Monthly Report of Overseas Construction

Report No.

17-Sep-16

Date
Mr. Felipe:

Country

E10 - 15 - 020

Job No.

Project Name

JAKARTA

Branch Office

MMKI

PT. MITSUBISHI MOTORS KRAMA YUDHA INDONESIA - NEW FACTORY PROJECT

1-May-15

Construction Period

Please directly input the


actual work accomplishment
Scope
in the column below then
the of Works
progress line will
1.
Power Incoming
automatically
adjust Work
accordingly
2. Sub-Station System Work

Owner

INDONESIA

17-Aug-16

Work Progress
Eq.Wt.

3. Emergency Generator System Work


4. Main Feeder System Work
5. Power Supply Work for Utiliy equipment
6. Lighting & Receptacle Work
7. Lighting Fixtures & Outdoor Lighting Work
8. Telephone & LAN System Work
9. Fire Alarm Work
10. Sound System Work
11. AV System Work
12. Security System Work
13. CCTV System Work
14. Building Monitoring System Work (BMS)
15. Lightning Protection Work

Total

Progress (%)

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
- - - - - - - - - - -###
-###
###
###
###
###
###
###
5.50

0.00

17.36

3%

0.49

1.04

0%

0.00

29.40

6%

1.73

13.51

0%

0.00

3.94

1%

0.02

10.65

0%

0.00

12.73

0%

0.00

0.56

0%

0.00

0.48

0%

0.00

0.11

0%

0.00

2.55

0%

0.00

0.46

0%

0.00

0.98

0%

0.00

0.74

62%

0.46

100.0

10

20

30

40

50

60

70

80

90

Work Progress
- Install support for lighting, cable rack & busduct at welding area.

Total

0%

- Install sleeve PVC crossing road for extra low voltage at


guard house south.

- Continue install supporting for lighting & cable rack & busduct
at power building.

- Install PVC Pipe 2 " for Coaxial Cable Lightning Protection Plan C & D.

- Continue install cable rack for power cable at power building.

- Install sleeve for DGPT & BMS at electrical room assembly factory.

- Install cable rack for power cable at pressing factory.

- Install lightning protection on building plan - C & D at welding factory.

Material & Delivery Progress


- Switchgear 20KV for electrical room power building onsite
12 december 2015.

- MVMDB 20KV & LVMDB power building onsite 12 december 2015.

- Lighting mitsubishi onsite 19 november 2015 for power building & panel.

- Transformers 2500 & 1600 kVA for power building onsite 12 december 2015.

100

2.71

- Cable rack & c - channel onsite 11 ~ 26 november 2015.

- Steel conduit parsial onsite middle november 2015 until end of may 2016

Presence of Fail cost


- Shop drawing civil for all electrical room not same with we request .
- Install cable rack at press factory distrub boom lift a engine problem schedule work not following target.
- Install supporting at welding factory distrub weather rainy & dark cloudy usually time 3 pm.
- Warehouse for storage materials capacity not enough so we must put down materials to other place (temporary materials storage).

Measures of Same as Above


- We information to supervisor site for pending work & coordination drawing with civil a not much out of material and cost payment worker twice work.
- We coordination with subcont boom lift for repair engine change spare parts too quickly for follow target work.
- We coordination with supervisor site to separate for a lot group to follow target delay because rainy and work not more than 2 pm.
- We coordinate with ME takenaka need temporary warehouse for storage materials before materials onsite at project.

Problem of Others
- Civil delayed schedule concrete slab at power building we not install cable rack & c-channel using scaffolding.
- Change current capacity for machine at painting factory.
- Change current capacity for machine and type busduct tap off for above 630 A & plug in below 400 A at welding factory.

Measures of Same as Above


- We using scaffolding include track for mobilization install cable rack & c-channel.
- We calculation to demand load for machine additional & quotation.
- We calculation to demand load for machine using tap off or plug in busduct for additional & quotation.

Consultant
JAKARTA

NIL
PT. TAKENAKA INDONESIA

Construction

Rp172,800,000,000

Amount

CT

K. HARA

Project Manager

P.M. Signature :

Manpower Progress
Total Manpower

Manpower

Accomplishments

Plan

Previous

Manpower Plans

This Month

Total

Next Month

Whole

After 2 Months

Progress (%)

<Japanese>
1,664

Site Staff
Total

2.71
A)

1,664

624

104

728

104

104 Operation (%)

624

104 C)

728

104

104 C/A
43.8

<Aside from
Japanese>

D/B

4.7
Site Staff
Site worker

4,160

1,522

260

1,782

260

260

159,885

3,938

1,992

5,930

7,280

9,070

O = (C+D)/(A+B)

5.1
Valuation

P>O
P=O
P<O
Total

B)

164,045

2,252 D)

5,460

7,712

7,540

9,330

Safety Measures
- Daily toolbox meeting before going to works.

- Weekly safety meeting / safety patrol.

- Make safety working plan for dangerous work.

- Use Handy talky at high work must use rope or other around a neck.

- Checking of personal protective equipment (PPE).

- Use Tools at high work must a using rope around the wrist and after work is placed at basket

- No mis connection & Deltamate check.

or safety belt.

Commercial Matter
Claim amount

Rp46,418,000,000

Balance amount

Rp126,382,000,000

DP

(24.43%)

Base on LOI ( letter of intent )

Latest working Budget

Rp172,800,000,000

( Revisi Budget Base on B2 2014-KDI-2119-R7 )

Presence of Variation
( Indicate additional work info )
Additional works :

Reports of Others
- Power on 28 February 2016 at PLN substation step 1 contract PLN 1,000 KVA step 2 8,000 KVA.
- Takenaka & Owner Final Inspection 1 - 8 August 2016.
- Handover document 17 August 2016.
- Weekly coordination with main contractor every thursday.
- Weekly coordination internal kinden every tuesday.
- Daily meeting progress work & tomorrow plan.
- Safety monitoring from HSE department kinden indonesia on 15 & 22 December 2015.
- QCAS monitoring from QCAS Electrical department kinden indonesia on 23 December 2015.
- FAT Transformers 2 ~ 4 december 2015.
- FAT Generator 3 ~ 4 december 2015.
- FAT Panel distribution 5 & 7 december 2015.
- FAT Busduct thailand 7 ~ 10 december 2015.
- Unloading materials swicthgear 20KV, MV, LV & Transformers for power building 12 december 2015.

Construction Photograph
Report No.
Date
Budget No.

Photo No.1

7
17-Sep-16
E10 - 15 - 020

Country
Project Name
Construction Period

(Location : External area )

INDONESIA

Owner

MMKI

PT. MITSUBISHI MOTORS KRAMA YUDHA INDONESIA - NEW FACTORY

1-May-15

Date :

01-Nov-15

Photo No.3

Remark :
Location project MMKI
at all area.

Photo No.2

(Location : Welding factory )

Date :

07-Nov-15

Remark :
Install lightning protection plan-C
C/L 5 B welding factory.

Photo No.4

Consultant
Branch Office

JAKARTA

ONESIA - NEW FACTORY PROJECT

Amount

17-Aug-16

Photo No.3

Construction

Project Manager

(Location : Press factory )

NIL
PT. TAKENAKA INDONESIA

Rp172,800,000,000
K. HARA

Date :

12-Nov-15

,
Remark :
Install cable rack
at Press factory.

Photo No.4

(Location : Welding factory )

21-Nov-15

Remark :
Install lightning protection plan-D
C/L 1 K welding factory.

Construction Photograph
Report No.
Date
Budget No.

Photo No.5

7
17-Sep-16
E10 - 15 - 020

Country
Project Name
Construction Period

(Location : Welding factory )

INDONESIA

Owner

MMKI

PT. MITSUBISHI MOTORS KRAMA YUDHA INDONESIA - NEW FACTORY

1-May-15

Date :

28-Nov-15

Photo No.6

Remark :
Install cable rack W 300 w/
bottom cover
at welding factory.

Photo No.7

(Location : Power building area )

Date :

28-Nov-15

Remark :
Install cable rack & c-channel
at power building.

Photo No.8

Consultant
Branch Office

JAKARTA

NDONESIA - NEW FACTORY PROJECT

Amount Rp

17-Aug-16

Photo No.6

Construction

Project Manager

(Location : Painting Factory )

NIL
PT. TAKENAKA INDONESIA
172,800,000,000
K. HARA

Date :

29-Nov-15

Remark :
Install clamp & hanger for
support cable rack W=500
at C/L 8-9 F-G painting area.

Photo No.8

(Location : Painting Factory )

Date :

30-Nov-15

Remark :
Install Block out (opening)
for cable rack W=300

at C/L 5 F 2nd Floor


painting area.

Project Name
Location
Project No.

: PT.MITSUBISHI MOTOR KRAMA YUDHA INDONESIA


: GIIC - DELTAMAS - CIKARANG
: E10-15-020

NO

TOTAL ESTIMATED COST


INDIRECT

PROJECT MANAGER
EXPAT ENGINEER
SITE MANAGER
ASSITANT SITE MANAGER
SITE ENGINEER
ASSITANT SITE ENGINEER
DRAFTSMAN
QCAS ENGINEER
SAFETY
TOTAL

=
=
=
=
=
=
=
=
=
=

DIRECT (MAX)

KEPALA TUKANG
TUKANG
PEMBANTU (SR )
PEMBANTU (JR )
TOTAL

280
Mochamad Riza:
Automatic

245
GAJI TUKANG
123,692
GROSS PAY
Rp
8,190,000
12 Hours

TOTAL DIRECT COST

Rp

INDIRECT COST

AVERAGE SALARY PER DAY

=
=
=
=
=
=
=
=

KEPALA TUKANG
TUKANG
PEMBANTU (SR)

Rp

x
x
/
/

11,188,704,705

Mochamad Riza:
Mochamad Riza:
Mochamad Riza:
1.49
=
Rp
183,750
Automatic according
Automatically
to Project
according to Automatic
DAYS
WORKSalary
Location
Highest
(See Average
Salary Working Mochamad Riza:
26 Days
= Fill
Rp
315,000
Table
Below and
Hour
per
A39)
Day)
Automatic
Mochamad
Riza:
Automatic according to
Highest Average Working Hour
per Day
Mochamad Riza:
Automatic

1
3
3
3
2
1
1

Person
Person
Person
Person
Person
Person
Person

x
x
x
x
x
x
x

12
10
12
11
11
11
9

Months
Months
Months
Months
Months
Months
Months

x
x
x
x
x
x
x

Rp11,000,000
Rp11,000,000
Rp15,000,000
Rp6,500,000
Rp8,000,000
Rp7,000,000
Rp8,000,000

=
=
=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp

Mochamad Riza:
Automatic
140

132,000,000
330,000,000
540,000,000
214,500,000
176,000,000
105
77,000,000
72,000,000
Mochamad Riza:
1,541,500,000

Automatic

70

:
=
=
=

210

175

Mochamad Riza: Mochamad Riza: Mochamad Riza:


Mochamad Riza:
x
x
=
Rp
Automatic
Automatic
Fill according to Project Fill according to Project

PHK HARIAN

8 Person
42 Person
85 Person
172 Person
307 Person

AVERAGE WORKING HOUR


PER DAY

Mochamad Riza:
Automatic

=
=
=
=
=

EXPAT ENGINEER
SITE MANAGER
ASSITANT SITE MANA
SITE ENGINEER
ASSITANT SITE ENGIN
DRAFTSMAN
QCAS ENGINEER
SAFETY
TOTAL

Author:
You
can adjust maximum scale
350
here, the scale ##
will filled
automatically ##

315

=
=
=
=
=

AVERAGE UNIT PER MANDAYS

Author:
Fill according to Project

1 Person
2 Person
1 Person
3 Person
3 Person
3 Person
2 Person
2 Person
1 Person
18 Person

SALARY FOR DIRECT (MAX)

MAN POWER

8 Person
42 Person
85 Person

x
x
x

Mochamad Riza:

Mochamad Riza:

Rp
4,288,000
=
Rp
Automatic according to Labour
Automatic
Rp
4,123,100
=
Rp
(Max)
Rp
3,636,000
=
Rp

Mochamad Riza:

34,304,000
Automatic
173,170,200
309,060,000

35

##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
###
###
###
###
###
###
###
###
###

Mochamad Riza:
Mochamad Riza:
Automatic according to Labour
Automatic
(Max)

6
PEMBANTU (JR)
TOTAL

TOTAL COST

=
=
=
=
=

Average Work Day per Month


Work Period

=
=

Man - Day

Salary

=
=

Rp
Rp

309,060,000
Mochamad Riza:
825,594,200

35

Automatic

Rp
Rp
Rp
Rp
Rp

11,188,704,705
1,541,500,000
825,594,200
47,785,400
13,603,584,305

Mochamad Riza:
Automatic
Mochamad Riza:
Automatic

MONTH

Mochamad Riza:
Automatic

:
=
=
=
=
=
=
=
=
=

7 WORKING HOURS
0.14286 MANDAYS
MANDAYS
MANDAYS
26 Days
16 Months

Mochamad Riza:
Fill according to Project Period
(Month)

