ENVIRONMENTAL
MANAGEMENT PLAN
Revision No 00
Prepared by :
Reviewed by :
Approved by:
Date : _______________
Signature : _______________
EHSAN
Environmental Management Plan DIV/ESH/APP 01, Rev: 1
Effective date: 27 July 2016
The Contractor has checked and confirmed with the Client on the Environmental
Impact Assessment (EIA) status.
3. If the project site is NOT subjected to EIA, compliance with the EIA
requirements is excluded from the EMP prepared.
Page 2 of 19
Environmental Management Plan DIV/ESH/APP 01, Rev: 1
Effective date: 27 July 2016
Attached
No. Attachment Descriptions Remarks
Yes No
- Canteen
- Fabrication yards
- Storage Room
Attached
No. Attachment Descriptions Remarks
Yes No
- Sanitary Facilities
- Access Road
- Security Post
- Maintenance Yard
- Stockpiled Area
- Access Road
Page 3 of 19
Environmental Management Plan DIV/ESH/APP 01, Rev: 1
Effective date: 27 July 2016
Page 4 of 19
Environmental Management Plan DIV/ESH/APP 01, Rev: 1
Effective date: 27 July 2016
Attached
No. Attachment Descriptions Remarks
Yes No
COMMENTS BY SO:
CONCLUSION
Approved By: (Please Tick)
Satisfactory
Not Satisfactory
Name : _____________________
Date : _________________________
Page 5 of 19
Environmental Management Plan DIV/ESH/APP 01, Rev: 1
Effective date: 27 July 2016
COMMENTS BY PMT:
CONCLUSION
Received By: (Please Tick)
Satisfactory
Not Satisfactory
Name : _____________________
Date : _________________________
Page 6 of 19
Environmental Management Plan DIV/ESH/APP 01, Rev: 1
Effective date: 27 July 2016
TABLE OF CONTENTS
2 Distribution List
11 Communication
12 Document Control
17 Records
19 Training
Page 7 of 19
Environmental Management Plan DIV/ESH/APP 01, Rev: 1
Effective date: 27 July 2016
Page 8 of 19
Environmental Management Plan DIV/ESH/APP 01, Rev: 1
Effective date: 27 July 2016
The master copy of the approved Environmental Management Plan is kept at the
contractor’s site office and copies of approved plan is distributed to the following:
Clients
Architect
M & E Engineer
No. 37A, Jalan Awan Hijau 1, Taman Overseas Union, 58200 Kuala Lumpur,
Quantity Surveyor
Page 9 of 19
Environmental Management Plan DIV/ESH/APP 01, Rev: 1
Effective date: 27 July 2016
Contractor
4.0 Scope
Page 10 of 19
Environmental Management Plan DIV/ESH/APP 01, Rev: 1
Effective date: 27 July 2016
Architect
M & E Engineer
No. 37A, Jalan Awan Hijau 1, Taman Overseas Union, 58200 Kuala Lumpur
Quantity Surveyor
Page 11 of 19
Environmental Management Plan DIV/ESH/APP 01, Rev: 1
Effective date: 27 July 2016
Main Contractor
The Master Work Programme and the works which are executed, completed
and maintained in the contract is briefly described and attached as
Appendix B.
5.1 The site of the proposed work is located as shown on the Environmental
Management Layout Plan (Appendix C).
Plan shall indicate the followings but not limited to (if any)
o Erosion and Sediment Control Plan (ESCP) (silt traps, wash trough, area to
be turfed, check dams, drainage system, etc). ESCP is reviewed by relevant
competent person, endorsed by Professional Engineer and approved by the
S.O., The ESCP is revised as per site progress/ condition.
o Contractors site office
o Canteen
o Fabrication yards
o Scheduled Waste Storage Area
o Skid Tank / Diesel Storage Area
o Storage Room
o Sanitary Facilities
o Access Road
o Security Post
o Quarry or blasting site
o Maintenance Yard
o Stockpiled Area
o Waste Collection Area
Page 12 of 19
Environmental Management Plan DIV/ESH/APP 01, Rev: 1
Effective date: 27 July 2016
Site surveying
Soil investigations
Resettling of existing squatters
Site clearance
Storage of diesel
Storage of schedule waste
Canteen operation
Construction of temporary access
Construction of temporary site office, canteen, fabrication yard, workers
quarters, guard house, toilet, etc
Machinery and maintenance workshop
Earthworks
Disposed of unsuitable materials
Diversion of existing stream/alteration of existing waterways
The construction of drainage main.
