implementation.
 Will ensure that method statement/risk assessment is carried out.
 Will ensure that ‘Emergency Evacuation’ training is carried out. Monitor for drill compliance and recommend areas of
improvement.
 Will ensure that workplace monitoring is implemented and carried out by the allocated managers.
 Site Manager / Section Manager:
The Site Manager will be responsible for following activities:
 Will implement engineering systems, documentation, and controls by compliance with Healthy Safety and
 Environmental Alemco and industry standards, including Temporary works.
 Will go through the project scope of work such as drawings, specification, Quality Plans, project program.
 Will check engineering drawings and specification to identify and resolve design conflicts.
 Will prepare method statements, ITPs, and risk assessments in accordance with Alemco Quality Systems as and when
required.
 Will ensure all technical information is available when required for delivery of design or construction.
 Will provide effective supervision and guidance to less experienced engineering staff.
 Will actively manage safety and quality on site ensuring side wide compliance and not just their area of operation.
 Site Engineer:
The site engineer will be responsible for following activities:
 Will go through the project scope of work such as drawings, specification, Quality Plans, project program.

CONTRACTOR: ALEMCO ELECTROMECHANICAL CONTRACTING LLC


MS Ref No.:
ZARA-ENOVA-ALEM-MSS-
PROJECT: MECH-0003
ZARA STORAGE Rev: 00
CREATION Date: 21 October 2023
Page 7 of 23
METHOD STATEMENT FOR FLUSHING & CHEMICAL CLEANING OF CHILLED WATER SYSTEM

 Will supervise site mobilization and demobilization for each and every activity under his / her control.
 Will formulate work breakdown structure and document sub-contractor package including estimates of man hours and
cost.
 Will oversee and administer Forman’s daily report to ensure direct labour efficiency.
 Will ensure periodic reports are transmitted to Project Leader.
 Will track and report material delivery.
 Will ensure SAFETY requirements are maintained.
 Will co-ordinate with sub-contractor to ensure interface problem are avoided and maximum Quality work achieved.
 Will prepare and control inspection requests, ITPs, method statements, risk assessment, check sheets and any other
quality requirements in conjunction with the project quality representative.
 Will ensure that the requirements of the Alemco Quality Procedures and followed and adhered to it.
 Will raise and process NCR.
 Will help create a site culture of best practice regarding safety, housekeeping, workmanship, and waste management.
 Will assist supervisors and managers to allocate correct resource to activities and to review and report on the same.
 Will create an open site culture where operative and foreman can raise concerns and discuss matters with the mangers
and administer result.
 QA/QC Engineer:
The QA/QC Engineer will be responsible for the following activities:
 Review the ITPs for each activity along with method statement from, Alemco direct works and sub-contractors works,
to verify the compliance to Project requirements. Ensure the team is adhering to the ITP and inspections are raised
accordingly.
 Conduct day to day site surveillance, identify, record, and communicate the deficiencies to team to avoid
reoccurrence.
 Conduct work inspections in co-ordination with Alemco team and consultant to verify the compliance to drawings and
specifications, Ensure the records are maintained.
 Coordinate and Conduct Material inspections with consultant to verify the compliance to the specifications. Ensure all
rejected materials from internal and consultant inspections are tagged and removed from the site.
 Conduct Supplier factory/fabrication yard inspections as per QA QC Manager Instruction to verify the compliance
with project requirements and communicate the observations to project team.
 Coordinate with Team and Consultant and ensure all the inspections are conducted as per approved ITP and ensure the
records are maintained.
 Coordinate with third-party laboratories and consultants for various field tests as per approved ITP and ensure the test
reports/records are submitted/maintained.

