T3- LUCKNOW AIRPORT PROJECT

TDS STATUS - ITEM NOT SUBMITTED AS ON DATE BY M/S. NCCL


1 2 3 4 5

SR.NO ITEM DESCRIPTION TDS STATUS SUB CONTRACTOR / VENDOR APPROVED DATE Remarks

1 HVAC PACKAGE NOT YET SUBMITTED 20.06.2019 ( VOLTAS Ltd)


2 STP PACAKAGE NOT YET SUBMITTED 28.06.2019( Premier Tech Brisanzia Ltd)
3 SOLAR PLANT NOT YET SUBMITTED
4 DB - VTPN / Flame retardent enclouser NOT YET SUBMITTED
5 HV /LT / UPS PANELS NOT YET SUBMITTED
6 DG SETS - Re-Submission NOT YET SUBMITTED
7 Lift & Escalators Re-submission NOT YET SUBMITTED
8 TMRS Package Re-submission NOT YET SUBMITTED
9 Power Cables NOT YET SUBMITTED
10 Light Fittings NOT YET SUBMITTED
11 Exhaust Fan and Ceiling Fan NOT YET SUBMITTED
12 WTP Pacakage NOT YET SUBMITTED
13 Earthing and Lighting Arrestor NOT YET SUBMITTED
14 Electrical Safety equipments NOT YET SUBMITTED
15 Fire Alarm Re submission NOT YET SUBMITTED
16 BUS Ducts NOT YET SUBMITTED
17 BMS system NOT YET SUBMITTED
FIRE FIGHTING- 29 Items including Fire Pumps
NOT YET SUBMITTED
18 Pressure switches , Orrifice plate etc.
19 Gas flooding & fire suppression system NOT YET SUBMITTED
TDS for Sanitary fixtures & CP Fittings , DI
Manhole covers , SS Gratings , Pipe fittings
,Paint , Pressure reducing station , Thermal NOT YET SUBMITTED
Insulation , water flow meter , Gully trap , Rainy
20 well & Harvesting Pits Items
STATUS OF TDS AS ON DATE
CONSTRUCTION OF NEW INTEGRATED PASSANGER TERMINAL BUILDING AT CCS INTERNATIONAL AIRPORT, LUCKNOW
E& M TECHNICAL DATA SHEET APPROVAL STATUS
1 2 3 4 5 6 7 8 9 10 11 12

AAI -Clarification / Approval


NCC Egis-India
Name of No of days taken
specialised by NCC for TDS No of EGIS NCC
No of
Sr. Vendor/ agency/ submission or Re- working
Item Description Working Present Status
No sub-contractor/ Submission -after Days by AAI ISSUED TO TDS
AAI/Egis Egis-India AAI NEEDS Days by AAI
TDS Submission Date and Response/ Comments NCC For RE-
manufacturer Comments Time issued Date, time
CLARIFICATION SUBMISSION of Approved
FROM EGIS
TDS Date By AAI

approval for MS Conduit and


First Submission 14.01.2019,18:00 hrs 18.01.2019, 12:35 hrs 3.5 Days NA 24.01.2019 24.01.2019 4 Days Re-Submission for MS
MS Conduit and accessories
1 AKG
Accessories

42 Days delay 07.03.2019, 17:00 hrs 08.03.2019, 13:00 hrs 0.5 days NA NA 12.03.2019 2.5 Days APPROVED, closed

First Submission 08.05.2019, 17:56 hrs 11.05.2019, 12:00 hrs 2.5 days NA 17.05.2019 NA 5 days Not Approved, Re-submit
MS Conduit and
2 BEC
Accessories
13 Days delay 01.06.2019,17:00hrs 04.06.2019,11:59 hrs 1.5days NA NA 07.06.2019 3 days APPROVED, closed
66 Days Delay 22.07.2019, 11:15 hrs 24.07.2019, 13:00 hrs 1.5 days NA NA 26.07.2019 1.5 days APPROVED, closed

Legrand First Submission 27.05.2019, 17:00 hrs 29.05.2019,15:24 hrs 1.5 days NA NA NA NA NCC not responded on Email

NCC responded the comments


33 Days Delay 03.07.2019, 15:55 hrs 04.07.2019, 15:10 hrs 1 Day NA NA NA NA
on email dated 11th July 2019

GI Modular Box,Flush Type NCC responded and given the


3 Switch socket,fan 7 days Delay 11.07.2019,18:48 hrs 12.07.2019, 12:14 hrs 1 Day NA NA NA NA reference of MOM held on 12th
regulator,bell push July 2019
MK (Honeywell)
Partially approved response
1 day Delay 13.07.2019,11:05hrs 23.07.2019,12:10 hrs 7.5 days NA 25.07.2019 NA 5.5 days send by AAI on dated
25.07.2019, NCC to re-submit

Approved with Comments,


12 Days Delay 06.08.2019, 12:00hrs 07.08.2019, 15:40 hrs 0.5 days NA NA 08.08.2019 1 Day
Closed

First Submission 21.05.2019, 16:00hrs 08.06.2019,16:55 hrs 16 days 14.06.2019 08.06.2019 NA 1 day NCC to Re-Submit, Not
Approved

Distribution
4 C&S
Board,MCB,RCCB
NCC responded on 26th July
2019, Sample Submission
43 days Delay 22.07.2019, 11:25hrs 23.07.2019,18:45 hrs 1 day NA NA NA NA delayed by NCCL- Delay by 15
Days, further it is under review
By Egis.

Not Comply, NCC to re-submit


Distribution in accordance with Comments
4 C&S NA NA 03.08.2019, 12:05 hrs 10days NA NA NA NA send by Email- NCCL TILL DATE
Board,MCB,RCCB
NO RESPONSE

No response from NCC


regarding the comments raised
on mail. After that final
NA NA 06.08.2019 1.5 DAYS NA NA 08.08.2019 1.5 Days observation and comments
submit to AAI for further
action, Approved with
comments, closed

MEM First Submission 07.05.2019, 17:56 hrs 09.05.2019,11:00 hrs 1.5 days NA 07.06.2019 NA 24 days NCC to Re-Submit,Not
Approved, Yet Not Submit.
5 GI Cable Tray
Approved with comments
Venus 63 Days Delay 19.08.2019, 16: 50hrs 09.09.2019, 12:00 hrs 15 days NA 10.09.2019 1 day closed

Sample Visual Checking delayed


by NCCL , due to non availibility
First Submission 05.07.2019,12:00 hr 29.07.2019,18:10 hrs 20 days NA 02.08.2019 NA 3 Days of Measuring Instrument - NCC
6 PVC Insulated Cu. Wire Rallison delay by 15 days and NCC to
Re-Submit for further approval

Approved with comments,


14 DAYS DELAY 21.08.2019,14:25 hrs 11.09.2019, 11.00 hrs 16 days NA NA 12.09.2019 1 day
closed
Approved with Comments,
7 10M High GRP Light Pole Crompton First Submission 22.07.2019,11:15 hrs 09.09.2019, 11.00hrs 36 days NA
Closed
Approved with Comments,
8 135W LED Street Light Crompton First Submission 22.07.2019, 11:15hrs 09.09.2019,11.00hrs 36 days NA
Closed

AAI raised clarification / query


to Egis letter - AAI/LKO/Engg-
First Submission 23.04.2019,14.30hrs 23.05.2019, 12:00 hrs 25 days 29.05.2019 NA NA 6 Days
Project/PMC/2019-20/288-291
dated 29.05.2019

TDS -Escalators- AAI raised clarification / query


27.05.2019, 17:20 hrs 12.06.2019,16:20hrs 13 days 18.06.2018 NA NA 5 days
First Submission to Egis-dated 18.06.2018

AAI raised clarification/ query


NA NA 14.06.2019,14:50 hrs 12 days 19.06.2019 NA NA 3 days
to Egis dated 19.06.2019

NA NA 24.07.2019, 11:00 hrs 29 days NA NA NA 4 days Response awaited from AAI

Lifts & Escalators Technical Johnson Lifts Pvt


After joint meeting with ED
North , Egis H.O Team, AAI LKO
Team ( final details preapared
and submit to AAI for further
Lifts & Escalators Technical Johnson Lifts Pvt 02.08.2019 necessary action. Not
9 NA NA 01.08.2019 1 day NA NA 1 day
Data Sheet Ltd approved, Re-submit by NCC-
Escalator system ( AAI/LKO/T-
3/ESCALATOR/ENGG(E )/ 2019-
20/532-534- NCC
to delay by 20 days

After joint meeting with ED


North , Egis H.O Team, AAI LKO
Team ( final details preapared
NA NA 05.08.2019 1 day NA 05.08.2019 NA 1 day and submit to AAI for further
necessary action. Not
approved, Re-submit by NCC-
Escalator system ( AAI/LKO/T-
3/Elevators /Engg (E )/ 2019-
20/548-550 dated 05.2019

Approved with Comments,


35 days delay 17.09.2019. 17:10 hrs 07.10.2019, 11.00hrs 15 days Closed.

First Submission- NCC to Re-Submit, Not


02.05.2019,17:54hrs 31.05.2019, 12:00hrs 25 days NA NA NA NA Approved, NCC Delay by 35
Lift
Lift GA Drawing/ Shop Johnson Lifts Pvt days
10 Drawing Ltd
NCC to Re-Submit, Not
Ecsalators 20.05.2019, 18:05 hrs 03.06.2019,11:00 hrs 11 days NA NA NA NA Approved, NCC Delay by 35
days

AAI raised clarification / query


First Submission 02.05.2019, 17:32hrs 05.06.2019, 14:40 hrs 28 days 17.06.2019 NA NA 9 days
to Egis
DG Sets TDS and 20 KL
11 HSD-TDS

NCC to Re-Submit, Not


NA NA 27.06.2019, 10:45 hrs 8 days NA 28.06.2019 NA 1 day Approved- Not Yet Submit -
delay by 46 days
Sterling & Wilson NCC to re-Submit , Not
20 KL HSD Tank GA Powergen Pvt Ltd First Submission
12 Drawing 02.05.2019,17:32 hrs 10.06.2019, 11.00hrs 32 days NA 10.06.2019 NA NA Approved , not yet submit-
delay by 46 days

NCC to re-Submit , Not


13 DG Set Cooling Tower First Submission 02.05.2019, 17:32hrs 05.06.2019, 14:40 hrs 28 days NA 10.06.2019 NA NA Approved , not yet submit- NCC
delay by 46 days

Layout , GA, Foundation NCC to re-Submit , Not


14 First Submission 02.05.2019,17:32 hrs 10.06.2019, 11.00hrs 34 days NA 10.06.2019 NA NA Approved , not yet submit- NCC
Drawing of DG Set
delay by 46 days
Comments Given by Mail, Re-
second Submission 25.09.2019, 12:20 hrs 27.09.2019, 12:45 hrs 2 days NA NA NA NA
DG Sets TDS and 20 KL Jakson Ltd- 70 Submission
15
HSD-TDS days delay
Re-Submission 03.10.2019, 16:15 hrs Under review by Egis

Not Approved , Resubmission,


First Submission 19.08.2019, 16:40hrs 27.08.2019, 17:50 hrs 30 days
NCC delay by 45 Days
16 Transformer Voltamp

Not aprroved Re-submit,


17 MK (Honeywell) First Submission 20.08.2019, 16:42 hrs 13.09.2019, 15:00 hrs 18 days
closed
GI Raceway & Junction
Boxes Clarification send to M/s. NCCL,
OBO- 10 days
second Submission 26.09.2019, 26.09.2019, 14:21Hrs 0.5 days awaited for Re-submission, NCC
delay
delay by 45 Days

aprroved with comments,


18 ELV Wires Rallison & Bonton First Submission 23.07.2019, 15:20 hrs 12.09.2019, 13.00 hrs 35 days
closed

approved with comments,


19 GI Earthing Strip MEM First Submission 09.09.2019, 15:05 hrs 11.09.2019, 12:00 hrs 2 days 12.09.2019 1 days
closed

Approved with Comments,


closed for VTPN DB and TPN
20 Flame Retardent DB Hensel First Submission 14.09.2019,13:20 hrs 20.09.2019, 18:00 hrs
DB -TDS to re-submission, NCC
Delay by 30 Days

Approved with comments,


21 DWC HPDE Pipe Astral First Submission 09.09.2019, 12:00 hrs 14.09.2019
closed

22 LT Panel ABB First Submissiom 13.09.2019, 17:00 Hrs 15.10.2019, 15:00 hrs Not Approved, Re-submission

Approved with Comment,


23 HT End Termination 3M First Submission 20.09.2019, 10:20 hrs 23.09.2019, 15:10 hrs Closed

Under Review by Egis to be


24 HT Panel Siemens First Submission 24.09.2019, 11:37 hrs
submitted by 18.10.2019
24 HVAC
Rollastar / Approved with Comments,
25 G.I Ducting First Submission 27.08.2019, 16:42 hrs 09.09.19, 12:20 hrs 9 days
Ductofab Closed

MS & GI Pipe, Balancing Jindal & Sail,


Approved with Comments,
26 Valve, Duct & Room Advnce & Castle, First Submission 09.09.2019, 14: 45 hrs 20.09.2019, 15:30 hrs
Acoustic Lining Twiga Closed

Butterfly Valve & Check Re-submission and approved


27 Valve(NRV) Advance & Castle First Submission 28.08.2019, 14:00 hrs 16.09.2019, 14:00 hrs 15 days with comments
Heat Load Calculation - Not Approved, Re-Submission,
28 Arrival & Mezzanine Level Voltas First Submission 18.09.2019, 14:20 hrs 01.10.2019, 12:00 hrs 11 days NCC delay by 15 Days

Mechanical Ventilation
ACHP Calculations- Design Parameters - under
29 Voltas First Submission 27.09.2019,16:25 hrs
Basement & Basement review by Egis
Mezzanine
30 Cooling Tower Pharphur First Submission 07.10.2019, 15:42 hrs under review by Egis

HVAC-BTU,Y-Strainer, Pot Omicron ,


31 Strainer, Auto Air Vents, Emerald, Anergy, First Submission 07.10.2019, 15:42 hrs under review by Egis
Thermal Insulation Aeroflex

32 Chillers First Submission 15.10.2019, 15:00 hrs under review by Egis


32 STP & WTP
wilo , Beta,
STP- 27 item ( raw sewage
Kirloskar, Rehau,
33 pump, air blowers, sludge First Submission 18.09.2019, 18:00hrs under review by Egis
roto, Aastha,
pump, sluice valve etc)
sukrut, MM Aqua

