NOTES & KEY

[1] Installation assumed to be TN-C-S (PME)


Earthing and a 69 kVA supply provided.

[2] PEN Fault Detection and Disconnection


installed at incoming to EVC LV Distribution
Board in compliance with 722.411.4.1 (iii) or
(v) and suitable for use in 3P systems.

²
[3] T2 SPD to be connected as CT1 or CT2
configuration, Table 534.5 with SPD to be
pre-wired by panel-builder.

[4] Installation method assumed in underground


single way ducts, circuits grouped touching,
with final circuit length up to 30 m

[5] Spare ways should ancillary services be


required e.g. lighting columns, feeder pillar
power socket, anti-condensation heater.

²
[6] EVC's to be Alfen single-outlet 7 kW being a

²
fixed load not subject to simultaneous
overload, max current draw for each EVC
circuit <= 32A.

[7] EVC's specified to include internal 6 mA


RDC-DD

[8] EVC's specified to include internal DP RCD


switching all live conductors (including neutral)

[9] Maximum prospective short circuit fault current


Isc to be < 10 kA. Should DNO or existing
supply conditions identify a fault current of
greater than 10 kA at EVC LV DB position, Rev Description By Date

QUOTATION
switchgear shall be designed to reflect higher
breaking capacity Icu requirement and include
either current-limiting fuses in-series with 1P
²
²
²

MCB or higher kA rated circuit-breakers.

[10] Ze at origin to allow for the MCB's to meet 5s Client:

disconnection times for a distribution circuit in


line with Table 41.3 or manufacturers In Partnership With:

specification, whichever is higher


Site Name:

[11] This is not a substitute for a detailed electrical Template 1 - 4 x Single-Outlet Fed From FP

design which shall be considered on a site by Drawing Title:


Single Line Diagram
site basic based on actual site design criteria, Scale @ A1: Drawn By: Checked By: Date:

infromation, requirements and characteristics NTS

Project Number:
AG SG

Drawing Number:
24.05.23

Revision:
0105 BLI-TEMP1-DRW-SCH-001 A