CONTRACTOR: ALEMCO ELECTROMECHANICAL CONTRACTING LLC


MS Ref No.:
ZARA-ENOVA-ALEM-MSS-
PROJECT: MECH-0003
ZARA STORAGE Rev: 00
CREATION Date: 21 October 2023
Page 8 of 23
METHOD STATEMENT FOR FLUSHING & CHEMICAL CLEANING OF CHILLED WATER SYSTEM

 Conduct internal verification/inspections for the implementation of corrective and preventive actions for the site NCRs
and deficiencies identified by the QA QC Team. Verify the effectiveness of corrective and preventive actions.
 Analyse the status of QA QC activities, prepare the trends including submittals, inspections, tests, deficiencies
identified & NCRs and communicate to QA QC Manager/Project team.
 Conduct snagging – De-snagging inspections coordinating with Alemco execution Team and Consultants.
 Lead and guide the inspection team to achieve the project Goals.
 Site Surveyor:
The Site Surveyor will be responsible for the following activities:
 Topographic and as built survey on site.
 Compute the area and volume for cut and fill.
 To setting out points of foundations, columns, beam lines, etc. before casting.
 To setting out the base plates, points for block works and slab edges.
 To prepare sketches and written reports following the surveying of an area.
 To prepare contour plans and compile data from survey findings.
 Solve practical problems and deal with the variables in situations where limited standardisation exists.
 To input and prepare coordinates using Auto Cad.
 To check the dimensions on drawings and ensure this reflects what is built on site.
 Update drawings to ensure any changes during construction are accounted for.
 To calculate distances, angles, area, and volume on site using surveying methods.
 To manage the surveying equipment, monitoring accuracy and ensuring it is calibrated.
 To assist the Alemco related businesses and Sub-Contractors in location of points and updating of drawings.
 Cooperate with the façade team in marking the accurate.
 Observe the displacement of structure for deflection.
 Take the as built for all construction items after casting concrete.
 General Foreman:
 Will supervise the work to ensure that technical, Quality and SAFETY requirement are met.
 Will go through the project scope of work such as drawings, specification, Quality Plans, project program.
 Will prepare site daily report.
 Will co-ordinate labor and sub-contractor in order to achieve program requirements.
 Will ensure compliance with stated Quality requirements.
 Will ensure comply with Safety requirements and regulation.
 Will attend daily site meeting and communicate his report with the Line Manager.
 Will participate in training and development of his subordinates.

CONTRACTOR: ALEMCO ELECTROMECHANICAL CONTRACTING LLC


MS Ref No.:
ZARA-ENOVA-ALEM-MSS-
PROJECT: MECH-0003
ZARA STORAGE Rev: 00
CREATION Date: 21 October 2023
Page 9 of 23
METHOD STATEMENT FOR FLUSHING & CHEMICAL CLEANING OF CHILLED WATER SYSTEM

 Will organize with the Site Engineer or Section Engineer to ensure the availability of plant, equipment, and labor to
his designated work activities.
 Will closely monitor the usage of consumable and materials by his crew in order to minimize wastage.
 Will co-ordinate with Site Engineer regarding material requisition orders.
 Will Maintain high standards of housekeeping on site.
Responsible persons for each stage of work are marked against each phase of work in work sequence section
5. WORKING ACCESS:
The access / egress for the construction vehicles for the installation of activities shall be as per the logistic Plan.
Ensure Proper coordination with all interfacing contractors for Logistics, access prior to commencement of all activities.
6. LIGHTING:
i. Safety Lighting:
The minimum safety lighting as per general requirements (Minimum 50 lux) will be provided.
ii. Task Lighting:
Task lighting shall be provided in addition to the safety lighting to undertake the task with the proper level of lighting to meet
acceptable safety and quality of workmanship standards.
7. PLANT & EQUIPMENT:
i. General:
 Appropriate plants and equipment shall be used for the execution of the activity. The plant, tools and equipment shall be
checked visually prior to use.
 Only authorized applicator approved and trained by the manufacturer to install manufacturer's products.
 All Operators shall be trained and certified by the 3rd party wherever required.
 No defective plant and equipment shall be allowed to use on site.
ii. Plant & Equipment Schedule:

Sl No Description of Plant, Equipment & Tools


1 Portable Hand Tools
2 MI/MS Pipe & Fittings for Connections
3 Spirit Level
4 Level Threads
5 Hacksaw Frame with Blades
6 Welding Machine
7 Cutting Equipmens (Oxygen, Acetylene Cylinders, Cutting Torch, etc.)
8 Threading Machine
9 Hole saw Cutter

CONTRACTOR: ALEMCO ELECTROMECHANICAL CONTRACTING LLC


MS Ref No.:
ZARA-ENOVA-ALEM-MSS-
PROJECT: MECH-0003
ZARA STORAGE Rev: 00
CREATION Date: 21 October 2023
Page 10 of 23
METHOD STATEMENT FOR FLUSHING & CHEMICAL CLEANING OF CHILLED WATER SYSTEM