WTP & RO System- Raw


water pump, Activated
Carbon Filter, Antiscalant
dosing system, micron
cartridge filter,High Wilo, Stalite, Asia
pressure feed pump, ROM, LMI, Sintex,
34 First Submission 25.09.2019, 12:00 hrs under review by Egis
CIP Pump, Wastech, Danfoss,
Hydropneumatic pump, Wellmate3
Softner feed pump,
Tubewell Submersible
pump, Pressure sand filter,
chlorination

35 Airport IT system
NCC to clarify and provide the
26.06.2019 ( submit on supporting documents - as per
First Submission 27.06.2019, 12.40hrs) 30.07.2019, 11:15hrs 28 days NA NA NA NA comments given in Email by
Honeywell/ Egis
36 CCTV- TDS
Siemens
soft copy received , hard copy
20 days delay 23.08.2019, 18:17 hrs
with stamp awaited from NCCL

Approved and for balance Extra


First Submission 15.03.2019, 13:00 hrs 20-04.2019, 11:00 hrs 30 days NA NA 29.04.2019 6 Days Item Re-submission of TDS
(RFID encoders etc)

ACS System Technical


37 Datasheet of 10 BOQ Item Solus
ACS System Technical NCC to clarify and provide the
37 Solus supporting documents - as per
Datasheet of 10 BOQ Item 50 Days delay 20.06.2019,14:45hrs 26.07.2019, 18:49 hrs 30 Days NA NA NA NA
comments given in Email by
Egis

7 Days delay 05.08.2019, 12: 00 hrs 13.08.2019, 14:50 hrs 5 days NA NA 13.08.2019 0.5 days letter issued to NCC, Closed

AAI raised Clarification from


First Submission 18.06.2019, 14:35hrs 27.06.2019, 12:40hrs 8.5 days 01.07.2019 NA NA 2 days
Egis

29 DAS-TDS Frogcellsat Partially Approved, Response


awaited from NCC for BOQ
NA NA 26.07.2019, 16:15hrs 21 days NA NA 30.07.2019 3 days
item number 1241- NCC delay
by 22 days

Response awaited from AAI


(File Process to CHQ for Extra
Passive Network- SCS
30 Belden First Submission 06.06.2019, 17:45hrs 20.06.2019, 14:30hrs 11.5 days NA NA NA 55 days Item In-Principle Approval ),Egis
System-TDS
response approved with
comments.

First Submission 15.03.19,12:00hrs 20.04.2019, 13.00hrs 29 days NA 29.04.2019 NA 6 days Not Approved, Re-submit
31 FDS -TDS Siemens Not Approved, Re-submit, yet
27.5 Days Delay 31.05.2019, 14:00Hrs 11.07.2019, 16:04 hrs 37.5 days NA 23.07.2019 NA 9 days not re-submit by
NCC -24 days delay
Response awaited from AAI
(File Process to CHQ for Extra
32 Active Network-TDS HP First Submission 10.04.2019, 18:10 hrs 20.06.2019, 14:30 hrs 58 days NA NA NA 55 days Item In-Principle Approval ),Egis
response approved with
comments.

AAI raised clarification from


First Submission 27.03.2019,14:45hrs 08.06.2019,17:50hrs 60 days 18.06.2019 NA NA 07 days Egis and Egis further required
clarification from NCCL

clarification required from


NA NA 21.06.2019, 09:32 hrs 3 days NA NA NA NA
NCC ,

Partially response received


33 EPABX-IP PBX- TDS Unify / Siemens 1 days delay 22.06.2019 25.06.2019,09.32hrs NA NA NA NA NA from NCC and further no
response received from NCC.

Not Approved , NCC to Re-


submit ( AAI/LKO/T-
NA NA 26.07.2019, 16:15 hrs 25 days NA 30.07.2019 NA 2.5 days 3/EPABX/ENGG ( E)/2019-
20/S13-S15) -
NCC delay by 25 days

23 days delay 26.08.2019

AAI raised clarification/ query


First Submission 27.03.2019,14:45hrs 15.06.2019, 14:55hrs 65 days NA NA NA 4 days
to Egis dated 21.06.2019

34 Data Centre- TDS Vertiv


email send to NCC - Response is
NA NA 26.06.2019,18:36 3.5 days NA NA NA NA still awaited from NCC- 28 days
34 Data Centre- TDS Vertiv delay
letter issued to NCC - response
NA NA 27.07.2019, 17:00 NA NA NA NA NA
awaited
under review by Egis- delay by
35 days delay 08.08.2019 13 days

New submission by NCC for Boq


DC- IT Hardware ( Servers Item 1305 to 1313 and 1323
35 and Thin Client) HP First Submission 26.08.2019. 13:25
to1331 ( Under review by Egis )

36 FIDS-TDS DELL First Submission 26.08.2019, 13:25 under review by Egis.

37 PAVA system-TDS BOSCH First Submission 27.08.2019, 16:55 under review by Egis.
Fire Fighting and Plumbing
3 item approved (Firemen axe,
flow switch, vibration
First Submission 03.04.2019, 17:45 hrs 10.04.2019, 11:00 hrs 5.5 days NA 16.04.2019 16.04.2019 4.5 days
eliminators) , 33 items not
approved, NCC to resubmit

4 items Approved (landing


valve (external
+internal ),pressure gauge,
Rosette plate )and 1 item not
26.5 days delay 17.05.2019, 12:43 hrs 23.05.2019, 12:00 hrs 4.5 days NA 29.05.2019 29.05.2019 4.5 days approved, NCC to resubmit ( Till
date balance items not Re-
submit by NCC- 73
days delay

Fire Fighting System Ranjeet 8 item approved (MS Pipe,


38 Technical Data Sheet of 36 Mechatronics Pvt Corrosion Protection Tape,
Nos Boq Item Ltd Primer paint , MS fittings, pipe
supports, strcuture support,
30 days delay 21.05.2019, 12:00hr 04.06.2019, 10:45 hrs 11 days NA 29.06.2019 29.06.2019 21 days B/F Valve, Sluice Valve, NRV )
and 8 not approved , ( till date
no re-submission by
NCC- delay by 55
Days)

Re-Submission by NCCL
( NRV,Ball Valve, Pressure
Switch, air vessel, Deluge Valve,
55 Days Delay 27.08.2019, 13:00 hrs 12.09.2019, 17:50 hrs 14 days Fire Extenguishers -4.5kg,
22.5kg,6 kg,50L (foam ),
approved with comments ,
closed
28.05.2019, recevied on
11.06.2019,12:00 hrs 8.5 days 13.06.2019 NA NA 1.5 days AAI raised clarification to Egis
30.05.2019
Fire Fighting Pump
Ranjeet
specification change
39 Mechatronics Pvt
confirmation as a AAI issued letter to NCC, and
Ltd
substitute item further NCC to Re-submit the
NA 28.06.2019, 11:00hrs 14 days NA NA 3.07.2019 1.5 Days TDS- till date no TDS resubmit
by NCC-
delay by 41 days

clarification responded by AAI,


40 Pressure Switch Switzer / Danfoss First Submission 21.06.2019,11.30hrs 24.07.2019, 10:35hrs 27 days NA NA 26.07.2019 2 Days closed

First Submission 08.08.2019,11.50hrs 08.08.2019,16:19hrs 0.5 Days NA NA NA NA Egis raised clarification to NCCL

41 MS Pipe for Plumbing NCCL Egis raised clarification to


NCCL , Not Approved, Re-
20.08.2019 , submit, yet not re-submit by
1 day 09.08.2019,09.50hrs 19.08.2019,17:15hrs 5.5 Days NA 14.25 hrs NA 1 day
NCC ,AAI issued letter to NCCL
for re-submission

Egis raised clarification to NCCL,


42 SS Pipe for Plumbing NCCL First Submission 06.08.2019,17:15hrs 08.08.2019,16:05hrs 2 Days NA NA NA NA Delay 18 days

43 Wrapping Coating Tape IWL India Ltd second Submission 16.09.2019, 16: 30 Hrs Approved

GM Sprinkler-Pendent,
upright, side wall,
concealed,Rosette
Plate,Flexiable Tube/ Pipe,
HD, Newage,
44 Y-Type Strainer, Fire 20.09.2019,10:25 hrs Under review by Egis
Leader, Kirloskar
Hydrant & Sprinkler
Pump,Diesel engine fire
pump, Jockey Pump,
Water curtain pump

45
46
T3 Lucknow Airport Project
STATUS OF Shop Drawings AS ON DATE
1 2 3 4 5 6 7 8 9

