On-siteDesignModification RequestSheet

Serial Number: TL-SWEPDI-KDPE-DE-003

THANG LONG 2x300MW THERMAL POWER PLANT PROJECT


Adjust wiring 接线调整 Volume 6.6kV SWITCHBOARD SECONDARY
Issue WIRING DIAGRAM
Name
6.6kV 开关柜二次线单元图
SECONDARY WIRING DIAGRAM OF
UNIT AUXILIARY TRANSFORMER
高压厂用电源二次线
Volume 50-F416S-D0603 REV.C
To KDPE
No. 50-F416S-D0608 REV.C

CC Date JUL-01-2017
Subject: Adjust wiring 接线调整
Causes:
Improve and perfect the hard-wired interlock according to owner's comments.
根据业主意见,修改硬接线闭锁。
Description: Submitted by:
Add hard-wired interlock wring for local operation circuit, relevant □ OWNER
to attach 1/15~15/15 , and unit 2 as same as the unit 1. □ KDPE
Implementation of this design modification may cause possible □ SWEPDI
security risks, relevant constructor should pay attention to the safety □ CTESI
for construction and operation and strictly abided by the safety □
regulations.

增加硬接线闭锁,见附图 1/15~15/15,其中机组部分#1 机
和#2 机做相同修改。
本设计变更在实施时可能会产生安全风险,请相关单位做
好相应的安全技术防范措施。

Prepared Checked Approved


/Date /Date /Date
SWEPDI/CTESI’s Comments:

KDPE’s Comments:

FICHTNER’s Comments:

OWNER’s Comments: