Professional Documents
Culture Documents
RISK ASSESSMENT
CCTV, Cleaning, Lining H&S Department
Rev.00
Date: 20 Sept. 2020
PROJECT:
20-09-20
00 For Approval Velosi
CLIENT:
DOCUMENT TITLE:
RISK ASSESSMENT FOR CCTV, Cleaning, CIPP, UV Lining
DOCUMENT NO.
Rev Page
AV-PLR-RA- 0 1 of 22
00
Check that all foreseeable risks to health, safety and the environment have been assessed via a structured risk assessment procedure:
(a) Process been identified i.e. are all the specific hazards identified? X
2. (b) Are the persons who are at risk identified? X
(c) Have the risks been quantified i.e. High/Med/Low or 1, 2, 3 etc? X
(d) Have effective control measures been put into place? X
Check that adequate health, safety and environment arrangements have been specified in the Method Statement:
(a) Supervisor in charge of operations named? X
(b) Has a person(s) been appointed to take charge of SHE issues? X
3.
(c) Has communication with the Principal Contractor been established? X
(d) Has information, instruction and training been given due regard? X
(e) Are emergency arrangements detailed inc. rescue from height / confined space etc? X
Check that the Method Statement is compatible with the CPP & IEMP and addresses the following:
(a) Are emergency plans (including fire and environmental emergency) compatible? X
(b) Are measures for site security, storage and waste management as required? X
(c) Are Site SHE rules being given due consideration? X
(d) Has the scope/description of work been adequately identified? X
(e) Is the sequence of operations clearly detailed in logical steps? X
4.
(f) Do these steps have hold points for key requirements such as the issue of permits? X
(g) If Temporary Works are included, is there reference TW Process (Design, Approval& Permits?) X
(h) Do these steps cover all the activity from start to finish? X
(i) Is plant and equipment needed for the activity clearly detailed? X
(j) If lifting operations are included, is reference made to the Lifting Plan & Permit To Lift? X
(k) Is interface & coordination with other activities / operations covered? X
Check that the Method Statement is compatible with the work of other contractors:
5.
(a) Are there any specific hazards required e.g. requirements for noise, COSHH, manual handling, welfare etc. X
If there are specific hazards such as COSHH, manual handling, noise, vibration etc. Are there separate and
(b) X
suitable assessments?
Check that all Permits below have been identified as hold points stating that the permits must be in place before that activity can
commence
(a) Permit to Dig X
(b) Confined Space Permit X
6. (c) Temporary Works Permit to Load / Proceed X
(d) Hot work Permit X
(e) Permit to Work Adjacent or Under H/V Overhead Cables X
(f) Permit to work on Electrical Equipment X
(g) Other permits (e.g. access permit from client), licences or consents X
Use the answers to the above questions to determine if further investigation will be required. On completion of the evaluation, the form
MUST then be appended to the Method Statement. This form MUST be signed by both parties: Costain and the subcontractor.
PVC Rubber
EN352Part 1/3
Hard Hat Face Visor Dry / EN471 Fuel / Oil – Nitrile EN 345
REF
Muff
EN397 EN166.3.9.B waterproof Class 2 /3 General Handling 200 joules
if >80dBA
EN388
1 Poor hygiene Leptospirosis / weils disease 4 4 16 Good hygiene standards – wash hands prior to 4 1 4
eating/ drinking etc avoid contact with
face/mouth during works.
Food and drink only to be consumed in
designated welfare areas.
Smoking only permitted in designated areas.
Waste food to be disposed of in designated
bins. Pest control to carry out regular
inspections.
All Cuts/abrasions open wounds to be covered
with water resistant plasters before entry
2 Site Plant & Exhaust Fumes from Plant & 5 4 20 No plant vehicles to be left switched on near 5 1 5
Vehicles Vehicles adjacent to entry hole.
Inspection Chamber
3 Materials & Plant Falls of Materials 4 4 16 Ensure all plant and materials are kept away 4 1 4
from edge of shaft
4 Manhole Cover Manual Handling 3 3 9 Frames and covers to be lifted using mechanical 3 1 3
Removal aids or lifting keys
The seal between the cover and the surround
will be broken by inserting the point of a
crowbar and moving it, if need be using a
rubber mallet.
If a small manhole joint lifting by two operatives
will be carried out using the long handled ‘keys’
and the manhole moved aside.
If a large manhole the lifting will be done using
the wheeled manhole lifter device after the
keys have engaged on the cover.
Replacement of the cover should be the reverse
of above
5 Working with Exposure to infection from 4 4 16 All staff have waterproof clothing, industrial 4 1 4
sewerage Leptospirosis / Weils Disease, gloves, face mask and disposable breathing
Tetanus, Typhoid, Hepatitis masks. Operatives change out of contaminated
B, Hepatitis C or other clothing at end of work.
Bacterium exposure. Work is carried out to avoid contamination of
clothing or skin as far as possible and
equipment and clothing is washed down after
use.
