SITARAM ENERGY AND LOGISTICS LIMITED

12, SHAKESPEARE SARANI, KOLKATA - 700071


DAILY PROGRESS REPORT & TIME BALANCE
RIG NO: SITARAM 150-1 WELL-GND # 331 DATE : 16.01.2019
TIME HOURS
SHORT DESCRIPTION OF JOB
FROM TO ODR NODR EBDR ILM ZDR

M/S SITARAM ENERGY AND LOGISTICS LTD , KOLKATA


HEARBY PERMITTED TOCOMMENCEMENT OF WORKOVER
OPARETION AT G# 331 W.E.F 16.01.2019 AT 06.00 HRS
06.00 15.00 WITH THE APPROVAL OF COMPETENT AUTHORITY. C/OUT
PREWORKOVER CONFERENCE. RECEVED 30 M3 1.15 SP.GR
AND 20 M3 BRINE. PREPARED 160 M3 1.05 BRINE 1.05
SP.GR. BRINE. RELEASED WELL PRESSURE.

M/A AND STARTED SUBDUING WELL WITH 1.05 SP.GR.


15.00 18.00 BRINE. GOT RETURN WATER AFTER PUMPING 11.5 M3 2.00
BRINE.FURTHER SUBDUING WELL IS IN PROGRESS.

18.00 06.00 CONTINUED SUBDUING WELL WITH 1.05 SP.GR. BRINE.


OBSERVED LOSS. FURTHER WELL SUBDUE IS IN PROGRESS.

TOTAL HOURS 2.00 - - - -


Total = 2.00
REMARKS :

SIGNATURE OF ONGC REPRESENTATIVE SIGNATURE OF RIG I/C


SITARAM ENERGY AND LOGISTICS LIMITED
12, SHAKESPEARE SARANI, KOLKATA - 700071
DAILY PROGRESS REPORT & TIME BALANCE
RIG NO: SITARAM 150-1 WELL-GND # 331 DATE : 17.01.2019
TIME HOURS
SHORT DESCRIPTION OF JOB
FROM TO ODR NODR EBDR ILM ZDR

06.00 11.00 PREPARED 23 M3 HIGH VISCOUS PILL AND 130 M3 1.05


SP.GR. BRINE.

11.00 13.00 PLACED 21 M3 VISCOUS BRINE AND SQUIEEZE 7 M3. 2.00

13.00 18.00 SUBDUE AND CIRCULATION IS IN PROGRESS.

18.00 23.00 SUBDUE THE WELL. OBSERVED NO ACTIVITY.


23.00 01.00 N/DN XMT
01.00 03.00 N/UP BOP

03.00 06.00 RECIPROCATION TO STAB OUT T/H CONE IS IN PROGRESS.

TOTAL HOURS 2.00 - - - -


Total = 2.00
REMARKS :

SIGNATURE OF ONGC REPRESENTATIVE SIGNATURE OF RIG I/C


SITARAM ENERGY AND LOGISTICS LIMITED
12, SHAKESPEARE SARANI, KOLKATA - 700071
DAILY PROGRESS REPORT & TIME BALANCE
RIG NO: SITARAM 150-1 WELL-GND # 331 DATE : 18.01.2019
TIME HOURS
SHORT DESCRIPTION OF JOB
FROM TO ODR NODR EBDR ILM ZDR

06.00 11.30 AFTER RECIPROCATION STAB OUT 02 T/H CONES.

11.30 13.30 RELEASED 9-5/8" HY/PKR AFTER RECIPROCATION. P/OUT 01 2.00


SGL OF 3-1/2" EUE TBGS.
13.30 15.30 CIRCULATION

15.30 17.30 C/OUT REPAIRING OF BOP RAM. TESTED BOP AT 3500 PSI
FOUND OK.
17.30 18.00 M/A FOR INITIAL P/OUT.

18.00 06.00 STARTED INITIAL P/OUT 02 NOS SGLS + 153 NOS DBLS OF 3-
1/2" EUE TBGS. FURTHER P/OUT IS IN PROGRESS.

TOTAL HOURS 2.00 - - - -


Total = 2.00
REMARKS :

SIGNATURE OF ONGC REPRESENTATIVE SIGNATURE OF RIG I/C


SITARAM ENERGY AND LOGISTICS LIMITED
12, SHAKESPEARE SARANI, KOLKATA - 700071
DAILY PROGRESS REPORT & TIME BALANCE
RIG NO: SITARAM 150-1 WELL-GND # 331 DATE : 19.01.2019
TIME HOURS
SHORT DESCRIPTION OF JOB
FROM TO ODR NODR EBDR ILM ZDR

CONTINUED INITIAL P/OUT 02 DBLS + 02 SGLS OF 3-1/2"


EUE TBGS + 01 SGL. OF 2-7/8" EUE TBG + EX/JT + S/S+ 9-
06.00 08.00 5/8" HY/PKR + POP. INITIAL P/OUT COMPLETED. TOTAL
P/OUT 155 DBLS + 05 SGLS 0F 3-1/2" EUE TBG + 01 SGLS OF
2-7/8" EUE TBG + EX/JT + S/S +9-5/8 HY/PKR + POP.
INSTALLED RISER NIPPLE.