10 Mechanical Tool Box


11 Step Ladder
12 Scaffolds
iii. Personal Protective Equipment:
(Refer Attachment-1 for Risk Assessment)
All operatives involved in the activity shall be provided with Job specific Personal Protective equipment which are and but not
limited as mentioned below
 Polycarbonate Safety Helmet
 Safety boots with steel toe
 Coverall with high visibility strips
 Hand Gloves
 Full body Harness
 Ear Plugs
 Eye protection / Goggles
iv. Power:
The Power supply used on site for power tools shall be 110V only. 230v or higher voltage power supply shall be provided to
site welfare areas and another site establishment.
v. Working Platforms:
 The working platforms for the task shall be firm and stable.
 The Mobile elevated working platforms- Man Lift / Scissor Lift (Supplied by Client) for the activity shall be used.
 Make Sure the tag system is in place and always followed.
 The operator shall have IPAF training.
 Man lift / Scissor lift shall lift must be inspected by the competent person.
 Barriers will be erected beneath the installation area to restrict access to other personnel.
 The Mobile working platforms shall be used as only platforms for working and shall not be used for loading heavy
material or equipment on to it.
8. MATERIALS:

SNO PRODUCT PRODUCT


1 ACCEPTA 2877 Cleaning Chemical
2 ACCEPTA 894 Passivator
3 ACCEPTA 2337 Scale Corrosion Inhibitor
4 ACCEPTA 2886 Microbicide

CONTRACTOR: ALEMCO ELECTROMECHANICAL CONTRACTING LLC


MS Ref No.:
ZARA-ENOVA-ALEM-MSS-
PROJECT: MECH-0003
ZARA STORAGE Rev: 00
CREATION Date: 21 October 2023
Page 11 of 23
METHOD STATEMENT FOR FLUSHING & CHEMICAL CLEANING OF CHILLED WATER SYSTEM

9. WORK SEQUENCE:
Responsible Reference/Verifying
DESCRIPTION OF SEQUENCE / METHOD OF WORK
Person Document
9.1 Preliminary Activities / Approvals
 Submit material submission for all materials related task for Engineer
approval.
 As per approved material submittal and IFC drawings / specification prepare
/ submit shop drawings.
 Submit MIR for the delivered materials on site.
CM / SM /
MSS / MSRA / RA
 Method Statement, Inspection, Test Plan & Risk Assessment shall be SE / QCM
submitted for Engineer approval.
 Identify, Quantity & Ensure all risk managed in this method statement &
residual risk are acceptable.
 Ensure proper coordination with all interfacing contractors for access/
completion of previous activities before starting all activities at site.
9.2 Pre-Construction Activities CM / SM / MSS / MSRA / RA
SE / QCM /
QC
PRE-CLEANING/FLUSHING START UP CHECKLIST

General

Before startup of any pre-cleaning activity, the following should be


considered:

1. Check all installations & pressure testing must be approved.

2. Check availability of supply of continuous fresh water


(Temporary or permanent as per site conditions).

3. Check availability of power and electricity for permanent system

4. Check availability of labour/manpower.

5. Check availability of chemicals required for flushing/cleaning


operation at site.

6. Identify clearly feed and drain points. Provide locations at site

CONTRACTOR: ALEMCO ELECTROMECHANICAL CONTRACTING LLC


MS Ref No.:
ZARA-ENOVA-ALEM-MSS-
PROJECT: MECH-0003
ZARA STORAGE Rev: 00
CREATION Date: 21 October 2023
Page 12 of 23
METHOD STATEMENT FOR FLUSHING & CHEMICAL CLEANING OF CHILLED WATER SYSTEM

Responsible Reference/Verifying
DESCRIPTION OF SEQUENCE / METHOD OF WORK
Person Document

conditions.
7. Make provision for drain from lowest points. Identify at site &
drawing.

8. Check availability of safety equipment at site and ensure that the


workers are trained in safety requirements.

9. Check operation of permanent system/temporary as per


requirement.