All exposed wounds or grazes are cleaned and
covered by a waterproof plaster.
Operatives wash exposed skin before eating
Hand cleanser supplied in trucks to be used.
A safe area will be designated for all PPE worn
in the sewer (decontamination area).
6. Environmental Contamination of 3 3 9 All Applus Ltd tanker trucks carrying oils, fuels 3 1 3 Public Statements
Spillage – watercourses; contamination or sewage will have the following basic Any public
Sewerage / Oil / of land / drainage; slipping emergency equipment: statements or
Resins hazards on roads Mobile phone for summoning aid. media interviews
PPE including rubber boots, WP trousers, regarding a spill
chemical resistant gloves, visibility clothing and involving a
eye protection goggles. company vehicle or
Bag of oil absorbent granules depot will be made
Spill cover for drains by the HOD or in his
Suitable shovel and liquid scraper. absence one of the
Suitable hand wash gels and wipes other Manager with
BS approved disinfectant his approval. The
Manager may
In the event of a spill incident the truck driver consult the
will contact his Divisional Manager who will company legal or
arrange suitable emergency response. H&S advice and
assistance before
The driver will attempt to prevent the spill making any
reaching the public drains or waterways using statement.
the basic emergency equipment and any sand
8. Use of generators Carbon Monoxide Poisoning 3 4 12 In one of the vans, Generator is fitted with a 3 1 3 Supervisor to ensure
in the van Quick Lift device which enables it to be lifted that generator is to be
out of the van and set away from the works lifted out of van when in
area. use. (if possible)
Generator is to be fitted with a long hose which
will take all fumes away from the works area.
Gas monitor to be used in the works area to
ensure carbon monoxide fumes are at a
minimum.
In the other vans, generator is built in to van
and fumes are filtered out through hose
connected to vehicle exhaust.
For the vans with the generator built in, carbon
monoxide monitors are fitted to each van.
Additionally all built in generators will be
ventilated with exhaust fumes directed outside
the van.
Battery Invertors to be used where possible to
Doc. No. L5-QAT-273B Rev 00 Date: 20.09.2020
L5-QAT-273B
person on site.
If a hazard
arises within
the manhole or
sewer,
personnel in
both will
immediately
exit and
contact the
Site Supervisor.
The Site
Supervisor will
re-evaluate the
space to
determine the
appropriate
course of
action.
If the alarm
from the
entrant in the
sewer is
activated, the
sewer entrant
will
immediately
exit the sewer
and the
manhole via
the procedure
in point 19
above
If the alarm
from the
worker in the
manhole (if
only manhole
work is being
carried out) is
activated the
manhole
entrant will
immediately
exit the
manhole
If the alarm
from the
Bottom man (if
there is an
entrant in the
sewer) is
activated the
manhole
entrant will
immediately
exit the
manhole. The
sewer entrant
will be
informed by
the Topman
that the alarm
of the Bottom
Man has been
activated and
the sewer
entrant will be
informed to
evacuate the
sewer also.
If at any time
there is any
questionable
action or non-
movement by
any of the
Authorized
Entrants, the
Top Man will
make a verbal
check. If there
is no response
or a
questionable
response, the
worker in the
space will be
ordered to
evacuate the
space
immediately.
If possible,
Authorized
Entrants will
initiate self-
rescue by
climbing out of
the space
Procedures using
Rescue Team (Manhole
Worker or Bottom
Man)
If self-rescue is
not possible for
the Manhole
Worker or the
Bottom Man,
one of the
rescue team
will don Full
Breathing
Apparatus,
enter the
manhole and
attempt to
retrieve the
entrant via
connecting the
retrieval line to
his harness.
The entrant
will then be
winched to
ground level by
the Topman.
If self-rescue is
via the
retrieval line,
another 2 men
will enter the
sewer via both
the upstream
and
downstream
manholes,
again wearing
full BA Kits and
being lowered
by the Topmen
(if lowering via
the winch is
applicable)
The two men
(one of who
will have a
stretcher) will
enter the
sewer to the
point that the
original sewer
entrant is.
He will be lifted
and strapped
to the stretcher
with the four
men (space
permitting)
lifting / pushing
him to the
closest
manhole.
Once in the
manhole, he
will be
connected to
the retrieval
line and
winched to
ground by the
Topman.
Emergency
services will
have already
been called by
the Site
Supervisor
when the
Topman lost
communication
with the sewer
entrant.
If any of the
entrants are
disabled due to
falling or
impact, he will
not be
removed from
the confined
space unless
there is
immediate
danger to his
life.
In this case,
Emergency
services are
used to recover
injured man –
the Site
Supervisor will
give details of
sewer layout,
position of
injured man
and other use
of specialized
equipment if
required
11. Working in Shaft Injuries caused by falling 3 3 9 Insure lighting is used when required. 3 1 3
materials, or due to poor The Top Man will take all measures
lighting conditions necessary to ensure tools, objects or loose
materials are kept clear of the open
manhole or access and that the manhole is
protected by a barrier to prevent members
of the public or other workers from
standing too close to the shaft and
accidentally knocking items onto the
person or persons below. All tools required
will be lowered in to chamber before
operatives enter and after operatives leave.