Mochamad Riza:
Example for calculation.
Filled
automatically
Man
- Power
x Ave Work Day per Month x Ave Working Hours per Day
249 Person x 26 Days x 12 Hours
77,688
Man - Hour / 7
77688 /7
11,098
Man - Day x Average Unit per day
11098 x 183750
Rp
2,039,257,500

###
###
###
###
###

Mochamad Riza:
Fill according to Project
2

APRIL

MAY

JUNE

JULY

YEAR

PLAN

=
=
=
=

Man - Hour

3,636,000

1 MANDAY
1 HOUR
TOTAL MANHOURS x 0.14286
TOTAL MANHOURS / 7

Calculation

Rp

TOTAL DIRECT COST


TOTAL INDIRECT COST
PHK HARIAN TOTAL
THR TOTAL (@1thn)
SUB TOTAL-1

Notes

ACTUAL

172 Person

Mochamad Riza:
Automatic

2015
Mochamad Riza:
15
Fill according to Man-Power of
Project that needed (Plan)

Man - Power

30

53

Man - Hour

840

6,240

10,080

Man - Day

120

446

891

1,440

Salary

16,658,040

65,173,088

130,200,048

210,424,320

Man - Power

17

17

Man - Hour

298

1,169

2,639

1,862

Man - Day

43

167

377

266

Salary

3,503,480

28,128,018

65,128,251

69,882,907

Mochamad Riza:
3,120
Automatically

Mochamad Riza:
Fill according to actual
in the
12
Project

CHECKED BY

APPROVED BY

APPROVED BY

APPROVED BY

APPROVED BY

PREPARED BY

Q-CAS

OD

GM

Section Mngr

Project Mngr

Site Mngr

MAN POWER SCHEDULE FOR ELECTRICAL WORKS

REMARK
: Man - Power Plan
: Man - Power Actual
: Progress Plan
: Progress Actual

100%

90%

80%

70%

60%

50%

40%

30%

20%

10%

10%

10

11

12

AUGUST

SEPTEMBER

OCTOBER

NOVEMBER

DECEMBER

JANUARY

FEB

MARCH

2015

2016

CONTRACT PERIOD
START

: Apr '15

PERIOD

: Aug '16

Mochamad Riza:
Fill according to Project
Contract Period

Mochamad Riza:
1,568
Automatic

88

111

133

169

197

213

249

302

Total ManPower

20,592

28,860

34,580

43,940

56,342

66,456

77,688

94,224

Total ManHour

442,962

2,942

4,123

4,940

6,277

8,049

9,494

11,098

13,461

Total ManDay

63,281

463,944,574

702,769,473

842,027,940

1,069,920,927

1,430,347,545

1,744,522,500

2,039,257,500

2,473,458,750

Total Salary (A)

Rp

11,188,704,705

Mochamad Riza:
Automatic
78

27

Total ManPower

4,480

Total ManHour

10,448

640

Total ManDay

1,493

Total Salary

108,362,684

Rp

275,005,340

Project Name
Location
Project No.

: PT.MITSUBISHI MOTOR KRAMA YUDHA INDONESIA


: GIIC - DELTAMAS - CIKARANG
: E10-15-020

NO

TOTAL ESTIMATED COST


INDIRECT

PROJECT MANAGER
EXPAT ENGINEER
SITE MANAGER
ASSITANT SITE MANAGER
SITE ENGINEER
ASSITANT SITE ENGINEER
DRAFTSMAN
QCAS Engineer
SAFETY
TOTAL

Author:

=
=
=
=
=
=
=
=
=
=

DIRECT (MAX)

MAN POWER

1 Person
Fill according to Project
2 Person
1 Person
3 Person
3 Person
3 Person
2 Person
2 Person
1 Person
Mochamad Riza:
18 Person

Author:
You can adjust
maximum
350
##
scale here, the scale will filled
##
automatically

Automatic

315

KEPALA TUKANG
TUKANG
PEMBANTU (SR )
PEMBANTU (JR )
TOTAL

=
=
=
=
=

8 Person
42 Person
85 Person
172 Person
307 Person
Mochamad Riza:

280

Automatic
SALARY FOR DIRECT (MAX)

AVERAGE UNIT PER MANDAYS


3

=
=
=
=
=

AVERAGE SALARY PER DAY


AVERAGE WORKING HOUR
PER DAY

245

TOTAL DIRECT COST

INDIRECT COST

GAJI TUKANG
x
K
Mochamad Mochamad
Riza:
Riza:
154,615
x
1.49
=
Rp
Automatic according
Automatically
to Project
according to
GROSS PAY Location/ Salary
DAYS
WORK
Highest
(See Salary
Average Working
Rp
8,190,000
/
26 Days
Rp
Table
Below
and
Hour
Fill
per
A39)
Day)=
Mochamad
Riza:
12 Hours
Rp

1
3
3
3
2
1
1

PHK HARIAN

KEPALA TUKANG
TUKANG
PEMBANTU (SR)

Person
Person
Person
Person
Person
Person
Person

Rp

7,459,782,658

x
x
x
x
x
x
x

8
5
6
6
6
6
6

Mochamad Riza:
Automatic

Mochamad Riza:
x
Fill according to Project

Months
Months
Months
Months
Months
Months
Months

x
x
x
x
x
x
x

175

Mochamad Riza:
=
Rp
Fill according to Project

Rp11,000,000
Rp11,000,000
Rp15,000,000
Rp6,500,000
Rp8,000,000
Rp7,000,000
Rp8,000,000

=
=
=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp

Mochamad Riza:
Automatic

88,000,000
165,000,000
270,000,000
117,000,000
96,000,000
42,000,000
48,000,000
Mochamad Riza:
826,000,000

140

105

Automatic

70

:
=
=
=

210

Automatic according to
Highest Average Working Hour
per Day

Mochamad Riza: Mochamad Riza:


x
Automatic

EXPAT ENGINEER
=
Automatic
SITE MANAGER
=
ASSITANT SITE MANA
=
SITE ENGINEER
=
ASSITANT SITE ENGIN =
DRAFTSMAN
=
QCAS Engineer
=
SAFETY
=
TOTAL

Mochamad Riza:
229,687
Automatic
Mochamad Riza:
315,000
Automatic

Mochamad Riza:

Mochamad Riza:

8 Person
x
Rp
2,010,000
=
Rp
Automatic according to Labour
Automatic
42 Person
Rp
1,932,700
=
Rp
(Max) x
85 Person
x
Rp
1,846,400
=
Rp

Mochamad Riza:
16,080,000
Automatic
81,173,400
156,944,000

35

##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
###
###
###
###
###
###
###
###
###

Mochamad Riza:
Mochamad Riza:
Automatic according to Labour
Automatic
(Max)

6
PEMBANTU (JR)
TOTAL

172 Person

TOTAL COST

TOTAL (1+2)

=
=
=
=
=
=

=
=

Salary

156,944,000

35

Mochamad Riza:
411,141,400
Automatic

Mochamad Riza:

Rp
Rp
Rp
Rp
Rp
Rp

7,459,782,658
Automatic
Mochamad Riza:
826,000,000
Automatic
411,141,400
1,278,690,800
Mochamad Riza:
9,975,614,858
Automatic
Mochamad Riza:
23,579,199,163

MONTH

7 WORKING HOURS
0.14286 MANDAYS
MANDAYS
MANDAYS

Mochamad Riza:
Fill according
13 to Project

APRIL

14

15

16

MAY

JUNE

JULY

181

84

Man - Hour

71,214

34,650

24,024

Mochamad Riza:
307
249
Fill according to Man-Power of
Project that needed (Plan)
Mochamad Riza:
95,784
Automatically

Man - Day

13,683

10,173

4,950

3,432

Salary

3,142,807,221

2,259,738,663

1,099,548,450

762,353,592

26 Days
6 Months

Mochamad Riza:
Fill according to Project Period
(Month)

Mochamad
:
Riza:
Example for calculation. Filled
automatically
=
Man - Power x Ave Work Day per Month x Ave Working Hours per Day
=
=
=
=
=
=
=
=

###
###
###
###
###

YEAR

Automatic

PLAN

Average Work Day per Month


Work Period

Man - Day

Rp
Rp

Man - Power
=
=
=
=

Man - Hour

=
=

1 MANDAY
1 HOUR
TOTAL MANHOURS x 0.14286
TOTAL MANHOURS / 7

Calculation

1,846,400

TOTAL DIRECT COST


TOTAL INDIRECT COST
PHK HARIAN TOTAL
THR TOTAL (@1thn)
SUB TOTAL-2

Notes

Rp

307 Person x 26 Days x 12 Hours


95,784
Man - Hour / 7
95784 /7
13,683
Man - Day x Average Unit per day
13683 x 229687
Rp 3,142,807,221

Man - Power

ACTUAL

Mochamad Riza:
Automatic

Man - Hour

Man - Day

Salary

Mochamad Riza:
Fill according to actual in the
Project

CHECKED BY

APPROVED BY

APPROVED BY

APPROVED BY

APPROVED BY

PREPARED BY

Q-CAS

OD

GM

Section Mngr

Project Mngr

Site Mngr

MAN POWER SCHEDULE FOR ELECTRICAL WORKS

REMARK
: Man - Power Plan
: Man - Power Actual
: Progress Plan
: Progress Actual

100%

90%

80%

70%

60%

50%

40%

30%

20%

10%

10%

16

17

18

19

20

21

22

23

24

JULY

AUGUST

SEPTEMBER

OCTOBER

NOVEMBER

DECEMBER

JANUARY

FEBRUARI

MARCH

2016

2017

CONTRACT PERIOD

Mochamad Riza:

START

according
to Project
:Fill
Apr
'15

PERIOD

: Aug '16

Contract Period

Mochamad Riza:
:
2,427
Automatic

84

26

12

Total ManPower

24,024

5,408

2,184

Total ManHour

676,226

3,432

773

312

Total ManDay

96,604

Total Salary (B)


762,353,592

141,196,180

54,138,552

TOTAL SALARY (A+B)

Total ManPower

Rp

7,459,782,658

Rp

18,648,487,363

Mochamad Riza:
Automatic
:

78

Total ManHour

10,448

Total ManDay

1,493

Total Salary

Rp

275,005,340

Project Name
Location
Project No.

: PT.MITSUBISHI MOTOR KRAMA YUDHA INDONESIA


: GIIC - DELTAMAS - CIKARANG
: E10-15-020

NO

TOTAL ESTIMATED COST


INDIRECT

PROJECT MANAGER
EXPAT ENGINEER
SITE MANAGER
ASSITANT SITE MANAGER
SITE ENGINEER
ASSITANT SITE ENGINEER
DRAFTSMAN
QCAS ENGINEER
SAFETY
TOTAL

=
=
=
=
=
=
=
=
=
=

DIRECT (MAX)

KEPALA TUKANG
TUKANG
PEMBANTU (SR )
PEMBANTU (JR )
TOTAL

280
Mochamad Riza:
Automatic

245
GAJI TUKANG
123,692
GROSS PAY
Rp
8,190,000
12 Hours

TOTAL DIRECT COST

Rp

INDIRECT COST

AVERAGE SALARY PER DAY

=
=
=
=
=
=
=
=

KEPALA TUKANG
TUKANG
PEMBANTU (SR)

Rp

x
x
/
/

9,397,569,308

Mochamad Riza:
Mochamad Riza:
Mochamad Riza:
1.49
=
Rp
183,750
Automatic according
Automatically
to Project
according to Automatic
DAYS
WORKSalary
Location
Highest
(See Average
Salary Working Mochamad Riza:
26 Days
= Fill
Rp
315,000
Table
Below and
Hour
per
A39)
Day)
Automatic
Mochamad
Riza:
Automatic according to
Highest Average Working Hour
per Day
Mochamad Riza:
Automatic

1
3
3
3
3
1
1

Person
Person
Person
Person
Person
Person
Person

x
x
x
x
x
x
x

12
10
12
11
11
11
9

Months
Months
Months
Months
Months
Months
Months

x
x
x
x
x
x
x

Rp11,000,000
Rp11,000,000
Rp15,000,000
Rp6,500,000
Rp8,000,000
Rp7,000,000
Rp8,000,000

=
=
=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp

Mochamad Riza:
Automatic
140

132,000,000
330,000,000
540,000,000
214,500,000
264,000,000
105
77,000,000
72,000,000
Mochamad Riza:
1,629,500,000

Automatic

70

:
=
=
=

210

175

Mochamad Riza: Mochamad Riza: Mochamad Riza:


Mochamad Riza:
x
x
=
Rp
Automatic
Automatic
Fill according to Project Fill according to Project

PHK HARIAN

8 Person
39 Person
78 Person
149 Person
274 Person

AVERAGE WORKING HOUR


PER DAY

Mochamad Riza:
Automatic

=
=
=
=
=

EXPAT ENGINEER
SITE MANAGER
ASSITANT SITE MANA
SITE ENGINEER
ASSITANT SITE ENGIN
DRAFTSMAN
QCAS ENGINEER
SAFETY
TOTAL

Author:
You
can adjust maximum scale
350
here, the scale ##
will filled
automatically ##

315

=
=
=
=
=

AVERAGE UNIT PER MANDAYS

Author:
Fill according to Project

1 Person
2 Person
1 Person
3 Person
3 Person
3 Person
3 Person
2 Person
1 Person
19 Person

SALARY FOR DIRECT (MAX)

