Professional Documents
Culture Documents
Relationships for directional inter- Fuzzy logic technology (the basis for
vals are not straightforward. Some artificial intelligence) is emerging as the
models are available, but most are best approach to evaluate hole-cleaning
incomplete. The danger is that exclu- performance at all angles and is the
sion of factors, such as gel strength, method of choice for M-I software.
pipe rotation, eccentricity, low-shear Fuzzy logic works well with missing
viscosity, interaction among different and incomplete data, both common to
intervals and others, can lead to hole-cleaning analysis. Performance is
wrong conclusions. described using words (poor, fair, good
and very good) rather than numbers.
Hole-Cleaning Criteria
Opinions vary on what constitutes used as a trend to highlight potential
Clearly, “good” hole cleaning. From a practical problems. Clearly, ratios below 1.0 indi-
ratios below perspective, hole cleaning is adequate cate that a hole-cleaning problem exists.
if no operational problems are encoun- A drawback to this technique is its
1.0 indicate tered. This implies that hole-cleaning inability to identify large cuttings which
that a hole- requirements vary among different remain downhole until they grind
cleaning wells and even different intervals in down into particles that are small
the same well. enough to be carried to the surface.
problem Poor cleaning would naturally be There are several techniques for pre-
exists. assumed if cuttings were not observed dicting downhole cleaning performance
on shaker screens. Drilling reactive when direct measurements are not pos-
shales using a highly dispersive water- sible. In vertical sections, minimum
base mud will limit cuttings observed at annular velocity, slip velocity, rise veloc-
the shaker. Other physical indicators of ity, cuttings transport ratio and cuttings
poor cleaning include hole fill in verti- concentration are the most common. In
cal wells, cuttings beds in directional directional wells, cuttings-bed thickness
wells, mud rings, bridges and packoffs. also is a good, although not definitive,
Unfortunately, high cuttings volumes indicator. Unlike hole fill in vertical
on the screens do not automatically wells, cuttings-bed thickness cannot
signal excellent cuttings transport. be measured.
Comparison between the volume of At one time, minimum annular
cuttings generated by the bit to the velocity was the traditional criterion for
volume of hole drilled is one of the “good” hole cleaning. Velocities from
field techniques available to measure 100 to 120 ft/hr were considered ade-
hole-cleaning efficiency. Zero-discharge quate, although dependence on hole
and no-cuttings-discharge operations size was evident. For very large holes
are examples where cuttings volumes (>171⁄2 in.) where 100-ft/min velocity
are monitored because they must be was not achievable, mud yield point
boxed and transported for disposal. was increased significantly to provide
Typically, the ratio of surface to down- adequate hole cleaning. A flocculated
hole cuttings volume varies from about gel fluid is a common system used for
1.5:2.2, but the ratio should only be this purpose.
Minimum Transport Velocity (MTV) flow. The annular velocity should meet
is a recent technique applicable to or exceed a calculated MTV value for
directional wells. This concept pre- both conditions. It would appear that
sumes that a hole interval can be effi- MTV values are conservative, but the
ciently cleaned if all cuttings are either concept has been refined by field data
suspended in the flow stream or in beds and has been used successfully.
moving upwards in the direction of
Hole-Cleaning Guidelines
When establishing hole-cleaning guide- 3. Control drill to manage difficult
lines, it is important to review relation- hole cleaning situations only as a
ships among the parameters in Table 1 last resort. Penetration rate deter-
and to recognize that some can be both mines the annular cuttings load. The
independent and dependent variables. negative implications of limiting
Often, one parameter, such as formation drill rate are self-evident.
type, will determine how to approach 4. Take advantage of top drives, if avail-
hole cleaning. For example, a typical able on the rig, to rotate and circulate
horizontal well drilled through a very (backream) when tripping out.
competent Austin Chalk formation 5. Continually monitor parameters
might use a brine reservoir drill-in fluid. affecting hole-cleaning, and react
It follows that these parameters would accordingly. Always consider the
be appropriate — turbulent flow, high consequences of changes on other
annular velocity, low fluid viscosity operations.
and gels, with minimal effects from 6. Measure mud rheology under
pipe eccentricity and rotation. On the downhole conditions, especially in
other hand, an unconsolidated-sand- deepwater and High-Temperature,
stone, horizontal interval would dictate High-Pressure (HTHP) applications.
tight filtration control and laminar 7. For deepwater wells with a large-
_______________________
flow. Elevated low-shear rheology and diameter riser, add a riser pump
_______________________ flat gels would be suitable, especially if to increase riser annular velocity.
_______________________ the eccentric pipe can be rotated. 8. Avoid using highly dispersive muds
Listed below are practical hole-cleaning that might help cleaning, but can
_______________________
guidelines aimed at field use. They are create a mud solids problem.
