You are on page 1of 12

BILL OF QUANTITY (BQ)

MEP WORKS
Project : UTILITAS RAWAT INAP
Location : Bali - Indonesia
Subject : Summary Works

TOTAL PRICE
No. DESCRIPTION
IDR

SUMMARY MEP WORKS

I PRELIMINARIES 12,500,000

II TOTAL ELECTRICAL WORKS 262,066,200

III TOTAL ELECTRONIC WORKS 195,110,500

IV TOTAL FIRE FIGHTING WORKS 55,860,300

V TOTAL PLUMBING WORKS 167,815,050

SUMMARY 693,352,050

ROUNDED 693,400,000

SUMMARY Page 1
BILL OF QUANTITY (BQ)
Project : UTILITAS RAWAT INAP
Location : Bali - Indonesia
Subject : Electrical Works

NO DESCRIPTION QTY. UNIT RATE TOTAL AMOUNT

(IDR) (IDR)
I ELECTRICAL WORKS

A MAIN & SUB DISTRIBUTION PANEL

1 MDP 1 Unit 18,750,000 18,750,000


2 SDP Lantai 1 1 Unit 9,680,000 9,680,000
3 SDP Lantai 2 1 Unit 9,680,000 9,680,000
4 SDP Lantai 3 1 Unit 10,845,000 10,845,000
5 Panel Lift 1 Unit exclude
6 Gounding 1 Unit 3,175,600 3,175,600

Sub Total Main& Sub Distribution Panel 52,130,600

B ELECTRICAL FEEDER CABLES.


1 From PLN to MDP; NYY 4 x 70 Sqmm ( Provisional sum ) 8 Mtr' 455,200 3,641,600
2 From MDP to SDP Lantai 1: NYY 4x25 mm + NYA 25 mm ( Provisional 12 Mtr' 264,800 3,177,600
sum )
3 From MDP to SDP Lantai 2: NYY 4x25 mm + NYA 25 mm ( Provisional 24 Mtr' 264,800 6,355,200
sum )
4 From MDP to SDP Lantai 3 : NYY 4x25 mm + NYA 25 mm ( Provisional 32 Mtr' 264,800 8,473,600
sum )
5 From MDP to Panel Lift : NYY 4x25 mm + NYA 25 mm ( Provisional 12 Mtr' 264,800 3,177,600
sum )

Sub Total Electrical Feeder Cable 24,825,600

C Lights, GPO & Cable Installation

C.1 LANTAI 1
Cabling Installation
1 Lighting cable installation. NYM 3x2.5 mm2 in HIC Clipsal 20 mm. 79 Point 211,700 16,724,300

2 Switch cable installation. NYM 3x2.5 mm2 in HIC Clipsal 20 mm 34 Point 104,200 3,542,800
3 Power outlet cable installation. NYM 3x2.5 mm2 in HIC Clipsal 20 mm. 37 Point 236,000 8,732,000

4 Indoor AC cable installation. NYM 3x2.5 mm2 in HIC Clipsal 20 mm. 14 Point 327,500 4,585,000

Lighting Fixtures ( Armature )


1 RM T8 2x18 watt + Grille Louvre 14 Unit 335,800 4,701,200
2 RM T8 2x18 watt + Cover 1 Unit 465,900 465,900
3 RM T8 2x18 watt + Cover (RM T8 3x18 watt + Cover not 17 Unit 465,900 7,920,300
available )
4 DL PLC 1 x 18 watt 36 Unit 171,000 6,156,000
5 DL PLC 1 x 8 watt 10 Unit 152,900 1,529,000
6 Baret Lamp 18 watt 1 Unit 301,500 301,500

Switch and Power Outlet ( Fix Only )


1 One Way One Gang / Single Switch 27 Nos 41,300 1,115,100
14 One Way Two Gang / Double Switch 7 Nos 46,100 322,700
15 Single GPO 220V-10A-1 Phase 37 Nos 53,300 1,972,100
18 Switch Socket Outlet 16A 220V - AC 14 Nos 77,200 1,080,800

Sub Total Lantai 1 59,148,700

C.2 LANTAI 2
Cabling Installation
1 Lighting cable installation. NYM 3x2.5 mm2 in HIC Clipsal 20 mm. 87 Point 211,700 18,417,900

2 Switch cable installation. NYM 3x2.5 mm2 in HIC Clipsal 20 mm 32 Point 104,200 3,334,400
3 Power outlet cable installation. NYM 3x2.5 mm2 in HIC Clipsal 20 mm. 38 Point 236,000 8,968,000

