Material Sample Method Statement As Built Plans / Procedure Others (Please Specify Doc Type)
The Contractor certifies that the Technical data submitted herewith is in compliance with the Contract drawings and specifications unless specifically
noted / highlighted here or on the attached documents.
Code A -Approved
Subject to approval from PMC
Code B - Approved with
Sirajudeen KV Comments
Code D - Rejected
Received Date
Al HUDAYRIYAT ISLAND (WEST)-HW2 Infrastructure - Dome Connectivity
DOCUMENT REVIEW SHEET
DOCUMENT REVIEW APPROVAL CODE B - APPROVED WITH COMMENTS OVERALL STATUS CODE Open
Document/Drawing No. IP1-02-002-00-11-CW-AGP-MT-000020 Date Received 03-Nov-23
Document/Drawing Title Method Statement for Cast In Situ Concrete Revision 01 Comments Issued On 06-Nov-23
Comment Code Legend (for individual comments): Reply Code Legend (for individual response):
1 = Action required for this issue 2 = advisory comment 3 = to be addressed at later stage i=incorporated ii= evaluated and not incorporated for the reason stated
Comment
No. Doc. Rev. Section/ Page/ Part No. Engineer/ Employer Comments Comment By Contractor/ Consultant Response Reply Code Reply By Status
Code
1 0 RA-General Serial numbers for the activities to be maintained. 1 PIL/SKV Noted. Serial numbers indicated in the revised risk assessment Closed
RA-Finishes and Working at height hazard not identified and existing control measures for working at height
2 0 1 PIL/SKV Noted. Incorporated in the revised risk assessment Closed
protection incorportaed. Please clarifiy?
3 0 RA-General As per work methodology use of concrete pump is required so RA to be incorporated all activities. 1 PIL/SKV Noted. Incorporated in the revised risk assessment Closed
Noted. Project Quality Plan reference already mentioned in section 2. For shop drawing
and material approval, Contractor would like to note that the method statement for in-situ
References approval for shop drawing and project quality plan and other materials to be added and
10 0 References 1 PIL/YA concrete casting is for general works (telecom, streetlight, mcc, potable water, etc) and Open
specified.
providing each reference number will be enormous. However, Contractor will ensure that
shop drawing & material approval is obtained prior to work at site
11 0 Content 4 Resources/4.5 Responsible for Material Engineer to be mentioned in Human Resources and RACI Matric 1 PIL/MY Material Engineer responsibilities included in Section 4.5 Closed
12 0 Content 6.2 (Methodology) Formation to be compacted to 95% MDD 1 PIL/MY Noted and incorporated in section 6.2.2 Closed
13 00 MS-Manpower Does AGC have a Temporary Works Coordinator or Temporary Works Supervisor 2 KL-EDC All works are coordinated monitored by the Construction Managers and Project Engineer. Closed
14 00 MS-6.2.3 Steel reinforcement How will steel reinforcement be delivered to the working area? 1 KL-EDC Noted and incorporated in section 6.2.3 Closed
MS-6.2.4 Preparation of
15 00 How will the formwork be lifted into position and removed? 1 KL-EDC Noted and incorporated in section 6.2.4 Closed
shuttering and Formworks
Page 1 of 3
Al HUDAYRIYAT ISLAND (WEST)-HW2 Infrastructure - Dome Connectivity
DOCUMENT REVIEW SHEET
DOCUMENT REVIEW APPROVAL CODE B - APPROVED WITH COMMENTS OVERALL STATUS CODE Open
Document/Drawing No. IP1-02-002-00-11-CW-AGP-MT-000020 Date Received 03-Nov-23
Document/Drawing Title Method Statement for Cast In Situ Concrete Revision 01 Comments Issued On 06-Nov-23
Comment Code Legend (for individual comments): Reply Code Legend (for individual response):
1 = Action required for this issue 2 = advisory comment 3 = to be addressed at later stage i=incorporated ii= evaluated and not incorporated for the reason stated
Comment
No. Doc. Rev. Section/ Page/ Part No. Engineer/ Employer Comments Comment By Contractor/ Consultant Response Reply Code Reply By Status
Code
16 00 MS-6.2.8 Pouring of concrete What safe working platform will be provided? 1 KL-EDC Most of the in situ casting are for the future ducts, hence no working platform is required Closed
No false work requires under this submitted method statement. Separate method
17 00 MS-6.2.8 Pouring of concrete Will there be any formwork that requires falsework? 2 KL-EDC Closed
statement will eb submitted if needed.
18 00 MS-6.2.8 Pouring of concrete Does AGC use a Permit to Load? 2 KL-EDC AGCC does not have Permit to Load Closed
19 00 MS-6.2.14 De-Shuttering Does AGC use a Permit to Strike? 2 KL-EDC AGCC does not have Permit to Strike Closed
20 00 Risk Grading Matrix The Intolerable risk is 15-25. The legend 21-25?? 3 KL-EDC Risk Grading Matrix revised as noted Closed
00 What has this task got to do with the casting of in-situ concrete? Noted. Risk assessment revised
21 RA-Manufacture of moulds 2 KL-EDC Open
01 Manufacture of moulds still included.
00 What has this task got to do with the casting of in-situ concrete? Noted. Risk assessment revised
RA-Inspection and Preparation of
22 2 KL-EDC Open
moulds for concreting
01 Inspection and Preparation of moulds for concreting still included
23 00 RA-General There is no risk assessment for the fabrication and installation of formwork or falsework 1 KL-EDC Noted. Incorporated in the revised risk assessment Closed
00 RA-General There is no risk assessment for de-shuttering activities 1 KL-EDC Noted. Incorporated in the revised risk assessment Closed
No risk identified. Include protruding nail risks and de-nailing areas under mitigation measures
24
01 RA-Deshuttering works Existing controls 'Ensure the operatives wear hand gloves, goggles and full body harness always 2 KL-EDC Open
while during de-shuttering works'. Why is full body harness required if most of the in situ casting are
for the future ducts, hence no working platform is required?
Refrain from using generic terminology 'Wear appropriate PPE for the specific task', '5-point PPE rule
00 Noted. Incorporated in the revised risk assessment
shall be complied with by all operatives' Specify the PPE required for each task.
Wherever there is a risk of collision with vehicle/plant/equipment - AGC is to ensure that a safe
00 Noted. Incorporated in the revised risk assessment
working distance of 10 metres is followed at Site
26 RA-General 1 KL-EDC Open
AGC is to ensure that a safe working distance of 10 metres is followed at Site - this has not been
01
incorporated in your Risk Assessment
Page 2 of 3
Al HUDAYRIYAT ISLAND (WEST)-HW2 Infrastructure - Dome Connectivity
DOCUMENT REVIEW SHEET
DOCUMENT REVIEW APPROVAL CODE B - APPROVED WITH COMMENTS OVERALL STATUS CODE Open
Document/Drawing No. IP1-02-002-00-11-CW-AGP-MT-000020 Date Received 03-Nov-23
Document/Drawing Title Method Statement for Cast In Situ Concrete Revision 01 Comments Issued On 06-Nov-23
Comment Code Legend (for individual comments): Reply Code Legend (for individual response):
1 = Action required for this issue 2 = advisory comment 3 = to be addressed at later stage i=incorporated ii= evaluated and not incorporated for the reason stated
Comment
No. Doc. Rev. Section/ Page/ Part No. Engineer/ Employer Comments Comment By Contractor/ Consultant Response Reply Code Reply By Status
Code
Will working at height be carried out? Most of the in situ casting are for the future ducts, hence no
28 01 RA-Working at height 2 KL-EDC Open
working platform is required?
Disclaimer: The PMC/ Employer/ Engineer reserve the right to add/change comments made here once all the documents related to and impacting on the document reviewed herewith are submitted and reviewed. This document does not releive the Contractor/ Consultant from it's obligations in accordance with the Contract
Documents.
Page 3 of 3
Employer PMC Consultant Contractor
Material Sample Method Statement As Built Plans / Procedure Others (Please Specify Doc Type)
The Contractor certifies that the Technical data submitted herewith is in compliance with the Contract drawings and specifications unless specifically
noted / highlighted here or on the attached documents.
Code A -Approved
Please refer to the attached DRS.
Code B - Approved with
Comments
Code D - Rejected
Received Date
Al HUDAYRIYAT ISLAND (WEST)-HW2 Infrastructure - Dome Connectivity
DOCUMENT REVIEW SHEET
DOCUMENT REVIEW APPROVAL CODE A - APPROVED OVERALL STATUS CODE Open
Document/Drawing No. IP1-02-002-00-11-CW-AGP-MT-000020 Date Received 31-Oct-23
Document/Drawing Title Method Statement for Cast In Situ Concrete Revision 00 Comments Issued On 03-Nov-23
Comment Code Legend (for individual comments): Reply Code Legend (for individual response):
1 = Action required for this issue 2 = advisory comment 3 = to be addressed at later stage i=incorporated ii= evaluated and not incorporated for the reason stated
Comment
No. Doc. Rev. Section/ Page/ Part No. Engineer/ Employer Comments Comment By Contractor/ Consultant Response Reply Code Reply By Status
Code
1 0 RA-General Serial numbers for the activities to be maintained. 1 PIL/SKV Noted. Serial numbers indicated in the revised risk assessment Closed
RA-Finishes and Working at height hazard not identified and existing control measures for working at height
2 0 1 PIL/SKV Noted. Incorporated in the revised risk assessment Closed
protection incorportaed. Please clarifiy?
