Professional Documents
Culture Documents
STD-00-000000-QA-5733-00057-0000
(PCAP Control ID # NA)
(Criticality Rating CR # 4)
00 Revision History
01 Holds List
NIL
REFERENCES
CONDITIONS
1 General
Approved Drawings or
Approval of Drawings Standard Client Civil Supervisor/
1.1 Verify if Drawings are approved for Construction All Drawings - H H R
Drawing. (Contractor QC Inspector
Scope of Work)
Every area to be Civil Supervisor/ Closed out RFI
1.2 SP-1279 Stable Ground Condition H M M
Nature of Ground excavated QC Inspector
Civil Supervisor/
Closed out RFI
1.3 SP-1279 Manual / Mechanical As per excavation Permit Every Permit QC Inspector H M M
Method of Excavation
Civil Supervisor/
No potential Hazardous identified in Hazard Closed out RFI
1.4 Hazard Analysis PR-1172 Every Permit QC Inspector H M M
Register as per authorized Work Permit
Checking for underground Underground Services/ Existing Services by Cable Civil Supervisor/
2.1 SP-1279 All Excavation H H W
existing services. (If any) Detector or GPR - Ground penetrating Radar. QC Inspector
Civil Supervisor/
3.5 Dimension of Excavation Approved Drawings Dimensions as per Drawings All Excavation Report H W M
QC Inspector
Bottom & Faces shall be properly trimmed and Permit Holder or
Report
3.6 Formation Level SP-1279 cleared of all loose material and foreign matter All Excavation Civil Supervisor/ H W W
-Approval from PDO QC Inspector
Soft soil to be removed until solid formation, Permit Holder or
Soft Area & Unsound
3.7 SP-1279 refilled and Compacted with approved material All Excavation Civil Supervisor/ Report H M M
Ground
from PDO QC Inspector
4 Spoil
Soil heaps shall be kept minimum 1M away from
the edge of excavation
Permit Holder or
-Different class of excavated material required for Closed out RFI
4.1 Spoil SP-1279 All Excavation Civil Supervisor/ H W M
backfilling or landscaping shall be kept separately
QC Inspector
excess soil shall be carted away to the location
approved by PDO.
5 Trench Works
All Trenches shall be free from rocks, stones, tree
roots or other harmful matter.
Excavation should be made with vertical sides in
compact and cohesive soil. Construction
Trench Excavation SP-1279 Where trench excavation is in loose sand, a Engineer /
5.1 All Excavation H H W
suitable batter shall be formed with approval. QC Inspector
Excavated material shall be kept at least one
meter away from the edge of the trench
excavation. Fill material shall not be placed on
services until the service is inspected & approved.
Construction
SP-1279 Dimensions of the trenches should be as
5.2 Dimensions of the trenches All Excavation Engineer / H H W
per approved Drawings.
QC Inspector
Material Approval
Site Engineer/
Source Approval from PDO MSE following Sheet Third Party
Approval of source (borrow Supervisor/
5.3 SP-1279 concurrence from PDO Site Management. All Sources (Borrow pit) Soil Analysis test H H R
pit) for backfill materials QC Inspector
Sources shall be clearly identified. report landmark
approved by PDO
One complete analysis
Soil Test Certificate,
on every: -5000 m³ of
Site Engineer/ Material / Landmark
SP-1279 fill-2000 m³ of formation
Ensuring backfill material is Supervisor / Approval Sheet and
5.4 Conformance to specification. in cutting, from top 300 H H W
offered for soil analysis test QC Inspector Third-Party soil
BS:1377 mm below formation
Analysis test
level.
Change of material.
Free from deleterious materials like rocks,
5.5 Received Material SP-1279 Lot wise QC Inspector Report H H M
concrete rubbles, roots, loose organic matters etc.
Shall be clean and free from organic matter, waste QC Inspector Water Analysis
5.6 Water Analysis SP-1279 Random H W M
material and other harmful substances. Report
Site Engineer/
Approved or Standard Report
6.3 Elevation As per Drawing Final Layer Supervisor / H W M
Drawings
QC Inspector
7 Termite Protection
SP-1279
Anti-Termite Treatment (if Approval of material from PDO. Material Approval
7.1 Manufacturer’s All Anti-termite materials QC Inspector H H M
applicable) Mixing ratio: as per Manufacturer’s Instruction. Sheet
Instruction
- Application/ Treatment shall be as per
Manufacturer’s Instruction.
- Soil under slabs at plinth level.
SP-1279
- Junction of wall and floor. All Anti-termite QC Inspector
7.2 Application of Anti-termite Manufacturer’s Method Statement H H M
- Critical areas such as soil under piers, floor applications
Instruction
drains etc.
- Soil along external perimeter of buildings to a
depth of 300mm.
8 Final Document Hand-Over
All Plan Completion QC Inspector or Plan Completion
8.1 Plan Completion Record - Plan Completion record signed off H H R
Records QA Engineer Record