Drawings submitted by M/s NCCL


S. Structure
NO. Name Title of Drawing Drawing Number EGIS RESPONSE Present Status
R0 R1 R2
LKO_WD_B_EL_0100_NCC_SD_2018 sheet 1
PTB Lighting Layout Basement Level
of 1 01.03.2019 26.03.2019 25.07.2019 17.08.2019 Approved with Comments
1
LKO_WD_B_EL_0100_NCC_SD_2018 sheet 1
PTB Lighting Layout Basement Level Zone-1 of 5 01.03.2019 26.03.2019 25.07.2019 17.08.2019 Approved with Comments
2
LKO_WD_B_EL_0100_NCC_SD_2018 sheet 2
PTB Lighting Layout Basement Level Zone-2 of 5 01.03.2019 26.03.2019 25.07.2019 17.08.2019 Approved with Comments
3
LKO_WD_B_EL_0100_NCC_SD_2018 sheet 3
PTB Lighting Layout Basement Level Zone-3
of 5 01.03.2019 26.03.2019 25.07.2019 17.08.2019 Approved with Comments
4
LKO_WD_B_EL_0100_NCC_SD_2018 sheet 4
PTB Lighting Layout Basement Level Zone-4 of 5 01.03.2019 26.03.2019 25.07.2019 17.08.2019 Approved with Comments
5
LKO_WD_B_EL_0100_NCC_SD_2018 sheet 5
PTB Lighting Layout Basement Level Zone-5 of 5 01.03.2019 08.03.2019 M/s NCCL to resubmit delay by - 171 days
6
LKO_WD_B_EL_0100_NCC_SD_ELEV_2018
PTB Elevation Layout Basement Level
sheet 1 of 1 01.03.2019 26.03.2019 30.04.2019 M/s NCCL to resubmit delay by - 118 days
7
LKO_WD_B_EL_0100_NCC_SD_SLD_2018
PTB Single line diagram Basement Level sheet 1 of 1 01.03.2019 26.03.2019 30.04.2019 M/s NCCL to resubmit delay by - 118 days
8
Drainage & sewarage system basement floor LKO_WD_B_PL_0100_NCC_SD_4003 sheet 1
PTB level of 1 01.03.2019 26.04.2019 30.05.2019 M/s NCCL to resubmit delay by - 115 days
9
Drainage & sewarage system basement floor LKO_WD_B_PL_0100_NCC_SD_4003 sheet 1
PTB
level Zone-1 of 5 01.03.2019 26.04.2019 30.05.2019 M/s NCCL to resubmit delay by - 115 days
10
Drainage & sewarage system basement floor LKO_WD_B_PL_0100_NCC_SD_4003 sheet 2
PTB level Zone-2 of 5 01.03.2019 26.04.2019 30.05.2019 M/s NCCL to resubmit delay by - 115 days
11
Drainage & sewarage system basement floor LKO_WD_B_PL_0100_NCC_SD_4003 sheet 3
PTB level Zone-3 of 5 01.03.2019 26.04.2019 30.05.2019 M/s NCCL to resubmit delay by - 115 days
12
Drainage & sewarage system basement floor LKO_WD_B_PL_0100_NCC_SD_4003 sheet 4
PTB
level Zone-4 of 5 01.03.2019 26.04.2019 30.05.2019 M/s NCCL to resubmit delay by - 115 days
13
Drainage & sewarage system basement floor LKO_WD_B_PL_0100_NCC_SD_4003 sheet 5
PTB
level Zone-5 of 5 01.03.2019 26.04.2019 30.05.2019 M/s NCCL to resubmit delay by - 115 days
14
Toilet detail sewagarge & water supply layout LKO_WD_B_PL_0100_NCC_SD_4003 sheet 1
PTB
basemnet level of 1 01.03.2019 26.04.2019 30.05.2019 M/s NCCL to resubmit delay by - 115 days
15
Service Lighting & Power layout service yard LKO_WD_B_IEL_0200_NCC_SD_2011 sheet 1
Yard basement of 2
26.03.2019 27.04.2019 28.06.2019 15.07.2019 M/s NCCL to resubmit delay by - 42 days
16
Service LKO_WD_B_IEL_0200_NCC_SD_2011 sheet 2
Yard
Elevation layout service yard basement
of 2 26.03.2019 27.04.2019 28.06.2019 15.07.2019 M/s NCCL to resubmit delay by - 42 days
17
Lighting Layout Basement Mezzanine Level LKO_WD_B_EL_0100_NCC_SD_2019 sheet 2
PTB
Zone-2 of 6 28.03.2019 08.04.2019 30.04.2019 M/s NCCL to resubmit delay by - 118 days
18
Power Layout Basement Mezzanine Level LKO_WD_B_EL_0100_NCC_SD_2026 sheet 2
PTB Zone-2 of 6 28.03.2019 08.04.2019 30.04.2019 M/s NCCL to resubmit delay by - 118 days
19
Elevation Layout Basement Mezzanine Level LKO_WD_B_EL_0100_NCC_SD_2019 sheet
PTB
Zone-2 2A of 6 28.03.2019 08.04.2019 30.04.2019 M/s NCCL to resubmit delay by - 118 days
20
Elevation Layout Basement Mezzanine Level LKO_WD_B_EL_0100_NCC_SD_2026 sheet
PTB Zone-2 2A of 6 28.03.2019 08.04.2019 30.04.2019 M/s NCCL to resubmit delay by - 118 days
21
Single line diagram Basement Mezzanine LKO_WD_B_EL_0100_NCC_SD_2019 sheet
PTB Level Zone-2 2B of 6 28.03.2019 08.04.2019 30.04.2019 M/s NCCL to resubmit delay by - 118 days
22
Single line diagram Basement Mezzanine LKO_WD_B_EL_0100_NCC_SD_2026 sheet
PTB
Level Zone-2 2B of 6 28.03.2019 08.04.2019 30.04.2019 M/s NCCL to resubmit delay by - 118 days
23
Lighting Layout Basement Mezzanine Level LKO_WD_B_EL_0100_NCC_SD_2019 sheet 3
PTB Zone-3 of 6 28.03.2019 22.04.2019 11.06.2019 M/s NCCL to resubmit delay by - 76 days
24
Lighting Layout Basement Mezzanine Level LKO_WD_B_EL_0100_NCC_SD_2026 sheet 3
PTB Zone-3 of 6 28.03.2019 22.04.2019 11.06.2019 M/s NCCL to resubmit delay by - 76 days
25
PTB Fire Alarm system layout basement level LKO_WD_B_FA_0100_DW_2053 sheet 1 of 1 28.03.2019 08.04.2019 M/s NCCL to resubmit delay by - 140 days
26
Fire Alarm system layout basement level
PTB Zone-2 LKO_WD_B_FA_0100_DW_2053 sheet 1 of 3 28.03.2019 08.04.2019 M/s NCCL to resubmit delay by - 140 days
27
Fire Alarm system layout basement level
PTB Zone-3 LKO_WD_B_FA_0100_DW_2053 sheet 2 of 3 28.03.2019 08.04.2019 M/s NCCL to resubmit delay by - 140 days
28
Fire Alarm system layout basement level
PTB
Zone-4
LKO_WD_B_FA_0100_DW_2053 sheet 3 of 3 28.03.2019 08.04.2019 M/s NCCL to resubmit delay by - 140 days
29
Fire Alarm system layout basement
PTB Mezzanine level LKO_WD_B_FA_0100_DW_2054 sheet 1 of 1 28.03.2019 08.04.2019 M/s NCCL to resubmit delay by - 140 days
30
Fire Alarm system layout basement
PTB Mezzanine level Zone- 1 LKO_WD_B_FA_0100_DW_2054 sheet 1 of 5 28.03.2019 08.04.2019 M/s NCCL to resubmit delay by - 140 days
31
Fire Alarm system layout basement
PTB
Mezzanine level Zone- 2
LKO_WD_B_FA_0100_DW_2054 sheet 2 of 5 28.03.2019 08.04.2019 M/s NCCL to resubmit delay by - 140 days
32
Fire Alarm system layout basement
PTB Mezzanine level Zone- 3 LKO_WD_B_FA_0100_DW_2054 sheet 3 of 5 28.03.2019 08.04.2019 M/s NCCL to resubmit delay by - 140 days
33
Fire Alarm system layout basement
PTB Mezzanine level Zone- 4 LKO_WD_B_FA_0100_DW_2054 sheet 4 of 5 28.03.2019 08.04.2019 M/s NCCL to resubmit delay by - 140 days
34
Fire Alarm system layout basement
PTB
Mezzanine level Zone- 5
LKO_WD_B_FA_0100_DW_2054 sheet 5 of 5 28.03.2019 08.04.2019 M/s NCCL to resubmit delay by - 140 days
35
PTB Fire Alarm system layout Arrival level LKO_WD_B_FA_0100_DW_2055 sheet 1 of 1 28.03.2019 08.04.2019 M/s NCCL to resubmit delay by - 140 days
36
PTB Fire Alarm system layout Arrival level Zone- 1 LKO_WD_B_FA_0100_DW_2055 sheet 1 of 5 28.03.2019 08.04.2019 M/s NCCL to resubmit delay by - 140 days
37
PTB Fire Alarm system layout Arrival level Zone- 2 LKO_WD_B_FA_0100_DW_2055 sheet 2 of 5 28.03.2019 08.04.2019 M/s NCCL to resubmit delay by - 140 days
38
PTB Fire Alarm system layout Arrival level Zone- 3 LKO_WD_B_FA_0100_DW_2055 sheet 3 of 5 28.03.2019 08.04.2019 M/s NCCL to resubmit delay by - 140 days
39
PTB Fire Alarm system layout Arrival level Zone- 4 LKO_WD_B_FA_0100_DW_2055 sheet 4 of 5 28.03.2019 08.04.2019 M/s NCCL to resubmit delay by - 140 days
40
PTB Fire Alarm system layout Arrival level Zone- 5 LKO_WD_B_FA_0100_DW_2055 sheet 5 of 5 28.03.2019 08.04.2019 M/s NCCL to resubmit delay by - 140 days
41
Fire Alarm system layout Departure level
PTB Zone- 1 LKO_WD_B_FA_0100_DW_2057 sheet 1 of 6 28.03.2019 10.04.2019 M/s NCCL to resubmit delay by - 138 days
42
Fire Alarm system layout Departure level
PTB Zone- 2 LKO_WD_B_FA_0100_DW_2057 sheet 2 of 6 28.03.2019 10.04.2019 M/s NCCL to resubmit delay by - 138 days
43
Fire Alarm system layout Departure level
PTB
Zone- 3
LKO_WD_B_FA_0100_DW_2057 sheet 3 of 6 28.03.2019 10.04.2019 M/s NCCL to resubmit delay by - 138 days
44
Fire Alarm system layout Departure level
PTB Zone- 4 LKO_WD_B_FA_0100_DW_2057 sheet 4 of 6 28.03.2019 10.04.2019 M/s NCCL to resubmit delay by - 138 days
45
Fire Alarm system layout Departure level
PTB Zone- 5 LKO_WD_B_FA_0100_DW_2057 sheet 5 of 6 28.03.2019 10.04.2019 M/s NCCL to resubmit delay by - 138 days
46
Fire Alarm system layout Departure level
PTB
Zone- 6
LKO_WD_B_FA_0100_DW_2057 sheet 6 of 6 28.03.2019 10.04.2019 M/s NCCL to resubmit delay by - 138 days
47
Lighting Layout Basement Mezzanine Level LKO_WD_B_EL_0100_NCC_SD_2019 sheet 1
PTB
Zone-1 of 6 08.04.2019 16.04.2019 M/s NCCL to resubmit delay by - 122 days
48
Power Layout Basement Mezzanine Level LKO_WD_B_EL_0100_NCC_SD_2026 sheet 1
PTB Zone-1 of 6 08.04.2019 16.04.2019 M/s NCCL to resubmit delay by - 122 days
49
Elevation Layout Basement Mezzanine Level LKO_WD_B_EL_0100_NCC_SD_2019 sheet
PTB
Zone-1 1A of 6 08.04.2019 29.04.2019 M/s NCCL to resubmit delay by - 118 days
50
Elevation Layout Basement Mezzanine Level LKO_WD_B_EL_0100_NCC_SD_2026 sheet
PTB
Zone-1 1A of 6 08.04.2019 29.04.2019 M/s NCCL to resubmit delay by - 118 days
51
PTB IT system layout drawing basement level LKO_WD_B_IT_0100_DW_B204 11.04.2019 19.04.2019 M/s NCCL to resubmit delay by - 129 days
52
IT system layout drawing basement level
PTB
Zone-2
LKO_WD_B_IT_0100_DW_B204 11.04.2019 19.04.2019 M/s NCCL to resubmit delay by - 129 days
53
IT system layout drawing basement level
PTB
Zone-3
LKO_WD_B_IT_0100_DW_B204 11.04.2019 19.04.2019 M/s NCCL to resubmit delay by - 129 days
54
IT system layout drawing basement level
PTB
Zone-4
LKO_WD_B_IT_0100_DW_B204 11.04.2019 19.04.2019 M/s NCCL to resubmit delay by - 129 days
55
IT system layout drawing basement
PTB
mezzanine level
LKO_WD_B_IT_0100_DW_B204 11.04.2019 19.04.2019 M/s NCCL to resubmit delay by - 129 days
56
IT system layout drawing basement
PTB
mezzanine level Zone-2
LKO_WD_B_IT_0100_DW_B204 11.04.2019 19.04.2019 M/s NCCL to resubmit delay by - 129 days
57
IT system layout drawing basement
PTB
mezzanine level Zone-3
LKO_WD_B_IT_0100_DW_B204 11.04.2019 19.04.2019 M/s NCCL to resubmit delay by - 129 days
58
PTB Airport system layout drawing basement level LKO_WD_B_IT_0100_DW_A205 11.04.2019 19.04.2019 M/s NCCL to resubmit delay by - 129 days
59
Airport system layout drawing basement
PTB
level Zone-1
LKO_WD_B_IT_0100_DW_A205 11.04.2019 19.04.2019 M/s NCCL to resubmit delay by - 129 days
60
Airport system layout drawing basement
PTB level Zone-2 LKO_WD_B_IT_0100_DW_A205 11.04.2019 19.04.2019 M/s NCCL to resubmit delay by - 129 days
61
Airport system layout drawing basement
PTB level Zone-3 LKO_WD_B_IT_0100_DW_A205 11.04.2019 19.04.2019 M/s NCCL to resubmit delay by - 129 days
62
Airport system layout drawing basement
PTB
level Zone-4
LKO_WD_B_IT_0100_DW_A205 11.04.2019 19.04.2019 M/s NCCL to resubmit delay by - 129 days
63
Airport system layout drawing basement
PTB Mezzanine level LKO_WD_B_IT_0100_DW_A204 11.04.2019 19.04.2019 M/s NCCL to resubmit delay by - 129 days
64
Airport system layout drawing basement
PTB Mezzanine level Zone-1 LKO_WD_B_IT_0100_DW_A204 11.04.2019 19.04.2019 M/s NCCL to resubmit delay by - 129 days
65
Airport system layout drawing basement
PTB
Mezzanine level Zone-2
LKO_WD_B_IT_0100_DW_A204 11.04.2019 19.04.2019 M/s NCCL to resubmit delay by - 129 days
66
Airport system layout drawing basement
PTB Mezzanine level Zone-3 LKO_WD_B_IT_0100_DW_A204 11.04.2019 19.04.2019 M/s NCCL to resubmit delay by - 129 days
67
Airport system layout drawing basement
PTB Mezzanine level Zone-4 LKO_WD_B_IT_0100_DW_A204 11.04.2019 19.04.2019 M/s NCCL to resubmit delay by - 129 days
68
Elevation layout basement mezzanine level LKO_WD_B_EL_0100_NCC_SD_2019 sheet
PTB
Zone-3 3A of 6 22.04.2019 11.06.2019 M/s NCCL to resubmit delay by - 76 days
69
Lighting layout basement mezzanine level LKO_WD_B_EL_0100_NCC_SD_2019 sheet 4
PTB Zone-4 of 6 22.04.2019 11.06.2019 M/s NCCL to resubmit delay by - 76 days
70
Elevation layout basement mezzanine level LKO_WD_B_EL_0100_NCC_SD_2019 sheet
PTB Zone-4 4A of 6 22.04.2019 11.06.2019 M/s NCCL to resubmit delay by - 76 days
71
Lighting layout basement mezzanine level LKO_WD_B_EL_0100_NCC_SD_2019 sheet 5
PTB
Zone-5 of 6 22.04.2019 11.06.2019 M/s NCCL to resubmit delay by - 76 days
72
Elevation layout basement mezzanine level LKO_WD_B_EL_0100_NCC_SD_2019 sheet
PTB Zone-5 5A of 6 22.04.2019 11.06.2019 M/s NCCL to resubmit delay by - 76 days
73
Lighting layout basement mezzanine level LKO_WD_B_EL_0100_NCC_SD_2019 sheet 6
PTB Zone-6 of 6 22.04.2019 11.06.2019 M/s NCCL to resubmit delay by - 76 days
74
Single line diagram basement mezzanine LKO_WD_B_IEL_0200_NCC_SD_2019 sheet
PTB
Level Zone-3,4,5 & 6 3B of 6 22.04.2019 11.06.2019 M/s NCCL to resubmit delay by - 76 days
75
Single line diagram basement mezzanine LKO_WD_B_IEL_0200_NCC_SD_2019 sheet
PTB Level Zone-3,4,5 & 6 3C of 6 22.04.2019 11.06.2019 M/s NCCL to resubmit delay by - 76 days
76
Elevation Layout basement mezzanine level LKO_WD_B_EL_0100_NCC_SD_2026 sheet
PTB
Zone-3 3A of 6 22.04.2019 11.06.2019 M/s NCCL to resubmit delay by - 76 days
77
Elevation Layout basement mezzanine level LKO_WD_B_EL_0100_NCC_SD_2026 sheet 4
PTB
Zone-4 of 6
22.04.2019 11.06.2019 M/s NCCL to resubmit delay by - 76 days
78
Elevation Layout basement mezzanine level LKO_WD_B_EL_0100_NCC_SD_2026 sheet
PTB
Zone-4 4A of 6 22.04.2019 11.06.2019 M/s NCCL to resubmit delay by - 76 days
79
Power Layout basement mezzanine level LKO_WD_B_EL_0100_NCC_SD_2026 sheet 5
PTB
Zone-5 of 6 22.04.2019 11.06.2019 M/s NCCL to resubmit delay by - 76 days
80
Elevation Layout basement mezzanine level LKO_WD_B_EL_0100_NCC_SD_2026 sheet
PTB Zone-5 5A of 6 22.04.2019 11.06.2019 M/s NCCL to resubmit delay by - 76 days
81
Power Layout basement mezzanine level LKO_WD_B_EL_0100_NCC_SD_2026 sheet 6
PTB
Zone-6 of 6 22.04.2019 11.06.2019 M/s NCCL to resubmit delay by - 76 days
82
LKO_WD_B_EL_0100_NCC_SD_2020 sheet 1
PTB Lighting Layout Arrival level Zone-1 of 6 09.05.2019 21.05.2019 M/s NCCL to resubmit delay by - 97 days
83
LKO_WD_B_EL_0100_NCC_SD_2020 sheet
PTB Elevation Layout Arrival level Zone-1 1A of 6 09.05.2019 05.06.2019 M/s NCCL to resubmit delay by - 82 days
84
LKO_WD_B_EL_0100_NCC_SD_2020 sheet
PTB Single line diagram Arrival Level Zone-1
1B of 6 09.05.2019 05.06.2019 M/s NCCL to resubmit delay by - 82 days
85
LKO_WD_B_EL_0100_NCC_SD_2027 sheet 1
PTB Power Layout Arrival level Zone-1 of 6 09.05.2019 21.05.2019 M/s NCCL to resubmit delay by - 97 days
86
LKO_WD_B_EL_0100_NCC_SD_2027 sheet
PTB Elevation Layout Arrival level Zone-1 1A of 6 09.05.2019 05.06.2019 M/s NCCL to resubmit delay by - 84 days
87
LKO_WD_B_EL_0100_NCC_SD_2027 sheet
PTB Single line diagram Arrival Level Zone-1
1B of 6 09.05.2019 05.06.2019 M/s NCCL to resubmit delay by - 84 days
88
89 DG GA Drawing of 2000KVA DG set SWPPL/NCC/AAI/IAL/001 02.05.2019 10.06.2019 M/s NCCL to resubmit delay by - 77 days
90 DG DG room Layout for 2000KVA DG set SWPPL/NCC/AAI/IAL/011 02.05.2019 10.06.2019 M/s NCCL to resubmit delay by - 77 days
91 DG Foundation drawing of 2000KVA GD set SWPPL/NCC/AAI/IAL/002 02.05.2019 10.06.2019 M/s NCCL to resubmit delay by - 77 days
92 DG GA Drawing of 990 Ltrs Day tank SWPPL/NCC/AAI/IAL/003 02.05.2019 10.06.2019 M/s NCCL to resubmit delay by - 77 days