3 0 RA-General As per work methodology use of concrete pump is required so RA to be incorporated all activities. 1 PIL/SKV Noted. Incorporated in the revised risk assessment Closed
As per work methodology scaffolding required for this task and RA is not included with hazards and
5 0 RA-General 1 PIL/SKV Noted. Incorporated in the revised risk assessment Closed
control measures of working with scaffolding.
Is there any requirement of using power tools for surface preperation ?If yes RA to be considered use
6 0 RA-General 1 PIL/SKV Noted. Incorporated in the revised risk assessment Closed
of power tools.
Noted. Future ducts drawing are attached in Appnedix F. Other element to be casted will
7 0 Appendix F: Approved Shop Drawing/s must be attached 1 PIL/YA Open
be based on the submitted shop drawing and site requirement.
Pre-commencement activities:
6.0 Detailed Construction
8 0 All required calibration certificate must be submitted to the Engineer and incorporate in the Method 1 PIL/YA Noted and incorporated in section 6.1.12 Open
Sequence (Methodology),
Statement.
Noted. Project Quality Plan reference already mentioned in section 2. For shop drawing
and material approval, Contractor would like to note that the method statement for in-situ
References approval for shop drawing and project quality plan and other materials to be added and
10 0 References 1 PIL/YA concrete casting is for general works (telecom, streetlight, mcc, potable water, etc) and Open
specified.
providing each reference number will be enormous. However, Contractor will ensure that
shop drawing & material approval is obtained prior to work at site
11 0 Content 4 Resources/4.5 Responsible for Material Engineer to be mentioned in Human Resources and RACI Matric 1 PIL/MY Material Engineer responsibilities included in Section 4.5 Closed
12 0 Content 6.2 (Methodology) Formation to be compacted to 95% MDD 1 PIL/MY Noted and incorporated in section 6.2.2 Closed
13 00 MS-Manpower Does AGC have a Temporary Works Coordinator or Temporary Works Supervisor 2 KL-EDC All works are coordinated monitored by the Construction Managers and Project Engineer. Open
14 00 MS-6.2.3 Steel reinforcement How will steel reinforcement be delivered to the working area? 1 KL-EDC Noted and incorporated in section 6.2.3 Open
Page 1 of 2
Al HUDAYRIYAT ISLAND (WEST)-HW2 Infrastructure - Dome Connectivity
DOCUMENT REVIEW SHEET
DOCUMENT REVIEW APPROVAL CODE A - APPROVED OVERALL STATUS CODE Open
Document/Drawing No. IP1-02-002-00-11-CW-AGP-MT-000020 Date Received 31-Oct-23
Document/Drawing Title Method Statement for Cast In Situ Concrete Revision 00 Comments Issued On 03-Nov-23
Comment Code Legend (for individual comments): Reply Code Legend (for individual response):
1 = Action required for this issue 2 = advisory comment 3 = to be addressed at later stage i=incorporated ii= evaluated and not incorporated for the reason stated
Comment
No. Doc. Rev. Section/ Page/ Part No. Engineer/ Employer Comments Comment By Contractor/ Consultant Response Reply Code Reply By Status
Code
MS-6.2.4 Preparation of
15 00 How will the formwork be lifted into position and removed? 1 KL-EDC Noted and incorporated in section 6.2.4 Open
shuttering and Formworks
16 00 MS-6.2.8 Pouring of concrete What safe working platform will be provided? 1 KL-EDC Most of the in situ casting are for the future ducts, hence no working platform is required Open
No false work requires under this submitted method statement. Separate method
17 00 MS-6.2.8 Pouring of concrete Will there be any formwork that requires falsework? 2 KL-EDC Open
statement will eb submitted if needed.
18 00 MS-6.2.8 Pouring of concrete Does AGC use a Permit to Load? 2 KL-EDC AGCC does not have Permit to Load Open
19 00 MS-6.2.14 De-Shuttering Does AGC use a Permit to Strike? 2 KL-EDC AGCC does not have Permit to Strike Open
20 00 Risk Grading Matrix The Intolerable risk is 15-25. The legend 21-25?? 3 KL-EDC Risk Grading Matrix revised as noted Open
21 00 RA-Manufacture of moulds What has this task got to do with the casting of in-situ concrete? 2 KL-EDC Noted. Risk assessment revised Open
23 00 RA-General There is no risk assessment for the fabrication and installation of formwork or falsework 1 KL-EDC Noted. Incorporated in the revised risk assessment Open
24 00 RA-General There is no risk assessment for de-shuttering activities 1 KL-EDC Noted. Incorporated in the revised risk assessment Open
Refrain from using generic terminology 'Wear appropriate PPE for the specific task', '5-point PPE rule
25 00 RA-General 2 KL-EDC Noted. Incorporated in the revised risk assessment Open
shall be complied with by all operatives' Specify the PPE required for each task.
Wherever there is a risk of collision with vehicle/plant/equipment - AGC is to ensure that a safe
26 00 RA-General working distance of 10 metres is followed at Site 1 KL-EDC Noted. Incorporated in the revised risk assessment Open
Disclaimer: The PMC/ Employer/ Engineer reserve the right to add/change comments made here once all the documents related to and impacting on the document reviewed herewith are submitted and reviewed. This document does not releive the Contractor/ Consultant from it's obligations in accordance with the Contract
Documents.
Page 2 of 2
Al HUDAYRIYAT ISLAND (WEST)-HW2 Infrastructure - Dome Connectivity
DOCUMENT REVIEW SHEET
DOCUMENT REVIEW APPROVAL CODE C - REVISE & RESUBMIT OVERALL STATUS CODE Open
Document/Drawing No. IP1-02-002-00-11-CW-AGP-MT-000020 Date Received 05-Oct-23
Document/Drawing Title Method Statement for Cast In Situ Concrete Revision 00 Comments Issued On 18-Oct-23
Comment Code Legend (for individual comments): Reply Code Legend (for individual response):
1 = Action required for this issue 2 = advisory comment 3 = to be addressed at later stage i=incorporated ii= evaluated and not incorporated for the reason stated
Comment
No. Doc. Rev. Section/ Page/ Part No. Engineer/ Employer Comments Comment By Contractor/ Consultant Response Reply Code Reply By Status
Code
1 0 RA-General Serial numbers for the activities to be maintained. 1 PIL/SKV Noted. Serial numbers indicated in the revised risk assessment Open
RA-Finishes and Working at height hazard not identified and existing control measures for working at height
2 0 1 PIL/SKV Noted. Incorporated in the revised risk assessment Open
protection incorportaed. Please clarifiy?
3 0 RA-General As per work methodology use of concrete pump is required so RA to be incorporated all activities. 1 PIL/SKV Noted. Incorporated in the revised risk assessment Open
As per work methodology scaffolding required for this task and RA is not included with hazards and
5 0 RA-General 1 PIL/SKV Noted. Incorporated in the revised risk assessment Open
control measures of working with scaffolding.
Is there any requirement of using power tools for surface preperation ?If yes RA to be considered use
6 0 RA-General 1 PIL/SKV Noted. Incorporated in the revised risk assessment Open
of power tools.
Noted. Future ducts drawing are attached in Appnedix F. Other element to be casted will
7 0 Appendix F: Approved Shop Drawing/s must be attached 1 PIL/YA Open
be based on the submitted shop drawing and site requirement.
Pre-commencement activities:
6.0 Detailed Construction
8 0 All required calibration certificate must be submitted to the Engineer and incorporate in the Method 1 PIL/YA Noted and incorporated in section 6.1.12 Open
Sequence (Methodology),
Statement.
Noted. Project Quality Plan reference already mentioned in section 2. For shop drawing
and material approval, Contractor would like to note that the method statement for in-situ
References approval for shop drawing and project quality plan and other materials to be added and
10 0 References 1 PIL/YA concrete casting is for general works (telecom, streetlight, mcc, potable water, etc) and Open
specified.
providing each reference number will be enormous. However, Contractor will ensure that
shop drawing & material approval is obtained prior to work at site
11 0 Content 4 Resources/4.5 Responsible for Material Engineer to be mentioned in Human Resources and RACI Matric 1 PIL/MY Material Engineer responsibilities included in Section 4.5 Closed
12 0 Content 6.2 (Methodology) Formation to be compacted to 95% MDD 1 PIL/MY Noted and incorporated in section 6.2.2 Closed
13 00 MS-Manpower Does AGC have a Temporary Works Coordinator or Temporary Works Supervisor 2 KL-EDC All works are coordinated monitored by the Construction Managers and Project Engineer. Open
14 00 MS-6.2.3 Steel reinforcement How will steel reinforcement be delivered to the working area? 1 KL-EDC Noted and incorporated in section 6.2.3 Open
Page 1 of 2
Al HUDAYRIYAT ISLAND (WEST)-HW2 Infrastructure - Dome Connectivity
DOCUMENT REVIEW SHEET
DOCUMENT REVIEW APPROVAL CODE C - REVISE & RESUBMIT OVERALL STATUS CODE Open
Document/Drawing No. IP1-02-002-00-11-CW-AGP-MT-000020 Date Received 05-Oct-23
Document/Drawing Title Method Statement for Cast In Situ Concrete Revision 00 Comments Issued On 18-Oct-23
Comment Code Legend (for individual comments): Reply Code Legend (for individual response):
1 = Action required for this issue 2 = advisory comment 3 = to be addressed at later stage i=incorporated ii= evaluated and not incorporated for the reason stated
Comment
No. Doc. Rev. Section/ Page/ Part No. Engineer/ Employer Comments Comment By Contractor/ Consultant Response Reply Code Reply By Status
Code
MS-6.2.4 Preparation of
15 00 How will the formwork be lifted into position and removed? 1 KL-EDC Noted and incorporated in section 6.2.4 Open
shuttering and Formworks
16 00 MS-6.2.8 Pouring of concrete What safe working platform will be provided? 1 KL-EDC Most of the in situ casting are for the future ducts, hence no working platform is required Open
No false work requires under this submitted method statement. Separate method
17 00 MS-6.2.8 Pouring of concrete Will there be any formwork that requires falsework? 2 KL-EDC Open
statement will eb submitted if needed.
