Project Organization Chart

Project title: 3 water boreholes rehabilitation and powering by solar system.


L1 PM- Firas

Direct Report 1 Direct Report2 Direct Report3 Direct Report4


L2 Project Officer Procurement Officer Quality Officer Project Controls
Amjad Ramy Ghania Emran

Project Site
Eng. Civil
(Mohamad)

Project Site
Eng.
L3
Mechanical
(Saeed)

Project Site
Eng. Electrical
(Mostafa)

Comments: The type of project is project based.