4 Indoor AC cable installation. NYM 3x2.5 mm2 in HIC Clipsal 20 mm. 13 Point 327,500 4,257,500

Lighting Fixtures ( Armature )


1 RM T8 2x18 watt + Grille Louvre 7 Unit 335,800 2,350,600
2 RM T8 2x18 watt +Cover 1 Unit 465,900 465,900

ELECTRICAL Page 2
NO DESCRIPTION QTY. UNIT RATE TOTAL AMOUNT

(IDR) (IDR)
3 RM T8 2x18 watt + Cover (RM T8 3x18 watt + Cover not 33 Unit 465,900 15,374,700
available )
4 DL PLC 1 x 18 watt 34 Unit 171,000 5,814,000
5 DL PLC 1 x 8 watt 11 Unit 152,900 1,681,900
6 Baret Lamp 18 watt 1 Unit 301,500 301,500

Switch and Power Outlet ( Fix Only )


1 One Way One Gang / Single Switch 22 Nos 41,300 908,600
14 One Way Two Gang / Double Switch 10 Nos 46,100 461,000
15 Single GPO 220V-10A-1 Phase 38 Nos 53,300 2,025,400
18 Switch Socket Outlet 16A 220V - AC 13 Nos 77,200 1,003,600

Sub Total Lantai 2 65,365,000

C.3 LANTAI 3
Cabling Installation
1 Lighting cable installation. NYM 3x2.5 mm2 in HIC Clipsal 20 mm. 76 Point 211,700 16,089,200

2 Switch cable installation. NYM 3x2.5 mm2 in HIC Clipsal 20 mm 40 Point 104,200 4,168,000
3 Power outlet cable installation. NYM 3x2.5 mm2 in HIC Clipsal 20 mm. 29 Point 236,000 6,844,000

4 Indoor AC cable installation. NYM 3x2.5 mm2 in HIC Clipsal 20 mm. 17 Point 327,500 5,567,500

Lighting Fixtures ( Armature )


1 RM T8 2x18 watt + Grille Louvre 7 Unit 335,800 2,350,600
2 RM T8 2x18 watt + Cover 1 Unit 465,900 465,900
3 RM T8 2x18 watt + Cover (RM T8 3x18 watt + Cover not 25 Unit 465,900 11,647,500
available )
4 DL PLC 1 x 18 watt 26 Unit 171,000 4,446,000
5 DL PLC 1 x 8 watt 16 Unit 152,900 2,446,400
6 Baret Lamp 18 watt 1 Unit 301,500 301,500

Switch and Power Outlet ( Fix Only )


1 One Way One Gang / Single Switch 38 Nos 41,300 1,569,400
14 One Way Two Gang / Double Switch 2 Nos 46,100 92,200
15 Single GPO 220V-10A-1 Phase 29 Nos 53,300 1,545,700
18 Switch Socket Outlet 16A 220V - AC 17 Nos 77,200 1,312,400

Sub Total Lantai 3 58,846,300


Sub Total Light, GPO & Cable Installation 183,360,000

D TESTING & COMISSIONING 1 lot 1,750,000 1,750,000.00

TOTAL ELECTRICAL WORKS 262,066,200

ELECTRICAL Page 3
BILL OF QUANTITY (BQ)
Project : UTILITAS RAWAT INAP
Location : Bali - Indonesia
Subject : Electronic Works

UNIT RATE TOTAL AMOUNT


NO DESCRIPTION QTY.
(IDR) (IDR)
II ELECTRONIC WORKS
A TELEPHONE
A.1. MAIN EQUIPMENT
1
Sub Distribution Frame (SDF) ; c/w 20 pair Krone LSA
terminal, Polyester Ex. Legrand IP 66"; to include all of
Electronic accessories

Sub Distribution Frame (SDF) Lantai 1 1.00 Unit 1,692,300 1,692,300

Sub Distribution Frame (SDF) Lantai 2 1.00 Unit 1,692,300 1,692,300

Sub Distribution Frame (SDF) Lantai 3 1.00 Unit 1,692,300 1,692,300

2 Grounding 1.00 lot 1,663,900 1,663,900

Sub Total Main Equipment 6,740,800

A.2. TELEPHONE FEEDER CABLE ( Provisional Sum )

