Professional Documents
Culture Documents
Effective Contract Management - All
Effective Contract Management - All
of the
Contract
Life Cycle
Contract Life Cycle
AWARD &
CONTRACT SIGNATURE
Employer
(Client)
Engineer Construction
Mian Contract
( Consultant) management
Vs Sub-
Contractor Contract
Sub-contractor
Mian Contract Vs Sub-Contract
EMPLOYER
(CLIENT)
Contract
CONSULTANTS
CONTRACTOR Subcontract
(MANAGEMEN
T
CONTRACTOR)
SUBCONTRACTORS
Partnership:
Joint
Venture (JV)
or
Consortium
Scope split is not necessary.
The work is done as if one
company does it.
Profit and loss are not shared. Only joint costs are shared. The joint costs
could be like the auditing expenses or the cost of managers working
Consortium
Managing
Managing Managing
JV/Consortium
Main Contract Subcontracts
Agreement
Thank you
Roles and
Responsibilities
Roles and Responsibilities
Contract
management
responsibilities
matrix.
is a good solution to
developed at the very
the question of “who is
beginning of a Project
doing what?”
to be performed to
is comprehensive list of administer a Contract
successfully
Responsibilities
tasks (main tasks and
sub-tasks) •is a good way of defining,
communicating, and
Matrix
assigning tasks to
individuals
Can be done (by Contract
Administrator) for each
contract
periodically reviewed,
revised, and re-distributed
Refer to the matrix example
Who manages
the contracts?
Contract Manager (most
common)
Contract Administrator
Typical Titles
Contract Specialist
Used for the
Role
Commercial Manager
Contract
administrator Establish Contract Baseline
– Main Tasks
Form Contract
Requirements Action List
and Flow-Downs
Develop Contract
Administration Manual
Contract
Establish Document Control
administrator Center
– Main Tasks
Do Contract Filing
Train the Team for Commercial
Awareness
Handle Correspondences
Contract
administrator
– Main Tasks Administer Changes
Contract
administrator Handle Handle Backcharges
– Main Tasks
Contract
administrator Manage Warranties
– Main Tasks
Manage Close-out
Developing
use software as possible to
strong add workflows
(DCC).
handle revisions
monitor Project submittals
(drawings, specifications, etc.)
Main Points
to Identify A party assigned for
While coordinating all others
Reading
Flow-down requirements
mentioned
Contract Baseline
Contract Baseline: what we base our price
o Escalate
o Exploit
o Share
o Enhance
o Accept
Example
Actions,
Notices,
Liabilities
Flow-downs
➢ Done while reading the full contract
Identifying subcontracts
Liability
Flow-down
Training the Team
Training the Team
✓ Stop-work requirements
o Pre-Bid Site Visit: An opportunity for bidders to see the site in all aspects and familiarize
themselves with the local conditions.
o Two-Stage Tendering
o Negotiated Tender
✓ Traditional Lump-Sum
✓ Traditional Re-measurement
✓ Cost Reimbursable
The main types of procurement routes
✓ Construction Management
✓ Management Contracting
o IChemE Contracts
tender.
✓ Tender packages should be issued together with the draft agreement and its
attachments.
Bid Evaluation
and Award
Bid Evaluation process
Thank You to
Bids Bids Bids Work
Unsuccessful
Received Evaluated Negotiated Awarded
Bidders
Bid Evaluation
✓ Bids are initially checked for completeness, validity, and bid bonds.
✓ Bids getting the higher overall score are selected for negotiation.
Award
✓ Upon successful negotiation with the high score bidders, the award takes place
with the preferred bidder.
✓ After the subcontract is signed and insurance certificates and performance bond
are received, then the bid bonds of unsuccessful bidders should be returned.
✓ Don’t forget: Letters are the main records for legal ramifications
Incoming
Letters If full answer is expected to delay,
an interim reply can be sent.
Correspondence Log
Log Update
Project:
Date:
Contract:
The possibility of an event
occurring that will have
an impact on the
achievement of
objectives.
Risk is measured in terms
of impact and likelihood.
Risk
Management
A process to identify,
assess, manage, and
control potential events or
situations to provide
reasonable assurance
regarding the
achievement of the
organization’s objectives.
In some projects, Employer provides
Construction All Risk (CAR) insurance
and/or Marine Cargo All Risk insurance.
o Claims Made: A 'claims made' basis covers claims that are made and
reported during the policy period only and not once the policy period
is over, which restricts the time that is allowed to make a claim.
should be mentioned in
Third Party Liability
the subcontracts.
Typical insurances
required in a Professional Liability
subcontract are:
Employer’s Liability
Subcontractors should be provided the
copies of insurance policies and made
aware of the deductible limits.
Modifications to the
insurance terms should also
be monitored.
Initiating
Insurance
Claims
First Action: Notify the
insurer (or the principal of
the policy) in time
Initiating
Consult with your insurance
Insurance broker about the event.
Claims
Initiating
Insurance Deductibles and coverage limits
are based on single event, not
Claims combination of multiple events.
(cont’d)
Multiple events might be similar in
nature but considered as
individual single events occurring
at different locations.
Prepare a comprehensive report
of the event which can be
Initiating provided to the loss adjuster
appointed by the insurer.
Insurance
Claims
Non-recovered portion should
(cont’d) be charged to the party
causing the event.
If covered by your insurance
policy, Subcontractors may
want to make use of your
Subcontractor policy.
