Progress Report #01 provides an update on the Caedo Fire Protection System project as of August 06, 2021. Key tasks such as fabrication of supports and pipe spools in various locations are nearly complete, with installation of main pipes and supports over 95% done in two blocks. Fabrication of supports in the supermarket is 10% finished while installation there is only 5% complete. The report lists the project in charge, foreman, and eight members of the manpower team.
Progress Report #01 provides an update on the Caedo Fire Protection System project as of August 06, 2021. Key tasks such as fabrication of supports and pipe spools in various locations are nearly complete, with installation of main pipes and supports over 95% done in two blocks. Fabrication of supports in the supermarket is 10% finished while installation there is only 5% complete. The report lists the project in charge, foreman, and eight members of the manpower team.
Progress Report #01 provides an update on the Caedo Fire Protection System project as of August 06, 2021. Key tasks such as fabrication of supports and pipe spools in various locations are nearly complete, with installation of main pipes and supports over 95% done in two blocks. Fabrication of supports in the supermarket is 10% finished while installation there is only 5% complete. The report lists the project in charge, foreman, and eight members of the manpower team.
Location: Caedo Commercial Center, Calicanto St., Batangas City Contractor: MCCD ENGINEERING SERVICES & TRADING Project In Charge: Aron May De Guzman Foreman: Domingo Reduta Jr. Manpower: Angelito Castillo Jr. Wilmar Garcia Tristan Carag Rexon Magnaye Jeeno Austria Ariel Brito Bernaldo Genita Marc Niño Mercado Franklin Pintor Jr. Summary of Work Completed as of August 06, 2021 TASK LOCATION % OF WORK COMPLETED Fabrication of Supports Stockroom, Block E (Rear), (Loop Hanger, Angle Bar) Block A (Rear), Main Building 100 (Side) Fabrication of Pipe Spools Stockroom 95 Installation of Main Pipes and Block A (Rear), Block E (Rear) 95 Supports Installation of Support and Main Main Building (Side) 50 Pipes Erection/ Installation of Pipes, Cross Main Pipes, Spools, and Stockroom 95 Supports Fabrication of Supports Supermarket 10 (Loop Hanger) Installation of Supports Supermarket 5