MAN POWER

8 Person
39 Person
78 Person

x
x
x

Mochamad Riza:

Mochamad Riza:

Rp
4,288,000
=
Rp
Automatic according to Labour
Automatic
Rp
4,123,100
=
Rp
(Max)
Rp
3,636,000
=
Rp

Mochamad Riza:

34,304,000
Automatic
160,800,900
283,608,000

35

##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
###
###
###
###
###
###
###
###
###

Mochamad Riza:
Mochamad Riza:
Automatic according to Labour
Automatic
(Max)

6
PEMBANTU (JR)
TOTAL

TOTAL COST

=
=
=
=
=

Average Work Day per Month


Work Period

=
=

Man - Day

Salary

=
=

Rp
Rp

283,608,000
Mochamad Riza:
762,320,900

35

Automatic

Rp
Rp
Rp
Rp
Rp

9,397,569,308
1,629,500,000
762,320,900
47,785,400
11,837,175,608

Mochamad Riza:
Automatic
Mochamad Riza:
Automatic

MONTH

Mochamad Riza:
Automatic

:
=
=
=
=
=
=
=
=
=

7 WORKING HOURS
0.14286 MANDAYS
MANDAYS
MANDAYS
26 Days
16 Months

Mochamad Riza:
Fill according to Project Period
(Month)

Mochamad Riza:
Example for calculation.
Filled
automatically
Man
- Power
x Ave Work Day per Month x Ave Working Hours per Day
249 Person x 26 Days x 12 Hours
77,688
Man - Hour / 7
77688 /7
11,098
Man - Day x Average Unit per day
11098 x 183750
Rp
2,039,257,500

###
###
###
###
###

Mochamad Riza:
Fill according to Project
2

APRIL

MAY

JUNE

JULY

YEAR

PLAN

=
=
=
=

Man - Hour

3,636,000

1 MANDAY
1 HOUR
TOTAL MANHOURS x 0.14286
TOTAL MANHOURS / 7

Calculation

Rp

TOTAL DIRECT COST


TOTAL INDIRECT COST
PHK HARIAN TOTAL
THR TOTAL (@1thn)
SUB TOTAL-1

Notes

ACTUAL

149 Person

Mochamad Riza:
Automatic

2015
Mochamad Riza:
12
Fill according to Man-Power of
Project that needed (Plan)

Man - Power

17

17

Man - Hour

525

3,536

4,200

Man - Day

75

357

505

600

Salary

10,411,275

52,167,696

73,794,640

87,676,800

Man - Power

17

17

Man - Hour

298

1,169

2,639

1,862

Man - Day

43

167

377

266

Salary

3,503,480

28,128,018

65,128,251

69,882,907

Mochamad Riza:
2,496
Automatically

Mochamad Riza:
Fill according to actual
in the
12
Project

CHECKED BY

APPROVED BY

APPROVED BY

APPROVED BY

APPROVED BY

PREPARED BY

Q-CAS

OD

GM

Section Mngr

Project Mngr

Site Mngr

MAN POWER SCHEDULE FOR ELECTRICAL WORKS

REMARK
: Man - Power Plan
: Man - Power Actual
: Progress Plan
: Progress Actual

100%

90%

80%

70%

60%

50%

40%

30%

20%

10%

10%

10

11

12

AUGUST

SEPTEMBER

OCTOBER

NOVEMBER

DECEMBER

JANUARY

FEB

MARCH

2015

2016

CONTRACT PERIOD
START

: Apr '15

PERIOD

: Aug '16

Mochamad Riza:
Fill according to Project
Contract Period

Mochamad Riza:
1,400
Automatic

41

81

123

163

196

222

249

274

Total ManPower

8,528

16,848

28,782

38,142

50,960

63,492

77,688

85,488

Total ManHour

380,685

1,218

2,407

4,112

5,449

7,280

9,070

11,098

12,213

Total ManDay

54,384

177,983,904

351,730,096

648,450,064

859,290,953

1,240,883,280

1,611,784,350

2,039,257,500

2,244,138,750

Total Salary (A)

Rp

9,397,569,308

Mochamad Riza:
Automatic
51

Total ManPower

Total ManHour

5,968

Total ManDay

853

Total Salary

Rp

166,642,656

Project Name
Location
Project No.

: PT.MITSUBISHI MOTOR KRAMA YUDHA INDONESIA


: GIIC - DELTAMAS - CIKARANG
: E10-15-020

NO

TOTAL ESTIMATED COST


INDIRECT

PROJECT MANAGER
EXPAT ENGINEER
SITE MANAGER
ASSITANT SITE MANAGER
SITE ENGINEER
ASSITANT SITE ENGINEER
DRAFTSMAN
QCAS Engineer
SAFETY
TOTAL

Author:

=
=
=
=
=
=
=
=
=
=

DIRECT (MAX)

MAN POWER

1 Person
Fill according to Project
2 Person
1 Person
3 Person
3 Person
3 Person
3 Person
2 Person
1 Person
Mochamad Riza:
19 Person

Author:
You can adjust
maximum
350
##
scale here, the scale will filled
##
automatically

Automatic

315

KEPALA TUKANG
TUKANG
PEMBANTU (SR )
PEMBANTU (JR )
TOTAL

=
=
=
=
=

8 Person
39 Person
78 Person
149 Person
274 Person
Mochamad Riza:

280

Automatic
SALARY FOR DIRECT (MAX)

AVERAGE UNIT PER MANDAYS


3

=
=
=
=
=

AVERAGE SALARY PER DAY


AVERAGE WORKING HOUR
PER DAY

245

TOTAL DIRECT COST

INDIRECT COST

GAJI TUKANG
x
K
Mochamad Mochamad
Riza:
Riza:
154,615
x
1.44
=
Rp
Automatic according
Automatically
to Project
according to
GROSS PAY Location/ Salary
DAYS
WORK
Highest
(See Salary
Average Working
Rp
7,260,522
/
26 Days
Rp
Table
Below
and
Hour
Fill
per
A39)
Day)=
Mochamad
Riza:
11 Hours
Rp

1
3
3
3
3
1
1

PHK HARIAN

KEPALA TUKANG
TUKANG
PEMBANTU (SR)

Rp

6,064,387,261

Person
Person
Person
Person
Person
Person
Person

x
x
x
x
x
x
x

8
5
7
6
6
6
6

Mochamad Riza:
Automatic

Mochamad Riza:
x
Fill according to Project

Months
Months
Months
Months
Months
Months
Months

x
x
x
x
x
x
x

175

Mochamad Riza:
=
Rp
Fill according to Project

Rp13,750,000
Rp13,750,000
Rp18,750,000
Rp8,125,000
Rp10,000,000
Rp8,750,000
Rp10,000,000

