Professional Documents
Culture Documents
Note: All Method Statement’s MUST be reviewed & signed off by a Temporary Work Coordinator. All Method Statement that
are in Temporary Work Category A or B, MUST be signed off by Temporary Work Coordinator and Head of Engineering Dept.
1. PREPARATION - SIGN OFF (Suitable Trained/Experienced Person.)
Preparation
Position Name Date Signature
2. CHECK – SIGN OFF (Site Agent and Sub-Contractor prior to review sign off.)
Position Name Review Date Signature
APPROVED BY
Signed by Project Team Signed by Project Team
Note:
This document is controlled in soft copy. Any hard copies
seen are uncontrolled unless chopped with Red Control
Stamp.
SCOPE
This method statement covers the Unloading (Lift) Operations using 600t mobile crane
for Genset (PTU) equipment site proposed work area.
1.1 Limitations:
A. Working Hours: 7am to 5am. (Remark: Unable to conduct any lifting activities during
night shift)
Any works carried out after office hours (7pm onwards) are required to follow the
Standard operation procedure as follows:
o Monitor traffic flow (in and out movement) around the construction area to
avoid any excessive noise and road accidents;
o Ensure cleanliness on the construction site;
o Ensure no damages in common areas such as road verge, turfing, flood issue
during heavy rain etc;
o Ensure no damages on the road kerb, drainage, landscape, etc. in common
areas during construction.
B. Environmental Concern
Noise pollution control – to place noise barriers at site where required
Dust control – to regularly sprinkle water on haul roads and excavations to
mitigate dust
Oil leakage / spillage from the plant and the machineries used – to refuel the
machineries off-site
Water pumps will be used if there is heavy rainfall. The water in the trenches
done previously will be pumped out.
Notification on access main route for transportation to OSE vendor require for
their verification and acceptance.
1. REFERENCES
Drawing List
2. SUBCONTRACTOR DETAILS
Personnel Responsibilities
No Division Type of Manpower Job Function
Manage Overall Lift & Shift
Project Manager
Activities
1 Management
Project Coordinator Manage Individual Task Activities
Work Operation Lifting Supervisor Lead the Lifting Activities & Manage
all the Lifting Gears
This section describes how the project team is planning to construct the works by
detailing the relevant sequence of key steps and stages to complete the works and the
persons involved.
item.
COP 007
2.1 Checking of
ground HOLD POINT: To obtain PTW prior to
conditions & start work & PUC
Mobile Crane
Set Up at 1. Checking of ground condition, foundation or
1.
2.6 Set-Up of steel 10. Steel plates 20ft x 5ft x 24mm x 8 pieces will
plates with be placed on timber blocks to ensure
timber block levelled & smooth skidding process onto
base concrete plinth
11. Steel Plates will be unloaded from low
loader.
12. Ground condition to be checked & ensure its
compaction is able to withstand a min. of 15
Tons per sq/m.
Related Safety
Standard:
Related Safety
Transport Safety Measures:
Standard:
9. The transport must be equipped with
appropriate safety measures, such as reflective
tape, warning lights, and signs indicating the
oversized load (applicable for low loader).
10. Once low loader has reached hoisting point,
mobile crane will be used to unload the
equipments.
11. Communication: ALL communication will be
done using UHF walkie talkie dedicated
channels to avoid distraction miscommunication.
12. Riggers to used certified mobile scaffold to
access lifting points that are at height, safety
harness attached to lifeline to be secured at all
time for any activities involving WAH.
Logistics Plan:
5. Transport carrying Genset/PTU section will
enter from west side of access road.
Rigging Method:
1) Top Section of Genset to be rigged using
webbing sling using container hook.
2) Top Section, Install 2 x Spreader bar with
eyelets before rigging with webbing sling to
crane main hook. As per Vertiv Assembly
& Installation Manual Provided.
Genset Hoist:
landing.
Skidding Method A:
JUNG Revolving Skates (4 x 4
Tons) 3) Fully Assembled genset will be skidded
into final position using 4 x 4 Tons JUNG
Revolving Skates with remote control to
position into the positioning area.
The Construction Risk Assessment (CRA) describes sequentially the operational tasks
along with the associated risks and their corresponding mitigating control measures to be
implemented for the works.
Non-Hazardous Substances/Materials
All non-hazardous materials like lifting equipments will be stored within laydown
boundary and barricaded properly with signages. IF ANY, the Disposal will be dispose at
Sunway’s designated waste disposal area.
Hazardous Substances/Materials
Hazardous materials on site should be identified / labelled and kept in Chemical Storage
temporarily. Hazardous material shall then be disposed with records by authorized
agent.
Key quality control and assurance issues for lifting activity are:
FWT/ FAT Report
Any transportation prior to move into site or move out from site shall fill in Materials,
Tools & Equipment Declaration Form. This form shall sign off from related personnel
prior to approval.
a. Quality records
7 ENVIRONMENTAL PROTECTION
During this activity (lifting operations), the regular environmental control measures will
be carried out as usual, such as:
- Oil spill kit, spill tray and proper fuel oil storage in place.
Reference should be made to the Environmental Control Plans for each environmental
aspect contained in the Environmental Management Plan.
Key: Level of Significance: Level 1 An impact that could cause pollution or degradation that may have irreversible detrimental
(High Severity) effects on the environment and/or community.
Level 2 An impact that could cause pollution or degradation that may have persistent but reversible
(Medium Severity) detrimental effects on the environment and/or community.
Level 3 An impact that could cause pollution or degradation that may have short term and reversible
(Low Severity) detrimental effects on the environment and/or community.
Aspects Sources Level of Significance Mitigation Plan Responsible By
Noise and Vibrations Use of Machinery 3 - Works would be undertaken Subcontractor / Superintendent/
within normal hours (0700- Supervisor/ Foreman
1900) General Day
- No such works shall be carried
out during restricted hours
(7pm to 7am and anytime of
General Holiday)
- Proper maintenance of
equipment / plant.
- Frequently maintain the plant /
machineries to reduce the
noise generation due to
machine components / parts
fatigue.
- all vessel and PMEs must
applied with Euro 5 diesel
Air Quality Use of Machinery 3 - Minimize idling time with engine Subcontractor / Superintendent/
off Supervisor/ Foreman
- Proper maintenance of
equipment / plant.
- all vessel and PMEs must
applied with Euro 5 diesel
Waste Management Inert / Non-inert waste 3 - Maintain good housekeeping Subcontractor / Superintendent/
generated practice including the waste Supervisor/ Foreman
sorting & segregation within
working area
- Remove generated waste from
works before off-duty daily
Action(s) Complete /
Control Measures
# Task Class 1 Risks Responsible Control in Place
Person Checked by/
Image/Photo Description Pre-Work During
Signature
1 Mobilization of Machinery Traffic accident 1. Conduct Field Control Briefing – Take 5 Site Supervisor
& Equipments. during machine 2. Place banksman to control traffic
delivery 3. Pedestrian to use dedicated walkway
2 Survey Work Fell from 1. Conduct Field Control Briefing Lifting Supervisor
height/ Slip, 2. Always check on ground condition
Trip, Fall before walking on slope
3. Work in buddy system
4. Workers to use proper PPE, safety boots,
long sleeve shirt, goggle, helmet, Impact
gloves
5. Always watch out for fall hazards when
working at installation area
3 Equipment Delivery Fall from height 1. Provide safeguarding system for all Operator
(Transport) moving, rotating and hazardous
machinery parts. Site Supervisor
Loose Material 2. Locate storage and loading areas
on/in transport away from areas of frequent
pedestrian activity
3. One way in, one way out and separate
IN/OUT entry
4. Assigned trained, competent and appointed
banksman to the designated areas.
5. Appointed banksman shall stay in the sight
of the operators/drivers and maintain
continuous signaling/ communicating until
the works done.
6. Provide a safe and even surface for the
machinery moves & mobilization of
mobile scaffold
7. Machinery operator shall check the
machinery’s condition before start work.
Ensure the machinery are all equipped with
Safety Devices for Plant and Equipment.
8. Comply to Class One Practice– 005-
Vehicle and Mobile Plant Movement
5 Lifting area preparation Crane 1. Outrigger must be positioned on a flat Site Supervisor
Overturning due surface
Operator
to ground 2. Using plate or suitable materials for pads
condition to evenly distribute the load on the
ground
3. Crane to be located within radius for the
load being lifted where space, the
outrigger shall always be fully extended
4. Fully barricade around the crane with the
road barrier
5. Install the crane camera behind the
crane Ensure to prevent body injury
6. the workers and vehicle stay on the
designated access roads and do not
take shortcut road
6 Prepare rigging equipment Irregular 1. Wire rope shall be provide properly Foreman
inspection on all identified for SWL and manufacture Site Supervisor
lifting equipment 2. Inspections shall be done by authorized
personnel and by the safety department
3. Safe workload (SWL) tag shall provide
by the manufacture
4. Use only component with a known or
labeled working load limit.
9 Unloading of Equipment Expose to the 1. Provide a safeguarding system for all Site supervisor
hanging moving, rotating and hazardous Foremen
overhead heavy machinery parts. Site Safety
equipment. 2. “No Entry” warning signs positioned at Supervisor
Crane topples the working premises. Operator
Fallen object 3. No one allowed to enter the working Banksman
Overload area, unless accompanied by a
Heat stress banksman who has positively
Remarks/Comments