- From Main Distribution Frame ( Existing ) To Sub


Distribution Frame Lantai 1: ITC 10x2x0,6 mm 31.00 Mtr 33,400 1,035,400

- From Main Distribution Frame ( Existing ) To Sub


Distribution Frame Lantai 2: ITC 20x2x0,6 mm 39.00 Mtr 45,500 1,774,500
- From Main Distribution Frame ( Existing ) To Sub
Distribution Frame Lantai 3 : ITC 20x2x0,6 mm 45.00 Mtr 45,500 2,047,500

Sub Total TELEPHONE FEEDER CABLE 4,857,400

A.3. TELEPHONE ACCECORIES INSTALLATION

1 Lantai 1

- Cable Installation point : ITC 2x2x0,6 mm 4.00 point 211,600 846,400

- Telephone Socket Outlet Wall type 4.00 unit 94,500 378,000

- Single Line Telephone hand set 4.00 unit 204,400 817,600

Sub Total Lantai 1 2,042,000

2 Lantai 2

- Cable Installation point : ITC 2x2x0,6 mm 4.00 point 211,600 846,400

- Telephone Socket Outlet Wall type 4.00 unit 94,500 378,000

- Single Line Telephone hand set 4.00 unit 204,400 817,600

Sub Total Lantai 2 2,042,000

3 Lantai 3

- Cable Installation point : ITC 2x2x0,6 mm 4.00 point 211,600 846,400

- Telephone Socket Outlet Wall type 4.00 unit 94,500 378,000

- Single Line Telephone hand set 4.00 unit 204,400 817,600

Sub Total Lantai 3 2,042,000

Sub Total Telephone Accessories Installation 6,126,000

Sub Total Telephone Works 17,724,200

B MATV
B.1. MAIN EQUIPMENT
1 MDF MATV 1.00 Unit existing -
2 Amplifier booster 1.00 Unit 2,426,700 2,426,700

ELECTRONIC Page 4
UNIT RATE TOTAL AMOUNT
NO DESCRIPTION QTY.
(IDR) (IDR)
3 Spliter 6 Way 2.00 Unit 515,200 1,030,400

Sub Total MAIN EQUIPMENT 3,457,100

B.2. MATV FEEDER CABLE - Provisional sum


Main feeder MATV Coaxial cable 7 C in HIC c/w support
material :

- From Main Distribution Frame To Sub Distribution Frame


Lantai 1 31.00 Mtr 53,900 1,670,900
- From Main Distribution Frame To Sub Distribution Frame
Lantai 2 35.00 Mtr 53,900 1,886,500
- From Main Distribution Frame To Sub Distribution Frame
Lantai 3 39.00 Mtr 53,900 2,102,100

Sub Total MATV FEEDER CABLE 5,659,500

B.3. MATV CABLE INSTALLATION

Installation MATV Cable, Coaxial 5C in HIC c/w support


material :
1 Lantai 1

Televisi Cabling Coaxial 5C in HIC c/w support material 8.00 point 243,800 1,950,400
Television Outlet 8.00 Unit 98,800 790,400
Spliter 2 Way 1.00 Unit 272,500 272,500
Spliter 6 Way 2.00 Unit 515,200 1,030,400

Sub Total Lantai 1 4,043,700

2 Lantai 2

Televisi Cabling Coaxial 5C in HIC c/w support material 12.00 point 243,800 2,925,600
Television Outlet 12.00 Unit 98,800 1,185,600
Spliter 2 Way 1.00 Unit 272,500 272,500
Spliter 6 Way 2.00 Unit 515,200 1,030,400

Sub Total Lantai 2 5,414,100

3 Lantai 3

Televisi Cabling Coaxial 5C in HIC c/w support material 16.00 point 243,800 3,900,800
Television Outlet 16.00 Unit 98,800 1,580,800
Spliter 4 Way 1.00 Unit 358,100 358,100
Spliter 6 Way 3.00 Unit 515,200 1,545,600

Sub Total Lantai 3 7,385,300

Sub Total MATV CABLE INSTALLATION 16,843,100

Subtotal MATV 25,959,700

C DATA WORKS

C.1. MAIN EQUIPMENT

1 EDP Lantai 1 c/w accessories as required 1.00 unit 4,737,800 4,737,800


2 EDP Lantai 2 c/w accessories as required 1.00 unit 1,722,400 1,722,400
3 EDP Lantai 3 c/w accessories as required 1.00 unit 1,722,400 1,722,400
Cabling Installation - Provisional sum