DG GA drawing for 20KL U/G HSD storage tank SWPPL/NCC/AAI/IAL/004 02.05.2019 10.06.2019 M/s NCCL to resubmit delay by - 77 days
93
Layout Drawing for 2x20KL U/g HSD storage
DG tank SWPPL/NCC/AAI/IAL/005 02.05.2019 10.06.2019 M/s NCCL to resubmit delay by - 77 days
94
General arrangement drawing of Lift L-15,L-
Lift 16& L-17 L-M8815-17 sheet 1 of 6 to 6 of 6 02.05.2019 31.05.2019 M/s NCCL to resubmit delay by - 87 days
95
Lift General arrangement drawing of Lift L-07 L-M8833 sheet 1 of 4 to 4 of 4 02.05.2019 31.05.2019 M/s NCCL to resubmit delay by - 87 days
96
Lift General arrangement drawing of Lift L-08 L-M8835 sheet 1 of 4 to 4 of 4 02.05.2019 31.05.2019 M/s NCCL to resubmit delay by - 87 days
97
Lift General arrangement drawing of Lift L-09 L-M8836 sheet 1 of 4 to 4 of 4 02.05.2019 31.05.2019 M/s NCCL to resubmit delay by - 87 days
98
Lift General arrangement drawing of Lift L-29 L-M8837 sheet 1 of 4 to 4 of 4 02.05.2019 31.05.2019 M/s NCCL to resubmit delay by - 87 days
99
Lift General arrangement drawing of Lift L-30 L-M8838 sheet 1 of 4 to 4 of 4 02.05.2019 31.05.2019 M/s NCCL to resubmit delay by - 87 days
100
General arrangement of Escalators for ES-01
Escalator
& ES- 02
E-7263 & 64 20.05.2019 03.06.2019 M/s NCCL to resubmit delay by - 84 days
101
Driver LKO_WD_B_EL_0300_NCC_SD_LTG_2049
Canteen
Lighting Layout Drivers canteen Ground Floor
sheet 1 of 1 28.06.2019 15.07.2019 M/s NCCL to resubmit delay by - 42 days
102
Driver LKO_WD_B_EL_0300_NCC_SD_ELEV_2049
Canteen Lighting Layout Drivers canteen Ground Floor sheet 1A of 1 29.06.2019 15.07.2019 M/s NCCL to resubmit delay by - 42 days
103
Driver LKO_WD_B_EL_0300_NCC_SD_ELEV_2049
Canteen
Lighting Layout Drivers canteen Ground Floor
sheet 1B of 1 29.06.2019 15.07.2019 M/s NCCL to resubmit delay by - 42 days
104
Driver LKO_WD_B_EL_0300_NCC_SD_PWR_2049
Canteen
Power Layout Drivers canteen Ground Floor
sheet 1 of 1
29.06.2019 15.07.2019 M/s NCCL to resubmit delay by - 42 days
105
Driver Power elevation Layout Drivers canteen LKO_WD_B_EL_0300_NCC_SD_PWR_2049
Canteen Ground Floor sheet 1A of 1 29.06.2019 15.07.2019 M/s NCCL to resubmit delay by - 42 days
106
Driver Power single line diagram Drivers canteen LKO_WD_B_EL_0300_NCC_SD_PWR_2049
Canteen Ground Floor sheet 1B of 1
29.06.2019 15.07.2019 M/s NCCL to resubmit delay by - 42 days
107

NCC_FCL_CCSIA_LKO_C205 (1 of 1
PTB DAS System ,NCC_FCL_CCSIA_LKO_C205(1 of 6 to 6 of 6) 05.08.2019 Under Review with M/s Egis delay by 17 days
108

EDS_CCSIA_LKO_B05_204 (1 of 1
PTB DAS System
,EDS_CCSIA_LKO_B05_204 (1 of 6 to 6 of 6) 05.08.2019 Under Review with M/s Egis delay by 17 days
109

EDS_CCSIA_LKO_L20_C201 (1 of 1
PTB DAS System ,EDS_CCSIA_LKO_L20_C201 (1 of 6 to 6 of 6) 05.08.2019 Under Review with M/s Egis delay by 17 days
110

EDS_CCSIA_LKO_L20_C202(1 of 1
PTB DAS System
,EDS_CCSIA_LKO_L20_C202 (1 of 6 to 6 of 6) 05.08.2019 Under Review with M/s Egis delay by 17 days
111
EDS_CCSIA_LKO_L20_C203_00(1 of 1
PTB DAS System EDS_CCSIA_LKO_L20_C203_00 (1 of 6 to 6 of 05.08.2019 Under Review with M/s Egis delay by 17 days
112 6)
Lighting & Power layout basement level LKO_WD_B_EL_0100_NCC_SD_L&P_2018
PTB
Zone-1 sheet 1 of 5 01.03.2019 26.03.2019 25.07.2019 17.08.2019 Approved with comments
113
Lighting & Power layout basement level LKO_WD_B_EL_0100_NCC_SD_L&P_2018
PTB
Zone-2 sheet 2 of 5 01.03.2019 26.03.2019 25.07.2019 17.08.2019 Approved with comments
114
Lighting & Power layout basement level LKO_WD_B_EL_0100_NCC_SD_L&P_2018
PTB
Zone-3 sheet 3 of 5 01.03.2019 26.03.2019 25.07.2019 17.08.2019 Approved with comments
115
Lighting & Power layout basement level LKO_WD_B_EL_0100_NCC_SD_L&P_2018
PTB
Zone-4 sheet 4 of 5
01.03.2019 26.03.2019 25.07.2019 17.08.2019 Approved with comments
116
Lighting & Power Elevation layout basement LKO_WD_B_EL_0100_NCC_SD_L&P_2018
PTB
level Zone-1,2,3,4 sheet 1A of 5 01.03.2019 26.03.2019 25.07.2019 17.08.2019 Approved with comments
117
Lighting & Power single line diagram LKO_WD_B_EL_0100_NCC_SD_L&P_2018
PTB
basement level Zone-1,2,3,4 sheet 1B of 5 01.03.2019 26.03.2019 25.07.2019 17.08.2019 Approved with comments
118
Service Lighting & Power layout service yard, ground LKO_WD_I_EL_0200_NCC_SD_L&P 2012
Yard floor 19.08.2019 Under Review with M/s Egis
119
Service Lighting & Power elevation layout service
Yard yard , ground floor
LKO_WD_I_EL_0200_NCC_SD_ELEV_ 2012 19.08.2019 Under Review with M/s Egis
120
Service Lighting & Power single line diagram service
Yard yard, ground floor LKO_WD_I_EL_0200_NCC_SD_SLD_ 2012 19.08.2019 Under Review with M/s Egis
121
Service Lighting & Power layout service yard, terrace LKO_WD_I_EL_0200_NCC_SD_L&P_ 2012
Yard floor 19.08.2019 Under Review with M/s Egis
122
Lighting Layout Arrival level Zone-2 sheet 2 of Under Review with M/s Egis
123 PTB 6 LKO_WD_B_EL_0100_NCC_SD_LTG_ 2020 23.08.2019
Lighting Elevation Layout Arrival level Zone-2 Under Review with M/s Egis
124 PTB sheet 2A of 6 LKO_WD_B_EL_0100_NCC_SD_ELEV_ 2020 23.08.2019
Lighting Single Line diagram Arrival level Under Review with M/s Egis
125 PTB Zone-2 sheet 2B of 6 LKO_WD_B_EL_0100_NCC_SD_SLD_ 2020 23.08.2019
Power and raceway layout Arrival level Zone- Under Review with M/s Egis
126 PTB 2 sheet 2 of 6 LKO_WD_B_EL_0100_NCC_SD_PWR_ 2027 23.08.2019
Power Elevation layout Arrival level Zone-2 Under Review with M/s Egis
127 PTB sheet 2A of 6 LKO_WD_B_EL_0100_NCC_SD_ELEV_ 2027_A 23.08.2019

Power Single Line diagram Arrival level Zone- Under Review with M/s Egis
128 PTB 2 sheet 2B of 6 LKO_WD_B_EL_0100_NCC_SD_SLD_ 2027_A 23.08.2019
T3- PTB - LUCKNOW AIRPORT PROJECT

MINUTES OF MEETING
28th August 2019
CONSTRUCTION OF NEW INTEGRATED PASSANGER TERMINAL BUILDING AT CCS INTERNATIONAL AIRPORT, LUCKNOW
AGENDA POINTS- MEP
Sr.No
1 AS PER BASELINE SCHEDULE TILL DATE 20 ITEMS TDS (TECHNICAL DATA SHEET) SUBMISSION IS OVERDUE .

2 AS PER BASELINE SCHEDULE SHOP DRAWING SUBMISSION IS DELAYED AND RE-SUBMISSION OF SHOP DRAWINGS DELAYED ON AN AVERAGE OF 90 DAYS.

3 TMRS , HT/ LT PANEL, SOLAR VENDOR TECHNICAL PROPOSAL SUBMISSION IS PENDING.

4 METHOD STATEMENTs & ITPs ( INSPECTION TEST PLAN) SUBMISSION IS PENDING/ DELAYED.

5 STORAGE OF MATERIAL AT SITE IS NOT UP TO THE MARK

6 SAMPLE ROOM IS NOT YET READY AND ALSO NOT EASILY ACCESSIABLE.

7 DELAY IN PROCUREMENT OF MATERIAL WHICH APPROVAL HAS ALREADY BEEN PROVIDED .

8 EXTERNAL CABLE DIVERSION WORK TILL DATE NOT COMPLETED.

9 DG STACK HEIGHT CLEARANCE (NOC) IS PENDING.

10 MICRO SCHEDULE FOR MEP WORKS TO BE SUBMITTED.


11 REQUIREMENT OF TECHNICAL REPRESENTATIVE AS PER CLAUSE 36 OF CONTRACT AGGREMENT IS PENDING.
LIST OF SPECIALIZED AGENCIES
1 2 3 4

S.No. System Description Specialized Agency Remarks


1 Solar Panel Not yet Finalized
2 TMRS Not yet Finalized
3 HT/ LT Panels Not yet Finalized
4 CCTV- Video Surveillance system
5 FIDS- Flight Information Display System
6 ACS- Access control System
7 BMS- Building Management system
8 PAVA- Public Address Voice announcement
9 FAS- Fire Alarm System SIEMENS
10 MCS- Master Clock System
11 EPABX- Electronic Private Automatic Branch Exchange
12 Passive system- Structured cabling
13 Active System- Network Switches
14 Datacentre
15 DAS- Distributed Antenna System FROG CELLSAT
16 Electrical Works AKASH ELECTROTEK
17 DG sets STERLING AND WILSON
18 Lifts and Escalators JOHNSON LIFTS
19 Fire Fighting and Fire Pumps RANJEET MECHATRONICS
20 HVAC VOLTAS
21 STP and WTP PREMIERTECH BRISANZIA
22 Transformers (Oil and Dry) VOLTAMP
Service
S. No. RFI ID RFI No. Head Sub Head
Section

7 NCCL/AAI/RFI/MEP/007 MEP 7 MEP LIFT


11 NCCL/AAI/RFI/MEP/011 MEP 11 MEP HVAC
19 NCCL/AAI/RFI/MEP/019 MEP 19 MEP LIFT
21 NCCL/AAI/RFI/MEP/021 MEP 21 MEP PLB
26 NCCL/AAI/RFI/MEP/026 MEP 26 MEP SYD
30 NCCL/AAI/RFI/CIV/030 30 MEP TBG/SYD
31 NCCL/AAI/RFI/MEP/031 MEP 31 MEP TBG
35 NCCL/AAI/RFI/MEP/035 MEP 35 MEP TBG
36 NCCL/AAI/RFI/MEP/036 MEP 36 MEP TBG
50 NCCL/AAI/RFI/MEP/050 MEP 50 MEP SYD
57 NCCL/AAI/RFI/MEP/057 MEP 57 Electrical TBG
60 NCCL/AAI/RFI/MEP/060 MEP 60 Electrical TBG
68 NCCL/AAI/RFI/MEP/068 MEP 68 Electrical TBG
81 NCCL/AAI/RFI/MEP/081 MEP 81 Electrical Road
98 NCCL/AAI/RFI/MEP/098 MEP 98 Electrical TBG
103 NCCL/AAI/RFI/MEP/103 MEP 103 ELECTRICAL Elevated Road

114 NCCL/AAI/RFI/MEP/114 MEP 114 ELECTRICAL TBG

119 NCCL/AAI/RFI/MEP/119 MEP 119 MEP TBG

129 NCCL/AAI/RFI/MEP/129 MEP 129 Electrical External location

130A NCCL/AAI/RFI/MEP/130 MEP 130 MEP Electrical

136 NCCL/AAI/RFI/FNS/136 136 Electrical TBG

143 NCCL/AAI/RFI/MEP/143 MEP 143 MEP Electrical

144 NCCL/AAI/RFI/MEP/144 MEP 144 MEP Electrical

153 NCCL/AAI/RFI/MEP/153 MEP 153 Electrical T3 Basement

Service Yard & T-3


154 NCCL/AAI/RFI/MEP/154 MEP 154 Electrical
Basement

155 NCCL/AAI/RFI/PAVA/155 155 Electrical T-3 Basement

156 NCCL/AAI/RFI/PAVA/156 156 Electrical T-3 Basement

157 NCCL/AAI/RFI/MEP/157 MEP 157 Electrical Service Yard & T-3


Basement
Service Yard & T-3
159 NCCL/AAI/RFI/MEP/159 MEP 159 Electrical
Basement
160 NCCL/AAI/RFI/MEP/160 MEP 160 Electrical Service Yard

161 NCCL/AAI/RFI/MEP/161 MEP 161 Electrical Service Yard

Service Yard & T-3


163 NCCL/AAI/RFI/MEP/163 MEP 163 Electrical
Basement
Driver Canteen &
164 NCCL/AAI/RFI/MEP/164 MEP 164 Electrical
Existing Bldg.
165 NCCL/AAI/RFI/MEP/165 MEP 165 Electrical TBG