M/A AND R/IN O/E BB SHOE +10 SGLS OF 2-7/8" EUE TBG +
08.00 17.00 155 DBLS + 01 SGLS OF 3-1/2" EUE TBGS. ADJUSTED TBG
SHOE AT 3010 MTRS.

17.00 18.00 CIRCULATION.

C/OUT CEMENT SQUIEEZE JOB. PLACED 1.91 M3 C/SLURRY


OF AV. SP. GR. 1.75. P/OUT 01 SGL + 05 DBLS. REVERSE
18.00 23.00 WASHED. SAFETY P/OUT 02 NOS DBLS. SQUEEZED 1 M3 AT
MAXIMUM SARFACE PRESSURE 2500 PSI. WELL CLOSED
UNDER PRESSURE FOR 12 HRS. WOC 24 HRS W.E.F 2300
HRS.

23.00 06.00 WOC.

TOTAL HOURS - - - - -
Total = -
REMARKS :

SIGNATURE OF ONGC REPRESENTATIVE SIGNATURE OF RIG I/C


SITARAM ENERGY AND LOGISTICS LIMITED
12, SHAKESPEARE SARANI, KOLKATA - 700071
DAILY PROGRESS REPORT & TIME BALANCE
RIG NO: SITARAM 150-1 WELL-GND # 331 DATE : 20.01.2019
TIME HOURS
SHORT DESCRIPTION OF JOB
FROM TO ODR NODR EBDR ILM ZDR
06.00 18.00 WOC.

18.00 06.00 WOC EXTENDED BASED ON SURFACE CEMENT SAMPLE.

TOTAL HOURS - - - - -
Total = -
REMARKS :

SIGNATURE OF ONGC REPRESENTATIVE SIGNATURE OF RIG I/C


SITARAM ENERGY AND LOGISTICS LIMITED
12, SHAKESPEARE SARANI, KOLKATA - 700071
DAILY PROGRESS REPORT & TIME BALANCE
RIG NO: SITARAM 150-1 WELL-GND # 331 DATE : 21.01.2019
TIME HOURS
SHORT DESCRIPTION OF JOB
FROM TO ODR NODR EBDR ILM ZDR
06.00 09.00 WOC. TAGGED C/TOP AT 2966 MTRS.

09.00 10.00 TESTED CASING H.T. AT 2500 PSI. FOUND OK.

10.00 18.00 M/A FOR P/OUT. 150 SGLS OF 3-1/2" EUE TBGS. FURTHER
P/OUT IS IN PROGRESS

CONTINUED P/OUT 160 SGLS OF 3-1/2" EUE TBGS + 10


18.00 06.00 SGLS OF 2-7/8" EUE TBGS + BB SHOE. M/A FOR R/IN AMT.
M/UP BHA R/IN 9-5/8 CSG .AMT + 02 SGLS OF 3-1/2" DRILL
COLARS. FURTHER R/IN IS IN PROGRESS.

NOTE :- NON WORKING JOINTS ARE TOO TIGHTS.

TOTAL HOURS - - - - -
Total = -
REMARKS :

SIGNATURE OF ONGC REPRESENTATIVE SIGNATURE OF RIG I/C


SITARAM ENERGY AND LOGISTICS LIMITED
12, SHAKESPEARE SARANI, KOLKATA - 700071
DAILY PROGRESS REPORT & TIME BALANCE
RIG NO: SITARAM 150-1 WELL-GND # 331 DATE : 22.01.2019
TIME HOURS
SHORT DESCRIPTION OF JOB
FROM TO ODR NODR EBDR ILM ZDR

CONTINUED R/IN 07 SGLS OF 3-1/2" D/COLLARS. REPLACE


06.00 12.00 BOP RAM FROM 3-1/2" TO 2/78" TESTED AT 3500 PSI. OK.
FURTHER R/IN 20 SGLS 2-7/8" RHDP.

12.00 14.30 OBSERVED BREAKE PROBLEM. RECTIFIED THE SAME.

14.30 18.00 CONTINUED R/IN 70 SGLS OF 2-7/8" RHDP IS IN


POROGRESS.

CONTINUED R/IN 170 SGLS OF 2-7/8" RHDP IS IN


18.00 06.00 PROGRESS. TOTAL R/IN AMT + 09 SGLS OF 3-1/2" D/COLLAR
+ 260 SGLS OF 2-7/8" RHDP. REVERSE. CIRCULATION.

TOTAL HOURS - - - - -
Total = -
REMARKS :

SIGNATURE OF ONGC REPRESENTATIVE SIGNATURE OF RIG I/C