Professional Documents
Culture Documents
PROJECT NAME
TRANSMISSION LINE PROJECT
EMPLOYER/PURCHASER
BIDDER/CONTRACTOR
TABLE OF CONTENTS
1. INTRODUCTION
2. PURPOSE
4.3 Topographic
ATTACHMENT
2
1. INTRODUCTION
This procedure describes the surveying method to determining site point for the Tower
275kV Transmission Line of The Batang Toru Hydro Electric Power Plant Project.
Sub-Contractor emphasizes that PT North Sumatera Hydro Energy (“Employer”) has
assigned BUT. Sinohydro Company Limited (“Contractor”) to develop the 275kV grid
system in Batang Toru which serves to evacuate power from Batang Toru Hydropower
Plant’s switchyard to Existing PLN’s 275kV Padang Sidempuan – Sarula Transmission
Line (“Project”).
275kV Transmission Line of The Batang Toru Hydro Electric Power Project involves the
construction of a 275kV overhead transmission line from the Switchyard located at
Batang Toru to Existing PLN’s 275kV Padang Sidempuan – Sarula Transmission Line.
The overall line route length is approximately 16 km for each Line A and B.. The Project’s
line route is located along Bukit Barisan and within Tapanuli Selatan districts.
The sub-Contractor understands that all documentation within the project specification is
either preliminary or conceptual in nature and shall be further developed and completed
in accordance with dedicated Contractor specifications and related PLN standards.
2. PURPOSE
This method/statement covers the work stages, tools and equipment and other
appropriate requirements in the execution of the erection of transmission lines tower.
The purpose of this method statement is as a guidance for establishing the work
execution in regard to align with Health, Safety and Environment requirement, meet to the
planned time schedule and comply with the Contractor’s technical requirements.
3
4.1.2. Create an surveying schedule.
a. Determination of knowing point and orientation to be measured.
b. Plan a route that allows a Polygon path for the Instrument standing position
and the next observable point.
c. Determining the method based on the type of terrain, location access,
availability of equipment, workers and other considerations.
4.1.3. Working Permits dan Safety Precautions
a. The contractor’s Working Permits and other appropriate permits have been
approved.
b. Contractor’s Permit to Works (PTW) has been approved.
c. HIRADC, JSA and other safety precautions have been prepared and
approved.
4.3 Topographic
a. Topographic measurement is a measurement that is focused on gives an idea
of the state of the ground surface, the rise and fall of the terrain (relief) here all
the details (field objects) are measured to obtain a map complete. The results
of these measurements are in the form of a topographic map which will be
displayed use for planning according to the purpose of the measurement itself.
A topographic map is a presentation of a portion of the earth's surface relief,
hydrography, and vegetation. Topographic measurements in o determine and
4
bind the orientation coordinates from a known point (BM)and so on From the
BM to Tower site point:
1. Polygon Measurement (angle and distance data).
2. Elevation Measurement (data on the difference in ground surface height
between points stake).
These topographic measurements will be this is carried out to determine and
bind the orientation coordinates from a known point (BM)and so on From the
BM to Tower site point.
c. Horizontal Framework
The measurement steps are as follows:
1. Set up the theodolite measuring instrument at point P, then adjust it accordingly
observation.
2. Direct the scope's crosshairs to point A, then clamp/lock it horizontal screw and
vertical screw, to align the aiming line scope to target point A move the horizontal
fine drive screw and vertical.
3. Reading the horizontal direction on a horizontal disk, for example: Pa,this
reading is called reading in Ordinary position (B).
4. Loosen the horizontal and vertical screws, then align the lines aim the scope at
point B. Clamp/lock again the horizontal and vertical screws, To align the scope's
crosshairs to target point B, move the screw horizontal and vertical smooth drive.
5. Reading the horizontal direction on a horizontal disk, for example: Pb, This
reading is called reading in Ordinary position (B)
6. The scope is reversed/rotated 180˚ and aimed again at point B, then read
horizontal direction, for example: Lb, this reading is called the Outside reading
Ordinary (LB). g. The binoculars are aimed at point A, then read the horizontal
direction, for example : La, this reading is called Extraordinary reading (LB). Pa
measurement (B), Pb (B), La (LB), Lb (LB) are called series measurements, while
the magnitude the horizontal angle (single) point P is the average difference
between Ordinary and Extraordinary readings:
single measurement
d. Azimuth
Azimuth is the horizontal angle that starts from the north and is rotated clockwise
the magnitude is between 0-360˚. Magnetic azimuth is azimuth that starting from
one end of the magnetic needle, ending at the objective end of the line aim and
5
the magnitude is the same as the reading number. Azimuth function; Provides
north orientation and as a yield control angle measurement. Example of azimuth
calculation using known coordinates for example, known coordinates A (XA, YA)
and coordinates B (XB, YB).
