Professional Documents
Culture Documents
Method Statement For Flushing & Chemical Cleaning of Chilled Water System
Method Statement For Flushing & Chemical Cleaning of Chilled Water System
:
PROJECT: ZARA-ENOVA-ALEM-MSS-
ZARA MECH-0003
Rev: 00
STORAGE
Date: 21 October 2023
CREATION
Page 1 of 23
METHOD STATEMENT FOR FLUSHING & CHEMICAL CLEANING OF CHILLED WATER SYSTEM
METHOD STATEMENT
STATEMENT
METHOD
FOR
TITLE
Sathiyamoorthy
00 21-10-2023 Issued for Approval Ajeesh Vijayan Henry Ungerer
Meyyappan
CONTENT
1. INTRODUCTION:.......................................................................................................................................3
2. SCOPE OF WORK:.....................................................................................................................................3
3. DEFINITIONS & ABBREVATIONS:........................................................................................................3
4. ROLES AND RESPONSIBILIITIES...........................................................................................................4
5. WORKING ACCESS:..................................................................................................................................9
6. LIGHTING:..................................................................................................................................................9
7. PLANT & EQUIPMENT:............................................................................................................................9
8. MATERIALS:............................................................................................................................................10
9. WORK SEQUENCE:.................................................................................................................................11
10. PROGRAMME...........................................................................................................................................15
11. RISKS & CONTROLS...............................................................................................................................15
12. EMERGENCY ARRANGEMENTS..........................................................................................................16
13. TRAINING.................................................................................................................................................16
14. SUPERVISION..........................................................................................................................................16
15. WORKING HOURS..................................................................................................................................16
16. HOUSEKEEPING......................................................................................................................................17
17. ATTACHMENTS.......................................................................................................................................17
1. INTRODUCTION:
This Method Statement describes the comprehensive requirements and procedures for the crucial phase of Flushing and
Chemical Cleaning of the Chilled Water System within the newly constructed Zara storage facility at the Mall of the Emirates,
Dubai. This meticulous process is pivotal to ensuring the optimal performance, longevity, and efficiency of the Chilled Water
System, comprising FCUs (Fan Coil Units), FAHUs (Fresh Air Handling Units), and related CHW pipe modifications in and
around the location.
2. SCOPE OF WORK:
The scope of this method statement is to define the procedure for Flushing and chemical cleaning of chilled water piping
system in accordance with the Specification Sections 15120.
PT Pressure Test
VCD Volume Control Damper
4. ROLES AND RESPONSIBILIITIES
Construction Manager
The construction manager will be responsible for following activities:
Ensure high standard of quality workmanship on site.
Ensure total Human Resource Management on site.
Contract improvement actions
Safeguard and promote Alemco interests when dealing with suppliers:
Ensure contract programme deadlines are met and exceeded where possible:
Materials and storage management:
Site Administration
Quality Manager:
The quality manager will be responsible for following activities:
Plan, Organize and Manage the QA QC team for the implementation of project quality management system.
Develop and implement the Project Quality Plan.
Develop and implement Internal and External Audit schedule and conduct /organize audits as per the schedule.
Coordinate with third party laboratories for initial testing activities and material testing. Verify the test reports for the
compliance to specification and submit to consultant.
Develop and establish a comprehensive schedule of all planned material submittals based on the project schedule.
Prepare Review and ensure the detailed material submittal schedule follows project schedule.
Coordinate with team and Consultants - to ensure the progress of material submittals is as per schedule.
Establish and Implement the Material and work Inspection procedure for the project. Monitor inspection status,
analysis status reports and trend analysis, implement corrective actions for the variations of plan.
Ensure the non-conforming materials are tagged and removed from site and provide the rejected material inspection
report to commercial and procurement for corrective actions.
Organize/Manage offsite inspections in coordination with team, Consultant and /supplier / manufacturer.
Establish and Implement procedures for monitoring and controlling quality of work including site surveillance,
recording the deficiencies and continuous follow up with construction tea for closing the recorded deficiencies.
Close Site Instructions/non-conformance reports from consultant within 14 days of receipt and conduct the review of
the Site instruction/corrective action to verify the scope for a potential claim.
Coordinate with team and consultant for implementing the corrective actions and closing the site instruction /NCR.
Coordinate with team for the timely submission of material submittals, test reports and O & M manual for the project.
Prepare the closeout documentation requirements for the project and manage the Preparation / compilation and
submission of project closeout documents to consultant.
Coordinate with consultant for testing and commissioning inspections.
Establish and implement the procedures for snagging /de-snagging at project site. Coordinate with Consultant to
complete the snagging and de-snagging inspections as per project schedule.
