Project No.

: 301-22-056
Project Name: 2022 Macau-Qingdao Beer Cultural Festival Revision: -
11/3/2022
TENDER INTERVIEW QUERY NO. 01 - Hap Chung

Section A - compilation of Owner's queries Section B - to be completed by Tenderer providing clarification


Ref. Origin of Raised By Date Raised Clarification Description Response Clarification Response Response Date of Status
Query (Required By) Owner Response to (Open/
Tenderer Closed)

Part A - WDD - Construction

A-01 Tender WDD 11/3/2022 What is the benefit or advantage you have or you can provide in this particular Tenderer
- CONST project?

A-02 Tender WDD 11/3/2022 Please provide O-chart indicating the management personnel to be assigned for Tenderer
- CONST this particular project. Please also indicate the office/site ratio of each personnel.

A-03 Tender WDD 11/3/2022 Please provide a sub-contractor list indicating their scope demarcation for better Tenderer
- CONST coordination and planning due to critical construction timeline.

A-04 Tender WDD 11/3/2022 Please provide specifications or material catalogs (Furniture, lighting and Tenderer
- CONST hanging fabric) to demonstrate material allowed in your tender submission.

A-05 Tender WDD 11/3/2022 Please confirm all your tent fabric (bubbles, Marquee & small tents) and hanging Tenderer
- CONST fabric materials have passed to 3rd party laboratory fire burn test, or fire spray
treatment to be provided at construction stage. Fire certificate and report is
required to be submitted prior to event open to public.

A-06 Tender WDD 11/3/2022 Please confirm the strcutrual engineering calculations (for all type of tents Tenderer
- CONST together with add-on elements) will be provided prior to event open to public.

A-07 Tender WDD 11/3/2022 Please confirm you have allowed enough spare materials for replacement / repair Tenderer
- CONST within 24 hours in case materials out of services during event period. You will be
responsible for maintenance on rental items; any cost incurred due to
maintenance will be at your own cost.

A-08 Tender WDD 11/3/2022 Please confirm you have included a full time site supervisor and an indiviual full Tenderer
- CONST time safety supervisor on site during installation and deinstallation. Leak of
supervision might result in punishment according to the 'WDD Safety Policy
Statement & Construction Safety Procedure' (see attachment #1).

A-09 Tender WDD 11/3/2022 Contractor to provide CV of Safety personnel (qualifications, relevant past Tenderer
- CONST working experience, etc) or established procedure to select competent safety
personnel.
A-10 Tender WDD 11/3/2022 Please confirm to comply with all Government and Wynn in-house requirement Tenderer
- CONST on health code checks and verification policies or procedures. All workers are
required NAT test every two days and RAT test on a daily basis. The expense
will be on contractor own cost.

1/2 15/12/2021
Project No.: 301-22-056
Project Name: 2022 Macau-Qingdao Beer Cultural Festival Revision: -
11/3/2022
TENDER INTERVIEW QUERY NO. 01 - Hap Chung

Section A - compilation of Owner's queries Section B - to be completed by Tenderer providing clarification


Ref. Origin of Raised By Date Raised Clarification Description Response Clarification Response Response Date of Status
Query (Required By) Owner Response to (Open/
Tenderer Closed)
A-11 Tender WDD 11/3/2022 Please confirm project works shall be fully compliant with 'WDD Safety Policy Tenderer
- CONST Statement & Construction Safety Procedure' as attached

Part D - WDD - Commercial

D1 Tender WDD 11/3/2022 Please confirm that the tender submission is fully compliant with the Tender Tenderer
- Com Documents, Drawings, Specification, Conditions of Contract and tender queries.
'Schedule of rate' as submitted do not bound to limit scope inclusion / exclusions
of the contract works.

D2 Tender WDD 11/3/2022 Please confirm your understanding except the items stated that the quantity is Tenderer
- Com provisional, no adjustment of quantity will be made should the actual quantities
carried out on site be different from the quantity provided by you.

D3 Tender WDD 11/3/2022 Please confirm that the items marked as "/", "N/A", "NIL", "-", "included" or Tenderer
- Com unpriced items as submitted in the 'Schedule of Rates' are deemed to be included
elsewhere within your submitted tender, unless you have separately list the
exclusion items as a tender clarification

D4 Tender WDD 11/3/2022 Please confirm that form of contract shall be used for this project is Wynn Tenderer
- Com Resorts (Macau) S.A. Minor Works Agreement, it is a lump sum contract based
on drawings and or specification.
D5 Tender WDD 11/3/2022 Please confirm that the following payment terms:- Tenderer
- Com 100% Monthly progress payment with 10% retention to a maximum of 5%
2.5% Retention released upon completion and end of DLP respectively

D6 Tender WDD 11/3/2022 Please provide with reasons, if any, summary list of Provisional Sums / Tenderer
- Com Provisional Quantities / PC Rates Item (provide separate sheet if required)

D7 Tender WDD 11/3/2022 Please review cost for item ref. B4.2.1 (extended rental cost) Tenderer
- Com

Notes: