Delay Event Project Team Discussion Meeting Result

1- Delay Event Information

Event Title Event Source Event Date Event By Notes

Change Marble
SWI 1 20 Jan 2013 Employer
Fixation

2- Impact Discussion

2.1 – New Scope of Work

Activity Estimated
New Activity Name Predecessor Notes
Id Duration
Demolish all fixed marble SWI1_1 3 SWI 1
Submit new method statement for mechanical
SWI1_2 3 SWI 1
fixation
Approved method statement for new method SWI1_3 3 SWI1_2
Material procurement order for new materials SWI1_4 7 SWI1_3

2.1 – Existing Scope of Work

Activity Id Planned
Existing Activity Name Predecessor Notes
Duration
MARBLE WORKS VIP SEC. WALL'S CLADDING
Arch1110 20 SWI1_4
&FLOORING

SWI 1 - Change Marble Fixation


SWI1_1 - Demolish all fixed marble

3 Days
New Activity
SWI1_2 - Submit new method statement for
Existing Activity
mechanical fixation
Finished Work 3 Days
SWI1_3 - Approved method statement for new
method
3 Days SWI1_4 - Material procurement
order for new materials

7 Days
ARCH1110 - MARBLE WORKS VIP SEC. WALL'S CLADDING
&FLOORING

www.planningengineer.net 20 Days Course Link


DaARCH11
10ys
Delay Event Project Team Discussion Meeting Result

1- Delay Event Information

Event Title Event Source Event Date Event By Notes

Change Painting
SWI2 15 March 2013 Employer
Color Code

2- Impact Discussion

2.1 – New Scope of Work

Activity Estimated
New Activity Name Predecessor Notes
Id Duration
Submit new material for approved SWI 2_1 3 SWI 2
Approved new material SWI 2_2 3 SWI 2_1
Material Procurement SWI 2_3 15 SWI 2_2

2.1 – Existing Scope of Work

Activity Id Planned
Existing Activity Name Predecessor Notes
Duration
Painting Site delivery date A2290 169 SWI 2_3

SWI 2 - Change Painting Color Code

SWI2_1 - Submit new material for approved -

3 Days
SWI2_2 - Approved new material

3 Days
SWI2_3 - Material Procurement

15 Days

New Activity
Existing Activity ARCH1080 - Painting Site delivery date
Finished Work

15 Days
www.planningengineer.net DaARCH11 Course Link
10ys
Delay Event Project Team Discussion Meeting Result

1-Delay Event Information

Event Title Event Source Event Date Event By Notes


Under Ground Water
RFI No.3 28 March 2012 Consultant
Level

2-Impact Discussion

2.1 – New Scope of Work

Activity Id Estimated
New Activity Name Predecessor Notes
Duration
Response from Consultant RFI No.3-1 10 RFI No.3
Dewatering RFI No.3-2 10 RFI No.3-1
Soil Replacement RFI No.3-3 7 RFI No.3-2

2.1 – Existing Scope of Work

Activity Id Planned
Existing Activity Name Predecessor Notes
Duration
COMPACTING WORKS UNDER THE P.C LAYER SUBZ100030 3
RFI No.3-3

RFI No.3- Under Ground


Water Level

RFI No.3-1 - Response from Consultant

10
RFI No.3-2 - Dewatering
Days

10 Days
RFI No.3-3 - Soil Replacement

7 Days

New Activity
Existing Activity
SUBZ100030 - COMPACTING WORKS
Finished Work
UNDER THE P.C LAYER

3 Days
www.planningengineer.net DaARCH11 Course Link
10ys
Delay Event Project Team Discussion Meeting Result

1- Delay Event Information

Event Title Event Source Event Date Event By Notes


Clash between
Lighting Unit and RFI- 6- 10-April-2012 10-April-2012 Consultant
Diffuser

2- Impact Discussion

2.1 – New Scope of Work

Activity Estimated
New Activity Name Predecessor Notes
Id Duration
Remove Fixed Lighting Fixture RFI-6- 1 20 RFI- 6
Modify cable and conducts RFI-6- 2 20 RFI-6- 1

2.1 – Existing Scope of Work

Activity Id Planned
Existing Activity Name Predecessor Notes
Duration
0801EL000
LIGHTING FIXTURES& SWITCHS & OUTLETS 60 RFI-6- 2
5

RFI By Contractor
RFI- 6- 10-April-2012 - Clash between Lighting Unit
and Diffuser Response New Activity