Provide accurate progress updates of material submittals to planning department weekly and monthly.
Provide accurate status of material inspections to planning department weekly.
Present weekly material submittal status, weekly look ahead, status of site instructions to management and implement
the actions decided for any variations from plan.
Report to commercial department regarding the poor performance of team in quality or any other concerns, which
needs to be taken contractually.
Organize trainings on special systems/new procedures introduced in the project.
Lead, motivate, Train and develop QA QC team.
Design Manager:
The design manager will be responsible for following activities:
Understand the conditions of the contract with the client.
Liaise with client to determine factors affecting planning of the interior architecture, such as budget, architectural
preferences, purpose and function.
Prepare detailed drawings and design specifications and submit these for approval by relevant planning authorities.
Carry out a thorough site survey to determine site characteristics and to assess likely problems.
Advise client on interior design factors such as space planning, layout and utilization of furnishings or equipment, and
colour coordination.
Ensure all fit out work is carried out to the specific requirements of the client.
Coordinate with other professionals, such as contractors, architects, Engineers, and planners, to ensure that work is
completed to the highest standards and that the highest quality product is delivered to the client.
Oversee all the tasks of the design team and to provide motivation and support for the team.
Review and detail shop drawings for construction plans.
Formulate environmental plan to be practical, aesthetic, and conducive to intended purposes, such as raising
productivity or selling merchandise.
Select or design, and purchase furnishings, art works, and accessories.
Render design ideas in form of paste-ups or drawings.
Use computer-aided drafting (CAD) and related software to produce construction documents.
Maintain an awareness of developments in the field of architecture so that up-to-date and accurate advice can be given
to clients.
Ensure all work is completed in compliance with the site HSE plan.
Coordinate with the local authorities where necessary
CRM Advisor / Safety Manager:
The CRM Manager will be responsible for the following activities:
Will train construction personnel in safe work practices on the job site.
Will prepare report as required by the Project Leader.
Will monitor, inspect, and report on unusual and/or serious accidents which may occur on the job sit.
Will submit written evaluation and recommendations direct to the Project Leader.
Will be based on site and manage the SAFETY performance of all project team personnel and operative.
Will assist the managers in overseeing SAFETY related activities that are associated with any of Alemco Sub-
contractor personnel, who are working on the project.
Will coordinate and supervise safety advisors and site clinic.
Will assist to prepare ‘lifting operations’ plan, ‘Fire and emergency’ plan and coordinate for its implementation.
Will ensure that method statement/risk assessment is carried out.
Will ensure that ‘Emergency Evacuation’ training is carried out. Monitor for drill compliance and recommend areas of
improvement.
Will ensure that workplace monitoring is implemented and carried out by the allocated managers.
Site Manager / Section Manager:
The Site Manager will be responsible for following activities:
Will implement engineering systems, documentation, and controls by compliance with Healthy Safety and
Environmental Alemco and industry standards, including Temporary works.
Will go through the project scope of work such as drawings, specification, Quality Plans, project program.
Will check engineering drawings and specification to identify and resolve design conflicts.
Will prepare method statements, ITPs, and risk assessments in accordance with Alemco Quality Systems as and when
required.
Will ensure all technical information is available when required for delivery of design or construction.
Will provide effective supervision and guidance to less experienced engineering staff.
Will actively manage safety and quality on site ensuring side wide compliance and not just their area of operation.
Site Engineer:
The site engineer will be responsible for following activities:
Will go through the project scope of work such as drawings, specification, Quality Plans, project program.
Will supervise site mobilization and demobilization for each and every activity under his / her control.
Will formulate work breakdown structure and document sub-contractor package including estimates of man hours and
cost.
Will oversee and administer Forman’s daily report to ensure direct labour efficiency.
Will ensure periodic reports are transmitted to Project Leader.
Will track and report material delivery.
Will ensure SAFETY requirements are maintained.
Will co-ordinate with sub-contractor to ensure interface problem are avoided and maximum Quality work achieved.
Will prepare and control inspection requests, ITPs, method statements, risk assessment, check sheets and any other
quality requirements in conjunction with the project quality representative.
Will ensure that the requirements of the Alemco Quality Procedures and followed and adhered to it.
Will raise and process NCR.
Will help create a site culture of best practice regarding safety, housekeeping, workmanship, and waste management.
Will assist supervisors and managers to allocate correct resource to activities and to review and report on the same.
Will create an open site culture where operative and foreman can raise concerns and discuss matters with the mangers
and administer result.
QA/QC Engineer:
The QA/QC Engineer will be responsible for the following activities:
Review the ITPs for each activity along with method statement from, Alemco direct works and sub-contractors works,
to verify the compliance to Project requirements. Ensure the team is adhering to the ITP and inspections are raised
accordingly.