1 Cable UTP cat 6E in PVC HI conduit from Server to


EDP 1 31.00 mtr 29,900 926,900
EDP 2 35.00 mtr 29,900 1,046,500
EDP 3 39.00 mtr 29,900 1,166,100

Sub Total Main Equipment 11,322,100

C.2. DATA ACCECORIES INSTALLATION


1 Lantai 1
Cabling Installation
UTP Cat 6 in HIC 5.00 point 329,000 1,645,000

ELECTRONIC Page 5
UNIT RATE TOTAL AMOUNT
NO DESCRIPTION QTY.
(IDR) (IDR)
Data Outlet 5.00 unit 122,800 614,000

Sub Total Lantai 1 2,259,000

2 Lantai 2
Cabling Installation
UTP Cat 6 in HIC 2.00 point 329,000 658,000
Data Outlet 2.00 unit 122,800 245,600

Sub Total Lantai 2 903,600

3 Lantai 3

Cabling Installation
UTP Cat 6 in HIC 2.00 point 329,000 658,000
Data Outlet 2.00 unit 122,800 245,600

Sub Total Lantai 3 903,600


Sub Total Data Accessories Installation 4,066,200

Sub Total Data Works 15,388,300

D FIRE ALARM

D.1. MAIN EQUIPMENT

Supply and Install MCFA c/w connection 220 V supply power and supporting material :

MCFA Conventional zoning system 5 zone 1.0 Unit 25,854,300 25,854,300


Supply and Install Annunciator 5 Zone c/w supporting
1.00 Unit 9,714,800 9,714,800
material.
UPS 1200VA 1.00 Unit 6,002,400 6,002,400
Supply and Install Fire Alarm Terminal Connection installed at
each floor c/w jumper cable and supporting material in side
of :
- Juntion Box FA / TB FA , Lantai 1 1.0 Unit 1,634,200 1,634,200
- Juntion Box FA / TB FA, Lantai 2 1.0 Unit 1,634,200 1,634,200
- Juntion Box FA / TB FA, Lantai 3 1.0 Unit 1,634,200 1,634,200

Sub Total Main Equipment 46,474,100

D.2. DISTRIBUTION FIRE ALARM CABLE INSTALLATION


( Provisional sum )
Main Control Fire Alarm cable ; install on tray, incl. Cable ties
and other support material from MC FA to:
- Annuciator control cable; 3 x NYYHY 4 x 1,5 mm2 1.0 lot 3,127,500 3,127,500

- fire alarm junction box Lantai 1 ( NYYHY 4 x 1,5 Sqmm) 25.0 Mtr' 31,000 775,000

- fire alarm junction box Lantai 2 ( NYYHY 4 x 1,5 Sqmm) 29.0 Mtr' 31,000 899,000

- fire alarm junction box Lantai 3 ( NYYHY 4 x 1,5 Sqmm) 35.0 Mtr' 31,000 1,085,000

Sub Total DISTRIBUTION FIRE ALARM CABLE INSTALLATION 5,886,500

D.3. FIRE ALARM INSTALLATION

1 Lantai 1

- Supply & Install Detector, Alarm Bell & Alarm Lamp Cable
28.0 point 301,000 8,428,000
NYYMHY 4x1.5 Sqmm in HIC
- Smoke Detector 25.0 Unit 902,500 22,562,500
- Manual Push Button 1.0 Unit 466,700 466,700
- Alarm Bell 1.0 Unit 466,700 466,700
- Alarm Indicator Lamp 1.0 Unit 227,700 227,700
- End Of Line Resistor 1.0 Unit 128,400 128,400

Sub Total Lantai 1 32,280,000

ELECTRONIC Page 6
UNIT RATE TOTAL AMOUNT
NO DESCRIPTION QTY.
(IDR) (IDR)

2 Lantai 2

- Supply & Install Detector, Alarm Bell & Alarm Lamp Cable
24.0 point 301,000 7,224,000
NYYMHY 4x1.5 Sqmm in HIC
- Smoke Detector 21.0 Unit 902,500 18,952,500
- Manual Push Button 1.0 Unit 466,700 466,700
- Alarm Bell 1.0 Unit 466,700 466,700
- Alarm Indicator Lamp 1.0 Unit 227,700 227,700
- End Of Line Resistor 1.0 Unit 128,400 128,400

