Darwin Jamadin
1 RTK Arifiyani 07.00 - 18.00 Topo Area Bukittinggi 3.8 Ha BTG-MAA
Imran Tomagola
Arfin
2 Total Station Irman 07.00 - 18.00 SO Monitoring Cut n Fill Jalan Tangkuban BTG-MAA
La Azwar
20/09/2023
Hoksan Bigis
3 Auto Level Alimin Amran 07.00 - 18.00 Monitoring elevasi cut and fill road ONC PT ONC & PT MMA
Ahmad Yusuf
Dafrin
Vauzan Burahim
4 Total Station 07.00 - 18.00 Topo Area Bukittinggi 1.4 Ha BTG-MAA
Salfin Malik
Ardian Abd. Manaf
Arfin
2 Total Station Irman 07.00 - 18.00 SO Monitoring Cut N Fill Jalan Tangkuban BTG-MAA
La Azwar
Hoksan Bigis
3 Auto Level Alimin Amran 07.00 - 18.00 Monitoring elevasi cut and fill road ONC PT ONC & PT MAA
21/09/2023
Ahmad Yusuf
Dafrin
Vauzan Burahim
4 Total Station 07.00 - 18.00 Topo Perimeter Barat -
Salfin Malik
Ardian Abd. Manaf
Wahyudi 07.00 - 09.00 Marking Elevasi Top Cor Box Culvet Kawasi CE Civil
5 Total Station Festerling Marking , monitoring elevasi rencana subgrade
09.00 - 18.00 FMT
parkiran lifting DCM