170 NCCL/AAI/RFI/MEP/170 MEP 170 Electrical Service Yard

T3 Basement &
171 NCCL/AAI/RFI/MEP/171 MEP 171 Electrical Basement
Mezzanine

174 NCCL/AAI/RFI/MEP/174 MEP 174 Electrical Metering Room

176 NCCL/AAI/RFI/MEP/176 MEP 176 Electrical TBG/SYD

SYD, BMS, Pri. &


182 NCCL/AAI/RFI/MEP/182 MEP 182 Electrical
Secd. Data Center

183 NCCL/AAI/RFI/MEP/183 MEP 183 Electrical SYD

186 NCCL/AAI/RFI/MEP/186 MEP 186 Electrical SYD

187 NCCL/AAI/RFI/MEP/187 MEP 187 Electrical SYD

188 NCCL/AAI/RFI/MEP/188 MEP 188 Electrical SYD

Basement M. &
189 NCCL/AAI/RFI/MEP/189 MEP 189 Electrical T3 Bldg

199 NCCL/AAI/RFI/MEP/199 MEP 199 Electrical Meetering Room

200 NCCL/AAI/RFI/MEP/200 MEP 200 Electrical Service Yard

201 NCCL/AAI/RFI/MEP/201 MEP 201 Electrical T3 Bldg


Short description

L-07, L-28, L-29, L-30


RFI for AHU & Chiller
Lift shaft details
Puddle flange details
UG Tank puddle flange clarification
Point Wiring
Cralification for follow up of Lift Schedule
Terminal Building Cout out location
Terminal Building- GI conduit
HT Panels Service yard
T-3 Terminal Building
T-3 Terminal Building
T-3 Terminal Building
External Street Lighting - Layout Site Plan
External Street Lighting - Layout Site Plan
External Street Lighting - Layout Site Plan

Zone-2 & 3 (Arrival Level)

Fire Fighting System

Astronomical timer

External Development

Type of pipe for cable laying in road crossing

External Development

External Development

BOQ Item No. 870, 872, 873 & 876

BOQ Item No. 817, 882, 883, 884, 885, 880 & 893

BOQ Item No. 828, 861, 862, 907, 908, 911, 912 & 914

BOQ Item No. 842, 850, 859, 905 & 906

SOQ Item No. 719, 729, 730, 733 & 1131


Cable Schedule No. EIAIIUP001-AAI-LKO-001 dated.
01.07.2019

BOQ 805.06 & 804.05

Staircase

BOQ 914, 835, 912 & 911

Pump Panel - BOQ item not there (Sump Pump)

Metering Room - Lighting, Earthing, Trench Layout &


230V Power Circuit

Earthing - BOQ Items 775, 776, 777, 780.02, 780.03

BOQ items 930.02, 931

BOQ items 702 & 706

BOQ items 702 & 709

BOQ items 702 & 710

BOQ items 702 & 711

BOQ items 735

Earthing, Panel, UPS,

Transformer

Transformer, LT & HT Panel, Solar Output


RFI
Drgs. / Doc Reference No. RFI Date Resolved
Date

SOQ 1176.08, 1176.11, 1176.13 24 Sep 18 09 Oct 18


- 05 Oct 18 16 Oct 18
LKO_WD_B_ARC_0100_DW_0407_01, 0412_01 27 Oct 18 21 Nov 18
LKO_WD_I_PL_0200_DW_4020 16 Nov 18 28 Nov 18
LKO_WD_I_PL_0200_DW_4020 SHEET 2 OF 2 21 Nov 18 13 Dec 18
LKO_WD_L_EL_0000_DW_2002 R0 17 Dec 18 28 Dec 18
LKO_WD_B_LE_001 24 Dec 18 26 Dec 18
LKO_WD_B_HVA_0100_DW_3011, 3007, 3016 05 Jan 19 10 Jan 19
LKO_WD_B_HVA_0100_DW_3011, 3007, 3016 05 Jan 19 17 Jan 19
TD_L_EL_0000_DW_2004 Sheet 1 to 7 (Tender drawing) 30 Jan 19 15 Feb 19
LKO_WD_B_EL_0100_DW_2018/2027/2028 20 Feb 19 27 Feb 19
HM000945-20LHM-AAI 20 Feb 19 20 Feb 19
LKO_WD_I_EL_0000_DW_2004_1 1-Mar-19 12-Mar-19
LKO_WD_I_EL_0300_DW_2001 28-Mar-19 29-Mar-19
LKO_WD_I_EL_0300_DW_2001 24-Apr-19 29-Apr-19
LKO_WD_I_0300_DW_2001 29-Apr-19 1-Jul-19
LKO_WD_B_EL_0100_DW_2027 (R0) Sheet 2 of 6, Zone-2,
24-May-19 6-Jun-19
LKO_WD_B_EL_0100_DW_2027 (R0) Sheet 3 of 6, Zone-3
LKO_WD_B_FF_0100_DW_5003, LKO_WD_B_FF_0100_DW_5004 27-May-19 7-Jun-19

LKO_WD_L_EL_0000_DW_2004_5 15-Jun-19 17-Jun-19

28-Jun-19
LKO_WD_L_EL_0000_DW_2004_5 15-Jun-19
01-Jul-19
LKO_WD_I_EL_0300_DW_2001 20-Jun-19 2-Jul-19
LKO_WD_L_EL_0000_DW_2004_1
28-Jun-19 3-Jul-19
LKO_WD_L_EL_0000_DW_2011
LKO_WD_L_EL_0000_DW_2004_2
28-Jun-19 3-Jul-19
LKO_WD_L_EL_0000_DW_2010
LKO_WD_L_EL_0000_DW_2004_8 8-Jul-19 12-Jul-19
LKO_WD_L_EL_0000_DW_2004_2
LKO_WD_L_EL_0000_DW_2004_4 8-Jul-19 25-Jul-19
LKO_WD_L_EL_0000_DW_2004_6
LKO_WD_L_EL_0000_DW_2004_12
8-Jul-19 15-Jul-19
LKO_WD_L_EL_0000_DW_2004_13
LKO_WD_L_EL_0000_DW_2004_9
LKO_WD_L_EL_0000_DW_2004_10 9-Jul-19 12-Jul-19
LKO_WD_L_EL_0000_DW_2004_11

LKO_WD_L_EL_0000_DW_2004_1 10-Jul-19 16-Jul-19

LKO_WD_L_EL_0000_DW_2004_2 10-Jul-19 15-Jul-19


LKO_WD_L_EL_0200_DW_2017 (Earthing Layout - Service Yard)
17-Jul-19 26-Aug-19
LKO_WD_L_EL_0000_DW_2000_1
LKO_WD_B_EL_0100_DW_2026
22-Jul-19 26-Jul-19
LKO_WD_L_EL_0000_DW_2002

LKO_WD_B_EL_0100_DW_2026 22-Jul-19 3-Aug-19

LKO_WD_B_EL_0300_DW_2049
22-Jul-19 26-Jul-19
LKO_WD_L_EL_0300_DW_2001
LKO_WD_B_STR_0200_DW_700(1 of 2 & 2 of 2) 22-Jul-19 26-Jul-19
LKO_WD_I_EL_0200_DW_2014
25-Jul-19 30-Jul-19
LKO_WD_I_EL_0200_DW_2015

LKO_WD_B_EL_0100_DW_2030 26-Jul-19 14-Aug-19

LKO_WD_I_RL_0300_DW_2001 29-Jul-19 23-Aug-19

LKO_WD_I_EL_0200_DW_2017
LKO_WD_I_EL_0000_DW_2005 (1 of 2)
30-Jul-19 22-Aug-19
LKO_WD_I_EL_0000_DW_2005 (1 of 2)
LKO_WD_B_EL_0100_DW_2026

LKO_WD_I_EL_0200_DW_2015
7-Aug-19 23-Aug-19
LKO_WD_I_EL_0200_DW_2012

LKO_WD_I_EL_0300_DW_2001
LKO_WD_I_EL_0200_DW_2017 7-Aug-19 22-Aug-19
LKO_WD_I_EL_0200_DW_2040

LKO_WD_I_EL_0300_DW_2001
LKO_WD_I_EL_0200_DW_2017 7-Aug-19 22-Aug-19
LKO_WD_I_EL_0200_DW_2043

LKO_WD_I_EL_0300_DW_2001
LKO_WD_I_EL_0200_DW_2017 7-Aug-19 14-Aug-19
LKO_WD_I_EL_0200_DW_2044

LKO_WD_I_EL_0300_DW_2001
LKO_WD_I_EL_0200_DW_2017 7-Aug-19 10-Aug-19
LKO_WD_I_EL_0200_DW_2045

- 8-Aug-19

BOQ Item - 651, 718 & 991.01


LKO_WD_B_EL_0300_DW_2050 21-Aug-19 26-Aug-19
LKO_WD_B_HVA_0300_DW_3051-R1
BOQ Item - 734, 736
LKO_WD_I_EL_0200_DW_2015 21-Aug-19

BOQ Item - 728


Doc Ref No.
21-Aug-19
LKO_WD_B_EL_0100_DW_2031-R1
LKO_WD_L_EL_0000_DW_2004_2
LKO_WD_I_EL_0200_DW_2010
Time taken
Status Remarks
for Reply

15 Closed
11 Closed
25 Closed
12 Closed
22 Closed
11 Closed
2 Closed
5 Closed
12 Closed
16 Closed
7 Closed
0 Closed
11 Closed
1 Closed
5 Closed
63 Closed

13 Closed

11 Closed

2 Closed

13 Closed

12 Closed

5 Closed

5 Closed

4 Closed

17 Closed

7 Closed

3 Closed

6 Closed

5 Closed
40 Closed

4 Closed

12 Closed

4 Closed

4 Closed

5 Closed

19 Closed

25 Closed

23 Closed

16 Closed

15 Closed

15 Closed

7 Closed

3 Closed

-43685 Closed

5 Closed

-43698 Open

-43698 Open
Total in Numbers Closed/FinalizedTil
S. No. Item Description Pending Status Remarks
submitted as on Date l Date

208 194 MEP/IT- 05 Nos. Under Review


1 RFI's (Request for Information) Civil- 09 Nos.
M/S NCCL to submit documents for
22 19 3 scrutiny for pending Vendors
2 Specialized Vendors
Approved with comments-
60 Nos.
Shop Drawings 128 113 Not Approved- 53 Nos. Under review- 15 Nos.
3
a) Approved -19 Nos.
b)Approved with M/S NCCL to submit documents for
4 TDS (Technical Datasheet) 68 21 comments- 2 Nos. resubmission/not approved items.
c) Not Approved- 35 Nos. Also TDS for 58 items not yet
d) submitted.
Under review- 12 Nos.
STATUS OF TDS AS ON DATE
CONSTRUCTION OF NEW INTEGRATED PASSANGER TERMINAL BUILDING AT CCS INTERNATIONAL AIRPORT, LUCKNOW
E& M TECHNICAL DATA SHEET APPROVAL STATUS
1 2 3 4 5 6 7 8 9 10 11 12

AAI -Clarification / Approval


NCC Egis-India
Name of No of days taken
specialised by NCC for TDS No of EGIS NCC
No of
Sr. Vendor/ agency/ submission or Re- working
Item Description Working Present Status
No sub-contractor/ Submission -after Days by AAI ISSUED TO TDS
AAI NEEDS Days by AAI
AAI/Egis TDS Submission Date and Response/ Comments Egis-India NCC For RE-
manufacturer Comments Time issued Date, time
CLARIFICATION SUBMISSION of Approved
FROM EGIS TDS Date By AAI

approval for MS Conduit and


First Submission 14.01.2019,18:00 hrs 18.01.2019, 12:35 hrs 3.5 Days NA 24.01.2019 24.01.2019 4 Days Re-Submission for MS
MS Conduit and accessories
1 Accessories AKG

42 Days delay 07.03.2019, 17:00 hrs 08.03.2019, 13:00 hrs 0.5 days NA NA 12.03.2019 2.5 Days APPROVED, closed

First Submission 08.05.2019, 17:56 hrs 11.05.2019, 12:00 hrs 2.5 days NA 17.05.2019 NA 5 days Not Approved, Re-submit

2 MS Conduit and BEC


Accessories
13 Days delay 01.06.2019,17:00hrs 04.06.2019,11:59 hrs 1.5days NA NA 07.06.2019 3 days APPROVED, closed

66 Days Delay 22.07.2019, 11:15 hrs 24.07.2019, 13:00 hrs 1.5 days NA 26.07.2019 1.5 days APPROVED, closed
NA

Legrand First Submission 27.05.2019, 17:00 hrs 29.05.2019,15:24 hrs 1.5 days NA NA NA NA NCC not responded on Email

NCC responded the comments


33 Days Delay 03.07.2019, 15:55 hrs 04.07.2019, 15:10 hrs 1 Day NA NA NA NA
on email dated 11th July 2019

GI Modular Box,Flush Type NCC responded and given the


3 Switch socket,fan 7 days Delay 11.07.2019,18:48 hrs 12.07.2019, 12:14 hrs 1 Day NA NA NA NA reference of MOM held on 12th
regulator,bell push July 2019
MK (Honeywell)
Partially approved response
1 day Delay 13.07.2019,11:05hrs 23.07.2019,12:10 hrs 7.5 days NA 25.07.2019 NA 5.5 days send by AAI on dated
25.07.2019, NCC to re-submit

Approved with Comments,


12 Days Delay 06.08.2019, 12:00hrs 07.08.2019, 15:40 hrs 0.5 days NA NA 08.08.2019 1 Day
Closed

First Submission 21.05.2019, 16:00hrs 08.06.2019,16:55 hrs 16 days 14.06.2019 08.06.2019 NA 1 day NCC to Re-Submit, Not
Approved

Distribution
NCC responded on 26th July
2019, Sample Submission
43 days Delay 22.07.2019, 11:25hrs 23.07.2019,18:45 hrs 1 day NA NA NA NA delayed by NCCL- Delay by 15
Days, further it is under review
By Egis.

Not Comply, NCC to re-submit


Distribution in accordance with Comments
4 C&S NA NA 03.08.2019, 12:05 hrs 10days NA NA NA NA
Board,MCB,RCCB send by Email- NCCL TILL DATE
NO RESPONSE

No response from NCC


regarding the comments raised
on mail. After that final
NA NA 06.08.2019 1.5 DAYS NA NA 08.08.2019 1.5 Days observation and comments
submit to AAI for further
action, Approved with
comments.