Sub Total Lantai 2 27,466,000

3 Lantai 3
- Supply & Install Detector, Alarm Bell & Alarm Lamp Cable
31.0 point 301,000 9,331,000
NYYMHY 4x1.5 Sqmm in HIC
- Smoke Detector 28.0 Unit 902,500 25,270,000
- Manual Push Button 1.0 Unit 466,700 466,700
- Alarm Bell 1.0 Unit 466,700 466,700
- Alarm Indicator Lamp 1.0 Unit 227,700 227,700
- End Of Line Resistor 1.0 Unit 128,400 128,400

Sub Total Lantai 3 35,890,500


Sub Total Fire Alarm Installation 26,559,500

Testing and commissioning, staff trainning and


D.4. 1.00 Lot 3,500,000 3,500,000
Depnaker sertification

Sub Total Fire Alarm Works 82,420,100

E CCTV SYSTEM

E.1. MAIN EQUIPMENT

Supply and Install CCTV Equipment and supporting material :

To supply & install CCTV equipment and accessories including


1.0 lot by specialist
all supporting material as required

Sub Total Main Equipment -

E.2. CCTV INSTALLATION

Lantai 1

- Supply & Install CCTV cable point : Coaxial RG 59 in HIC 5.0 Point 592,400 2,962,000

- Outdoor Camera 1080 P Full HD 2.0 MP 3.0 Unit by specialist


- Outdoor Camera 1080 P Full HD 2.0 MP 1 2.0 Unit by specialist

Sub Total Lantai 1 2,962,000

Lantai 2

- Supply & Install CCTV cable point : Coaxial RG 59 in HIC 5.0 Point 592,400 2,962,000

- Outdoor Camera 1080 P Full HD 2.0 MP 2.0 Unit by specialist


- Outdoor Camera 1080 P Full HD 2.0 MP 1 3.0 Unit by specialist

Sub Total Lantai 2 2,962,000

Lantai 3

- Supply & Install CCTV cable point : Coaxial RG 59 in HIC 5.0 Point 592,400 2,962,000

- Outdoor Camera 1080 P Full HD 2.0 MP 2.0 Unit by specialist


- Outdoor Camera 1080 P Full HD 2.0 MP 1 3.0 Unit by specialist

Sub Total Lantai 3 2,962,000

Sub Total CCTV Installation 8,886,000

Sub Total CCTV Works 8,886,000

ELECTRONIC Page 7
UNIT RATE TOTAL AMOUNT
NO DESCRIPTION QTY.
(IDR) (IDR)
F SOUND SYSTEM

F.1. MAIN EQUIPMENT

Supply and Install sound system Equipment and supporting material :

To supply & install Sound System equipment and accessories


1.0 lot by specialist
including all supporting material as required

Sub Total Main Equipment -

F.2. SOUND SYSTEM INSTALLATION

Lantai 1

- Supply & Install Sound Cable NYMHY 2 x1.5 Sqmm in HIC 22.0 Point 193,000 4,246,000

- Supply & Install Volume Control Cable, NYMHY 3x1.5 Sqmm


10.0 Point 222,000 2,220,000
in HIC
- Ceiling Speaker 3W 22.0 Unit 258,100 5,678,200
- Volume Control 10.0 Unit 197,100 1,971,000

Sub Total Lantai 1 14,115,200

Lantai 2

- Supply & Install Sound Cable NYMHY 2 x1.5 Sqmm in HIC 18.0 Point 193,000 3,474,000

- Supply & Install Volume Control Cable, NYMHY 3x1.5 Sqmm


13.0 Point 222,000 2,886,000
in HIC
- Ceiling Speaker 3W 18.0 Unit 258,100 4,645,800
- Volume Control 13.0 Unit 197,100 2,562,300

Sub Total Lantai 2 13,568,100

Lantai 3

- Supply & Install Sound Cable NYMHY 2 x1.5 Sqmm in HIC 22.0 Point 193,000 4,246,000

- Supply & Install Volume Control Cable, NYMHY 3x1.5 Sqmm


17.0 Point 222,000 3,774,000
in HIC
- Ceiling Speaker 3W 22.0 Unit 258,100 5,678,200
- Volume Control 17.0 Unit 197,100 3,350,700

Sub Total Lantai 3 17,048,900


Sub Total Sound System Installation 44,732,200

Sub Total sound System 44,732,200

TOTAL ELECTRONIC 195,110,500

ELECTRONIC Page 8
BILL OF QUANTITY (BQ)
Project : UTILITAS RAWAT INAP
Location : Bali - Indonesia
Subject : Fire Fighting Works

