Professional Documents
Culture Documents
FOR
OPERATION & MAINTENA
MAINTENAN
NANCE
OF
VIBRATING EQUIPMENT
1
a) Use auxiliary transport eyes or traverses resp. provided.
Knocking on construction parts and welding of auxiliary transport
devices is not permitted.
Remove transport traverses before commissioning.
b) Mount supporting brackets, cable suspensions of spring plates resp.,
and insert springs. Maintain dimensions of TMML arrangement
drawing.
Bolt all suspension brackets tightly to their supports. Weld or bolt
spring support plates to supporting structure only after final alignment
of the equipment.
c) Fill isolation frame (if applicable) with concrete as per arrangement
drawing. Place isolation frame on springs. Align lengthwise and
across by means of leveling instrument (water or hose balance).
d) Bolt spring consoles and splash plates (if removed for transport) to
equipment.
All bolts on vibrated parts are strength grade 8.8. See table for
tightening torque.
Required
Dimensions Tightening
Torque
in Nm
M 12 84
M 16 210
M 20 410
M 24 710
M 30 1450
2
Fasten spring support plates.
In case of cable suspension tightens cables evenly.
k) Provide safety catches (ropes, brackets, cross bars, etc.) for
equipment suspended by cables, chains or bars.
Be sure that cables are not bent at tensioning points nor chafe at any
point.
Equipment or Cardan shafts are not to knock against any other part
during start-upand stoppage.
3
MAINTENANCE OF VIBRATING EQUIPMENT’S
b) Check all bolts and tighten loose bolt after the first 50 hours of
operation, then after 200 hours of operation later after 500 hours of
operation. Check fasteners subjected to heat above 200°C daily.
To cool off equipment handling hot material does not spray with water!
4
1. No change of vibrated weight, by adding e.g. screen plates, chutes,
wear plates, etc., or by increasing the plate thickness, except after
consultation with TMML.
3. If side walls are protected by skirt plates, the height of bed must not
exceed these plates so as to protect the walls. (Adjustment of the
bed by gates at the hopper outlet). Make sure that the material is
continuously fed across the entire width of the screen/feeder.
Height of fall limited to 300mm to 400mm.
5
Normal stroke 2s (double amplitude s) :
at 1500 oscillations/min-1 = 2.5 - 4.5 mm,
at 1000 oscillations/min-1 = 6 - 10 mm
at 750 oscillations / min-1 = 10 - 12 mm.
α = Angle of throw
2s = Stroke
6
9. Step-by-step adjustment of the conveying speed can be made by
changing the stroke. To that end, unbalance weights are added or
removed (see “Vibration Exciter”). There is an inter-relation between
the so-called static moment (Kg-cm) of the exciter, the weight W(kg)
of the vibrated structure, and the amplitude s (cm), due to the fact
that in a speed range above approx. 400 rpm the amplitude is
almost independent of the speed and therefore, constant.
Static moment
S= (cm)
Weight
The diagram shows the relationship between feed rate Q and amplitude 2s.
7
10. The conveying capacity increases if the deck has a downward slope
and decreases in the case of an upward slope. If inclination is too
steep (above 15°) and particularly if the equipment is short, the feed
material might slide beyond the trough after equipment is stopped.
(This is especially true if feed tends to flush. In that case, only a slight
slope is permissible and the feeder must not be too short).
The brake torque should be about equal to the starting torque of the
drive motor (approx. 2.5 times the rated torque).
12. For screens the vertical acceleration component must be too small,
since otherwise material might get stuck in the openings. Therefore,
speed control of screens is not recommended.
13. For maximum screening efficiency feed material evenly across the
entire width of the deck.
8
similar type of restriction should be placed about an individual machine at
a distance of approx. I’m, with chain, etc., but be capable of being easily
removed when work on the shutdown machine is to be carried out.
I I
a) General Remarks
Feed the material evenly across the entire width of the Screen at the
least possible height of drop.
b) Assembly
Tension the screen mat so tight that it rests firmly on the supports and
does not lift off due to the vibrations of the Screen. (Avoid over
tensioning).
Tensioning bolts or bars have to rest firmly and fully in the tensioning
folds.
c) Maintenance
Retention a newly installed screen mats after 3 hours of operation
check and tightened fasteners if required. Check after another 10
hours of operation check and tightened fasteners if required, do the
same exercise after every week after operation.
If applicable, loosen the lateral wedges and tighten them again after
tensioning. Check wear of screen mats frequently. Repair smaller
damaged areasat once, for instance by inserting new wires or
attaching screen mat remnants. Never weld spring steel wires!
If only small areas are worn, turn screen mat or exchange individual
sections
9
THANK YOU!
10