18 00 MS-6.2.8 Pouring of concrete Does AGC use a Permit to Load? 2 KL-EDC AGCC does not have Permit to Load Open
19 00 MS-6.2.14 De-Shuttering Does AGC use a Permit to Strike? 2 KL-EDC AGCC does not have Permit to Strike Open
20 00 Risk Grading Matrix The Intolerable risk is 15-25. The legend 21-25?? 3 KL-EDC Risk Grading Matrix revised as noted Open
21 00 RA-Manufacture of moulds What has this task got to do with the casting of in-situ concrete? 2 KL-EDC Noted. Risk assessment revised Open
23 00 RA-General There is no risk assessment for the fabrication and installation of formwork or falsework 1 KL-EDC Noted. Incorporated in the revised risk assessment Open
24 00 RA-General There is no risk assessment for de-shuttering activities 1 KL-EDC Noted. Incorporated in the revised risk assessment Open
Refrain from using generic terminology 'Wear appropriate PPE for the specific task', '5-point PPE rule
25 00 RA-General 2 KL-EDC Noted. Incorporated in the revised risk assessment Open
shall be complied with by all operatives' Specify the PPE required for each task.
Wherever there is a risk of collision with vehicle/plant/equipment - AGC is to ensure that a safe
26 00 RA-General working distance of 10 metres is followed at Site 1 KL-EDC Noted. Incorporated in the revised risk assessment Open
Disclaimer: The PMC/ Employer/ Engineer reserve the right to add/change comments made here once all the documents related to and impacting on the document reviewed herewith are submitted and reviewed. This document does not releive the Contractor/ Consultant from it's obligations in accordance with the Contract
Documents.
Page 2 of 2
AL HUDAYRIAT ISLAND WEST INFRASTRUCTURE
WORKS – DOME CONNECTIVITY
Prepared by:
Al Geemi Contracting Company LLC.
PO Box 2877,
Abu Dhabi United Arab Emirates
www.algeemi.com
Prepared for:
Parsons International Limited
P.O. Box 5498,
Abu Dhabi, United Arab Emirates
www.parsons.com
Programme Management
Infrastructure Works
Hudayriat Island
REVISION HISTORY
00 05-10-2023 Status C
APPROVALS
Printed initials in the boxes confirms that the document has been reviewed and approved.
Approved records are saved on Hudayriat Island Programme LIbrary.
Table of Contents
DESCRIPTION PAGE NO.
4.0 Resources:............................................................................................................. 8
8.0 Quality Control - ITP & Inspection Check list…. (Attachment: Appendix-C) ............ 27
Objective:
The objective of this method statement is to presents the procedures and practices to be
followed at site during cast in-situ concrete construction in accordance with the
Specifications. The aforesaid activities are in accordance with requirements of the project,
authorities' specification. For the Project “Al HUDAYRIYAT ISLAND (WEST) Infrastructure
- Dome Connectivity”
This statement covers the various steps and sequence of works for cast-in-situ concrete
construction.
➢ Setting out
➢ Steel Reinforcement
➢ Pouring of concrete
➢ Vibrating of concrete
➢ Curing of Concrete
➢ De-shuttering
2.0 References
Document Reference No. Title
Specification Details
Contract Specifications
PROJECT PLANS
IP1-02-00002-04-11-HS-
Project HSE Plan
AGP-PL-000001
IP1-02-00002-00-11-QA-
Project Quality Plan
AGP-PL-000001
3.0 Definitions
4.0 Resources:
4.1 Materials:
(All Materials shall be approved by Employer/Engineer Prior to Use)
• Curing Compound
• Compressible Board ( For Joints )
• Not Applicable
Manpower
1. Project Manager
2. Construction manager
3. Project Engineer
4. QA/QC Engineer
5. HSE Engineer/Officer
Project Manager
➢ Project Manager is the full authority & overall responsible for the safe project
site execution.
➢ Responsible for the overall implementation of the approved method statement
and risk assessment, approved Project HSE Plan and approved shop drawings.
➢ Responsible to ensure that HSE procedures and guidelines of OSHAD, and concern
authorities are implemented; permits/NOC and approvals are in-placed prior to work
and during the execution of works.
➢ Responsible to ensure that correct manpower, materials and resources are available
for the safe execution of work
➢ Responsible to take disciplinary action for the repeated HSE noncompliance during
the work.
Construction Manager
➢ Provide leadership in the implementation of all HSE approved method statement and
risk assessment during the execution of work.
➢ Responsible to provide overall functioning of the project execution, planning, progress
oversight
➢ Responsible to support the construction and QHSE team for the proper and safe
execution of the project in compliance with the contract specification, drawings and
other applicable contractual requirements.
➢ Responsible for arranging work permits / NOC and approvals for prior to
commencement of works.
➢ Responsible to ensure that all site works are complying the with the work permits /
NOC requirements
➢ Responsible to ensure that all site personnel receive induction from Safety department
and Supervisory team are fully aware of the drawings, specifications and quality and
inspection requirements.
➢ Responsible to ensure that all site works are executing as per approved method
statement and risk assessment , approved Project HSE Plan, Authority Safety
guidelines , Client’s Key HSE requirements and OSHAD COP,s .
➢ Responsible for arranging all the required safety control measures, sufficient
resources, welfare facilities and manpower prior to start the works and during the
execution on site to ensure the safe execution of works
➢ Responsible to stop any unsafe act or unsafe condition at work site to avoid any safety
noncompliance and to take immediate corrective action.
➢ Responsible to ensure good housekeeping at work area.
Project Engineer
➢ Responsible to obtain MODON work permit the task in place prior to work and ensure
full compliance with MODON permit to Work/Work Management.
➢ Responsible to execute the construction work at site as per approved method
statement/ risk assessment , approved shop drawings , materials and specifications
all in accordance with the project technical ad contractual requirements .
➢ Responsible for procuring/assigning materials & workforce and to perform the planned
works
➢ Responsible to execute the construction work as per approved Project HSE Plan,
Authority Safety guidelines , Client’s Key HSE requirements and OSHAD COP,s
➢ Responsible for arranging all the required safety control measures including welfare
facilities ( rest shelter , toilets , drinking water etc. ) in place prior to start the works
and during the execution on site .
➢ To ensure that required HSE & Quality aspects are followed during the works.
➢ Ensure required NOC /PTW (internal and external), method statement, risk
assessment available at work place and fully implemented during the execution of
work
➢ Co-ordinate with site QA/QC Engineer at all relevant stages of work for site inspection.
➢ Responsible for strict compliance with valid PTW requirements.
➢ Responsible to conduct daily task briefing to all work force and need to be recorded
➢ Responsible to ensure that all heavy equipment’s working at site have valid third party
certificates and had undergone pre-mobilized inspection by the Safety Department
➢ Responsible to ensure sufficient resources are available for workers to do their jobs
safely and all personnel using required Task PPE ‘s properly at work site
➢ Responsible to stop any unsafe act or unsafe condition at work site to avoid any safety
noncompliance and to take immediate corrective action.
➢ Ensure good housekeeping ,waste management and safe access / egrees at work
area.
QA/QC Engineer
➢ Responsible to ensure that specified quality standards are incorporated in to the
works.
➢ Responsible to verify that materials used for the works are having required approvals
and the documents referred are approved.
➢ Responsible to ensure that tests/inspections specified for the works are conducted
and records maintained.
➢ Responsible to ensure that required method statement, work procedures being
approved as per Contract Conditions and Specification.
➢ Responsible to ensure that site construction team are working as per approved
method statement and compliance shall be monitored on ground / site.
➢ Responsible for conduction/coordinating required Job specific training to the work
force.
HSE Engineer/Officer
➢ Responsible for conducting safety training, safety training programs /Campaign
induction for all work force to ensure the site staffs are familiar with the safety
requirements for this activity.
➢ Responsible to communicate the approved risk assessment with concern workforce,
trained them to comply with safety requirements.
➢ Responsible for daily inspection of work site and monitoring of required safety
measures during work as per safe practices / method statement, approved Project
HSE Plan, complying with Authority Safety guidelines , Client’s Key HSE
requirements and OSHAD COP,s .
➢ Ensure task briefing /tool Box Talks are conducted by the Site Engineer / Foreman to
the work force and records available at work site.