Conduct day to day site surveillance, identify, record, and communicate the deficiencies to team to avoid
reoccurrence.
Conduct work inspections in co-ordination with Alemco team and consultant to verify the compliance to drawings and
specifications, Ensure the records are maintained.
Coordinate and Conduct Material inspections with consultant to verify the compliance to the specifications. Ensure all
rejected materials from internal and consultant inspections are tagged and removed from the site.
Conduct Supplier factory/fabrication yard inspections as per QA QC Manager Instruction to verify the compliance
with project requirements and communicate the observations to project team.
Coordinate with Team and Consultant and ensure all the inspections are conducted as per approved ITP and ensure the
records are maintained.
Coordinate with third-party laboratories and consultants for various field tests as per approved ITP and ensure the test
reports/records are submitted/maintained.
Conduct internal verification/inspections for the implementation of corrective and preventive actions for the site NCRs
and deficiencies identified by the QA QC Team. Verify the effectiveness of corrective and preventive actions.
Analyse the status of QA QC activities, prepare the trends including submittals, inspections, tests, deficiencies
identified & NCRs and communicate to QA QC Manager/Project team.
Conduct snagging – De-snagging inspections coordinating with Alemco execution Team and Consultants.
Lead and guide the inspection team to achieve the project Goals.
Site Surveyor:
The Site Surveyor will be responsible for the following activities:
Topographic and as built survey on site.
Compute the area and volume for cut and fill.
To setting out points of foundations, columns, beam lines, etc. before casting.
To setting out the base plates, points for block works and slab edges.
To prepare sketches and written reports following the surveying of an area.
To prepare contour plans and compile data from survey findings.
Solve practical problems and deal with the variables in situations where limited standardisation exists.
To input and prepare coordinates using Auto Cad.
To check the dimensions on drawings and ensure this reflects what is built on site.
Update drawings to ensure any changes during construction are accounted for.
To calculate distances, angles, area, and volume on site using surveying methods.
To manage the surveying equipment, monitoring accuracy and ensuring it is calibrated.
To assist the Alemco related businesses and Sub-Contractors in location of points and updating of drawings.
Cooperate with the façade team in marking the accurate.
Observe the displacement of structure for deflection.
Take the as built for all construction items after casting concrete.
General Foreman:
Will supervise the work to ensure that technical, Quality and SAFETY requirement are met.
Will go through the project scope of work such as drawings, specification, Quality Plans, project program.
Will prepare site daily report.
Will co-ordinate labor and sub-contractor in order to achieve program requirements.
Will ensure compliance with stated Quality requirements.
Will ensure comply with Safety requirements and regulation.
Will attend daily site meeting and communicate his report with the Line Manager.
Will participate in training and development of his subordinates.
Will organize with the Site Engineer or Section Engineer to ensure the availability of plant, equipment, and labor to
his designated work activities.
Will closely monitor the usage of consumable and materials by his crew in order to minimize wastage.
Will co-ordinate with Site Engineer regarding material requisition orders.
Will Maintain high standards of housekeeping on site.
Responsible persons for each stage of work are marked against each phase of work in work sequence section
5. WORKING ACCESS:
The access / egress for the construction vehicles for the installation of activities shall be as per the logistic Plan.
Ensure Proper coordination with all interfacing contractors for Logistics, access prior to commencement of all activities.
6. LIGHTING:
i. Safety Lighting:
The minimum safety lighting as per general requirements (Minimum 50 lux) will be provided.
ii. Task Lighting:
Task lighting shall be provided in addition to the safety lighting to undertake the task with the proper level of lighting to meet
acceptable safety and quality of workmanship standards.
7. PLANT & EQUIPMENT:
i. General:
Appropriate plants and equipment shall be used for the execution of the activity. The plant, tools and equipment shall be
checked visually prior to use.
Only authorized applicator approved and trained by the manufacturer to install manufacturer's products.
All Operators shall be trained and certified by the 3rd party wherever required.
No defective plant and equipment shall be allowed to use on site.
ii. Plant & Equipment Schedule:
9. WORK SEQUENCE:
Responsible Reference/Verifying
DESCRIPTION OF SEQUENCE / METHOD OF WORK
Person Document
9.1 Preliminary Activities / Approvals
Submit material submission for all materials related task for Engineer
approval.
As per approved material submittal and IFC drawings / specification prepare
/ submit shop drawings.
Submit MIR for the delivered materials on site.
CM / SM /
MSS / MSRA / RA
Method Statement, Inspection, Test Plan & Risk Assessment shall be SE / QCM
submitted for Engineer approval.