UNIT RATE TOTAL AMOUNT


NO DESCRIPTION QTY.
(IDR) (IDR)

III FIRE FIGHTING WORK

A FIRE EXTINGUISER

Lantai 1
Fire Extingusher CO2 Kap. 5 Kg 6.0 Unit 2,068,900 12,413,400
Sub Total Lantai 1 12,413,400

Lantai 2
Fire Extingusher CO2 Kap. 5 Kg 12.0 Unit 2,068,900 24,826,800
Sub Total Lantai 2 24,826,800

Lantai 3
Fire Extingusher CO2 Kap. 5 Kg 9.0 Unit 2,068,900 18,620,100

Sub Total Lanatai 3 18,620,100

TOTAL FIRE FIGHTING WORKS 55,860,300

FIRE FIGHTING Page 9


BILL OF QUANTITY (BQ)
Project : UTILITAS RAWAT INAP
Location : Bali - Indonesia
Subject : Plumbing Works

NO DESCRIPTION QTY. UNIT RATE TOTAL AMOUNT

(IDR) (IDR)

IV PLUMBING WORKS
A MAIN EQUIPMENT
A.1. CLEAN WATER :
1 Booster pump Cap 4 m³ ,Daya 1.8 KW/220 V/50HZ 2900 Rpm 1 unit 9,787,000 9,787,000
,Head 38 M complete panel control
2 PFR Roof Tank 2.200 liter 1 unit 5,100,000 5,100,000
3 Gate Valve Ø 1" 2 unit 166,100 332,200
4 Gate Valve Ø 2" 16 unit 420,100 6,721,600
5 Check Valve Ø 2" 1 unit 532,300 532,300
6 Check Valve Ø 2" 1 unit 532,300 532,300
7 Floating valve dia 1" 1 unit 1,185,900 1,185,900
8 Material bantu 1 lot 2,698,500 2,698,500

Sub Total Main Equipment 26,889,800

A.2 CLEAN WATER INSTALLATION

A.2.1 Lantai 1
Pipe PVC AW Class
1 Dia 1" 57 Mtr' 25,800 1,470,600
2 Dia 3/4" 98 Mtr' 22,100 2,165,800
3 dia 1/2" 94 Mtr' 19,700 1,851,800
4 Gate valve Ø 1" 4 Unit 166,100 664,400
5 Fitting & support 1 lot 1,176,000 1,176,000

Sub Total Lantai 1 7,328,600

A.2.2 Lantai 2
Pipe PVC AW Class
1 Dia 1" 62 Mtr' 25,800 1,599,600
2 Dia 3/4" 104 Mtr' 22,100 2,298,400
3 dia 1/2" 92 Mtr' 19,700 1,812,400
4 Gate valve Ø 1" 4 Unit 166,100 664,400
5 Fitting & support 1 lot 1,116,000 1,116,000

Sub Total Lantai 2 7,490,800

A.2.3 Lantai 3
Pipe PVC AW Class
1 Dia 2" 62 Mtr' 56,600 3,509,200
2 Dia 1" 98 Mtr' 25,800 2,528,400
3 Dia 3/4" 164 Mtr' 22,100 3,624,400
4 dia 1/2" 136 Mtr' 19,700 2,679,200
5 Gate valve Ø 1" 4 Unit 166,100 664,400
6 Gate valve Ø 1/2" 1 Unit 134,800 134,800
6 Fitting & support 1 lot 2,160,000 2,160,000

Sub Total Lantai 3 15,300,400


Sub Total Clean Water Installation 30,119,800
Sub Total Clean Water 57,009,600

B Sewage & Waste Water


B.1 Main Equipment
1 Seftic tank konventional 1 unit by others
2 Absorption pit 1 unit by others

Sub Total Main Equipment -

PLUMBING Page 10
NO DESCRIPTION QTY. UNIT RATE TOTAL AMOUNT

(IDR) (IDR)

B.2 SEWAGE & WASTE WATER INSTALLATION

B.2.1 Lantai 1
1 PVC "AW" Dia. 4" 132 Mtr' 110,100 14,533,200
2 PVC "AW" Dia. 3" 88 Mtr' 80,000 7,040,000
3 PVC "AW" Dia. 2" 34 Mtr' 56,600 1,924,400
4 PVC "AW" Dia. 1.5" 22 Mtr' 44,300 974,600
5 PVC "AW" Dia. 1.25" ( Venting ) 68 Mtr' 39,200 2,665,600
6 Floor drain 11 nos 195,100 2,146,100
7 Pipe fitings and support 1 lot 4,749,100 4,749,100
Sub Total Lantai 1 34,033,000