MEM First Submission 07.05.2019, 17:56 hrs 09.05.2019,11:00 hrs 1.5 days NA 07.06.2019 NA 24 days NCC to Re-Submit,Not
Approved, Yet Not Submit.
5 GI Cable Tray
Venus 63 Days Delay 19.08.2019, 16: 50hrs 09.09.2019, 12:00 hrs 15 days NA NA 12.09.2019 1 day Approved with comments .

Sample Visual Checking delayed


by NCCL , due to non availibility
First Submission 05.07.2019,12:00 hr 29.07.2019,18:10 hrs 20 days NA 02.08.2019 NA 3 Days of Measuring Instrument - NCC
delay by 15 days and NCC to
Re-Submit for further approval
6 PVC Insulated Cu. Wire Rallison

14 DAYS DELAY 21.08.2019,14:25 hrs 11.09.2019, 11.00 hrs 16 days NA NA 12.09.2019 1 day Approved with comments.

Re-submissiom of
Compliance report 15.11.2019, 17:50 hrs 18.11.2019, 17:00 hrs 1.5 days NA NA Approved with comments
( Delay by -60 days)

First Submission 22.07.2019,11:15 hrs 09.09.2019, 11.00hrs 36 days NA 12.09.2019 3 days Approved with Comments
NA
First Submission 22.07.2019, 11:15hrs 09.09.2019,11.00hrs 36 days NA 12.09.2019 3 days Approved with Comments
NA
10M High GRP Light Pole &
7 Crompton Re-submission as per
Light Fixtures Re-Submission of
perviously submitted
Compliance ( Delay 06.11.2019, 17:30 hrs 13.11.2019, 14:30 hrs 5 days NA NA 13.11.2019 1 days
By-7 days) comments ( email sent to M/s.
NCCL for compliance )

Re-submit by NCCL 18.12.2019 Re-submission , M/s. NCCL to


07.01.2020 13 days NA 09.01.2019 NA 1 day
delay by 25 days re-submit
AAI raised clarification / query
to Egis letter - AAI/LKO/Engg-
First Submission 23.04.2019,14.30hrs 23.05.2019, 12:00 hrs 25 days 29.05.2019 NA NA 6 Days
Project/PMC/2019-20/288-291
dated 29.05.2019

TDS -Escalators- AAI raised clarification / query


27.05.2019, 17:20 hrs 12.06.2019,16:20hrs 13 days 18.06.2018 NA NA 5 days
First Submission to Egis-dated 18.06.2018

AAI raised clarification/ query


NA NA 14.06.2019,14:50 hrs 12 days 19.06.2019 NA NA 3 days
to Egis dated 19.06.2019

NA NA 24.07.2019, 11:00 hrs 29 days NA NA NA 4 days Response awaited from AAI

After joint meeting with ED


North , Egis H.O Team, AAI LKO
Team ( final details preapared
and submit to AAI for further
02.08.2019 necessary action. Not
NA NA 01.08.2019 1 day NA NA 1 day
Lifts & Escalators Technical Johnson Lifts Pvt approved, Re-submit by NCC-
1 Data Sheet Escalator system ( AAI/LKO/T-
Ltd
3/ESCALATOR/ENGG(E )/ 2019-
20/532-534- NCC
to delay by 20 days

After joint meeting with ED


North , Egis H.O Team, AAI LKO
Team ( final details preapared
NA NA 05.08.2019 1 day NA 05.08.2019 NA 1 day and submit to AAI for further
necessary action. Not
approved, Re-submit by NCC-
Escalator system ( AAI/LKO/T-
3/Elevators /Engg (E )/ 2019-
20/548-550 dated 05.2019

17.09.2019 (Escalator) / Approved with Comments,


35 days delay 17.09.2019. 17:10 hrs 15 days NA NA 18.09.2019 / 1 day /
07.10.2019, 11.00hrs (Lift) Closed.

First Submission- NCC to Re-Submit, Not


02.05.2019,17:54hrs 31.05.2019, 12:00hrs 25 days NA NA NA NA Approved, NCC Delay by 35
Lift
days

Ecsalators 20.05.2019, 18:05 hrs 03.06.2019,11:00 hrs 11 days NA NA NA NA NCC to Re-Submit, Not
10 Approved, NCC Delay by 35
days
Lift GA Drawing/ Shop Johnson Lifts Pvt Ecsalators- Re-
Drawing Ltd submission of G.A
2.11.2019 08.11.2019 4 days NA NA NA NA Approved with comments
Drawing- delay by
40 days
Lift GA Drawing/ Shop Johnson Lifts Pvt
Drawing Ltd

Lift GA Drawings re-


submit by

AAI raised clarification / query


First Submission 02.05.2019, 17:32hrs 05.06.2019, 14:40 hrs 28 days 17.06.2019 NA NA 9 days
to Egis
DG Sets TDS and 20 KL
11
HSD-TDS
NCC to Re-Submit, Not
NA NA 27.06.2019, 10:45 hrs 8 days NA 28.06.2019 NA 1 day Approved- Not Yet Submit -
delay by 46 days

Sterling & Wilson NCC to re-Submit , Not


20 KL HSD Tank GA
12 Powergen Pvt Ltd First Submission 02.05.2019,17:32 hrs 10.06.2019, 11.00hrs 32 days NA 10.06.2019 NA NA Approved , not yet submit-
Drawing delay by 46 days

NCC to re-Submit , Not


13 DG Set Cooling Tower First Submission 02.05.2019, 17:32hrs 05.06.2019, 14:40 hrs 28 days NA 10.06.2019 NA NA Approved , not yet submit- NCC
delay by 46 days

Layout , GA, Foundation NCC to re-Submit , Not


14 First Submission 02.05.2019,17:32 hrs 10.06.2019, 11.00hrs 34 days NA 10.06.2019 NA NA Approved , not yet submit- NCC
Drawing of DG Set
delay by 46 days

second Submission-
Comments Given by Mail, Re-
70 days delay by 25.09.2019, 12:20 hrs 27.09.2019, 12:45 hrs 2 days NA NA NA NA
Submission taken 5 days
NCC
15

Re-submission by M/s.NCCL ,
NCC- Re-submit 03.10.2019, 16:15 hrs 01.11.2019, 24 days NA 04.11.2019 NA 1 day
delay by 22 days

NCC Re-submit- Approved with comments ,


26.11.2019, 15:37hrs 07.12.2019 9 DAYS NA 19.12.2019 NA
delay by 22 days compliance to re-submit

DG Sets TDS and 20 KL Meeting point mail to NCCL on


HSD-TDS / fuel pipe layout, Re-submit by NCCL 30.12.2019 ( NCCl responed on
26.12.2019
GA & fabrication drawing Jakson Ltd ( 6 days ) mail 09.01.2020) under review
for 30 Meter exhaust by egis
( total 13 items) etc

First Submission
( Shop
drawing+HSD+Cooli 02.11.2019 30.11.2019 25 days NA NA Re-submission to NCCL
ng tower ) method
ststement

DG Cooling Tower 26.11.2019 17.12.2019 17 days NA 21.12.2019 NA 3 days Re-submission to NCCL

First Submission
(Boq item 742 to Under review by Egis to be
20.12.2019
756, 758 to 774 )- submit to AAI by 14.01.2020
valves etc
Not Approved , Resubmission,
First Submission 19.08.2019, 16:40hrs 27.09.2019, 17:50 hrs 35 days NA 03.10.2019 NA 5 days
NCC delay by 40 days

Re-submission with full


22.11.2019 ( 2MVA and complete compliance by
NCC - Re-submit 05.12.2019 ( 2.5MVA) 10 days 5.11.2019 05.12.2019 NA
2.5MVA ), 9:45 hrs M/s.NCCL for 2 & 2.5 MVA ( as
Transformer - 6 Oil Type + per ED 02.12.2019 meeting)
16 Voltamp
3 Dry Type
NCC Re-submit-
Under review by Egis to be
delay by 25 days 03.01.2020,13:29 hrs
submit to AAI by 14.01.2020
( 2.5 MVA )

Re-Submit under review by Egis to Be


( 2MVA ) 09.01.2020, 10:36 hrs submit to AAI with in 7 days

Not aprroved Re-submit,


MK (Honeywell) First Submission 20.08.2019, 16:42 hrs 13.09.2019, 15:00 hrs 18 days NA 17.09.2019 NA 3 days
closed

Clarification send to M/s. NCCL,


OBO- 10 days
second Submission 26.09.2019, 26.09.2019, 14:21Hrs 0.5 days NA NA NA NA awaited for Re-submission, NCC
delay delay by 50 Days
GI Raceway & Junction
17 Boxes

Email sent to NCC As decided in MOM


Re-submission Not responded 23.12.2019 NA NA NA 24.12.2019
for clarification ( 18.12.2019 ) accordingly given
comments to NCC - approved
with comments, Closed
18 GI Earthing Strip MEM First Submission 09.09.2019, 15:05 hrs 11.09.2019, 12:00 hrs 2 days NA NA 12.09.2019 1 days approved with comments

Approved with Comments,


closed for VTPN DB and TPN DB
First Submission 14.09.2019,13:20 hrs 20.09.2019, 18:00 hrs 5 days NA 24.09.2019 24.09.2019 3 days
-TDS Re-submission, NCC Delay
19 Flame Retardent VTPN & Hensel by 24 Days
TPN-DB

Re-submission 18.10.2019 22.10.2019 2 days NA NA 31.10.2019 4 days Approved with comments

Approved with comments,


20 DWC HPDE Pipe Astral First Submission 09.09.2019, 12:00 hrs 14.09.2019 4 days NA NA 17.09.2019 3 days
closed

Not Approved, Re-submission.


First Submissiom 13.09.2019, 17:00 Hrs 15.10.2019, 15:00 hrs 25 days NA 23.10.2019 NA 6 days
Delay by M/s. NCCL- 26 days

Re-Submission for
21 LT Panel- 121 Nos. ABB 11 Panels( delay by 29.11.2019 24.12.2019 24 days 26.12.2019 27.12.2019 NA 2 days re-submission not approved
30 days )

Re-Submit 109
panels ( delay by 55 24.12.2019 04.01.2020 7 days NA 04.01.2020 NA .5 days Re-Submission not approved
days )
Approved with Comment,
22 HT cable End Termination 3M First Submission 20.09.2019, 10:20 hrs 23.09.2019, 15:10 hrs 3 days NA NA 25.09.2019 2 days
Closed

Not Approved, Re-submission.


First Submission 24.09.2019, 11:37 hrs 23.10.2019, 12:00 hrs 25 days NA 30.10.2019 NA
Delay by M/s. NCCL- 65 days
23 HT Panel Siemens

Re-Submit

Approved with comments,


24 DB-Isolator-MCB/MCCB ABB First Submission 02.11.2019 18.11.2019 12 days NA NA
Closed

FRP Cable tray Indiana First Submission 24.12.2019 06.01.2020 8 days NA NA With AAI

Approved with Comments,


HT & LT Cables Gloster First Submission 02.12.2019 02.01.2020 25 days NA NA 04.01.2020 NA
Closed

25 HVAC
Rollastar / Approved with Comments,
First Submission 27.08.2019, 16:42 hrs 09.09.19, 12:20 hrs 9 days NA NA 11.09.2019 1 day
Ductofab Closed
Factory Fabricated G.I
26 Ducting
Ductofab Compliance 22.10.2019, 15:30 hrs 04.11.2019 9 days NA NA 07.11.2019 2 days Approved

Site Fabricated G.I Ducting Jindal First Submission 04.12.2019 13.12.2019 7 days NA NA 13.12.2019 0.5 days Approved with comments

MS & GI Pipe, Balancing Jindal & Sail,


27 Valve, Duct & Room Advnce & Castle, First Submission 09.09.2019, 14: 45 hrs 20.09.2019, 15:30 hrs 10 days NA NA 23.09.2019 2 days Approved with Comments,
Closed
Acoustic Lining Twiga

Re-submission of Butterfly
valve ( NCC delay by 30 days )
Advance & Castle First Submission 28.08.2019, 14:00 hrs 16.09.2019, 14:00 hrs 15 days NA NA 17.09.2019 1 day
and approved with comments
28 for Check Valve
Butterfly Valve & Check
Valve(NRV), Balancing Castle- Re-submit-Delay by 01.11.2019
15.11.2019 11 days NA NA 18.11.2019 1 day Approved with comment
Valve 40 days

Butterfly Valve, Balancing


Castle Compliance 11.12.2019 26.12.2019 13 Days NA NA 26.12.2019 0.5 Days Valve (Approved with
comment), NRV (Approved)

Not Approved, Re-Submission,


First Submission 18.09.2019, 14:20 hrs 01.10.2019, 12:00 hrs 11 days NA 03.10.2019 NA 2 days
NCC delay by 15 Days

Re-submission - Jointly M/s. NCCL and Egis


soft copy on finialize the basement heat
29 07.11.2019 and 7.11.2019 19.11.2019 9 days 19.11.2019 load on 21.11.2019 and further
hard copy on M/s. NCCL to Submit hard copy
Heat Load Calculation - 20.11.2019 and soft copy
Voltas
Arrival & Mezzanine Level
29

Heat Load Calculation -


Voltas
Arrival & Mezzanine Level
Re-Submission of
Basement and
25.11.2019 28.11.2019 3 days NA 02.12.2019 4 days Approved, Close
Basement
Mezzanine

Arrival, Mezzanine,
Departure, Service 02.01.2020 09.01.2020 5 Days Pending at AAI
Yard

30 First Submission 27.09.2019,16:25 hrs 25.10.2019 25 days NA 25.10.2019 NA 0.5 days Re-submission by M/s. NCCL
Mechanical Ventilation
ACHP Calculations-
Voltas
Basement & Basement
Mezzanine AAI raised clarification on
Re-submission after 5 days/ 6
06.11.2019 13.11.2019 / 21.11.2019 15.11.2019 NA 15.11.2019 to Egis, Approved
10 days days
with comments

Re-submission by Egis and


31 Pharphur First Submission 07.10.2019, 15:42 hrs 31.10.2019 19 days NA NA 06.11.2019 4 days Approved with comments by
Cooling Tower AAI
Pharphur Re submission 13.12.2019 26.12.2019 11 days NA NA 27.12.2019 1 days Approved with comments

