You are on page 1of 1

Construction of Masdar Big Square -Roads, Utilities and Public Ream Packages 1A & 1B

Remaining Precast Items Dated 23-Aug-23

Utilities Total Quantity Actual Quantity Remaining

Potable Water Fire Hydrants 21 19 2

Telecom Chambers 57 50 7

Street Light Pull Boxes 410 259 151

Protection Slab (Water Works) 3,650 1,256 2,394

Concrete Barrier (MCC) 23 15 8

Bus Shelter Foundation 14 14

1.0m Pole Foundation - Landscape 47 47

4.0m Pole Foundation - Landscape 66 66

Cover Slab - Water Chamber 18 3 15

Cover Slab - Fire Hydrant Chamber 21 21

Shade Structure Foundation 942 771 171

Bollard 499 5 494

Cycle Rack 84 81 3

Smart Bench 13 13
TOTAL 5,865 2,459 3,406