SPARKLIGHT ENGINEERING LIMITED

DAILY PROGRESS REPORT


ENG 001

DATE: 20th February , 2015

Project Name and Location: Gateway Spark light Estate.

Name of Staff: Ayeni Adedeji

Site Area working on (Residual): AD5, AF3 and Neighborhood Centre

Description of worked done:


AF3 building
* Block setting at 93%
AD5 building
* Block setting, Infill concrete and Plastering of septic tank (unit A) 100% completed
Neighborhood Centre
* Placing of reinforcement beams at 97%
* Formwork for water tank slab and roof beams at 98% (waiting for AA Design on wind
turbine).
Any challenges encountered:
* Our contractor on AF3 building (Mr Adesoye) disappointed us.
Solution if solved:
We used 2nos of our ATI guys and a Labour to move the block setting on AF3 forward.
Project Engr. Signature: Ayeni Adedeji