=
=
=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp

Mochamad Riza:
Automatic

110,000,000
206,250,000
393,750,000
146,250,000
180,000,000
52,500,000
60,000,000
Mochamad Riza:
1,148,750,000

140

105

Automatic

70

:
=
=
=

210

Automatic according to
Highest Average Working Hour
per Day

Mochamad Riza: Mochamad Riza:


x
Automatic

EXPAT ENGINEER
=
Automatic
SITE MANAGER
=
ASSITANT SITE MANA
=
SITE ENGINEER
=
ASSITANT SITE ENGIN =
DRAFTSMAN
=
QCAS Engineer
=
SAFETY
=
TOTAL

Mochamad Riza:
222,131
Automatic
Mochamad Riza:
279,251
Automatic

Mochamad Riza:

Mochamad Riza:

8 Person
x
Rp
2,010,000
=
Rp
Automatic according to Labour
Automatic
39 Person
Rp
1,932,700
=
Rp
(Max) x
78 Person
x
Rp
1,846,400
=
Rp

Mochamad Riza:
16,080,000
Automatic
75,375,300
144,019,200

35

##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
###
###
###
###
###
###
###
###
###

Mochamad Riza:
Mochamad Riza:
Automatic according to Labour
Automatic
(Max)

6
PEMBANTU (JR)
TOTAL

149 Person

TOTAL COST

1,846,400

=
=

Rp
Rp

144,019,200

TOTAL (1+2)

=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp

Mochamad Riza:

6,064,387,261
Automatic
Mochamad Riza:
1,148,750,000
Automatic
379,493,700
1,278,690,800
Mochamad Riza:
8,871,321,761
Automatic
MochamadROUNDED
Riza:
Rp
20,708,497,369

MONTH

Average Work Day per Month


Work Period

7 WORKING HOURS
0.14286 MANDAYS
MANDAYS
MANDAYS

=
=

PLAN

Man - Power
=
=
=
=

Man - Day

Salary

Mochamad Riza:
:
Example for calculation. Filled
automatically
=
=
=
=
=
=
=
=
=

Mochamad Riza:
Fill according
13 to Project

APRIL

14

15

16

MAY

JUNE

JULY

152

81

Man - Hour

55,484

43,472

21,060

Mochamad Riza:
220
194
Fill according to Man-Power
of Project that needed (Plan)
Mochamad Riza:
62,920
Automatically

Man - Day

8,989

7,926

6,210

3,009

Salary

1,996,735,559

1,760,610,306

1,379,433,510

641,109,576

26 Days
6 Months
Mochamad Riza:

Fill according to Project Period


(Month)

Man - Hour

###
###
###
###
###

YEAR

20,725,000,000

Automatic

1 MANDAY
1 HOUR
TOTAL MANHOURS x 0.14286
TOTAL MANHOURS / 7

Calculation

35

Mochamad Riza:
379,493,700
Automatic

TOTAL DIRECT COST


TOTAL INDIRECT COST
PHK HARIAN TOTAL
THR TOTAL (@1thn)
SUB TOTAL-2

Notes

Rp

Man - Power x Ave Work Day per Month x Ave Working Hours per Day
220 Person x 26 Days x 11 Hours
62,920
Man - Hour / 7
62920 /7
8,989
Man - Day x Average Unit per day
8989 x 222131
Rp 1,996,735,559

Man - Power

ACTUAL

Mochamad Riza:
Automatic

Man - Hour

Man - Day

Salary

Mochamad Riza:
Fill according to actual in the
Project

CHECKED BY

APPROVED BY

APPROVED BY

APPROVED BY

APPROVED BY

PREPARED BY

Q-CAS

OD

GM

Section Mngr

Project Mngr

Site Mngr

MAN POWER SCHEDULE FOR ELECTRICAL WORKS

REMARK
: Man - Power Plan
: Man - Power Actual
: Progress Plan
: Progress Actual

100%

90%

80%

70%

60%

50%

40%

30%

20%

10%

10%

16

17

18

19

20

21

22

23

24

JULY

AUGUST

SEPTEMBER

OCTOBER

NOVEMBER

DECEMBER

JANUARY

FEBRUARI

MARCH

2016

2017

CONTRACT PERIOD

Mochamad Riza:

START

to Project
: Fill
Apraccording
'15

PERIOD

: Aug '16

Contract Period

Mochamad Riza:
:
2,104
Automatic

81

32

12

Total ManPower

21,060

6,656

2,184

1,456

910

Total ManHour

574,827

3,009

951

312

208

130

Total ManDay

82,119

Total Salary (B)


641,109,576

173,709,660

54,138,552

36,092,368

22,557,730

TOTAL SALARY (A+B)

Total ManPower

Rp

6,064,387,261

Rp

15,461,956,569

Mochamad Riza:
Automatic
:

51

Total ManHour

5,968

Total ManDay

853

Total Salary

Rp

166,642,656

Project Name
Location
Project No.

: PT.MITSUBISHI MOTOR KRAMA YUDHA INDONESIA - NEW FACTORY PROJECT


: GIIC - DELTAMAS - CIKARANG
: E10-15-020

NO

TOTAL ESTIMATED COST


INDIRECT

PROJECT MANAGER
EXPAT ENGINEER
SITE MANAGER
ASSITANT SITE MANAGER
SITE ENGINEER
ASSITANT SITE ENGINEER
DRAFTSMAN
QCAS ENGINEER
SAFETY
TOTAL

=
=
=
=
=
=
=
=
=
=

DIRECT (MAX)

KEPALA TUKANG
TUKANG
PEMBANTU (SR )
PEMBANTU (JR )
TOTAL

280
Mochamad Riza:
Automatic

245
GAJI TUKANG
123,692
GROSS PAY
Rp
8,190,000
12 Hours

TOTAL DIRECT COST

Rp

INDIRECT COST

AVERAGE SALARY PER DAY

=
=
=
=
=
=
=
=

KEPALA TUKANG
TUKANG
PEMBANTU (SR)

Rp

x
x
/
/

9,397,569,308

Mochamad Riza:
Mochamad Riza:
Mochamad Riza:
1.49
=
Rp
183,750
Automatic according
Automatically
to Project
according to Automatic
DAYS
WORKSalary
Location
Highest
(See Average
Salary Working Mochamad Riza:
26 Days
= Fill
Rp
315,000
Table
Below and
Hour
per
A39)
Day)
Automatic
Mochamad
Riza:
Automatic according to
Highest Average Working Hour
per Day
Mochamad Riza:
Automatic