B.2.2 Lantai 2
1 PVC "AW" Dia. 4" 88 Mtr' 110,100 9,688,800
2 PVC "AW" Dia. 3" 124 Mtr' 80,000 9,920,000
3 PVC "AW" Dia. 2" 44 Mtr' 56,600 2,490,400
4 PVC "AW" Dia. 1.5" 29 Mtr' 44,300 1,284,700
5 PVC "AW" Dia. 1.25" ( Venting ) 66 Mtr' 39,200 2,587,200
6 Floor drain 12 nos 195,100 2,341,200
7 Pipe fitings and support 1 lot 4,545,100 4,545,100
Sub Total Lantai 2 32,857,400

B.2.3 Lantai 3
1 PVC "AW" Dia. 4" 143 Mtr' 110,100 15,744,300
2 PVC "AW" Dia. 3" 129 Mtr' 80,000 10,320,000
3 PVC "AW" Dia. 2" 56 Mtr' 56,600 3,169,600
4 PVC "AW" Dia. 1.5" 44 Mtr' 44,300 1,949,200
5 PVC "AW" Dia. 1.25" ( Venting ) 88 Mtr' 39,200 3,449,600
6 Floor drain 16 nos 195,100 3,121,600
7 Pipe fitings and support 1 lot 6,160,750 6,160,750
Sub Total Lantai 3 43,915,050
Sub Total Sewage & Waste Water Installation 110,805,450
Sub Total Sewage & Waste Water 110,805,450

TOTAL PLUMBING 167,815,050

PLUMBING Page 11
BILL OF QUANTITY (BQ)
Project : UTILITAS RAWAT INAP
Location : Bali - Indonesia
Subject : Specification Material

NO. MATERIAL SPECIFICATION BRAND

ELEKTRIKAL
1 LV Switchboard Component MCB, MCCB ABB, MG
2 Panel maker PRISMA ELEKTRIK
3 Kabel Feeder NYY, SUPREME / METAL
4 Kabel Instalasi NYM SUPREME / METAL
5 Switch / GPO VIVACE SCHNEIDER
6 Conduit DIA 20MM LEGRAND / CLIPSAL
7 Lighting Fixtures LED PHILLIPS /Sakasuwi
8 Lighting Bulb LED PHILLIPS

TELEPHONE
1 PABX Existing
2 Telephone Outlet VIVACE SCHNEIDER
3 Telephone Cable BELDEN
4 Conduit DIA 20MM LEGRAND / CLIPSAL

MATV
1 Equipment Boster / Spliter IKUZI
2 Coaxial Cable 5C, 7C COMSCOPE/BELDEN
3 TV Outlet VIVACE SCHNEIDER
4 Conduit DIA 20MM LEGRAND / CLIPSAL

CCTV
1 Equipment Existing
2 CCTV Cable RG 59 BELDEN
3 Conduit DIA 20MM LEGRAND / CLIPSAL

DATA
1 Equipment SBO
2 DATA Cable CAT 6 BELDEN
3 DATA Outlet VIVACE SCHNEIDER
4 Conduit DIA 20MM LEGRAND / CLIPSAL

FIRE ALARM
1 Equipment CONVENTIONAL NOHMI
2 Kabel Instalasi NYYHY / NYMHY SUPREME / METAL

SOUND SYSTEM
1 Main Equipment Existing
2 Ceiling Speaker NYYHY TOA
3 Kabel Instalasi NYYHY SUPREME / METAL

PLUMBING
1 Distribution Pump Boster Pump GRUNDFOS CM PT 5-5
2 Valve dia 15-50 mm BRASS CLASS 125 PSI screw KITZ
3 Clean Water Pipe PVC Class AW Wavin
4 Sewage & Waste Water Pipe CLASS AW Wavin
5 Vent Pipe CLASS AW Wavin
6 PVC Fitting CLASS TS / DV RUCIKA
7 Seftic tank Conventional By Civil
8 Absorption Fit Concrete By Civil

FIRE FIGHTING
1 Fire Extinguiser CO 2 Cap. 5 Kg Hooseki

SPEECS Page 12

You might also like