The Construction of Super Structures
Relocation of Existing Services/Utilities
Laying of main utilities, i.e. water, sewer, electricity, etc.
Pumping of Water from Construction Pit Construction of Site Construction
of Temporary Site Drainage.
The construction of road/roadside drainage.
Piling works.
Excavation and Construction of Foundation/Substructures Works
Rock blasting
R.C. Structure, Brickwork's and Frames, M & E Works, Ceiling & Roofing,
Plastering & Painting
Other relates activities
7.3 The progress of the action plan will be submitted to the Superintending
Officer (SO) on a monthly basis.
8.1 All contractors, sub-contractors, site personnel, visitors and other persons
are adhered to all legal and other requirements which include the
followings:
o Environmental Quality Act 1974
o EIA Approval Conditions (if applicable)
Page 13 of 19
Environmental Management Plan DIV/ESH/APP 01, Rev: 1
Effective date: 27 July 2016
8.2 The legal register including the EIA Approval Conditions is attached as
Appendix F.
11.0 Communication
Page 14 of 19
Environmental Management Plan DIV/ESH/APP 01, Rev: 1
Effective date: 27 July 2016
12.4 All amended / new drawings and old drawings are identified by stamping for
Construction and Obsolete / Superseded respectively.
12.5 One (1) set of the document / drawings is kept in SDPB Operations Office and
one (1) set is kept at project site office.
Page 15 of 19
Environmental Management Plan DIV/ESH/APP 01, Rev: 1
Effective date: 27 July 2016
15.2 The environmental inspection is carried out using the established checklist on
a weekly basis (minimum) by the contractor Environmental Officer (EO) and
Clerk of Work (COW) in charge and is verified by SO/COW. The inspection
records are accessed by SDP PMT as and when required.
15.3 For water quality monitoring, the test results of the water samples collected
by competent Field Monitoring Officers is submitted by the contractors to SO
cover the following parameters (subject to site & DOE approval conditions),
attached with a location plan showing the water collections points and
photograph of the sampling activity. Report will be reviewed, analyzed and
submitted by SO to SDP PMT for notification. Issues are highlighted by SO
especially on any violation of legal requirements.
15.4 The water sample tests (if any/identified) include parameters as per stated in
the EIA Approval conditions:
o Biochemical Oxygen Demand (BOD)
o Chemical Oxygen Demand (COD)
o Oil and grease
o PH value
o Total Suspended Solids (TSS)
o E. Coli
o Dissolved Oxygen (DO)
o Ammonical Nitrogen
o Others (as when required by Sime Darby Property Berhad / DOE)
15.5 The water sample tests for silt trap include parameters as per stated in the
EIA Approval conditions:
o Total Suspended Solids (TSS)
o Turbidity
o Others (as when required by Sime Darby Property Berhad / DOE)
15.6 Attach layout plan showing the locations of sampling. Other monitoring such
as for air, noise and other monitoring is carried out as in Appendix E
Page 16 of 19
Environmental Management Plan DIV/ESH/APP 01, Rev: 1
Effective date: 27 July 2016
Page 17 of 19
Environmental Management Plan DIV/ESH/APP 01, Rev: 1
Effective date: 27 July 2016
17.0 Records
17.1 The list of environmental records is comprised of but not limited to the
followings:-
17.2 All environmental records are kept and maintained at SDPB project site office
throughout the duration of the contract.
17.3 The project Manager and Resident Engineer will ensure the proper storage
and control of these records in their respective sections in accordance to ISO
9001 procedures.
17.4 These environmental records are kept and retained for a period of three (3)
years from the contract commencement date.
18.1 All relevant environmental matters are raised at the site meeting and the
conclusions and decisions is recorded in the minutes of meeting / progress
report.
Page 18 of 19
Environmental Management Plan DIV/ESH/APP 01, Rev: 1
Effective date: 27 July 2016
19.0 Training
19.1 All contractors ensure that their staff and workers have undergone
Environmental Awareness Training at least once prior to commencing
work.
Page 19 of 19