Identify, Quantity & Ensure all risk managed in this method statement &
residual risk are acceptable.
Ensure proper coordination with all interfacing contractors for access/
completion of previous activities before starting all activities at site.
9.2 Pre-Construction Activities CM / SM / MSS / MSRA / RA
SE / QCM /
QC
PRE-CLEANING/FLUSHING START UP CHECKLIST
General
Responsible Reference/Verifying
DESCRIPTION OF SEQUENCE / METHOD OF WORK
Person Document
conditions.
7. Make provision for drain from lowest points. Identify at site &
drawing.
10. Check and identify all air vents present in the circuit. Identify high
level location at site.
12. Make the complete chilled water piping into a single loop by
making necessary bypass connections to all equipment.
14. Check and ensure that all isolating valves enabling circulation in
this circuit are
fully open.
Responsible Reference/Verifying
DESCRIPTION OF SEQUENCE / METHOD OF WORK
Person Document
A) Static Flushing.
B) Dynamic flushing.
C) Chemical cleaning.
D) Dynamic flushing.
E) Reinstatement of plant items and back flushing.
F) Final inhibition.
Find below the supply water quality parameters to be required for CHW INFO
flushing activity.
Responsible Reference/Verifying
DESCRIPTION OF SEQUENCE / METHOD OF WORK
Person Document
Responsible Reference/Verifying
DESCRIPTION OF SEQUENCE / METHOD OF WORK
Person Document
C) Dynamic Flushing
Responsible Reference/Verifying
DESCRIPTION OF SEQUENCE / METHOD OF WORK
Person Document
Responsible Reference/Verifying
DESCRIPTION OF SEQUENCE / METHOD OF WORK
Person Document
Responsible Reference/Verifying
DESCRIPTION OF SEQUENCE / METHOD OF WORK
Person Document
Responsible Reference/Verifying
DESCRIPTION OF SEQUENCE / METHOD OF WORK
Person Document
Responsible Reference/Verifying
DESCRIPTION OF SEQUENCE / METHOD OF WORK
Person Document
Responsible Reference/Verifying
DESCRIPTION OF SEQUENCE / METHOD OF WORK
Person Document
Open both the flow and return valves ensuring the flushing by-pass is
fully closed.
Continue these steps with every previously isolated plant item on the
system.
Water Bird to test and confirm acceptance of water quality, which
shall be as per parameters mentioned below.
PARAMETERS VALUE
pH 7.0-9.5
Conductivity, (µ siemens/cm) Max 800
TDS, (ppm) Max 500
Total Iron, (ppm as Fe) Max 1.0
Suspended Solids (ppm) Max 20
E) Final Inhibition
Responsible Reference/Verifying
DESCRIPTION OF SEQUENCE / METHOD OF WORK
Person Document
Total Iron < 0.1 ppm < 1.0 ppm Fe44
Suspended Solids < 10 ppm < 10 ppm
Note: After addition of final treatment chemicals, the system must be left full and
completely circulated without any stagnancy.
Ensure clear access to the emergency assembly area with signage’s in place.
No construction activity shall block the access leading to the emergency assembly point. In case of any deviation, the
access has to divert and the same shall be communicated to all the operatives on site.
ii. Fire Precautions
Fire extinguishers shall be put in place in each working zone and a clear access shall be provided to the
location.
All the operatives shall be trained for fire precautions on site.
A fire warden is appointed and trained from each team of operatives.
iii. Communication
The communication on site shall be through mobile provided by the contractor or by two-way wireless radio systems.
13. TRAINING
Necessary safety or operational training shall be provided to the operatives involved in the activities.
14. SUPERVISION
Adequate supervision shall be provided for executing each activity.
Project QA/QC Engineers shall monitor the workmanship and quality of the works.
15. WORKING HOURS
Site working hours as below:
o Day shift - 7:00am to 6:00pm (Break 12:00 pm to 01:00 pm)
Weekly six days will be normal working period and Sunday will be the day off. In emergencies, working will be
extended to Sunday and any public holidays.
16. HOUSEKEEPING
The work areas shall be clean and tidy.
No debris from construction activities are allowed to accumulate in the work area.
Work areas shall be cleaned on daily basis at the end of the shift or on completion of the activity.
Sufficient Waste collection bins shall be provided at each working zone.
Waste segregation area (where recyclable / landfill materials are segregated, usually as Steel, Wood, Plastic, Concrete
and Debris) shall be established to control the waste generated on site due to construction.
17. ATTACHMENTS
1. ITP
2. Risk Assessment
3. Checklists
4. Pressure Test Form