HVAC-BTU,Y-Strainer, Pot Omicron ,


32 Strainer, Auto Air Vents, Emerald, Anergy, First Submission 07.10.2019, 15:42 hrs 5.11.2019 22 days NA 8.11.2019 NA 2 days Not approved, Re-Submission
Thermal Insulation Aeroflex

33 Resistoflex First Submission 21.10.2019, 15:11 hrs 15.11.2019 20 days NA 18.11.2019 NA 2 days Not approved , Re-submission
Flexiable connection for
Pipe
Resistoflex Re-submission 16.12.2019 23.12.2019 6 Days NA NA 26.12.2019 2 days Approved with comments

34 KEPL First Submission 21.10.2019, 15:11 hrs 18.11.2019 25 days NA 20.11.2019 NA 2 days Not approved, re-submission
Hot Water Generator
KEPL Resubmission 16.12.2019 27.12.2019 9 days NA 02.01.2020 NA 5 days Not approved, re-submission

35 Twin pump pressurization Anergy First Submission 01.11.2019, 14.30 hrs 26.11.2019 22 days NA 28.11.2019 NA 2 days Not Approved, Re-submit
unit

36 Motorized Butterfly valave Castle First Submission 01.11.2019, 14.30 hrs 27.11.2019 22 days NA 28.11.2019 NA 1 day Not approved, Re-submission

37 STP & WTP


wilo , Beta,
Kirloskar, Rehau, First Submission
38 18.09.2019, 18:00hrs 16.11.2019 50 days NA 18.11.2019 NA 1 day Not Approved , Resubmission
roto, Aastha,
sukrut, MM Aqua
STP- 27 item ( raw sewage
pump, air blowers, sludge
pump, sluice valve etc)
STP- 27 item ( raw sewage
pump, air blowers, sludge
pump, sluice valve etc)

Premier Tech Pending at AAI


Re-submission 06.12.2019 13.01.2020 27 Days NA NA
Brisanzia Ltd. head

WTP & RO System- Raw


water pump, Activated
Carbon Filter, Antiscalant
dosing system, micron Wilo, Stalite, Asia
cartridge filter,High LMI, Sintex,
39 First Submission 25.09.2019, 12:00 hrs 21.11.2019 50 days NA 22.11.2019 NA Not approved, Re-submission
pressure feed pump, ROM, Wastech, Danfoss,
CIP Pump, Wellmate3
Hydropneumatic pump,
Softner feed pump,
Tubewell Submersible
pump, Pressure sand filter,
chlorination

Premier Tech AAI will review and forward to


Re-submission 06.12.2019 09.01.2020 27 Days NA NA
Brisanzia Ltd. M/s NCCL

Fire Fighting and Plumbing


3 item approved (Firemen axe,
flow switch, vibration
First Submission 03.04.2019, 17:45 hrs 10.04.2019, 11:00 hrs 5.5 days NA 16.04.2019 16.04.2019 4.5 days
eliminators) , 33 items not
approved, NCC to resubmit

4 items Approved (landing


valve (external
+internal ),pressure gauge,
26.5 days delay 17.05.2019, 12:43 hrs 23.05.2019, 12:00 hrs 4.5 days NA 29.05.2019 29.05.2019 4.5 days Rosette plate )and 1 item not
approved, NCC to resubmit ( Till
date balance items not Re-
submit by NCC- 73 days delay

Fire Fighting System Ranjeet 8 item approved (MS Pipe,


1 Technical Data Sheet of 36 Mechatronics Pvt Corrosion Protection Tape,
Nos Boq Item Ltd Primer paint , MS fittings, pipe
supports, strcuture support,
30 days delay 21.05.2019, 12:00hr 04.06.2019, 10:45 hrs 11 days NA 29.06.2019 29.06.2019 21 days B/F Valve, Sluice Valve, NRV )
and 8 not approved , ( till date
no re-submission by
NCC- delay by 55
Days)
Re-Submission by NCCL
( NRV,Ball Valve, Pressure
Switch, air vessel, Deluge Valve,
55 Days Delay 27.08.2019, 13:00 hrs 12.09.2019, 17:50 hrs 14 days NA NA 17.09.2019 4 days Fire Extenguishers -4.5kg,
22.5kg,6 kg,50L (foam ),
approved with comments ,
closed

28.05.2019, recevied on
11.06.2019,12:00 hrs 8.5 days 13.06.2019 NA NA 1.5 days AAI raised clarification to Egis
30.05.2019
Fire Fighting Pump
Ranjeet
specification change AAI issued letter to NCC, and
2 Mechatronics Pvt
confirmation as a further NCC to Re-submit the
Ltd
substitute item NA 28.06.2019, 11:00hrs 14 days NA NA 3.07.2019 1.5 Days TDS- till date no TDS resubmit
by NCC-
delay by 41 days

clarification responded by AAI,


3 Pressure Switch Switzer / Danfoss First Submission 21.06.2019,11.30hrs 24.07.2019, 10:35hrs 27 days NA NA 26.07.2019 2 Days
closed

First Submission 08.08.2019,11.50hrs 08.08.2019,16:19hrs 0.5 Days NA NA NA NA Egis raised clarification to NCCL

4 MS Pipe for Plumbing NCCL Egis raised clarification to


NCCL , Not Approved, Re-
20.08.2019 ,
1 day 09.08.2019,09.50hrs 19.08.2019,17:15hrs 5.5 Days NA NA 1 day submit, yet not re-submit by
14.25 hrs
NCC ,AAI issued letter to NCCL
for re-submission

42 SS Pipe for Plumbing NCCL First Submission 06.08.2019,17:15hrs 08.08.2019,16:05hrs 2 Days NA NA NA NA Egis raised clarification to NCCL,
Delay 18 days

43 Wrapping Coating Tape IWL India Ltd second Submission 09.09.2019, 12:00 hrs 16.09.2019, 16: 30 Hrs 6 days NA NA 17.09.2019 1 day Approved

GM Sprinkler-Pendent,
upright, side wall,
concealed,Rosette Approved with comments. Re-
Plate,Flexiable Tube/ Pipe, NCC Delay by 41 submission of Y-strainer. Main
HD, Newage,
44 Y-Type Strainer, Fire days for re- 20.09.2019,10:25 hrs 25.10.2019 24 days 01.11.2019 NA 4.11.2019 2 days Pump driver , jockey driver,
Leader, Kirloskar
Hydrant & Sprinkler submission water curtain driver by M/s.
Pump,Diesel engine fire NCCL
pump, Jockey Pump,
Water curtain pump

45 Y-strainer, 4 Way FBI , Fire Leader, Newage Re-submission 13.11.2019 06.12.2019 23 Days NA NA 11.12.2019 5 Days Approved with comments
Shaft door

SS 304 Branch Pipe Newage First Submission 30.12.2019 07.01.2020 5 Days NA NA 08.01.2020 1 day Approved with comments

Hydraulic Calculation for


First Submission 26.11.2019 03.01.2020 30 Days NA NA 06.01.2020 2 Days Approved
External Hydrant system
One Way draw out
Ranjeet
connection, Single float air
Mechatronics Pvt First Submission 27.11.2019 17.12.2019 17 days NA NA 19.12.2019 2 Days Approved with comments
release valve, Test cum
Ltd
drain assembly
STATUS OF TDS AS
CONSTRUCTION OF NEW INTEGRATED PASSANGER TERMINAL BUILDING AT CCS INTERNATIONAL AIRPORT, LUCKNOW
E& M TECHNICAL DATA SHEET APPROVAL STATUS
1 2 3 4 5

NCC
Name of No of days taken
specialised by NCC for TDS
Sr. Vendor/ agency/ submission or Re-
Item Description
No sub-contractor/ Submission -after
AAI/Egis TDS Submission Date and
manufacturer Comments Time

First Submission 14.01.2019,18:00 hrs


MS Conduit and
1 AKG
Accessories

42 Days delay 07.03.2019, 17:00 hrs

First Submission 08.05.2019, 17:56 hrs


2 MS Conduit and BEC
Accessories
13 Days delay 01.06.2019,17:00hrs
66 Days Delay 22.07.2019, 11:15 hrs

Legrand First Submission 27.05.2019, 17:00 hrs

33 Days Delay 03.07.2019, 15:55 hrs

GI Modular Box,Flush Type


3 Switch socket,fan 7 days Delay 11.07.2019,18:48 hrs
regulator,bell push
MK (Honeywell)

1 day Delay 13.07.2019,11:05hrs

12 Days Delay 06.08.2019, 12:00hrs

First Submission 21.05.2019, 16:00hrs


43 days Delay 22.07.2019, 11:25hrs

NA NA
4 Distribution C&S
Board,MCB,RCCB

NA NA

MEM First Submission 07.05.2019, 17:56 hrs


5 GI Cable Tray
Venus 63 Days Delay 19.08.2019, 16: 50hrs

First Submission 05.07.2019,12:00 hr


6 PVC Insulated Cu. Wire Rallison

14 DAYS DELAY 21.08.2019,14:25 hrs

7 10M High GRP Light Pole Crompton First Submission 22.07.2019,11:15 hrs

8 135W LED Street Light Crompton First Submission 22.07.2019, 11:15hrs

First Submission 23.04.2019,14.30hrs

TDS -Escalators-
27.05.2019, 17:20 hrs
First Submission
NA NA

NA NA

Lifts & Escalators Technical Johnson Lifts Pvt


9 NA NA
Data Sheet Ltd

NA NA

35 days delay 17.09.2019. 17:10 hrs


First Submission-
02.05.2019,17:54hrs
Lift GA Drawing/ Shop Johnson Lifts Pvt Lift
10 Drawing
Ltd
Ecsalators 20.05.2019, 18:05 hrs

First Submission 02.05.2019, 17:32hrs


DG Sets TDS and 20 KL
11
HSD-TDS
NA NA

20 KL HSD Tank GA
12 Sterling & Wilson First Submission 02.05.2019,17:32 hrs
Drawing
Powergen Pvt Ltd

13 DG Set Cooling Tower First Submission 02.05.2019, 17:32hrs

Layout , GA, Foundation


14 First Submission 02.05.2019,17:32 hrs
Drawing of DG Set
DG Sets TDS and 20 KL
15 Jakson Ltd second Submission
HSD-TDS
16 Transformer Voltamp First Submission 19.08.2019, 16:40hrs

17 GI Raceway & Junction MK (Honeywell) First Submission 20.08.2019, 16:42 hrs


Boxes

18 ELV Wires Rallison & Bonton First Submission 23.07.2019, 15:20 hrs

19 GI Earthing Strip MEM First Submission 09.09.2019, 15:05 hrs

20 Flame Retardent DB Hensel First Submission 14.09.2019,13:20 hrs

21 DWC HPDE Pipe Astral First Submission 09.09.2019, 12:00 hrs

22 LT Panel ABB First Submissiom 13.09.2019, 17:00 Hrs


23 HT End Termination 3M First Submission 20.09.2019, 10:20 hrs
24 HVAC
25 G.I Ducting Rollastar / First Submission 27.08.2019, 16:42 hrs
Ductofab
MS & GI Pipe, Balancing Jindal & Sail,
26 Valve, Duct & Room Advnce & Castle, First Submission 09.09.2019, 14: 45 hrs
Acoustic Lining Twiga
Butterfly Valve & Check
27 Valve(NRV) Advance & Castle First Submission 28.08.2019, 14:00 hrs

Heat Load Calculation -


28 Voltas First Submission 18.09.2019, 14:20 hrs
Arrival & Mezzanine Level

29 STP
wilo , Beta,
STP- 27 item ( raw sewage
Kirloskar, Rehau,
30 pump, air blowers, sludge roto, Aastha, First Submission 18.09.2019, 18:00hrs
pump, sluice valve etc)
sukrut, MM Aqua

31 Airport IT syste

26.06.2019 ( submit on
First Submission
27.06.2019, 12.40hrs)
Honeywell/
32 CCTV- TDS
Siemens

20 days delay 23.08.2019, 18:17 hrs

First Submission 15.03.2019, 13:00 hrs

ACS System Technical


33 Datasheet of 10 BOQ Item Solus
ACS System Technical
33 Solus
Datasheet of 10 BOQ Item
50 Days delay 20.06.2019,14:45hrs

7 Days delay 05.08.2019, 12: 00 hrs

First Submission 18.06.2019, 14:35hrs

29 DAS-TDS Frogcellsat
NA NA

Passive Network- SCS


30 System-TDS Belden First Submission 06.06.2019, 17:45hrs

First Submission 15.03.19,12:00hrs

31 FDS -TDS Siemens


27.5 Days Delay 31.05.2019, 14:00Hrs

32 Active Network-TDS HP First Submission 10.04.2019, 18:10 hrs

First Submission 27.03.2019,14:45hrs

NA NA

33 EPABX-IP PBX- TDS Unify / Siemens 1 days delay 22.06.2019

NA NA

23 days delay 26.08.2019

First Submission 27.03.2019,14:45hrs

34 Data Centre- TDS Vertiv


NA NA
34 Data Centre- TDS Vertiv

NA NA

35 days delay 08.08.2019

35 DC- IT Hardware ( Servers HP First Submission 26.08.2019. 13:25


and Thin Client)

36 FIDS-TDS DELL First Submission 26.08.2019, 13:25


37 PAVA system-TDS BOSCH First Submission 27.08.2019, 16:55
Fire Fighting and Plumbing

First Submission 03.04.2019, 17:45 hrs

26.5 days delay 17.05.2019, 12:43 hrs

Fire Fighting System Ranjeet


38 Technical Data Sheet of 36 Mechatronics Pvt
Nos Boq Item Ltd

30 days delay 21.05.2019, 12:00hr

55 Days Delay 27.08.2019, 13:00 hrs

28.05.2019, recevied on
30.05.2019
Fire Fighting Pump
Ranjeet
specification change
39 Mechatronics Pvt
confirmation as a Ltd
substitute item
Fire Fighting Pump
Ranjeet
specification change
39 Mechatronics Pvt
confirmation as a Ltd
substitute item NA

40 Pressure Switch Switzer / Danfoss First Submission 21.06.2019,11.30hrs

First Submission 08.08.2019,11.50hrs

41 MS Pipe for Plumbing NCCL


1 day 09.08.2019,09.50hrs

42 SS Pipe for Plumbing NCCL First Submission 06.08.2019,17:15hrs

43 Wrapping Coating Tape IWL India Ltd second Submission

GM Sprinkler-Pendent,
upright, side wall,
concealed,Rosette
Plate,Flexiable Tube/ Pipe,
HD, Newage,
44 Y-Type Strainer, Fire 20.09.2019,10:25 hrs
Leader, Kirloskar
Hydrant & Sprinkler
Pump,Diesel engine fire
pump, Jockey Pump,
Water curtain pump