10. Check and identify all air vents present in the circuit. Identify high
level location at site.

11. Install temporary filtration units.

12. Make the complete chilled water piping into a single loop by
making necessary bypass connections to all equipment.

13. All bypass connection should be equal sized. MEP Contractor to


check & provide check list.

14. Check and ensure that all isolating valves enabling circulation in
this circuit are
fully open.

15. To the extent of its applicability on this job, safety precautions in


handling of chemicals should be taken on site. The persons
handling the chemicals while mixing shall wear gloves and
goggles. Clean water will be made available at site by the
contractor. The necessary handling information for the chemicals
as provided in the MSDS shall be put up at the place where
chemicals are being dosed into the system.

16. Samples & Sample Containers: MEP contactor shall submit


samples in clear bottles of a type that is locally available during
various stages of the treatment (as provided in the checklist).
These bottles will be labelled with information of time and
location of sampling point.
17. On site sampling test to be carried out by Water Bird. Final
sample will be collected by independent third party for analysis in
their laboratory.

CONTRACTOR: ALEMCO ELECTROMECHANICAL CONTRACTING LLC


MS Ref No.:
ZARA-ENOVA-ALEM-MSS-
PROJECT: MECH-0003
ZARA STORAGE Rev: 00
CREATION Date: 21 October 2023
Page 13 of 23
METHOD STATEMENT FOR FLUSHING & CHEMICAL CLEANING OF CHILLED WATER SYSTEM

Responsible Reference/Verifying
DESCRIPTION OF SEQUENCE / METHOD OF WORK
Person Document

9.3 Material Receiving & Storage


 All When received at site, all chemicals should be checked for
the label and safety instruction and stored properly as per the
product data sheet.

 Any item found damaged or not found suitable as per project CM / SM /


requirements shall be quarantined. Non-compliant material shall SE / QCM / MSS / MSRA / RA
be clearly marked and stored separately to prevent any QC
inadvertent use until returned to vendor.

 Manufacturer’s instruction shall be strictly followed as


applicable.
.
9.4 Installation Activities
The processes involve the following four states:

A) Static Flushing.
B) Dynamic flushing.
C) Chemical cleaning.
D) Dynamic flushing.
E) Reinstatement of plant items and back flushing.
F) Final inhibition.
Find below the supply water quality parameters to be required for CHW INFO
flushing activity.

Parameter Supply Water


pH 7.0 to 8.5
TDS Max. 250 ppm
Conductivity Max. 350 µs/cm
Total Iron Max. 0.1 ppm
Suspended Solids Max. 5 ppm
Appearance Clear
CM / SM / MSS / MSRA / RA
A) Static Flushing SE / QCM /
QC
The initial static flush should be carried out as detailed below:

 MEP Contractor to ensure all pre-requisites as mentioned in the


initial stages have been met.

CONTRACTOR: ALEMCO ELECTROMECHANICAL CONTRACTING LLC


MS Ref No.:
ZARA-ENOVA-ALEM-MSS-
PROJECT: MECH-0003
ZARA STORAGE Rev: 00
CREATION Date: 21 October 2023
Page 14 of 23
METHOD STATEMENT FOR FLUSHING & CHEMICAL CLEANING OF CHILLED WATER SYSTEM

Responsible Reference/Verifying
DESCRIPTION OF SEQUENCE / METHOD OF WORK
Person Document

 Fill the system with plain water.


 Fully vent the system to ensure no air is trapped within the pipe
work by opening all the system air vents manually.
 Gravity flushing will be carried out to remove major debris, loose
particles and suspended solids from the system. Drain from lowest
point to remove all suspended solids and loose debris from the
system.
 Circulate the system using the permanent system/temporary
pumps for 6-8 hours.
 After circulating open the drain valves at the lowest point in the
system.
 Flushed water should be disposed out in the storm water drain or
disposal tanks provided at site.
B) Dynamic Flushing

 Add make-up water.