➢ Ensure required work permits available at work place and fully implemented during
the execution of work
➢ Ensure certified / trained personnel assigned for performing of works.
➢ Manage and Supervise the HSE team for onsite construction.
Foreman
➢ Always be present throughout site works for safe execution of work.
➢ To supervise the site activities and ensure that all works are executed with valid PTW,
as per approved method statement and risk assessment , approved Shop drawings
, approved Project HSE Plan, complying with Authority Safety guidelines , Client’s
Key HSE requirements and OSHAD COP,s .
➢ Ensure approved materials only are used for the works
➢ Inspection/testing are conducted at the stages specified in approved ITP,
➢ Responsible to conduct daily task briefing to all work force and need to be recorded
➢ Responsible to ensure the concern work force under his team is completely aware for
the safe work procedure as per the approved method statement and risk assessment.
➢ Daily heavy equipment inspection and ensure only certified / good condition
equipment operation at work place
➢ Deploy only trained and experienced personnel for the task with close supervision.
➢ Responsible to ensure all personnel using required Task PPE ‘s properly at work site
➢ Ensure usable and good condition welfare facilities ( rest area, drinking water , toilet )
available at work place.
➢ Responsible to stop any unsafe act or unsafe condition at work site to avoid any safety
noncompliance and to take immediate corrective action
➢ Responsible for daily housekeeping at work site and maintain the worksite clean & tidy
with safe access and egress.
Emergency Procedure:
• Emergency Evacuation and Rescue procedure for unsafe working condition while
repairing precast element or working in a confined space subject to breathing issue
• If someone notice unsafe working while repairing precast concrete element or
working in confined space subject to breathing issue shall report immediately to
their immediate supervisor, Emergency number EHS Engineer, and emergency
coordinator about the situation.
• Warn immediately fellow staff/ workers near the possible unsafe area to avoid
human casualty or tragic incidents.
• The emergency response team/ Site Engineer/ Foreman will evaluate and assist
the situation if Emergency Response procedure will be activated.
• In unsafe working condition while repairing precast element or working in a
confined space subject to breathing issue , the safety officer shall immediately
report to Emergency coordinator for activating the Emergency procedure and for
calling outside help if necessary. When hearing continuous siren all staff /workers
shall evacuate and proceed to designated Assembly point.
• All equipment shall be drive away from area avoiding obstruction.
• All engines shall be shut down and operators proceeded to assembly point.
• The rescue team shall immediately respond in retrieving any staff/ workers buried
or trap in the collapsed trenches/ structures until civil defense arrives in the site.
• The Nurse/ first aider shall give necessary medical attention to the victim until
emergency medical support arrives.
• Head count shall be done at assembly point.
• Nobody will be allowed to go to work unless instructed by Emergency coordinator.
• Follow instructions given by Emergency Response Team.
• Any Emergency incident report shall be submitted to Client /AGC Management
and Regulatory Authority.
• Modon incident reporting escalation protocol must be followed at site.
• Al Geemi shall strictly ensure all adequate resources, trained personnel and
arrangements are available in the project for any emergency arising during the
excavation activity. And to ensure the preparedness, Al Geemi to conduct
emergency mock drills at regular intervals.
Emergency Equipment:
• Stretcher
• Resuscitators
• First Aid Kits
• Breathing Apparatus
• Emergency Vehicle
• Male Nurse
• Vehicle Equipment Horn
• Mobile Air Horn
• Static Manual Alaram
• Eye wash stations or showers
• Hand tools (mops, buckets, squeegees and bins, personal protective clothing)
6.2 METHODOLOGY:
• The finished surface shall not deviate from the required profile
by more than 10mm over a 3m gauge length or have any abrupt
irregularities more than 3mm.
a) If the membrane film is broken or damaged at any time during the curing
period, the area or areas shall be recoated to the original requirements.
b) Curing compounds shall be applied to unformed surfaces as soon as
the water sheen has practically disappeared from the concrete, or as
soon as the forms have been removed from surfaces not to be rubbed.
c) Curing compounds shall not be used on areas receiving a rubbed finish.
d. If there is to be any delay in applying curing compound, the surface
shall receive moist curing until the compound can be applied.
d) Curing compound shall be applied with equipment which will produce a
fine spray, and all compounds shall be thoroughly agitated just prior to
use. The surface shall be sprayed again immediately at right angles to
the first application. The rate of each application shall be not less than
1 liter for each 3.6 square meters of surface. Care shall be taken to
prevent application to joints where concrete bond is required to
reinforcement steel, and to joints where joint sealer is to be placed.
e) Timber formwork covering the concrete shall be moistened with water
at frequent intervals to keep it from drying during the curing period.
Metal formwork exposed to the sun must be shaded from its direct rays,
painted white or otherwise protected during the curing period. When
forms are removed before the end of the 7-day curing period, specified
curing procedures shall be implemented by the Contractor and
continued until the end of the 7-day period as specified.
Quality Control - ITP & Inspection Check list (Attachment Appendix -C)
(Attachment Appendix -D)
Risk Assessment / Hazard Assessment
(Attachment Appendix -E)
Third party approval requirements, <if any. >
Appendix -A:
Human Resources and
RACI Matrix/ Contact
Number
APPENDIX
Al HUDAYRIYAT ISLAND (WEST)-HW2 Infrastructure - Dome Connectivity
PROJECT DIRECTORY
S.No. Name Dsignation Email Address M. No.
PROJECT SUPPORT
1 Mr Bassam Kharbat Project Director bassam.kharbat@algeemi.com 0506198760
2 Mr. Mohammad Kelani Senior Planning Engineer mohammad.kelani@algeemi.con 05004168456
3 Mr. Anil Kumar QHSE Manager anil.kumar@algeemi.com 0506420184
DESCRIPTION
REFERENCE NO.
Hisham Manuel
Amjad Mohd Al Thomas Husan Mohamma Nimesh Thomas Sarraj Satyapal Mohamme Sarfraz
MANAGEMENT TEAM Abualeinei Wael Adel Romel
Harara Bayouk A.V. Dakwar d Gaith Valsan Roy Alshawwa Saran d Nahas Hussain
n Ante
NOC Coordinator C
Traffic Engineer C
Mechanical Engineer RA
Sr Quantity Surveyor I
Electrical Project
R/A
Manager
Sr Planning Engineer I
Appendix -B:
Construction Program
(To Follow)
APPENDIX
Employer PMC Engineer/Consultant Contractor
Appendix -C:
Quality Control - ITP &
Inspection Check list
APPENDIX
INSPECTION AND TEST PLAN – CAST IN SITU CONCRETE
Project Name Al HUDAYRIYAT ISLAND (WEST) Infrastructure - Dome Connectivity
Project Description Infrastructure Works
Subject ITP for Cast In Situ Concrete Works Date: 05 Oct 2023
Document ref. no: IP1-02-002-00-11-CW-AGP-IT-000020 Rev. no: 00
Inspection Points
Specification Verifying Independen Client/
No. Activity Description Type of Inspection Acceptance Criteria Contract
Reference Document t
or
Consulta
Laboratory nt
Approval
All necessary permits of
Contract from relevant
1.1 the commencing of Review of documents Check list H R/A
documents authority/Consultant/
precast concrete Works
Employer
Shop Drawing
Ready Mix Concrete Mix Project Standard Comply with Approved Material
3.1 Review of documents - H R/A
Designs Specifications Specifications Submittal
Project Standard To check & verify the Comply to Specifications MIR & Test
5.1 Steel reinforcement Specifications Reports - H W
Material at site
C Construction Phase
6 Activity 1 (according to the subject)
Is rebar size, spacing & plaxement are done as per approved shop drawing
6
details?
PVC conduits, sleeves, block outs, lifting hooks etc. provided as per
8
approved Shop drawing
Is MEP clearance is taken and coordinated with disciplienes prior to proceed
9
with concrete.
23 Safety requirenents are fillfilled (sign board, warning tape, barrication etc.
Accompanying document :
For Contractor
For Supervision consultant (Engineer)
Quality Inspector Quality Engineer
Name
Designation
Date
CHECK LIST
Project Name Hudayriyat Island Priority Development Area PMC EllissDon
Project Description Infrastructure Works Lead Consultant Parsons International Limited
Employer Modon Properties PJSC Contractor Al Geemi Cont.Co. L.L.C.
Checklist Title: Cast In Situ Concrete Works (Water Curing) WIR no.
Works Location: Checklist No. IP1-02-002-00-11-CW-AGP-CL-000020B
Related ITP # IP1-02-002-00-11-CW-AGP-IT-000020 [00]
Related Drawing(s)
Related MS # IP1-02-002-00-11-CW-AGP-MT-000020 [00]
Status - Acceptable
SN Description of checking to be carried out Remarks
Yes No NA
PRE-CONSTRUCTION ACTIVITIES
Curing water shall be done with sweet water for wetting of concrete
8
surfaces.
SAFETY ISSUES
Remarks:
Accompanying document :
For Contractor
For Supervision consultant (Engineer)
Quality Inspector Quality Engineer
Name
Designation
Date
CHECK LIST
Project Name Hudayriyat Island Priority Development Area PMC EllissDon
Project Description Infrastructure Works Lead Consultant Parsons International Limited
Employer Modon Properties PJSC Contractor Al Geemi Cont.Co. L.L.C.
Checklist Title: Cast In Situ Concrete Works (Repair Works) WIR no.
Works Location: Checklist No. IP1-02-002-00-11-CW-AGP-CL-000020C
Related ITP # IP1-02-002-00-11-CW-AGP-IT-000020 [00]
Related Drawing(s)
Related MS # IP1-02-002-00-11-CW-AGP-MT-000020 [00]
Status - Acceptable
SN Description of checking to be carried out Remarks
Yes No NA
PRE-CONSTRUCTION ACTIVITIES
15 Safety requirenents are fillfilled (sign board, warning tape, barrication etc.
Remarks:
Accompanying document :
For Contractor
For Supervision consultant (Engineer)
Quality Inspector Quality Engineer
Name
Designation
Date
Employer PMC Engineer/Consultant Contractor
Appendix -D:
Risk Assessment /
Hazard Assessment
APPENDIX
HSE Risk/Hazard Assessment Form
Activity undertaken: In Situ Concrete Works Date and Time Risk Assessment Completed: 05-10-2023
RR – Risk Rating
IR- Intolerable Risk
Likely (3) 3 6 9 12 15 7-14 High Risk
Almost
5 10 15 20 25
Certain (5)
Residual
Existing risk
Risk
Applicable Legal
R/ Affected R/ Proposed controls R/
Activity Hazard Risk Existing controls L S Responsibility L S and other
NR group R Measures R
requirement
• Personal • Safe access to work area to be OSHAD SF
Pre- • Vehicle • Follow
injury provided CM / Engineers / CoP 2.0
commenceme Movem R A, B, C 4 4 16 approve 1 4 4
• Property • Operatives to be given induction Foreman / HSE CoP 9.0
nt of activities ent d control
damage training before entering work area CoP 44.0
MP-PMP-12.06-003-00 HSE Risk/Hazard Assessment Form Page 11 of 11
Residual
Existing risk
Risk
Applicable Legal
R/ Affected R/ Proposed controls R/
Activity Hazard Risk Existing controls L S Responsibility L S and other
NR group R Measures R
requirement
• Loading • Tool box talk shall be conducted docume
offloadi prior to start the activity nt
ng of • 3rd Party Certified operators shall
material operate all the vehicles and
equipment's
• All drivers / operators must have
valid 3rd UAE driving license
• Competent flagman with third party
certification shall be assigned with
equipment's
• Safe Materials handling as per HSE
plan
• Unloading area is forbidden for
unauthorized entry if potential
hazards exist
• Emergency response plan to be
communicated to all operatives and
emergency number provided.
• Strict supervision of the in-charge
Engineer / Foreman
Sharp edges, OSHAD SF
Cut, Bruises, • TBT meeting to be conducted with
Protruding
Personal injury, all operatives involve
objects, Fire,
Burn, Explosion, • Only competent operatives shall be COP 2.0
hot surfaces,
Manufactur Death used for the job • Follow Supervisor/Forem
Flammable
R A,B, C, D • Competent and approved by AEP 4 4 16 approve 14 4
e of moulds gases, Use of an/HSE COP 17.0
welder to be used for welding d MSRA
incompetent
activity
operative,
• Work area to be isolated and COP 21.0
Inadequate signage installed
supervision,
Applicable Legal
R/ Affected R/ Proposed controls R/
Activity Hazard Risk Existing controls L S Responsibility L S and other
NR group R Measures R
requirement
Lack of job • Gas cylinder to be placed inside COP 35.0
specific PPE trolley
• Arc welding machine shall be 3rd
party certified and inspected for any
defect before use
• Hot work PTW system shall be
followed
• Ensure that combustibles materials
are 10 meters away from hot work
area and to be covered with a fire
rated material
• Protruding steel shall be covered
with rebar cap
• Ensure the MSRA are briefed by
plant supervisor & understood by
foreman & work force.
• Appropriate Mandatory PPEs and
High visibility clothing shall be used
by all operatives and workers while
working.
• Comply with hot works procedure.
• Work area must be isolated with
barricade and adequate signs.
• Ensure the spark or molten metal will
not contact with flammable or
combustible materials.
• Flash back arrestors must be fitted to
cylinder hose.
• Ground all welding machine frames.
Applicable Legal
R/ Affected R/ Proposed controls R/
Activity Hazard Risk Existing controls L S Responsibility L S and other
NR group R Measures R
requirement
• Do not use matches or lighters to ignite
the torches. Use only sparks igniters.
• If a wrench is needed to open an
acetylene cylinder valve, leave the
wrench in the valve while the cylinder
is in use to perform quick emergency
shut-off.
• Disconnect all hoses at the end of each
work.
• Thorough inspection of equipment,
tools and workplace to be made
prior to commencing of activities
• Inspection tag must be displayed
and maintained.
• Adequate FFE is available, such as;
fire extinguisher, fire blanket.
Trained fire watcher is available.
• Proper ventilation of area is
ensured.
• Wear appropriate PPE for the
specific task, such as; welding
gloves, apron, face shield, ear and
respiratory protection, etc.
• Ensure certified first aiders and first-
aid equipment are available.
• Close monitoring and competent
supervision
• HSE induction must be conducted
for all employees.
• TBT prior to commencing work.
Applicable Legal
R/ Affected R/ Proposed controls R/
Activity Hazard Risk Existing controls L S Responsibility L S and other
NR group R Measures R
requirement
• Compressed gas cylinders safe
handling.
• Basic firefighting training for all
exposed employees.
•
• Operatives inducted into site and
warned of dangers.
• Close monitoring to be ensured by
competent supervisor
• Ensure certified first aiders and first-aid
equipment is available.
Exposure to OSHAD SF
• Wear appropriate PPE for the specific
plant and
task
equipments,
• Thorough inspection of equipment, COP 2.0
Noise,
tools and workplace to be made prior
Dust, Major or minor
to commencing work. Inspection tag
Rebar works Sharp/Protrudin injury, Follow approved COP 4.0
must be displayed and maintained.
g edges, Property damage, A,B, control CM/Supervisor/F
Awkward body
R • all reinforcing steel (bars) to be handled 3 3 9 13 3
C,D, documents. oreman/HSE
positioning, by person wearing leather working Cop 22.0
Poor gloves
housekeeping • all mesh to be stored laying down on
Cop 34.0
wooden bearers
• eye protection to BS standards to be
worn when fixing steel
• excess binding steel to be disposed of
correctly
• to prevent person becoming entangled and
tripping
• protruding steel to be covered with rebar
cap
MP-PMP-12.06-003-00 HSE Risk/Hazard Assessment Form Page 11 of 11
Residual
Existing risk
Risk
Applicable Legal
R/ Affected R/ Proposed controls R/
Activity Hazard Risk Existing controls L S Responsibility L S and other
NR group R Measures R
requirement
• bars and mesh to be handled by adequate
number of people
• (separate manual handling assessment
required)
• 5 point PPE to be complied with
Applicable Legal
R/ Affected R/ Proposed controls R/
Activity Hazard Risk Existing controls L S Responsibility L S and other
NR group R Measures R
requirement
• Moving plate.
tool bits • Trailing cables should not be in the
• Slips, trips path of other workers.
and falls Plugs and sockets should be water
resistant and colour
Use of
compressed air
for cleaning
• Flying
particles or
dust
• Sudden
snatching or
surging of
hose/handle
• Failure of
hoses or
couplings
• Vibration
• Noise
Fire
▪ TBT to be conducted to all workers OSHAD SF
engaged.
• Lacerati Close and
Deshuttering ▪ Hand tools to be in good condition. Cop 2.0
on effective PM/Supervisor/F
works A,B,C ▪ Protruding nails to be removed & 3 3 9 13 3
• Slip, Trip supervision oreman/HSE
segregated.
, Fall Cop 40.0
▪ Select physically competent
operatives.
Applicable Legal
R/ Affected R/ Proposed controls R/
Activity Hazard Risk Existing controls L S Responsibility L S and other
NR group R Measures R
requirement
▪ Maintain housekeeping throughout CoP 42.0
the work.
▪ Mandatory supervision throughout
the works.
▪ Ensure the operatives wear hand
gloves, goggles and full body harness
always while during de-shuttering
works
• TBT and MSRA briefing to be
conducted by competent supervisor OSHAD SF
prior to start of work
• Work area is maintained free from
obstruction. COP 2.0
Manual
• Tools and equipment are stored
handling,
appropriately. COP 14.0
Inspection Awkward body
• Ground shall be maintained levelled and dry
and positioning, Use
with safe access and egress. Openings Follow approved
of defected Personal injury, PM/Supervisor/F COP 21.0
Preparation shall be covered properly.
tools, Poor R Back pain, A,B,C,D 3 3 9 control 13 3
of moulds • Adequate lighting is provided. oreman/HSE
housekeeping Property damage document
for • Employee shall take extra care when COP 22.0
Use of
working in the area.
concreting incompetent
• Work instruction and signage must be
operative,
posted.
Uneven floor
• Close monitoring and competent
supervision
• Periodic inspections of locking wedges to be
carried out to ensure that there is no
wear and tear.
Applicable Legal
R/ Affected R/ Proposed controls R/
Activity Hazard Risk Existing controls L S Responsibility L S and other
NR group R Measures R
requirement
• All rotating part of equipment use for
mould preparation to be properly
guarded
• Trained and skilled persons to carry out
stressing.
