PROJECT NAME Indore Metro Rail Project PROJECT NO/CONTRACT ID.: BI 01/04 Indore
DISCIPLINE: STR DOCUMENT TYPE: Document Review Sheet (DRS ) Issue Comment Status by The Engineer
SUBJECT: GFC Drawings of Admin Building Part-1 - Terrace level beam and slab
Document references
Comment Status by The
No. Initials Reviewers Comments (GC) Issue Contractors/Suppliers Answers Closure Date
Engineer
Doc / Rev Clause Page No:
1 SMJ/MRK General Top level of Stub Column SC1 at Grid 5,6 & 7 to be marked Minor Top level marked as commented
Please note that as per GCC Sub Clause 2.7;3.5; any acceptance, agreement, approval, check, certificate, comment, consent, disapproval, examination, inspection, instruction, Notice, No-objection, record(s) of meeting, permission, proposal, record, reply, report, request, Review, test, valuation, or similar act (including the
absence of any such act) by the Engineer, the Engineer's Representative or any assistant shall not relieve the Contractor from any duty, obligation or responsibility the Contractor has under or in connection with the Contract.
Decipline Head /
Initials Positions SIGN ISSUED BY Reviewer’s Name Approved By:
Coordinator
S.M.Jampani SMJ Chief Structures Expert NAME: Simon Fourie Name Soumen Guin Name Paramjit Singh Duggal
Reviewers Initials Positions SIGN POSITION: Project Director Position: Sr. DGM / CED (RITES - DDC) Position: Team Leader - DDC - RITES
SIGN:
Survey SUR
Sustainability SUS
Systems Engineering Management SYE
Systems SYS
Testing , Commissioning and
TCH
Handover
Telecommunications TEL
Training TRG
Track and Track works TRK
Traction Power TRP
Temporary Traffic Management TTM
Tunnels & Shafts TUN
Tunnel Ventilation System TVS
Temporary Work TWK
Urban Interface UIF
Utilities UTI
BH01/01
IN-02A
BI-05
BH-02
IN-02
IN-03
Please note that as per GCC Sub Clause 3.2; any acceptance, agreement, approval, check, certificate,
comment, consent, disapproval, examination, inspection, instruction, Notice, No-objection,
record(s) of meeting, permission, proposal, record, reply, report, request, Review, test, valuation, or
similar act (including the absence of any such act) by the Engineer, the Engineer's Representative or
any assistant shall not relieve the Contractor from any duty, obligation or responsibility the
Contractor has under or in connection with the Contract.
Please note that as per GCC Sub Clause 3.2; any acceptance, agreement, approval, check, certificate,
comment, consent, disapproval, examination, inspection, instruction, Notice, No-objection,
record(s) of meeting, permission, proposal, record, reply, report, request, Review, test, valuation, or
similar act (including the absence of any such act) by the Engineer, the Engineer's Representative or
any assistant shall not relieve the Contractor from any duty, obligation or responsibility the
Contractor has under or in connection with the Contract.
Please note that as per GCC /PC Sub Clause 2.7.3.5; Any acceptance, agreement, approval, check,
certificate, comment, consent, disapproval, examination, inspection, instruction, Notice,
Noobjection, record(s) of meeting, permission, proposal, record, reply, report, request, Review, test,
valuation, or similar act (including the absence of any such act) by the Engineer or any assistant shall
not relieve the Consultant from any duty, obligation or responsibility the Consultant has under or in
connection with the Contract.
Please note that as per GCC Sub Clause 3.2; any acceptance, agreement, approval, check, certificate,
comment, consent, disapproval, examination, inspection, instruction, Notice, No-objection,
record(s) of meeting, permission, proposal, record, reply, report, request, Review, test, valuation, or
similar act (including the absence of any such act) by the Engineer, the Engineer's Representative or
any assistant shall not relieve the Contractor from any duty, obligation or responsibility the
Contractor has under or in connection with the Contract.
Please note that as per GCC Sub Clause 3.2; any acceptance, agreement, approval, check, certificate,
comment, consent, disapproval, examination, inspection, instruction, Notice, No-objection,
record(s) of meeting, permission, proposal, record, reply, report, request, Review, test, valuation, or
similar act (including the absence of any such act) by the Engineer, the Engineer's Representative or
any assistant shall not relieve the Contractor from any duty, obligation or responsibility the
Contractor has under or in connection with the Contract.
Please note that as per GCC Sub Clause 3.2; any acceptance, agreement, approval, check, certificate,
comment, consent, disapproval, examination, inspection, instruction, Notice, No-objection,
record(s) of meeting, permission, proposal, record, reply, report, request, Review, test, valuation, or
similar act (including the absence of any such act) by the Engineer, the Engineer's Representative or
any assistant shall not relieve the Contractor from any duty, obligation or responsibility the
Contractor has under or in connection with the Contract.
Bhopal Minor
Indore Major
Bhopal & Indore
BH 01/01
BH 02
Bhopal Metro Rail Project BH 03
Indore Metro Rail Project BH 04
BH 05
BH 06
BH 07
0 IN 2A/01
1 IN 02
2 IN 03
3 IN 04
4 IN 05
5 IN 06
IN 07
IN 08
BI 01/01
BI 01/04
BI 01/05
BH&IN 01
BH&IN 02 & 04
BH&IN 03
BH&IN 05
BH&IN 06
BH&IN 07
BH&IN 08
BH&IN 09
BH&IN 10
BH&IN 11
Viaduct
8 EL Stations
Viaduct & 6 EL Stations
Tunnel, 2 UG Stations & 2 Ramps
Viaduct & 13 EL Stations
Depot Civil and E&M Works
Viaduct
7 EL Stations
Viaduct & 9 EL Stations
Viaduct & EL Stations
UG Tunnels, Stations & 1 Ramp
UG Tunnels, Stations & 1 Ramp
Depot Civil and E&M Works
Geotechnical SI
Depot DDC- EoT Required
DDC PST- EoT Required
RISA (R&R, Implementation Support Agency)
Rolling Stock, Signalling & Train Control and
Telecommunication
Track Systems - Supply of Material. Following sub
contracts:
A. UIC 880 Rails
B. 1080 HH Rails
C. Scissors, X-Overs, Turnouts
Level 2 BH.P.GW.01.KM.WI Works Related Key Interfaces Interface with all Interfacing Contractors / Third party, etc.
Level 2 BH.P.GW.01.GA.MOB Mobilization Example - Plant & Machinery and Other Resources etc.
Level 4 BH.P.GW.01.VIA.001.TTM.TMP Traffic Management Plan including safety barricades , safety plan , signages etc
Level 2 BH-P-GW-IW-01-R0.1 Finishing ,testing & handing over the entire scope of work Level 1 BH.P.GW.01.FW Finishing Works