 Once water comes from the air vent, close the air vent valve and
start dynamic flushing.
 Slowly open the drain valves at the lowest points in the whole
system and adjust it to equate makeup and drainage.
 Note: the drainage flow must never be more than the clean make-
up water flow as to avoid system pressure loss and drainage.
 Confirm the water is circulating throughout system or adjust the
valve to make sure the circulation.
 Return water will be passed through the filter of 25 micron size to
remove any suspended solids and suspended iron.
 Systematically remove, examine and clean the entire strainer,
filters and change the same.
 Flushing velocities will be measured using calibrated ultra-sonic
flow measurement. Readings will be taken on the largest pipe in
the system. Velocity will be in line with BSRIA Regulations.
C) Chemical Cleaning

 Chemical cleaning should be carried out immediately after


dynamic flushing.
 The purpose of chemical cleaning is to remove metal oxide
deposits from metal surfaces.
 Dose required quantities of cleaning agent using temporary
tank/pump system or manual dosing pot.
 Add cleaning chemical Accepta 2877 Neutral pH Cleaner dose at
the rate of 1.0 Kg/m3 as per the system volume.

CONTRACTOR: ALEMCO ELECTROMECHANICAL CONTRACTING LLC


MS Ref No.:
ZARA-ENOVA-ALEM-MSS-
PROJECT: MECH-0003
ZARA STORAGE Rev: 00
CREATION Date: 21 October 2023
Page 15 of 23
METHOD STATEMENT FOR FLUSHING & CHEMICAL CLEANING OF CHILLED WATER SYSTEM

Responsible Reference/Verifying
DESCRIPTION OF SEQUENCE / METHOD OF WORK
Person Document

 Circulate the chemical for about 48 hrs, to run either continuously


or intermittently based on the system water temperature not
exceeding 500 C.
 Flushed water can be disposed out to the storm water drain at site
subject to compliance with the norms set by municipality for
disposal of water.
 Chemical treated water must be taken away by tankers and
disposed of in a suitable location.

C) Dynamic Flushing

 Dynamic Flushing is to take out all the left over suspended


particles, mill scale, debris and metal oxides, which are
accumulated in the system during chemical cleaning stage by
continuously flushing with dynamic flushing.
 Keep the system in circulation, using all the flushing pumps.
 Dynamic flushing through the filter of 10 micron size to remove
any suspended solids and suspended iron.
 Open the clean water feed to the system
 Slowly open the drain valves at the lowest points in the whole
system and adjust it to equate makeup and drainage.
 Note: the drainage flow must never be more than the clean make-
up water flow as to avoid system pressure loss and drainage.
 Carry out filling, draining & circulating until the water is visibly
clear and the below parameters are met.
 After dynamic flushing is over the system, check the water quality
and clean the strainer.
 Water Bird to test and confirm acceptance of water quality, which
shall be as per parameters mentioned below.

CONTRACTOR: ALEMCO ELECTROMECHANICAL CONTRACTING LLC


MS Ref No.:
ZARA-ENOVA-ALEM-MSS-
PROJECT: MECH-0003
ZARA STORAGE Rev: 00
CREATION Date: 21 October 2023
Page 16 of 23
METHOD STATEMENT FOR FLUSHING & CHEMICAL CLEANING OF CHILLED WATER SYSTEM

Responsible Reference/Verifying
DESCRIPTION OF SEQUENCE / METHOD OF WORK
Person Document

CONTRACTOR: ALEMCO ELECTROMECHANICAL CONTRACTING LLC


MS Ref No.:
ZARA-ENOVA-ALEM-MSS-
PROJECT: MECH-0003
ZARA STORAGE Rev: 00
CREATION Date: 21 October 2023
Page 17 of 23
METHOD STATEMENT FOR FLUSHING & CHEMICAL CLEANING OF CHILLED WATER SYSTEM

Responsible Reference/Verifying
DESCRIPTION OF SEQUENCE / METHOD OF WORK
Person Document

CONTRACTOR: ALEMCO ELECTROMECHANICAL CONTRACTING LLC


MS Ref No.:
ZARA-ENOVA-ALEM-MSS-
PROJECT: MECH-0003
ZARA STORAGE Rev: 00
CREATION Date: 21 October 2023
Page 18 of 23
METHOD STATEMENT FOR FLUSHING & CHEMICAL CLEANING OF CHILLED WATER SYSTEM

Responsible Reference/Verifying
DESCRIPTION OF SEQUENCE / METHOD OF WORK
Person Document