1
3
3
4
3
1
1

Person
Person
Person
Person
Person
Person
Person

x
x
x
x
x
x
x

12
10
12
11
11
11
9

Months
Months
Months
Months
Months
Months
Months

x
x
x
x
x
x
x

Rp11,000,000
Rp11,000,000
Rp15,000,000
Rp6,500,000
Rp8,000,000
Rp7,000,000
Rp8,000,000

=
=
=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp

Mochamad Riza:
Automatic
140

132,000,000
330,000,000
540,000,000
286,000,000
264,000,000
105
77,000,000
72,000,000
Mochamad Riza:
1,701,000,000

Automatic

70

:
=
=
=

210

175

Mochamad Riza: Mochamad Riza: Mochamad Riza:


Mochamad Riza:
x
x
=
Rp
Automatic
Automatic
Fill according to Project Fill according to Project

PHK HARIAN

8 Person
39 Person
78 Person
149 Person
274 Person

AVERAGE WORKING HOUR


PER DAY

Mochamad Riza:
Automatic

=
=
=
=
=

EXPAT ENGINEER
SITE MANAGER
ASSITANT SITE MANA
SITE ENGINEER
ASSITANT SITE ENGIN
DRAFTSMAN
QCAS ENGINEER
SAFETY
TOTAL

Author:
You
can adjust maximum scale
350
here, the scale ##
will filled
automatically ##

315

=
=
=
=
=

AVERAGE UNIT PER MANDAYS

Author:
Fill according to Project

1 Person
2 Person
1 Person
3 Person
3 Person
3 Person
3 Person
2 Person
1 Person
19 Person

SALARY FOR DIRECT (MAX)

MAN POWER

8 Person
39 Person
78 Person

x
x
x

Mochamad Riza:

Mochamad Riza:

Rp
4,288,000
=
Rp
Automatic according to Labour
Automatic
Rp
4,123,100
=
Rp
(Max)
Rp
3,636,000
=
Rp

Mochamad Riza:

34,304,000
Automatic
160,800,900
283,608,000

35

##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
###
###
###
###
###
###
###
###
###

Mochamad Riza:
Mochamad Riza:
Automatic according to Labour
Automatic
(Max)

6
PEMBANTU (JR)
TOTAL

TOTAL COST

=
=
=
=
=

Average Work Day per Month


Work Period

=
=

Man - Day

Salary

=
=

Rp
Rp

283,608,000
Mochamad Riza:
762,320,900

35

Automatic

Rp
Rp
Rp
Rp
Rp

9,397,569,308
1,701,000,000
762,320,900
47,785,400
11,908,675,608

Mochamad Riza:
Automatic
Mochamad Riza:
Automatic

MONTH

Mochamad Riza:
Automatic

:
=
=
=
=
=
=
=
=
=

7 WORKING HOURS
0.14286 MANDAYS
MANDAYS
MANDAYS
26 Days
16 Months

Mochamad Riza:
Fill according to Project Period
(Month)

Mochamad Riza:
Example for calculation.
Filled
automatically
Man
- Power
x Ave Work Day per Month x Ave Working Hours per Day
249 Person x 26 Days x 12 Hours
77,688
Man - Hour / 7
77688 /7
11,098
Man - Day x Average Unit per day
11098 x 183750
Rp
2,039,257,500

###
###
###
###
###

Mochamad Riza:
Fill according to Project
2

APRIL

MAY

JUNE

JULY

YEAR

PLAN

=
=
=
=

Man - Hour

3,636,000

1 MANDAY
1 HOUR
TOTAL MANHOURS x 0.14286
TOTAL MANHOURS / 7

Calculation

Rp

TOTAL DIRECT COST


TOTAL INDIRECT COST
PHK HARIAN TOTAL
THR TOTAL (@1thn)
SUB TOTAL-1

Notes

ACTUAL

149 Person

Mochamad Riza:
Automatic

2015
Mochamad Riza:
12
Fill according to Man-Power of
Project that needed (Plan)

Man - Power

17

17

Man - Hour

525

3,536

4,200

Man - Day

75

357

505

600

Salary

10,411,275

52,167,696

73,794,640

87,676,800

Man - Power

17

17

Man - Hour

298

1,169

2,639

1,862

Man - Day

43

167

377

266

Salary

3,503,480

28,128,018

65,128,251

69,882,907

Mochamad Riza:
2,496
Automatically

Mochamad Riza:
Fill according to actual
in the
12
Project

CHECKED BY

APPROVED BY

APPROVED BY

APPROVED BY

APPROVED BY

PREPARED BY

Q-CAS

OD

GM

Section Mngr

Project Mngr

Site Mngr

MAN POWER SCHEDULE FOR ELECTRICAL WORKS

REMARK
: Man - Power Plan
: Man - Power Actual
: Progress Plan
: Progress Actual

100%

90%

80%

70%

60%

50%

40%

30%

20%

10%

10%

10

11

12

AUGUST

SEPTEMBER

OCTOBER

NOVEMBER

DECEMBER

JANUARY

FEB

MARCH

2015

2016

CONTRACT PERIOD
START

: Apr '15

PERIOD

: Aug '16

Mochamad Riza:
Fill according to Project
Contract Period

Mochamad Riza:
1,400
Automatic

41

81

123

163

196

222

249

274

Total ManPower

8,528

16,848

28,782

38,142

50,960

63,492

77,688

85,488

Total ManHour

380,685

1,218

2,407

4,112

5,449

7,280

9,070

11,098

12,213

Total ManDay

54,384

177,983,904

351,730,096

648,450,064

859,290,953

1,240,883,280

1,611,784,350

2,039,257,500

2,244,138,750

27

42

48

67

Total ManPower

4,480

7,322

9,793

13,944

Total ManHour

41,507

640

1,046

1,399

1,992

Total ManDay

5,930

108,362,684

209,742,884

383,534,556

382,391,472

Total Salary

Total Salary (A)

Rp

9,397,569,308

Mochamad Riza:
Automatic
235

Rp

1,250,674,252

Project Name
Location
Project No.

