Professional Documents
Culture Documents
RISK ASSESSMENT
CCTV INSPECTION SURVEY H&S Department
Rev.00
Date: 20 Sept. 2020
PROJECT:
20-09-20
00 For Approval Velosi
CLIENT:
DOCUMENT TITLE:
RISK ASSESSMENT FOR CCTV INSPECTION SURVEY
DOCUMENT NO.
Rev Page
AV-PLR-RA-00 0 1 of 22
Check that all foreseeable risks to health, safety and the environment have been assessed via a structured risk assessment procedure:
(a) Process been identified i.e. are all the specific hazards identified? X
Check that adequate health, safety and environment arrangements have been specified in the Method Statement:
(d) Has information, instruction and training been given due regard? X
(e) Are emergency arrangements detailed inc. rescue from height / confined space etc? X
Check that the Method Statement is compatible with the CPP & IEMP and addresses the following:
(a) Are emergency plans (including fire and environmental emergency) compatible? X
(b) Are measures for site security, storage and waste management as required? X
(g) If Temporary Works are included, is there reference TW Process (Design, Approval& Permits?) X
(h) Do these steps cover all the activity from start to finish? X
(i) Is plant and equipment needed for the activity clearly detailed? X
(j) If lifting operations are included, is reference made to the Lifting Plan & Permit To Lift? N/A
Check that the Method Statement is compatible with the work of other contractors:
5. Are there any specific hazards required e.g. requirements for noise, COSHH, manual handling, welfare
(a) X
etc.
If there are specific hazards such as COSHH, manual handling, noise, vibration etc. Are there separate
(b) X
and suitable assessments?
Check that all Permits below have been identified as hold points stating that the permits must be in place before that activity can
commence
PPE
TYPE
PVC Rubber
Face Visor Muff Dry / Safety Jacket Fuel / Oil – Nitrile Safety
REF
If a hazard
arises within
the manhole or
sewer,
personnel in
both will
immediately
exit and
contact the
Site
Supervisor.
The Site
Supervisor will
re-evaluate the
space to
determine the
appropriate
course of
action.
If the alarm
If self-rescue is
not possible
for the
Manhole
Worker or the
Bottom Man,
one of the
rescue team
will don Full
Breathing
Apparatus,
enter the
manhole and
attempt to
retrieve the
entrant via
connecting the
If self-rescue is
not possible
for the entrant
to the sewer,
both bottom
men will enter
the sewer at
both the upper
and lower
manholes
(they are
15. All site works Slips. Trips & Falls 3 3 9 Good housekeeping and suitable 3 1 3
lighting
16. All site works Manual Handling 4 4 16 Mechanical lifting aids to be used where 4 2 8
possible. Maximum weight for single
person lift to be 25kg. Items heavier than
this or longer than 2m to be carried by at
least 2 operatives. Operatives to be trained
in manual handling
17. Working at Fall from Heights, Strike 5 3 15 Secure Barriered and Signed Exclusion 5 1 5
Height by falling object Zone: Placed around the base of the
access equipment to prevent unauthorised
entry into the area below the work site.
Areas Beneath Work Areas: Where
equipment or materials could fall barriers,
nets or other equipment to protect persons
underneath or prevent persons accessing
hazardous areas will be used. Access:
shall be made in reference to the
applicable Safe System of Work. Where
work is undertaken within 2 metres of
Prepared By: Reviewed By: Approved By:
Raja Krishnasamy GLENNIS Mark Thomas Loughman