AB = arc tan XB - XA
N
YB -YA
AB
AB = azimuth A – B
B
XB – YB = Coordinate Point B
A
XA – YA = Coordinate Point A
e. Distance Measurement
Distance is length in the horizontal plane. In distance measurement, method
used are:
1. Direct distance measurement
Direct distance measurement is distance measurement carried out using
The results obtained can be seen directly by reading the tool without
through a calculation process. For example, the tool used is a measuring
laser distance or measuring tape
Point Point
direct horizontal measuring distance
A-B
Terrain Surface
Information
Horizon Line
BA : Top thread
BT : Middle Thread
BB : Bottom thread
H: Helling angle
Z : Zenith angle
Distance A - B
6
4.4 Polygon method for determining coordinates
a. Polygon
Polygon meaning is a series of consecutive lines whose length and direction
are determined from field measurements. The polygon method is a positioning
method more than one point on the surface of the earth, which is located
lengthwise so that forming a polygon The elements measured in polygon
measurements are elements of angle and distance, if the initial coordinates
are known (BM), then the points are other coordinates of the polygon can be
determined (Point of Tower site).
Drawing caption :
In a perfectly bound open polygon the geometric conditions apply the conditions
that must be met are:
In general, the results of measuring distances and angles do not meet the above
requirements, but it will be :
In this case :
7
∑ = number of measuring angles
n = number of polygon points
f = closing angle measurement error
∑ (d * sin ) = number of abscissas
∑ (d * cos ) = number of ordinates
f∆X = abscissa cover error
f∆Y = ordinate cover error
P – Q = azimuth towards the end of the tie point
A – B = azimuth of the initial direction of the tie point
XP,YP = final coordinates of the tie point
XB,YB = initial coordinates of the tie point
1. Calculate the azimuth of the initial tie point from the azimuth of the final tie point
(A – B - P – Q)
provided that:
+/+ : = the results obtained are constant
+/- : = the results obtained are constant + 180°
-/- : = the results obtained are + 180°
-/+ : = the results obtained are didapat + 360°
∑ = B + 1 + 2 + 3 + P
f = ∑ - (P – Q - A – B) + (n * 180°)
If one corner cover (f) falls within the required tolerance, then the calculation
continues, but if it does not enter tolerance, a check must be carried out angle or
re-measurement.
’B = B + f/n
-
-
’P = P + f/n
8
5. Add up the distance measures (∑d)
∑d = dB – 1 + d1 – 2 + d2 – 3 + d3 - P
∆X B – 1 = dB – 1 * sin B – 1 ∆Y B – 1 = dB – 1 * cos B – 1
- -
- -
- -
∆X 3 – P = d3 – P * sin 3 – P ∆Y 3 – P = d3 – P * cos 3 – P
7. Calculate the abscissa and ordinate cover error using the formula
For abscissa:
For Ordinate:
If one of the abscissa and ordinate covers falls within the required tolerance, then
The calculation continues, but if it does not enter the tolerance, check the distance
or repeat measurements.
If the abscissa and ordinate errors are negative (-), then the correction is positive
(+), and vice versa
9. Calculating coordinates (X,Y)
known coordinates of the initial tie point (XB, YB), then:
X1 = XB + ∆XB - 1 + f∆XB – 1 Y1 = YB + ∆YB - 1 + f∆YB – 1
- -
- -
- -
X3 = X2 + ∆X2 - 3 + f∆X2 – 3 Y3 = Y2 + ∆Y2 - 3 + f∆Y2 – 3
If the calculated coordinates of the end point (XP,YP) are the same as the tie
point coordinates the end is known then the calculation is declared correct.
9
4.5 Vertical Framework
A place on the surface of the earth other than its horizontal position can be
determined, the Level/height position can also be determined. To determine the
vertical position of a point in the field measurements are carried out which are
usually called height measurements.
Auto level
leveling measurement
In this measurement the tool stands exactly between two points with the same
distance, this method is often used in topographic measurements. How to
calculate height difference (∆H) :
∆H AB = bt A – bt B
In this case :
∆H AB = height difference
Bt A = middle thread at point A
Bt B = middle thread of point B
H B = H A + ∆H AB
10