CONTRACTOR: ALEMCO ELECTROMECHANICAL CONTRACTING LLC


MS Ref No.:
ZARA-ENOVA-ALEM-MSS-
PROJECT: MECH-0003
ZARA STORAGE Rev: 00
CREATION Date: 21 October 2023
Page 19 of 23
METHOD STATEMENT FOR FLUSHING & CHEMICAL CLEANING OF CHILLED WATER SYSTEM

Responsible Reference/Verifying
DESCRIPTION OF SEQUENCE / METHOD OF WORK
Person Document

CONTRACTOR: ALEMCO ELECTROMECHANICAL CONTRACTING LLC


MS Ref No.:
ZARA-ENOVA-ALEM-MSS-
PROJECT: MECH-0003
ZARA STORAGE Rev: 00
CREATION Date: 21 October 2023
Page 20 of 23
METHOD STATEMENT FOR FLUSHING & CHEMICAL CLEANING OF CHILLED WATER SYSTEM

Responsible Reference/Verifying
DESCRIPTION OF SEQUENCE / METHOD OF WORK
Person Document

PARAMETERS VALUE (ppm)


pH 7.0-9.0
Conductivity, (µ siemens/cm) Max 800
TDS, (ppm) Max 500
Total Iron, (ppm as Fe) Max 2.0
Suspended Solids (ppm) Max 50

Addition of Passivation Chemical

> Fill the system with make-up water.


Add WB Accepta 894 Passivation Chemical at the rate of 0.1 Kg/ m3.

Circulate the same for about 24 hrs for proper passivation


During circulation the water will be passed through filter of 5 micron size
to remove any leftover suspended solids and suspended iron.

D) Reinstatement of plant items & back flushing

 Ensure constant make-up water is supplied


 Go to each individual plant item and attach a hose to the return pipe-
work drain off cock, ensure the un-attached end is in a drain or
suitably sized container to take more than the volume of the items coil
and flow & return pipe-work twice.
 Close The by-pass
 Open the flow isolation valve ensuring the return DRV is still fully
closed.
 Slowly open the drain cock and let water flow into the drain or
container until it is visibly clear.
 Close the drain cock.
 Close the flow isolation valve.
 Open the return DRV.
 Slowly open the drain cock and let water flow into the drain or
container until it is visibly clear.
 Close the drain cock.
 Close all valves serving the plant item, Remove the strainer (where
applicable) clean and replace.

CONTRACTOR: ALEMCO ELECTROMECHANICAL CONTRACTING LLC


MS Ref No.:
ZARA-ENOVA-ALEM-MSS-
PROJECT: MECH-0003
ZARA STORAGE Rev: 00
CREATION Date: 21 October 2023
Page 21 of 23
METHOD STATEMENT FOR FLUSHING & CHEMICAL CLEANING OF CHILLED WATER SYSTEM

Responsible Reference/Verifying
DESCRIPTION OF SEQUENCE / METHOD OF WORK
Person Document

 Open both the flow and return valves ensuring the flushing by-pass is
fully closed.
 Continue these steps with every previously isolated plant item on the
system.
 Water Bird to test and confirm acceptance of water quality, which
shall be as per parameters mentioned below.

PARAMETERS VALUE
pH 7.0-9.5
Conductivity, (µ siemens/cm) Max 800
TDS, (ppm) Max 500
Total Iron, (ppm as Fe) Max 1.0
Suspended Solids (ppm) Max 20

E) Final Inhibition

 Corrosion Inhibitor & Microbiocide chemicals shall be added at


this point. Accepta 2886 microbiocide at the rate 0.1 Kg/m 3 and
circulate it for 3-4hrs. Then add Accepta 2337 shall be added at
the rate of 3.0 Kg/m3 of Nitrite base Corrosion Inhibitor and
circulate.
 Keeps the system in circulation including all the equipment for a
minimum period of 24 hours.