45
46
TATUS OF TDS AS ON DATE
ATIONAL AIRPORT, LUCKNOW

6 7 8 9 10 11

AAI -Clarification / Approval


Egis-India
No of EGIS NCC
working No of
Working
Days by AAI ISSUED TO TDS
Egis-India AAI NEEDS Days by AAI
Response/ Comments NCC For RE-
issued Date, time
CLARIFICATION SUBMISSION of Approved
FROM EGIS TDS Date By AAI

18.01.2019, 12:35 hrs 3.5 Days NA 24.01.2019 24.01.2019 4 Days

08.03.2019, 13:00 hrs 0.5 days NA NA 12.03.2019 2.5 Days

11.05.2019, 12:00 hrs 2.5 days NA 17.05.2019 NA 5 days

04.06.2019,11:59 hrs 1.5days NA NA 07.06.2019 3 days


24.07.2019, 13:00 hrs 1.5 days NA NA 26.07.2019 1.5 days

29.05.2019,15:24 hrs 1.5 days NA NA NA NA

04.07.2019, 15:10 hrs 1 Day NA NA NA NA

12.07.2019, 12:14 hrs 1 Day NA NA NA NA

23.07.2019,12:10 hrs 7.5 days NA 25.07.2019 NA 5.5 days

07.08.2019, 15:40 hrs 0.5 days NA NA 08.08.2019 1 Day

08.06.2019,16:55 hrs 16 days 14.06.2019 08.06.2019 NA 1 day


23.07.2019,18:45 hrs 1 day NA NA NA NA

03.08.2019, 12:05 hrs 10days NA NA NA NA

06.08.2019 1.5 DAYS NA NA 08.08.2019 1.5 Days

09.05.2019,11:00 hrs 1.5 days NA 07.06.2019 NA 24 days

09.09.2019, 12:00 hrs 15 days NA 10.09.2019 1 day

29.07.2019,18:10 hrs 20 days NA 02.08.2019 NA 3 Days

11.09.2019, 11.00 hrs 16 days 12.09.2019 1 day

09.09.2019, 11.00hrs 36 days NA

09.09.2019,11.00hrs 36 days NA

23.05.2019, 12:00 hrs 25 days 29.05.2019 NA NA 6 Days

12.06.2019,16:20hrs 13 days 18.06.2018 NA NA 5 days


14.06.2019,14:50 hrs 12 days 19.06.2019 NA NA 3 days

24.07.2019, 11:00 hrs 29 days NA NA NA 4 days

02.08.2019
01.08.2019 1 day NA NA 1 day

05.08.2019 1 day NA 05.08.2019 NA 1 day

31.05.2019, 12:00hrs 25 days NA NA NA NA

03.06.2019,11:00 hrs 11 days NA NA NA NA

05.06.2019, 14:40 hrs 28 days 17.06.2019 NA NA 9 days

27.06.2019, 10:45 hrs 8 days NA 28.06.2019 NA 1 day

10.06.2019, 11.00hrs 32 days NA 10.06.2019 NA NA

05.06.2019, 14:40 hrs 28 days NA 10.06.2020 NA NA

10.06.2019, 11.00hrs 34 days NA 10.06.2021 NA NA


13.09.2019, 15:00 hrs

12.09.2019, 13.00 hrs 35 days

11.09.2019, 12:00 hrs 2 days 12.09.2019 1 days

20.09.2019, 18:00 hrs

14.09.2019

HVAC
09.09.19, 12:20 hrs 9 days

20.09.2019, 15:30 hrs

16.09.2019, 14:00 hrs 15 days

STP

Airport IT system

30.07.2019, 11:15hrs 28 days NA NA NA NA

20-04.2019, 11:00 hrs 30 days NA NA 29.04.2019 6 Days


26.07.2019, 18:49 hrs 30 Days NA NA NA NA

13.08.2019, 14:50 hrs 5 days NA NA 13.08.2019 0.5 days

27.06.2019, 12:40hrs 8.5 days 01.07.2019 NA NA 2 days

26.07.2019, 16:15hrs 21 days NA NA 30.07.2019 3 days

20.06.2019, 14:30hrs 11.5 days NA NA NA 55 days

20.04.2019, 13.00hrs 29 days NA 29.04.2019 NA 6 days

11.07.2019, 16:04 hrs 37.5 days NA 23.07.2019 NA 9 days

20.06.2019, 14:30 hrs 58 days NA NA NA 55 days

08.06.2019,17:50hrs 60 days 18.06.2019 NA NA 07 days

21.06.2019, 09:32 hrs 3 days NA NA NA NA

25.06.2019,09.32hrs NA NA NA NA NA

26.07.2019, 16:15 hrs 25 days NA 30.07.2019 NA 2.5 days

15.06.2019, 14:55hrs 65 days NA NA NA 4 days


26.06.2019,18:36 3.5 days NA NA NA NA

27.07.2019, 17:00 NA NA NA NA NA

10.04.2019, 11:00 hrs 5.5 days NA 16.04.2019 16.04.2019 4.5 days

23.05.2019, 12:00 hrs 4.5 days NA 29.05.2019 29.05.2019 4.5 days

04.06.2019, 10:45 hrs 11 days NA 29.06.2019 29.06.2019 21 days

12.09.2019, 17:50 hrs 14 days

11.06.2019,12:00 hrs 8.5 days 13.06.2019 NA NA 1.5 days


28.06.2019, 11:00hrs 14 days NA NA 3.07.2019 1.5 Days

24.07.2019, 10:35hrs 27 days NA NA 26.07.2019 2 Days

08.08.2019,16:19hrs 0.5 Days NA NA NA NA

20.08.2019 ,
19.08.2019,17:15hrs 5.5 Days NA NA 1 day
14.25 hrs

08.08.2019,16:05hrs 2 Days NA NA NA NA

16.09.2019, 16: 30 Hrs


12

Present Status

approval for MS Conduit and


Re-Submission for MS
accessories

APPROVED, closed

Not Approved, Re-submit

APPROVED, closed
APPROVED, closed

NCC not responded on Email

NCC responded the comments


on email dated 11th July 2019

NCC responded and given the


reference of MOM held on 12th
July 2019

Partially approved response


send by AAI on dated
25.07.2019, NCC to re-submit

Approved with Comments,


Closed
NCC to Re-Submit, Not
Approved
NCC responded on 26th July
2019, Sample Submission
delayed by NCCL- Delay by 15
Days, further it is under review
By Egis.

Not Comply, NCC to re-submit


in accordance with Comments
send by Email- NCCL TILL DATE
NO RESPONSE

No response from NCC


regarding the comments raised
on mail. After that final
observation and comments
submit to AAI for further
action, Approved with
comments, closed

NCC to Re-Submit,Not
Approved, Yet Not Submit.
Approved with comments
closed

Sample Visual Checking delayed


by NCCL , due to non availibility
of Measuring Instrument - NCC
delay by 15 days and NCC to
Re-Submit for further approval

Approved with comments,


closed
Approved with Comments,
Closed
Approved with Comments,
Closed

AAI raised clarification / query


to Egis letter - AAI/LKO/Engg-
Project/PMC/2019-20/288-291
dated 29.05.2019

AAI raised clarification / query


to Egis-dated 18.06.2018
AAI raised clarification/ query
to Egis dated 19.06.2019

Response awaited from AAI

After joint meeting with ED


North , Egis H.O Team, AAI LKO
Team ( final details preapared
and submit to AAI for further
necessary action. Not
approved, Re-submit by NCC-
Escalator system ( AAI/LKO/T-
3/ESCALATOR/ENGG(E )/ 2019-
20/532-534- NCC
to delay by 20 days

After joint meeting with ED


North , Egis H.O Team, AAI LKO
Team ( final details preapared
and submit to AAI for further
necessary action. Not
approved, Re-submit by NCC-
Escalator system ( AAI/LKO/T-
3/Elevators /Engg (E )/ 2019-
20/548-550 dated 05.2019
NCC
to delay by 15 days
Under Review by Egis
NCC to Re-Submit, Not
Approved, Delay by 25 days
NCC to Re-Submit, Not
Approved, Delay by 25 days
AAI raised clarification / query
to Egis

NCC to Re-Submit, Not


Approved- Not Yet Submit -
delay by 46 days
NCC to re-Submit , Not
Approved , not yet submit-
delay by 46 days

NCC to re-Submit , Not


Approved , not yet submit- NCC
delay by 46 days

NCC to re-Submit , Not


Approved , not yet submit- NCC
delay by 46 days
Not Yet submitted delay by 65
days delay
Under review by Egis
Not aprroved Re-submit,
closed
aprroved with comments,
closed
approved with comments,
closed
Approved with Comments,
closed
Approved with comments,
closed
Under Review by Egis
under review by egis

Approved with Comments,


Closed

Approved with Comments,


Closed

Re-submission and approved


with comments

Design Parameters - under


review by Egis

under review by Egis

NCC to clarify and provide the


supporting documents - as per
comments given in Email by
Egis

soft copy received , hard copy


with stamp awaited from NCCL

Approved and for balance Extra


Item Re-submission of TDS
(RFID encoders etc)
NCC to clarify and provide the
supporting documents - as per
comments given in Email by
Egis
letter issued to NCC, Closed
AAI raised Clarification from
Egis

Partially Approved, Response


awaited from NCC for BOQ
item number 1241- NCC delay
by 22 days

Response awaited from AAI


(File Process to CHQ for Extra
Item In-Principle Approval ),Egis
response approved with
comments.

Not Approved, Re-submit

Not Approved, Re-submit, yet


not re-submit by
NCC -24 days delay
Response awaited from AAI
(File Process to CHQ for Extra
Item In-Principle Approval ),Egis
response approved with
comments.

AAI raised clarification from


Egis and Egis further required
clarification from NCCL

clarification required from


NCC ,

Partially response received


from NCC and further no
response received from NCC.

Not Approved , NCC to Re-


submit ( AAI/LKO/T-
3/EPABX/ENGG ( E)/2019-
20/S13-S15) -
NCC delay by 25 days

AAI raised clarification/ query


to Egis dated 21.06.2019
email send to NCC - Response is
still awaited from NCC- 28 days
delay
letter issued to NCC - response
awaited
under review by Egis- delay by
13 days

New submission by NCC for Boq


Item 1305 to 1313 and 1323
to1331 ( Under review by Egis )

under review by Egis.


under review by Egis.

3 item approved (Firemen axe,


flow switch, vibration
eliminators) , 33 items not
approved, NCC to resubmit

4 items Approved (landing


valve (external
+internal ),pressure gauge,
Rosette plate )and 1 item not
approved, NCC to resubmit ( Till
date balance items not Re-
submit by NCC- 73
days delay

8 item approved (MS Pipe,


Corrosion Protection Tape,
Primer paint , MS fittings, pipe
supports, strcuture support,
B/F Valve, Sluice Valve, NRV )
and 8 not approved , ( till date
no re-submission by
NCC- delay by 55
Days)

Re-Submission by NCCL
( NRV,Ball Valve, Pressure
Switch, air vessel, Deluge Valve,
Fire Extenguishers -4.5kg,
22.5kg,6 kg,50L (foam ),
approved with comments ,
closed

AAI raised clarification to Egis


AAI issued letter to NCC, and
further NCC to Re-submit the
TDS- till date no TDS resubmit
by NCC-
delay by 41 days

clarification responded by AAI,


closed

Egis raised clarification to NCCL

Egis raised clarification to


NCCL , Not Approved, Re-
submit, yet not re-submit by
NCC ,AAI issued letter to NCCL
for re-submission

Egis raised clarification to NCCL,


Delay 18 days

Approved

Under review by Egis


STATUS OF TDS AS ON DATE
CONSTRUCTION OF NEW INTEGRATED PASSANGER TERMINAL BUILDING AT CCS INTERNATIONAL AIRPORT, LUCKNOW
E& M TECHNICAL DATA SHEET APPROVAL STATUS
1 2 3 4 5 6 7 8 9 10 11 12

AAI -Clarification / Approval


NCC Egis-India
Name of No of days taken
specialised by NCC for TDS No of EGIS NCC
No of
Sr. Vendor/ agency/ submission or Re- working
Item Description Working Present Status
No sub-contractor/ Submission -after Days by AAI ISSUED TO TDS
AAI/Egis Egis-India AAI NEEDS Days by AAI
TDS Submission Date and Response/ Comments NCC For RE-
manufacturer Comments Time issued Date, time
CLARIFICATION SUBMISSION of Approved
FROM EGIS
TDS Date By AAI

HVAC
Rollastar / Approved with Comments,
Ductofab First Submission 27.08.2019, 16:42 hrs 09.09.19, 12:20 hrs 9 days NA NA 11.09.2019 1 day Closed
1 G.I Ducting
under review by Egis to be
Ductofab Compliance 22.10.2019, 15:30 hrs
submit by 02.11.2019
MS & GI Pipe, Balancing Jindal & Sail,
Approved with Comments,
2 Valve, Duct & Room Advnce & Castle, First Submission 09.09.2019, 14: 45 hrs 20.09.2019, 15:30 hrs 10 days NA NA 23.09.2019 2 days Closed
Acoustic Lining Twiga

Re-submission of Butterfly
Butterfly Valve & Check valve ( NCC delay by 30 days )
3 Advance & Castle First Submission 28.08.2019, 14:00 hrs 16.09.2019, 14:00 hrs 15 days NA NA 17.09.2019 1 day
Valve(NRV) and approved with comments
for Check Valve

Heat Load Calculation - Not Approved, Re-Submission,


4 Arrival & Mezzanine Level Voltas First Submission 18.09.2019, 14:20 hrs 01.10.2019, 12:00 hrs 11 days NA 03.10.2019 NA 2 days NCC delay by 15 Days

Mechanical Ventilation
ACHP Calculations-
5 Voltas First Submission 27.09.2019,16:25 hrs 25.10.2019 25 days
Basement & Basement
Mezzanine
6 Cooling Tower Pharphur First Submission 07.10.2019, 15:42 hrs 31.10.2019 19 days

HVAC-BTU,Y-Strainer, Pot Omicron ,


under review by Egis to be
7 Strainer, Auto Air Vents, Emerald, Anergy, First Submission 07.10.2019, 15:42 hrs
Thermal Insulation Aeroflex submit by 01.11.2019

Hot Water Generator &


8 Flexiable connection for KEPL & Resistoflex First Submission 21.10.2019, 15:11 hrs under review by Egis
Pipe
9