You are on page 1of 1

CONSTRUCTION OF TOILET BLOCK FOR

HIGH SCHOOL (BOYS)FOR 251 TO 500 STRENGTH


UNDER MANABADI :NADU-NEDU PHASE-II IN AP STATE

1) Toilet block is designed for 251 to 500 Strength without water tank.
2) Depending upon the area available the plan may be reworked out.

1615 14640 A
V2 V1 V1 V1 V1

WASH BASINS
WASH BASINS
WC WC WC WC WC
BOYS- 1500x1200 1500x1200 1500x1200 1500x1200 1500x1200
D1 PH WC
3600

3600
2400x1900 BOYS TOILET D3 D3 D3 D3 D3

V
11550x3140
URINALS
D2

V1 V1 V1 V1

UP
UP A
RAMP
1:12 TO 1:20-SLOPE

DRG.NO: PROJECT: //APPROVED//


01/MBNN/APEWIDC/TOILET BLOCK/G.FLOOR/HS-BOYS
/251-500/AD CONSTRUCTION OF TOILET BLOCK FOR NOTE: Sd-xxxxx
HIGH SCHOOL (BOYS)FOR 251 TO 500 STRENGTH CHIEF ENGINEER
1. USE VIBRATED REINFORCED CONCRETE OF
GROUND FLOOR PLAN UNDER MANABADI :NADU-NEDU PHASE-II IN 1
APEWIDC, VIJAYAWADA.
AP STATE MIX (1:1(2):3) CONFORMING TO IS:456-2000.
2. USE HYSD BARS OF Fe-500 AS PER IS:1786-2008. //TRUE COPY//
REFERENCE: V2 - VENTILATOR2 - 1.94 X 0.45 m 3. THE STRUCTURE IS DESIGNED FOR GROUND
D1 - DOOR 1 - 1.20 X 2.10 m FLOOR ONLY.
D2 - DOOR 2 - 0.90 X 2.10 m 4. FOOTINGS ARE DESIGN FOR
GROUND FLOOR AREA : 52.70 SQM (OR) 567 SFT D3 - DOOR 3 - 0.75 X 2.10 m 100,150,200,250,300 kN/sqm
V - VENTILATOR - 3.36 X 0.45 m EXECUTIVE ENGINEER(D)
NOTE : ALL DIMENSIONS
V1 - VENTILATOR1 - 2.20 X 0.45 m ARE IN MILLIMETERS NADU-NEDU PHASE-II APEWIDC, VIJAYAWADA.