12. 110V electric Electrocution 5 3 15 All portable electrical plant and tools to be 5 1 5
portable tools and used by trained and competent operatives.
plant Portable electrical equipment to be PAT
tested with identification tag attached. No
damaged tools / equipment to be used.
13. Night Working Exceeding consented noise 3 3 9 Portable task lighting shall be provided. If work 3 1 3
requirements. Sprains. progresses into the evening
Crushing injuries. Trips and Operatives shall ensure that the task lighting is
falls. pointed away from sensitive receptors.
Doc. No. L5-QAT-273B Rev 00 Date: 20.09.2020
L5-QAT-273B
15. All site works Slips. Trips & Falls 3 3 9 Good housekeeping and suitable lighting 3 1 3
16. All site works Manual Handling 4 4 16 Mechanical lifting aids to be used where possible. 4 2 8
Maximum weight for single person lift to be 25kg.
Items heavier than this or longer than 2m to be
carried by at least 2 operatives. Operatives to be
trained in manual handling
17. Working at Height Fall from Heights, Strike by 5 3 15 Secure Barriered and Signed Exclusion Zone: Placed 5 1 5
falling object around the base of the access equipment to prevent
unauthorised entry into the area below the work
site. Areas Beneath Work Areas: Where equipment
or materials could fall barriers, nets or other
equipment to protect persons underneath or
prevent persons accessing hazardous areas will be
used. Access: shall be made in reference to the
applicable Safe System of Work. Where work is
undertaken within 2 metres of edges: edge
protection in the form of a guard rail of height not
less than 950mm shall be installed where reasonably
practicable Fall Arrest: Where edge protection is not
provided then fall arrest devices or other suitable
protection must be provided and used by persons
when inflating the Vibration; Ensure the area of the manhole in which controls;
Liner Eye injuries; the liner is to be inserted is clean and free Operatives to
Damage to Liner; of sharp edges and protrusions; constantly
Over inflation of Liner; Insert the liner into the pipe as per Method monitor air
Statement pressure in
Connect the air inflation hose to the steel liner;
packers inflation point. Ensure connection Correct PPE to
is tight. Turn on the compressor. be worn by all
Inflate the liner until the desired pressure is operatives
achieved – approximately 400 / 500 mbar. involved in the
When the curing process has been operation.
completed, the compressor can be turned
off and the hose and connection removed
form the steel packer.
21. Use of UV Damage to eyes and tissue if 3 3 9 All operatives involved in the operation of 3 1 3
Emitting exposed to UV radiation. checking the UV Lighting before it goes into
Equipment – Light the sewer should be wearing Full UV face
Train protection labelled ‘SUITABLE FOR UV
PROTECTION’ CE marked to the following
specification:
As well as eye/face protection, operatives
should be wearing protection for skin
(hands, arms, and chin.)
When checking the UV lamps are working
before putting the equipment in the sewer,
it should be carried out by one person,
wearing appropriate PPE and in the safety
of the Van. This is to ensure that other
operatives and members of the public do
not come into contact with the UV rays.
Storage procedures should be adequate for
PPE – PPE should be inspected regularly
and maintained.
Only authorised operators, trained in the
use of the UV Light Train & Light Kern
Doc. No. L5-QAT-273B Rev 00 Date: 20.09.2020
L5-QAT-273B
I confirm that I have read / have had read to me and understand this Risk Assessment:
Name Date Signature Name Date Signature
Risk Ranking
Utilising resultant risk values or scores, risk can be appropriately ranked in order to determine mitigation or process
requirements.
Severity Evaluation
1 Insignificant First aid injury, slight property damage with minimal cost that
is unlikely to impact upon works, insignificant environmental
impact contained within site
Hazard Probability
The probability or likelihood of the hazard occurring should be evaluated using the applicable table
provided below.
Probability Evaluation
Score General
1 Improbable Unlikely
2 Remote Rare
3 Occasional Irregular
4 Probable Likely
5 Frequent Regular
Score Construction Operations
1 Improbable Less than once every 10,000 cycles/similar
operations
2 Remote 1,000 to 10,000 cycles/similar operations
3 Occasional 100 to 1,000 cycles/similar operations
4 Probable 10 to 100 cycles/similar operations
5 Frequent 1 to 10 cycles/similar operations
Score Tunnelling
1 Improbable Less than one every 100,000 metres
2 Remote 10,000 to 100,000 metres
3 Occasional 1000 to 10,000 metres
4 Probable 100 to 1000 metres
5 Frequent 0 to 100 metres
Score Railway Systems
1 Improbable Less than 100 years
2 Remote 10 to 100 years
3 Occasional 1 to 10 years
4 Probable Monthly to annually
5 Frequent Daily to monthly