 During circulation the water will be passed through filter of 1


micron size to remove any leftover suspended solids and
suspended iron.
 Water samples have to be collected from areas selected by
Engineer and Water Bird shall confirm the corrosion inhibitor
level
 A final water analysis indicating all the required parameters as
mentioned in below table will be submitted by Water Bird.
Parameter Supply Water After addition of Final Chemical
pH 7.0 to 8.5 8.5 to 11.0
TDS < 250 ppm < 2100 ppm
Conductivity < 350 µs/cm < 3000 µs/cm
Chlorides < 60 ppm <150 ppm
Total Hardness < 60 ppm < 100 ppm as CaCO3
Total Alkalinity < 60 ppm < 250 ppm as CaCO3

CONTRACTOR: ALEMCO ELECTROMECHANICAL CONTRACTING LLC


MS Ref No.:
ZARA-ENOVA-ALEM-MSS-
PROJECT: MECH-0003
ZARA STORAGE Rev: 00
CREATION Date: 21 October 2023
Page 22 of 23
METHOD STATEMENT FOR FLUSHING & CHEMICAL CLEANING OF CHILLED WATER SYSTEM

Responsible Reference/Verifying
DESCRIPTION OF SEQUENCE / METHOD OF WORK
Person Document
Total Iron < 0.1 ppm < 1.0 ppm Fe44
Suspended Solids < 10 ppm < 10 ppm

Nitrite (ppm asNaNO2) NA 600 - 1200

Appearance Clear Clear

Note: After addition of final treatment chemicals, the system must be left full and
completely circulated without any stagnancy.

9.5 Quality Control


 Site Management and QAQC personnel should monitor the installation to
CM / SM /
ensure it is done according to the approved drawings. SE / QCM / MSS / MSRA / RA
 Ensure phases of inspection and testing are completed as detailed in QC
approved ITP.
10.
PROGRAMME
As per the site construction programme.
11. RISKS & CONTROLS
i. Hazards / Risks
Please refer to the attached Risk Assessment page.
ii. Control Measures / Permits
Please refer to the attached Risk Assessment page.
iii. 3rd party Protection
Please refer to the attached Risk Assessment page.
12. EMERGENCY ARRANGEMENTS
i. General
 The Site HSE department shall be responsible to arrange and coordinate with site execution teams in arranging Day &
Night emergency procedures.
 In case of any emergency, the CRM will be informed about the emergency.
 Emergency assembly point shall be allotted and communicated to all the operatives involved in the job.

CONTRACTOR: ALEMCO ELECTROMECHANICAL CONTRACTING LLC


MS Ref No.:
ZARA-ENOVA-ALEM-MSS-
PROJECT: MECH-0003
ZARA STORAGE Rev: 00
CREATION Date: 21 October 2023
Page 23 of 23
METHOD STATEMENT FOR FLUSHING & CHEMICAL CLEANING OF CHILLED WATER SYSTEM

 Ensure clear access to the emergency assembly area with signage’s in place.
 No construction activity shall block the access leading to the emergency assembly point. In case of any deviation, the
access has to divert and the same shall be communicated to all the operatives on site.
ii. Fire Precautions
 Fire extinguishers shall be put in place in each working zone and a clear access shall be provided to the
location.
 All the operatives shall be trained for fire precautions on site.
 A fire warden is appointed and trained from each team of operatives.
iii. Communication
 The communication on site shall be through mobile provided by the contractor or by two-way wireless radio systems.
13. TRAINING
 Necessary safety or operational training shall be provided to the operatives involved in the activities.
14. SUPERVISION
 Adequate supervision shall be provided for executing each activity.
 Project QA/QC Engineers shall monitor the workmanship and quality of the works.
15. WORKING HOURS
 Site working hours as below:
o Day shift - 7:00am to 6:00pm (Break 12:00 pm to 01:00 pm)
 Weekly six days will be normal working period and Sunday will be the day off. In emergencies, working will be
extended to Sunday and any public holidays.
16. HOUSEKEEPING
 The work areas shall be clean and tidy.
 No debris from construction activities are allowed to accumulate in the work area.
 Work areas shall be cleaned on daily basis at the end of the shift or on completion of the activity.
 Sufficient Waste collection bins shall be provided at each working zone.
 Waste segregation area (where recyclable / landfill materials are segregated, usually as Steel, Wood, Plastic, Concrete
and Debris) shall be established to control the waste generated on site due to construction.
17. ATTACHMENTS
1. ITP
2. Risk Assessment
3. Checklists
4. Pressure Test Form

CONTRACTOR: ALEMCO ELECTROMECHANICAL CONTRACTING LLC

You might also like