• Proper signage’s and barricades to be put in
place to caution people working nearby.
• HSE induction must be conducted for
exposed employees.
• Train employees on proper handling
• 5 point PPE to be complied with
• All equipment shall be 3rd party OSHAD SF
certified and operator shall also be
3rd party certified. COP 2.0
Moving vehicle, • Dust suppression shall be ensured around
Absence of working area
Concrete flagman, use of Personal Injury, • Concrete waste washing area to be COP 4.0
incompetent Struck by moving provided
Concrete operators, Use vehicle, Property • Only the competent / designated operator Follow approved COP 8.0
will operate the machine PM/Supervisor/F
mixing, of uninspected R damage, Skin A,B,C,D, 3 4 12 control 14 4
• HSE induction must be conducted for oreman/HSE
transporting equipment by irritation, documents COP 14.0
exposed employees.
and 3rd party, Poor Respiratory • Train employees on proper handling
placement access, Uneven problem • Regular TBT / HSE briefing CoP 38.0
ground, Dust, • Buckets used for distributing concrete shall
Noise, Chemical be inspected and certified by 3r party.
• Proper housekeeping to be ensured
• Access to site or precast area to be in good
condition
Applicable Legal
R/ Affected R/ Proposed controls R/
Activity Hazard Risk Existing controls L S Responsibility L S and other
NR group R Measures R
requirement
• Competent persons under proper
supervision to carry out the job.
• Good housekeeping practices to be
maintained at all times
• Ensure the protection of environment
during concrete work. Avoid concrete
spillage on the ground and provide
concrete wash area
• The correct use of PPE to include
coveralls, safety spectacles, gloves,
helmets, ear plugs, dust masks and
safety shoes. Comply with 5 point
PPE
Applicable Legal
R/ Affected R/ Proposed controls R/
Activity Hazard Risk Existing controls L S Responsibility L S and other
NR group R Measures R
requirement
• No one else is permitted to alter any
scaffolding without the approval of
scaffolding inspector.
• Scaffoldings must be fitted with toe
working at heights.
• Qualified scaffolding inspector should
out.
• Scaff tag should be available on all
scaffoldings.
Continuity check is to be used for
the purpose.
Applicable Legal
R/ Affected R/ Proposed controls R/
Activity Hazard Risk Existing controls L S Responsibility L S and other
NR group R Measures R
requirement
Using defective Personnel placing concrete will wear PPE, assessment COP 36.0
plant suitable gloves/footwear and eye approved and
/equipment Protection. properly COP 38.0
Falling • Plant and equipment used
executed
materials. during concrete placing will be operated
by trained and authorized personnel COP 42.0
under close supervision.
• All plant and equipment will
carry current certification and be
maintained in a safe condition• Defective
plant/equipment will be removed from
service and effective remedial actions
taken.
• Safe working distance of
10meter will be followed with the
vehicle/ Plant
• Approved plant/equipment will
be used
• Slinging and lifting operations
will be carried out by trained personnel.
• Unauthorized personnel will be
prohibited from entering areas where
concrete placing activities are being
undertaken.
• Ground will be levelled for the
outriggers pad to fix properly.
• Concrete wash area will be
available at site and truck hoppers will be
washed properly before leaving the site.
MP-PMP-12.06-003-00 HSE Risk/Hazard Assessment Form Page 11 of 11
Residual
Existing risk
Risk
Applicable Legal
R/ Affected R/ Proposed controls R/
Activity Hazard Risk Existing controls L S Responsibility L S and other
NR group R Measures R
requirement
Access across re-bar fixing will be
maintained with timber boarding to
provide a safe access and place of work.
• TBT on daily basis before
commencing activity
• Proper handling, storing and disposal of
hazardous substance as per MSDS &
Exposure to WMP are observed.
OSHAD SF
hazardous • MSDS is made available at the area and
substance or communicated among workers.
chemical Skin & eye • Curing area is well ventilated. COP 2.0
handling. irritation and lung • Drip tray is provided for temporary storing
Exposure to disease of curing chemical at the working area.
COP 1.0
adverse • Proper housekeeping is strictly observed
weather Injury • Trained and competent workers are
CURING: assigned to carry-out curing work. Provide proper COP 14.O
condition.
R A,B,C,D • HSE induction must be conducted for
3 4 12 14 4
Dermatitis PPE
Contact with exposed employees.
COP 35.0
water Ground • Train employees on safe handling of
Trip and fall contamination chemical and curing works
Biological • Task must be carried out under close COP 36.0
hazard monitoring and supervision.
Collection of • Ensure rubber gloves and rubber boot
water shall be used.
• TBT shall be conducted.
• Water collection shall be clear from
ground.
• Reduce time of exposure to water.
• Rotate workers to reduce work rate.
Applicable Legal
R/ Affected R/ Proposed controls R/
Activity Hazard Risk Existing controls L S Responsibility L S and other
NR group R Measures R
requirement
• Proper housekeeping and cleaning shall
be maintained.
• Curing hoses/equipment shall be
maintained.
• Curing hoses shall be properly arranged
• Ensure proper connection of water
hoses.
• Water hoses shall be protected to avoid
any damage.
• Adequate PPEs are used such as; chemical
gloves, safety glass, musk, etc.
• Comply with 5 point PPE
chemical OSHAD SF
hazards • Task must be carried out under close
monitoring and supervision.
• proper ventilation COP 2.0
Rough or sharp
• Comply with casting procedure and proper
surfaces
handling of concrete and HAZMAT. COP 3.0
• Select appropriate working platform during
Manual Skin Irritation
concrete finishing/repairs
Finishes and handling COP 14.O
• If by motorized equipment, only trained and PM/Supervisor/F
protection R Cut/Bruise A,B,C,D 3 4 12 14 4
authorized person can operate the oreman/HSE
Inadequate equipment.
Fatigue/Body pain COP 35.0
supervision • Avoid concrete spillage.
• HSE induction must be conducted for
Working at exposed employees. COP 36.0
height • Train employees on proper handling
• Regular TBT / HSE briefing
• Train employees on heat tress awareness
Applicable Legal
R/ Affected R/ Proposed controls R/
Activity Hazard Risk Existing controls L S Responsibility L S and other
NR group R Measures R
requirement
• Wear mandatory PPE and rubber boots,
rubber gloves and safety glasses when
handling concrete.
• Comply with 5 point PPE
• Heat stress monitoring shall be
maintained on site
• Work rotation must be followed as
per the Heat stress Index
• Heavy works shall be scheduled
during the cooler part of the day
• Heat stress awareness training
shall be provided
• Close supervision shall be available
at all time OSHAD SF
Working in Wind storm, Weather forecast
Fever/Illness • Appropriate mandatory PPE’s that COP 2.0
adverse High Humidity, information shall PM / CM / Engineer
A, C suits the weather shall be used by 3 4 12 14 4 CoP 8.0
weather Rainfall, be communicated / Foreman / HSE
Dehydration all workers on site CoP 11.0
condition Extreme Cold on daily basis
• Welfare facilities like rest shelters, CoP 53.0
washrooms, cold drinking water
shall be made available on site
• Provide ORS to workers.
• All outside works shall be
suspended during high wind and
• No lifting activities to be
performed during high wind
• 5-point PPE rule shall be complied
with by all operatives
Appendix -E:
Third party approval
requirements,
APPENDIX
Employer PMC Engineer/Consultant Contractor
Appendix -F:
Shop drawings/
sketches/certificates
etc. as required.
APPENDIX
Employer PMC Consultant Contractor
Material Sample Method Statement As Built Plans / Procedure Others (Please Specify Doc Type)
The Contractor certifies that the Technical data submitted herewith is in compliance with the Contract drawings and specifications unless specifically
noted / highlighted here or on the attached documents.
Code A -Approved
R e fe r to th e c o m m e n ts o n th e d ra w in g .
Code B - Approved with
Comments
Code D - Rejected
Reviewed By Date
Corrections or comments made relative to submittals during this review do not relieve the contractor from compliance with the Contract requirements and
specifications. Any changes from previous revisions of the submittal or contract documents, unless specifically highlighted are not necessarily reveiwed
and hence not necessarily approved.
Received Date
Drawing Lists
Date Friday, August 25, 2023
SR.No Title Drawing No Revision Copies Status Remark
Proposed Combined Utility Ducts Layout &
1
Schedules at Road HW-CAW-10 & HW-CBL-01
IP1-02-002-00-11-RW-AGP-SD-000010 00 B
Proposed Combined Utility Ducts Layout &
2
Schedules at Road HW-CAW-10 & HW-CBL-01
IP1-02-002-00-11-RW-AGP-SD-000011 00 B
Proposed Combined Utility Ducts Schedules at
3
Road HW-CAW-10 & HW-CBL-01
IP1-02-002-00-11-RW-AGP-SD-000012 00 C
Proposed Combined Utility Ducts Schedules at
4
Road HW-CAW-10 & HW-CBL-01
IP1-02-002-00-11-RW-AGP-SD-000013 00 C
Proposed Combined Utility Ducts Schedules at
5
Road HW-CAW-10 & HW-CBL-01
IP1-02-002-00-11-RW-AGP-SD-000014 00 C
Proposed Combined Utility Ducts Schedules at
6
Road HW-CAW-10 & HW-CBL-01
IP1-02-002-00-11-RW-AGP-SD-000015 00 C
KEY PLAN
GSM
BIOTOPIA
LANDSCAPE
MAIN
HOUSE /
POOL CHECK-IN
BEACH
LANDSCAPE
SPECIAL
F&B
LUXURY
WELLNESS
RESORT
SPA
01
GSM
GYM
GSM
02 BUS
03 04
STOP
ﻣﻮﻗﻒ
ﺣﺎﻓﻼﺕ
BUS SHELTER
DSS 07
ﺣﺎﻓﻼﺕ
ﻣﻮﻗﻒ
STM. WATER
BUS
SHELTER
OUTFALL
STOP
BUS
EQUESTRIAN
05 06 07 EQUESTRIAN
08 DSS-08
GSM
09 10 11 12
CLUB (VIP)
CENTER
DSS 11
Noise Buffer /
Event Staging
& Parking
13 14 16 18 19
LAND SAILING
15 17
STOP
BUS
BUS SHELTER
ﻣﻮﻗﻒ
CENTER
ﺣﺎﻓﻼﺕ
SHELTER
ﻣﻮﻗﻒ
BUS
WELCOME
STOP
BUS
CENTER PLANETARIUM
Parking BUS
STOP
BUS SHELTER
ﻣﻮﻗﻒ
ﺣﺎﻓﻼﺕ
ﺣﺎﻓﻼﺕ
ﻣﻮﻗﻒ
STOP
SHELTER
BUS
BUS
BUS
STOP
GAS
ﺣﺎﻓﻼﺕ
PR GSM
EQUEST.
BUSINESS WHITE
HOUSEGUARD
20 21 22 23 24 26 27
WATER
28
-3
SUBSTATION
25
PUMP
ROOM
FIRE
CLUB
CENTER
BEACH
ﺣﺎﻓﻼﺕ
ﻣﻮﻗﻒ
WATER
PARKLAND ZOO
PARKING
TANK FIRE
BUS SHELTER
STOP
TANK
BUS
POTABLE
WATER
868 SPACES
WATER
POTABLE
IRRIGATION
ROOM
SHOOTING /
AND
PUMP
TANK
312 Spaces
WATER
DSS 04
IRRIGATION
Bus / Coach
ARCHERY
YARD
ROOM SERVICE
Parking
TANK
STATION
SWITCH
WATER
GSM
LIFTING
&WASTE
ELECTRICAL
BOH
PLAZA
SOCIAL CENTER
ARRIVAL
HOUSE
WINCH
Taxi
YARD
RESISTOR
BRAKING
Staging Area
GOLF
TREATMENT
CLUB
WATER
BEACH
TANKS
ROAD
SERVICE
POLYMER
ROOM
BASIN
STATION
PUMP WAVE
BASIN
WELCOME
WAVE
CENTER 424 Spaces
BASIN
WAVE
DSS 05
MOBILITY
LV CABLE TRENCH
MV CABLE TRENCH LV SWITCH BOARDE2
TRM
TR
Y
B
MV CABLE TRENCH
7.50
2.90
BUS
SHELTER
STOP
MV CABLE TRENCH 4.50
R
N
FIRE ALARM
PANEL PANEL
RTU BUS
9.10
HUB
ﻣﻮﻗﻒ
ﺣﺎﻓﻼﺕ
ROAD
SERVICE
BUNDLE
WAVE
35
YARD
CHILLER
34
&
-1
SUBSTATION
31 36 37
BASIN
29 30 32 33
WAVE
BUS SHELTER
ﺣﺎﻓﻼﺕ
ﻣﻮﻗﻒ
STOP
ﺣﺎﻓﻼﺕ
ﻣﻮﻗﻒ
Noise Buffer /
BUS
STOP
BUS
GUARD
HOUSE
BUS SHELTER
ﺣﺎﻓﻼﺕ
ﻣﻮﻗﻒ
STOP
BUS
GATE
BUS SHELTER
ENTRY
MAIN
ROAD FENCING / COMBAT
VELODROME
SERVICE
BUNDLE
DSS 09
WAVE
236 Spaces
Stairs
Water
Stairs
Feature
CLUB
SURF
BASIN
WAVE
PLAZA
ARRIVAL
GSM
GSM
HOTEL
1- C o n tra c to r m u s t s u b m it C la s h a n a ly s is w ith 3D m o d e l / B IM .
ROAD
PARKING
SERVICE
VIP
AND
CLUB
BUNDLE
SURF
153 SPACES
WAVE
BASIN
WAVE
YARD
BRAKING
RESISTOR
ROAD
INTAKE
STATION
PUMP
SERVICE
HOUSE
DSS 12
HIGH
WINCH
RAMP
44 45
BOAT
38 40 46
TANK
WATER
39 41 47 48
HOLDING
WASTE
43
BUS
STOP
BUS
PERFORMANCE
SHELTER
42
EXTREME
ﻣﻮﻗﻒ
ﺣﺎﻓﻼﺕ
GSM
IRRIGATION STM. WATER
TANK
CENTER
-5
OUTFALL
SUBSTATION
HUB Utility-RO-Plant
OVERFLOW / FM
PLOT
EVENT PARKING GSM
MOBILITY
HUB GSM
ﺣﺎﻓﻼﺕ
ﻣﻮﻗﻒ
DSS 01
STOP
BUS SHELTER
BUS
FM
PLOT
BRIDGE-2 CIVIL
DEFENSE
SUSTAINABILITY 28 Spaces
TRANSCO
RO
LEARNING
SCHOOL POLICE
PARKING
STATION
BUS
STOP
258 SPACES
SHELTER
ﺣﺎﻓﻼﺕ
ﻣﻮﻗﻒ
ﻣﻮﻗﻒ
BUS
BUS SHELTER
ﺣﺎﻓﻼﺕ
58
STOP
BUS
BRIDGE-1
49 50 SPORTS VILLAGE
51 52 53 SPORTS
54 55 56 57 PETROL
59
BUS
SHELTER
BUS
EXPANSION 1b
STOP
MCC
ﻣﻮﻗﻒ
ﺣﺎﻓﻼﺕ
PARKING POP
GSM
MY
F
F
1 2 3 1 2 3 4 5 6 7 8 10
9 11 12 13 14 15 16 17 18 20
19 21 22 23 24 26
25 27 28 29 30
MY WHOOSH
138 137 136 135 134133 132 131 130 129 128127 126 125 124 123 122 121 120 119 118 117116 115 114 113 112 111110
WHOOSH
109
31
32
108
33 107
35 105
36 196 195 194 193 192191 190 189 188 187 186185 184 183 182 181 180 179 178 177 176 175174 173 172 171 170 169168 104
103
37
38
102
MY
G
SPORTS
39 101
321 SPORTS
40 100
MY PARKIN
PARKIN
41 225 224 223 222
221 220 219 218 217 215
216 214 213 212 211 210 209 208 207 206 204
205 203 202 201 200 199
198 197 99
DSS 03
42 98
WHOOSH
97
VILLAGE
43
44 245 244 243 242 241 240239 238 237 236 235 234233 232 231 230 229228 227 226 96
(EXISTING)
45
46 90 91 93
92
94 95
WHOOSH G
EXPANSION 2
47 86 87 8889
49
50 7879 80 81
51 75 76 77 STORAGE
52 71 72 73
74
DSS 06
53
54 63 6465 66
67 68 6970
SPORTS
55
56 5960 61 62
57 58
PLOT 3
FE
SPORTS
PLOT 1
67
SUSTAINABILITY
68
CYCLE
60 61 62 63 64 65 66
GSM
CYCLE CENTER PLOT 4 MEGA STORE
WOLFI'S
M70505
CENTER M70505
3 STAR
3 STAR HOTEL
STOP
ﺣﺎﻓﻼﺕ
BUS
ﻣﻮﻗﻒ
LIMIT OF WORKS
HOTEL
EN Y
STOP BUS
ﻣﻮﻗﻒ
ﺣﺎﻓﻼﺕ
HERITAGE
RD WA
BUS SHELTER
BUS SHELTER
STOP
ﺣﺎﻓﻼﺕ
BUS
ﻣﻮﻗﻒ
TRAIL
GA TE
DSS 10
GA
MOBILITY
HUB
WORK AREA
3- P u ll b o x lo c a tio n s a n d c o v e r L e v e ls s h o u ld b e fu lly c o o rd in a te d w ith th e ro a d a n d la n d s c a p e fin is h in g re q u ire m e n ts .
FM
SPORTS
MOBILITY SUPERSTORE PLOT
DIVING/AQUATIC HUB 107 SPACES
ﺣﺎﻓﻼﺕ
ﻣﻮﻗﻒ
STOP
BUS
FM
BUS SHELTER
CENTER 20 SPACES
PLOT
LEARNING
170 Spaces
AREA 15
ON
E-GAMING
EXHIBITI
HALL
DRONE R.C.
69 GSM
70 71 CINEMA
72
MARSANA
EXTENSION OLI OLI
4 - P ro p o s e d c o n c re te e n c a s e m e n t la y o u t s h a ll b e fu lly c o o rd in a te d w ith o th e r s e rv ic e s .
