You are on page 1of 2

CONSTRUCTION OF NEW INTEGRATED PASSENGER TERMINAL AT

C.C.S. AIRPORT, LUCKNOW, INDIA

DOCUMENT REVIEW SHEET

Construction of New Integrated Passenger Contractor NCC Ltd. Date Received 21 Nov 2019
Contract Terminal at C.C.S. Airport, Lucknow, India NCCL/AAI-LKO/735/19-20
Ref. No. Response by 11 Dec 2019

Egis- India/AAI- Resubmission No Yes


Dts No. Shop Drawing As Built OTHER
LKO/SD/DRS/____

Doc No./ Drawing List Title Date Revision


NCCL/AAI-LKO/735/2019-20 Method Statement for RCC Hume Pipe Laying for Electrical Services 11 Dec 2019 0

Discipline Comments Comments


Ref. No. incorporated by
Contractor

Discipline (EL - Electrical) Yes/No

Review Status:
Code A Approved no Comments1
Code B Approved with Comments2
Code C Not Approved3
Code D Not considered, Re-submit
Code E Review and/or Approval not Required

EL 01 Objective: Please add: ………..as per BOQ & TS of CA, CPWD & relevant IS standard.
02 Scope: Add: Excavation, Laying, Jointing & refilling as per BOQ & TS of CA.
EL 03 References: 1. Add relevant dwg. no i.e. GFC and Shop dwg, etc., BOQ item no. and clause no. of TS of CA.
EL Equipment: 1. Add night related equipment’s as time slot is from 8 am to 8 pm.
04
2. Include safety equipment and tools.

1
2

Discipline Comments Comments


Ref. No. incorporated by
Contractor
3. Add ladder as depth is more than one meter.
EL 05 Safety precautions: Add barricading related point.
EL 06 Work procedure: Add safety point in procedure.

Note-
 Incorporate all the comments and resubmit shop drawings for further approval and records.
 A1 size 3 coloured sets of shop drawings shall be submitted as per the contract and TS.
 Provide a copy of commented drawings- 2 sets (1 for Egis and 1 for AAI records).

Reviewed by Discipline Lead Amit Kr. Mishra Amit Saini Date- 19/08/2019
Name /Signature / Date

1
Work may proceed
2
Work may proceed provided comments raised by the Consulting Engineer are incorporated into the document. Contractor is required to resubmit the document for record purposes.
3
Submittal is not in compliance with the Contract. Do not proceed with the work covered by the submittal. Prepare a new submittal in compliance with the Contract.

You might also like