2177365-1 Service Report - Juvel - CAT 3508 Top-End
2177365-1 Service Report - Juvel - CAT 3508 Top-End
Ship: Juvel
Job: Top-end
Engine/Gear: CAT 3508
Location: Frederikshavn
Date: January 2018
Project no.: 2177365-1
Installation: Juvel
Location: Frederikshavn
Ordered by: Frode Utgård Date: 13-09-2017
Work performed by: Tommy Svenningsen, Kim Borregård Date started: 23-12-2017
Date finished: 5-1-2018
Work summary
Cat 3508 major overhaul.
SERVICE
REPORT
Ordered / Conducted
Cylinder head:
Cylinder head exchanged with recon cylinder covers.
Tightening specification:
1. step: 200 Nm
2. step: 200 Nm
3. step: 180 °
Piston:
Piston standard overhauled acc. to encl. VMS procedure / measurement record.
Connecting rod:
Connecting rod standard overhauled acc. to encl. VMS procedure / measurement record.
Tightening specification:
1. step: 90 Nm
2. step: 90 °
Cylinder liner:
Cylinder liner exchanged with new.
Engine block:
Engine block cleaned and visually inspected for corrosion / pitting.
Camshaft:
Camshaft visually inspected.
Crankshaft:
Crankshaft journals visually inspected.
Axial clearance:
After: 0,38 mm
Main bearing:
Main bearing inspected.
Tightening specification:
1. step: 190 Nm
2. step: 180 °
Idler gear(s):
Front gear wheels visually inspected.
Pump overhauled.
Coolers:
Charge air cooler cleaned and pressure tested.
Test pressure:
Charge air cooler: 4,5 Bar
Thermostatic elements:
HT thermostat exchanged with new.
Thermostatic housing cleaned and reassembled with new gaskets and seals.
Turbo:
Turbo charger exchanged with recon / new.
Miscellaneous
Fuel lines:
Fuel lines visually inspected for leaks and damages.
Water lines:
Water lines visually inspected for leaks and damages.
Exhaust lines:
Exhaust lines visually inspected for leaks and damages.