Insurance
Claim Subcontractors should be
allowed to make their claims
even if the event is due to
Subcontractor’s failure.
Bonds and
Guarantees
Bid Bonds
✓ If the bid is not honored by the bidder, then the bid bond might be forfeited.
✓ Its value may range 2-5% of the estimated value of the work package.
Warranty
and Retention Bond may function as Warranty
Bond.
Retention
Bonds
It is a good practice to request Warranty
Bond (or Retention Bond) from your lower-
tier companies if the whole withheld cash
money needs to be released.
Keeping
Bonds and
Guarantees
Log
✓ All bonds and guarantees, either received
or submitted, should be closely monitored.
✓ One of the most important duties of
Contract Administrator
Keeping Bonds
✓ Requirements for notification on renewal
and Guarantees and/or expiry should be fulfilled in a timely
Log manner.
✓ The original copies of the bonds should be
safely kept ideally by Accounts Department.
Keeping Bonds and Guarantees Log
(Cont’d
Cost
Unit Price Lump-Sum
Reimbursable
material/equipment submittals.
Employer’s approval.
documents.
Request For
✓ Lack of clear information can cause cost
Information
(RFIs) and time impact.
drawing/specification attachments.
Request For
✓ Employer should reply RFIs on time to
Information
avoid delays in the project.
(RFIs)
✓ RFIs and incoming replies should be
tracked in a log.
“Developing
Baseline
Schedule”
Developing Baseline
Schedule
✓ A schedule is the most valuable tool for managing the
project.
✓ All parties coordinate their work according to this
schedule.
✓ The first schedule approved by Employer is called
“baseline schedule”.
Developing Baseline
Schedule
✓ This is the most important submittal in a
project.
✓ Actual progress is always compared to
baseline schedule.
✓ Maintaining the baseline schedule is the
prime responsibility of Contractor.
✓ Slippages on the schedule may or may not
be compensable by Employer.
✓ Baseline schedule should include the
following information, as minimum:
o Start Date of the Work
o Contract and Project Milestones
objectively.
the reports.
Project Status
Reports ✓ Status Reports later serve for supporting
claim entitlements.
Compliance to
Health, Safety,
and
Environment
(HSE)
Requirements”
✓ All contracts specify the HSE requirements:
Zero-Accident Policy.
Environment
✓ HSE performance should be closely
(HSE)
monitored.
Requirements
✓ Penalties apply in case of performance
failures.
workmanship.
terms.
commercial section.
Warranties (cont’d)
WARRANTY
SUBCONTRACTOR’S/
MANUFACTURER’S SUPPLIER’S
INSTALLER’S
WARRANTY WARRANTY
WARRANTY
✓ For big projects, managing warranties could be
complicated.
(cont’d) Employer.
✓ Extended time for completion or any down times
extension.
notices, etc.
✓ Claims are submitted after carefully thinking
1. Introduction
7. Conclusion
“Acceleration
Claim”
✓ Some contracts define the work
acceleration as a change under certain
conditions.
✓ Defined or not, if an acceleration is ordered
explicitly (directed acceleration) or implied
Acceleration by not giving a time extension
(constructive acceleration), then the
Claim associated costs should be compensated.
✓ An acceleration is done either for
recovering the delay or shortening the
project delivery duration.
✓ Typical cost heads for an acceleration claim
are:
o increased cost for overtime work
o increased cost for weekend and/or
Acceleration holiday works
increased cost for increased manhour
Claim (cont’d)
o
(lower productivity) due to inefficieny
o whole cost of added supervision
✓ whole cost of added tools, plant and
equipment, scaffolding, PPE
o increased cost for short term direct
manpower employment
o whole cost of additional jobsite and HSE
Acceleration training
✓ If acceleration is voluntary to save from
Claim (cont’d) preliminaries costs,
then no acceleration claim should be
submitted.
“Disruption Claim”
✓ The most difficult retrospective (backward
looking) claim to prove and defend for lost
productivity or inefficiency.
✓ Some contracts do not allow disruption
claims explicitly.
Disruption ✓ There is no standard method to calculate
Claim the loss but one is selected and tried based
on the available contemporaneous
documentation in hand.
✓ There might be several factors affecting the
efficiency, so it’s not easy to isolate the
factors caused by Employer.
Disruption ✓ Efforts, which results in a weak or global
Claim claim, might be wasted.
Disruption Claim (cont’d)
✓ The methods for estimating the lost labour productivity can be classified as follows
(SCL Delay and Disruption Protocol 2nd Ed):
Analysis ✓
actual/as-built critical path.
Prospective Delay Analysis: First Cause, Then
(cont’d) Effect
✓ Retrospective Delay Analysis: First Effect, Then
Cause
Time Impact (Delay) Analysis (cont’d)
“Negotiating
and Settling
Claims”
✓ Claims are not settled with their submitted
values.
✓ There is always some negotiation and
Negotiating and challenge while settling them.
Settling Claims ✓ Negotiation should be a fair and equitable
resolution.
✓ After validation of all aspects of the claim, a
settlement amendment agreement can
cover the whole negotiation.
Negotiating and ✓ Be careful not to waive your past and/or
future rights which are not negotiated.
Settling Claims
✓ Unsuccessful negotiations should be
resolved by the dispute resolution process
written in the contract.
Thank you
Closing-out Contract
“Employer's
Acceptance, Taking
Over, and Transfer
of Liability”
Employer's Acceptance, Taking Over, and Transfer of
Liability