: PT.MITSUBISHI MOTOR KRAMA YUDHA INDONESIA - NEW FACTORY PROJECT


: GIIC - DELTAMAS - CIKARANG
: E10-15-020

NO

TOTAL ESTIMATED COST


INDIRECT

PROJECT MANAGER
EXPAT ENGINEER
SITE MANAGER
ASSITANT SITE MANAGER
SITE ENGINEER
ASSITANT SITE ENGINEER
DRAFTSMAN
QCAS Engineer
SAFETY
TOTAL

Author:

=
=
=
=
=
=
=
=
=
=

DIRECT (MAX)

MAN POWER

1 Person
Fill according to Project
2 Person
1 Person
3 Person
3 Person
3 Person
3 Person
2 Person
1 Person
Mochamad Riza:
19 Person

Author:
You can adjust350
maximum
##
scale here, the scale will filled
##
automatically

Automatic

315

KEPALA TUKANG
TUKANG
PEMBANTU (SR )
PEMBANTU (JR )
TOTAL

=
=
=
=
=

8 Person
39 Person
78 Person
149 Person
274 Person
Mochamad Riza:

280

Automatic
SALARY FOR DIRECT (MAX)

AVERAGE UNIT PER MANDAYS


3

=
=
=
=
=

AVERAGE SALARY PER DAY


AVERAGE WORKING HOUR
PER DAY

245

TOTAL DIRECT COST

INDIRECT COST

GAJI TUKANG
x
K
Mochamad Riza:
Mochamad Riza:
154,615
x
1.44
=
Rp
Automatic according
Automatically
to Project
according to
GROSS PAY
/
DAYS
WORK
Location Salary
Highest
(See Salary
Average Working
Rp
7,260,522
/ and
26
Days
Rp
Table
Below
Hour
Fillper
A39)
Day) =
Mochamad
Riza:
11 Hours
Rp

1
3
3
4
3
1
1

PHK HARIAN

KEPALA TUKANG
TUKANG
PEMBANTU (SR)

Rp

6,064,387,261

Person
Person
Person
Person
Person
Person
Person

x
x
x
x
x
x
x

8
5
7
7
6
6
6

Mochamad Riza:
Automatic

Mochamad Riza:
x
Fill according to Project

Months
Months
Months
Months
Months
Months
Months

x
x
x
x
x
x
x

175

Mochamad Riza:
=
Rp
Fill according to Project

Rp13,750,000
Rp13,750,000
Rp18,750,000
Rp8,125,000
Rp10,000,000
Rp8,750,000
Rp10,000,000

=
=
=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp

Mochamad Riza:
Automatic

110,000,000
206,250,000
393,750,000
227,500,000
180,000,000
52,500,000
60,000,000
Mochamad Riza:
1,230,000,000

140

105

Automatic

70

:
=
=
=

210

Automatic according to
Highest Average Working Hour
per Day

Mochamad Riza: Mochamad Riza:


x
Automatic

EXPAT ENGINEER
=
Automatic
SITE MANAGER
=
ASSITANT SITE MANA
=
SITE ENGINEER
=
ASSITANT SITE ENGIN =
DRAFTSMAN
=
QCAS Engineer
=
SAFETY
=
TOTAL

Mochamad Riza:
222,131
Automatic
Mochamad Riza:
279,251
Automatic

Mochamad Riza:

8 Person
x
Rp
Automatic according
39 Person
x
Rp
Labour (Max)
78 Person
x
Rp

Mochamad Riza:

2,010,000
=
Automatic
1,932,700
=
1,846,400
=

to

Rp
Rp
Rp

Mochamad Riza:
16,080,000
Automatic
75,375,300
144,019,200

35

##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
###
###
###
###
###
###
###
###
###

Mochamad Riza:
Automatic according to
Labour (Max)

6
PEMBANTU (JR)
TOTAL

TOTAL COST

Rp

1,846,400

=
=

Rp
Rp

144,019,200

TOTAL (1+2)

=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp

Mochamad Riza:

6,064,387,261
Automatic
Mochamad Riza:
1,230,000,000
Automatic
379,493,700
1,278,690,800
Mochamad Riza:
8,952,571,761
Automatic
Mochamad ROUNDED
Riza:
Rp
20,861,247,369

MONTH

Average Work Day per Month


Work Period

7 WORKING HOURS
0.14286 MANDAYS
MANDAYS
MANDAYS

=
=

PLAN

Man - Power
=
=
=
=

Man - Day

Salary

Mochamad Riza:
:
Example for calculation. Filled
automatically
=
=
=
=
=
=
=
=
=

Mochamad Riza:
Fill according
13 to Project

APRIL

14

15

16

MAY

JUNE

JULY

152

81

Mochamad Riza:
220
194
Fill according to Man-Power
of Project that needed (Plan)

Man - Hour

Mochamad Riza:
62,920
Automatically

55,484

43,472

21,060

Man - Day

8,989

7,926

6,210

3,009

Salary

1,996,735,559

1,760,610,306

1,379,433,510

641,109,576

26 Days
6 Months
Mochamad Riza:

Fill according to Project


Period (Month)

Man - Hour

###
###
###
###
###

YEAR

20,880,000,000

Automatic

1 MANDAY
1 HOUR
TOTAL MANHOURS x 0.14286
TOTAL MANHOURS / 7

Calculation

35

Mochamad Riza:
379,493,700
Automatic

TOTAL DIRECT COST


TOTAL INDIRECT COST
PHK HARIAN TOTAL
THR TOTAL (@1thn)
SUB TOTAL-2

Notes

Mochamad Riza:
Automatic

Man - Power x Ave Work Day per Month x Ave Working Hours per Day
220 Person x 26 Days x 11 Hours
62,920
Man - Hour / 7
62920 /7
8,989
Man - Day x Average Unit per day
8989 x 222131
Rp 1,996,735,559

Man - Power

ACTUAL

149 Person

Mochamad Riza:
Automatic

Man - Hour

Man - Day

Salary

Mochamad Riza:
Fill according to actual in
the Project

CHECKED BY

APPROVED BY

APPROVED BY

APPROVED BY

APPROVED BY

PREPARED BY

Q-CAS

OD

GM

Section Mngr

Project Mngr

Site Mngr

MAN POWER SCHEDULE FOR ELECTRICAL WORKS

REMARK
: Man - Power Plan
: Man - Power Actual
: Progress Plan
: Progress Actual

100%

90%

80%

70%

60%

50%

40%

30%

20%

10%

10%

16

17

18

19

20

21

22

23

24

JULY

AUGUST

SEPTEMBER

OCTOBER

NOVEMBER

DECEMBER

JANUARY

FEBRUARI

MARCH

2016

2017

CONTRACT PERIOD

Mochamad Riza:
Fill
according
to Project
: Apr
'15
Contract Period

START
PERIOD

: Aug '16

Mochamad Riza:
:
Automatic

81

32

12

Total ManPower

21,060

6,656

2,184

1,456

910

Total ManHour

574,827

3,009

951

312

208

130

Total ManDay

82,119

Total Salary (B)


641,109,576

173,709,660

54,138,552

36,092,368

22,557,730

TOTAL SALARY (A+B)

Total ManPower

2,104

Rp

6,064,387,261

Rp

15,461,956,569

Mochamad Riza:
Automatic
:

235

Total ManHour

41,507

Total ManDay

5,930

Total Salary

Rp

1,250,674,252