Plaza ROLLER
RINK
MOBILITY
HUB
DSS 02
GSM
HW-CA
NOTES
1. ALL LEVELS ARE BASED ON NADD (NEW ABU DHABI DATUM)
AND COORDINATES RELATED TO UTM_ZONE_40N, DATUM : WGS_1984.
2. ALL DIMENSIONS ARE IN METERS, UNLESS OTHERWISE STATED.
1 V0
LEGEND
HW-ACR 07
PROPOSED MCC DUCT
PROPOSED WATER DUCT
PROPOSED IRRIGATION DUCT
PROPOSED TELEPHONE DUCT
PROPOSED TCS DUCT
PROPOSED STREET LIGHT DUCT
PROPOSED ROAD
PROP.TELEPHONE CHAMBER
PROPOSED ROAD CENTER LINE
MC-03 ED-04 DOME BOUNDARY
IR-7A IR-7B
TL-01 ED-03 TL-07 TL-09C
TL-06
IR-06 IR-14
WD-01 IR-7C IR-7D
MC-01 TL-04 WD-04 WD-05 WD-08C
MC-04 ED-07 SL-04 TL-08 ED-15
HW-CAV 09 SL-01 IR-01
MC-08 ED-11 IR-08 IR-15
ED-08 IR-13
SL-03 MC-09 ED-12
HW-CAV 10 IR-11
MC-06 MC-10 IN028
TD-16 TD-14
TD-13
TD-15 TD-12
TD-05 TD-07
TD-04 TD-06
TD-08
IR-02 MC-05 TL-03 MC-11
MC-02 ED-05 MC-07
MC-13 MC-12 DRAWING REFERENCE:
TL-02 IR-03
WD-02 IR-04 ED-09 SL-05 SL-07 ED-13 IR-12
ED-01 IN022
ED-02 IR-05 SL-06 IR-10
SL-02 ED-14
ED-06 ED-10 WD-07 IR-09 SP REV. DATE DRAWING NO.
MC-14
TL-05 TL-09 WD-08A REVISION HISTORY:
WD-03 WD-06 WD-08
IR-07
IR-44
IN021 TL-09A
CM020
IN024
HW-CAV 01
DWG. STATUS:
HW-CST 07
SHOP DRAWING
CLIENT:
MODON PROPERTIES
ABU DHABI
UAE
P.O. BOX: 62221
PMC:
CONSULTANT:
ABU DHABI
UAE
P.O.BOX: 5498
TEL: +971 2 6142416
CONTRACTOR:
GATEWAY
ENGINEER DOCUMENT REVIEW
Document is reviewed for compliance to design concept and is not PROJECT TITLE:
checked for accuracy or suitability of purpose. The review does not
relieve the contractor from his contractual obligations, nor does it AL HUDAYRIAT ISLAND WEST
authorize changes in the contract sum/period
INFRASTRUCTURE
A - Approved
B - Approved with comments CONTRACT NO: JOB NO
C - Revise & Resubmit 269-002
D - Rejected
DRAWING TITLE: DOME PLOT ACCESS
E - Review not required
Signature & Stamp: Date: 31-08-2023 PROPOSED COMBINED UTILITY DUCTS
LAYOUT & SCHEDULES AT ROAD
HW-CAW-10 & HW-CBL-01
DRAWN BY SK / HWD DATE 25-08-23
CHECKED BY Eng.AMJAD SCALE @ A3 1:1000
APPROVED BY Eng.HISHAM SHEET NO. 1 OF 6
DRAWING NO. REVISION
IP1-02-002-00-11-RW-AGP-SD-000010 00
Employer PMC Consultant Contractor
Material Sample Method Statement As Built Plans / Procedure Others (Please Specify Doc Type)
The Contractor certifies that the Technical data submitted herewith is in compliance with the Contract drawings and specifications unless specifically
noted / highlighted here or on the attached documents.
Code A -Approved
Refer to the comments on drawing.
Code B - Approved with
Comments
0 2 /0 8 /2 0 2 3
Code C - Revise and Resubmit
Code D - Rejected
Reviewed By Date
Corrections or comments made relative to submittals during this review do not relieve the contractor from compliance with the Contract requirements and
specifications. Any changes from previous revisions of the submittal or contract documents, unless specifically highlighted are not necessarily reveiwed
and hence not necessarily approved.
Received Date
Drawing Lists
Date Tuesday, August 1, 2023
SR.No Title Drawing No Revision Copies Status Remark
Standard Details Concrete Duct for Irrigation and
1 Recycle Water Pipe Crossing the Road and Villa IP1-02-002-00-11-IR-AGP-SD-000027 00 B
Entrance
DUCT :
ROAD CROSSING 1Wx300Ø (FD)
DUCT (RD) 1Wx150Ø FUTURE CROSSING DUCT
FRL PROTECTION SLAB 2Wx150Ø (FD)
PLOT ENTRY (PS) FUTURE CROSSING DUCT
TYPICAL PLAN OF FUTURE CROSSING DUCT FOR FUTURE SECONDARY INFRA-2 BOUNDARY IRRIGATION RISER (R)
IRRIGATION NETWORK & FUTURE TERTIARY CROSSING ROAD IRRIGATION CORRIDOR PROPOSED CABLE PULL
BOX
(NTS)
ABBREVIATIONS:
uPVC- UNPLASTICISED-POLYVINYL FRL- FINISHED ROAD LEVEL
DETAIL '1' CHLORIDE GRP- GLASS REINFORCED PIPES
FD-FUTURE DUCT ROAD CROSSING PS- PROTECTION SLAB
HDPE- HIGH DENSITY POLYETHYLENE IR- IRRIGATION NETWORK
Ø- DIAMETER RW- RECYCLE WATER NETWORK
PN- NOMINAL PRESSURE SMP- SECTOR MEASURING POINT
OD- OUTSIDE DIAMETER AV- AIR RELEASE VALVE
DN- NOMINAL DIAMETER WO- WASHOUT
ROW-RIGHT OF WAY FM- FLOW METER
IPF- INTEGRAL PUDDLE FLANGE CV- CONTROL VALVE
L.O.C- LIMIT OF CONTRACT IV- ISOLATION VALVE
ADM- ABU DHABI CITY MUNICIPALITY IL- INVERT LEVEL
MAIN RECYCLE WATER NETWORK CROSSING PLOT ENTRY ADDC-ABU DHABI DISTRIBUTION SDR- STANDARD DIMENSION RATIO
COMPANY E- EASTING N- NORTHING
CROSS SECTIONAL DETAILS OF PROTECTION SLAB
UNDER PLOT ENTRANCE (NTS) REFERENCE ADM DRAWING & DOCUMENTS:
DETAIL F
FRL NTS
DRAWING REFERENCE:
NTS
TYPICAL SECTION OF CONCRETE ENCASED DUCT
FOR MAIN IRRIGATIO NETWORK CROSSING ROAD
REV. DATE DESCRIPTION BY CHK. APPD.
DWG. STATUS:
SHOP DRAWING
CLIENT:
PMC:
1 . A ll the work s to b e carried ou t in comp liance with the latest v ersion of standards and Document is reviewed for compliance to design
AL HUDAYRIYAT ISLAND PDA
concept and is not checked for accuracy or suitability
sp ecifications of au thorities su ch as A D D C , A D Q C C , and all A b u D hab i related A u thorities. of purpose. The review does not relieve the INFRASTRUCTURE - INFRA 2
2 . S hop drawings to b e ex tracted from the coordinated L O D 4 0 0 M odel . C ontractor to contractor from his contractual obligations, nor does
ensu re Rou tings, T aggings, E lev ations, and C oordinates are matching with the cu rrent it authorize changes in the contract sum/period CONTRACT NO:
JOB NO.269
A - Approved 001013-MOD-ALG-LOA-BR-663
rev ised IF C drawings. B - Approved with comments
3 . C hamb er cov er ty p e and lev el shall b e in-line with the req u irements of master p lan. C - Revise & Resubmit DRAWING TITLE:
4 . A p p rov al is su b ject to fu lfillment of P IL C omments/ and to comp liance with all C ontract TABLE 'B' PROTECTION SLAB DETAILS D - Rejected STANDARD DETAILS CONCRETE DUCT
req u irements/A u thority sp ecifications, and shall in no-way reliev e the contractor from any of E - Review not required FOR IRRIGATION & RECYCLE WATER PIPE
the ob ligations, du ties/resp onsib ilities u nder the C ontract. DETAIL C Signature & Stamp: Date:03/08/2023 CROSSING THE ROAD & VILLA ENTRANCE
NTS DRAWN BY SNH DATE 01-08-2023
TYPICAL SECTION OF DIRECT BURIED MAIN IRRIGATION NETWORK CHECKED BY Eng. NAZAR SCALE @ A3 NTS
APPENDIX
Quality - Risk Register
Past
Prior to Mitigation Action After Mitigation Action
Sr. Occurrence Effect Residual
Description of risk Risk Type Risk Rating Mitigation Action Responsibility Remarks
No Severity *LT / MT / ST Risk
Yes / No Probability Severity Rating Probability
Rating
A QUALITY RISKS
Work started at site prior to approval of Follow & obtain approval for materials/
External/ Project Based
A2 documents (Material submittal, drawings, Yes Moderate Likely 9 MT documents prior to use the material or Minor Unlikely 4
Internal Management
Method Statement etc) start the activity at site.