_______________________ grouped according to general (all wells),
VERTICAL AND NEAR-VERTICAL WELLS
_______________________ vertical/near-vertical wells and direc-
1. Keep cuttings concentration less
tional wells (including horizontal).
_______________________ than 5% (by volume) in order to
_______________________ GENERAL minimize drilling problems.
1. Use the highest possible annular 2. For efficiency and cost considera-
_______________________
velocity to maintain good hole tions, use a mud viscosity selected
_______________________ cleaning, regardless of the flow based on hole size and slip velocity
_______________________ regime. Annular velocity provides calculations. Further increase yield
the upward impact force necessary point and LSYP only when hole-
_______________________
for good cuttings transport, even in cleaning problems have been
_______________________ directional and horizontal wells. encountered or are imminent.
_______________________ 2. Rely on mud rheology and gel
_______________________
strengths for suspension and
transport capabilities.
Hole Cleaning 20B.11 Revision No: A-1 / Revision Date: 02·28·01
CHAPTER
3. Maintain LSYP between 0.4 and 0.8 16. Schedule periodic wiper trips and
times the hole diameter in inches pipe rotation intervals for situations
unless hole conditions dictate oth- where sliding operations are exten-
erwise. Yield point and LSYP for sive and bed formation is expected.
highly dispersed muds typically are 17. When using FLO-PROT systems for
low, so higher annular velocities coiled-tubing drilling, periodically
may be required. run wiper trips to remove cuttings
4. Use periodic high-density/high- beds. For re-entry wells with large
viscosity sweeps to correct cleaning casing, select the best compromise
problems. Do not run sweeps unless to clean both the horizontal and
hole conditions warrant. Sweeps casing intervals.
should be >0.5 lb/gal heavier than 18. Rotate pipe at speeds above about
the mud and should be combined 50 RPM if possible to prevent bed
with vigorous fluid and mechanical formation and to help remove pre-
agitation, if possible. existing beds. Fully eccentric pipe
5. Monitor the hole for symptoms combined with proper LSYP values
of cuttings accumulation, fill can provide best results.
and bridges. 19. Increase mud weight to correct well-
6. Do not expect pipe rotation to bore stresses problems masquerading
help hole cleaning, especially in as hole-cleaning problems.
larger-diameter holes. 10. Recognize that turbulent flow
across the annulus may be difficult
DIRECTIONAL WELLS
to achieve and maintain.
11. Use hole-cleaning techniques to
11. Consider drilling small-diameter,
minimize cuttings-bed formation
competent, horizontal intervals
and subsequent slumping which
using turbulent flow. Low-viscosity
can occur in 30 to 60° hole sections.
fluids enter a state of turbulence at
12. Utilize elevated-viscosity fluids
lower flow rates than viscous ones.
from the start, because cuttings
Any beds which form can be eroded
beds are easy to deposit, but
by the high flow rates required for
difficult to remove.
turbulent flow.
13. Maintain LSYP between 1.0 and
12. Expect little help from viscous
1.2 times the hole diameter in
sweeps, unless they are accompa-
inches when in laminar flow.
nied by high flow rates and pipe
14. Treat mud to obtain elevated, flat
rotation and/or reciprocation.
gels for suspension during static
and low-flow-rates periods.
15. For optimum performance from
FLO-PROT fluids, maintain Brookfield
viscosity above 40,000 cP.
Introduction
Fluid displacements are a common • Reverse circulation. The new fluid is
procedure in the drilling, completing pumped down the annulus and the
A displace- and workover of wellbores. A displace- existing fluid is displaced up and out
ment occurs ment occurs when one fluid replaces of the drillstring or tubing. This pro-
another in the wellbore. This chapter cedure is most commonly used when
when one will discuss two separate displacement a lighter fluid is used to displace a
fluid replaces categories. The first covers standard heavier fluid (see Figure 2).
another in fluid displacements including water-
base muds, oil-base muds, synthetic-
the wellbore. base fluids, completion fluids and
workover fluids. The second category
covers cementing displacements.
There are a number of different dis-
placement procedures used in wellbore
operations. Listed below are some of
the more common procedures.
Up drill pipe
Down annulus
• Conventional or standard dis-
placement procedure. The new
fluid is pumped down the drill pipe
or tubing to displace the existing
fluid up and out of the annulus. This
is the normal method of wellbore
circulation (see Figure 1).
Down drill pipe
Displacements and Cementing 20C.1 Revision No: A-0 / Revision Date: 03·31·98