Existing
Activity
Finished
RFI-6- 1 - Remove Fixed Lighting Fixture
Work

20
RFI-6- 2 - Modify cable and
conducts -
20

0801EL0005 - LIGHTING FIXTURES& SWITCHS &


OUTLETS

60
www.planningengineer.net Course Link
Delay Event Project Team Discussion Meeting Result

3- Delay Event Information

Event Title Event Source Event Date Event By Notes

Local Authorities
Letter 1 25 March 2012 Employer
Permissions

4- Impact Discussion

2.1 – New Scope of Work

Activity Id Estimated
New Activity Name Predecessor Notes
Duration
Authorities Permissions Letter 1 - 1 20 Letter 1

2.1 – Existing Scope of Work

Activity Id Planned
Existing Activity Name Predecessor Notes
Duration
Excavation Activity SUBz100020 6 Letter 1 - 1

Letter 1 - Authorities Permissions Letter

New Activity
Letter 1 – 1 - Authorities Permissions
Existing Activity
Finished Work 20

SUBz100020 - Excavation Activity

www.planningengineer.net Course Link


Delay Event Project Team Discussion Meeting Result

5- Delay Event Information

Event Title Event Source Event Date Event By Notes

Site Handing Over Letter 2 20 March 2012 Employer

6- Impact Discussion

2.1 – New Scope of Work

Activity Id Estimated
New Activity Name Predecessor Notes
Duration
Site Delivery Delay Letter 2 - 1 10 Letter 2

2.1 – Existing Scope of Work

Activity Id Planned
Existing Activity Name Predecessor Notes
Duration
Mobilization SUBZ100010 26 Letter 2

Letter 2 - Site Handing Over

New Activity
Letter 2 – 1 - Site Delivery Delay
Existing Activity
Finished Work 10

SUBZ100010 - Mobilization

26

www.planningengineer.net Course Link


Delay Event Project Team Discussion Meeting Result

7- Delay Event Information

Event Title Event Source Event Date Event By Notes

Pumps Submittal MAR-20 1 April 2012 Consultant

8- Impact Discussion

2.1 – New Scope of Work

Activity Estimated
New Activity Name Predecessor Notes
Id Duration
New Pumps Submittal MAR-20-1 5 MAR-20
Pumps Approval MAR-20-2 3 MAR-20-1
Pumps Procurement MAR-20-3 180 MAR-20-2

2.1 – Existing Scope of Work

Activity Id Planned
Existing Activity Name Predecessor Notes
Duration
0801MW00
INSTALLATION OF WATER & FIRE PUMPS 17 MAR-20-3
11

MAR-20 - Pumps MAR Response

New Activity
MAR-20-1 - New Pumps Submittal
Existing Activity
Finished Work 5
MAR-20-2 - Pumps Approval

3 MAR-20-3 - Pumps Procurement

180

0801MW0011 - NSTALLATION OF WATER & FIRE PUMPS

17

www.planningengineer.net Course Link


Delay Event Project Team Discussion Meeting Result

9- Delay Event Information

Event Title Event Source Event Date Event By Notes

Lighting Fixture Type 12-May-12


MAR 4 Consultant
2*26 w

10- Impact Discussion

2.1 – New Scope of Work

Activity Estimated
New Activity Name Predecessor Notes
Id Duration
Delay of MAR response MAR 4-1 27 MAR 4

2.1 – Existing Scope of Work

Activity Id Planned
Existing Activity Name Predecessor Notes
Duration
LIGHTING FIXTURES& SWITCHS Procurement A2250 47 MAR 4-1

MAR 4 -

New Activity
MAR 4-1 – Delay of MAR response
Existing Activity
Finished Work 27

A2250 - LIGHTING FIXTURES& SWITCHS


Procurement
47

www.planningengineer.net Course Link


Delay Event Project Team Discussion Meeting Result

11- Delay Event Information

Event Title Event Source Event Date Event By Notes

Doors and Windows


SDF 2 21 April 2012 Consultant
Shop Drawing

12- Impact Discussion

2.1 – New Scope of Work

Activity Estimated
New Activity Name Predecessor Notes
Id Duration
New Door Submittal SDF 2-1 5 SDF 2
New Door Approval SDF 2-2 3 SDF 2-1
Door Procurement SDF 2-3 280 SDF 2-2

2.1 – Existing Scope of Work

Activity Id Planned
Existing Activity Name Predecessor Notes
Duration
WOODEN DOORS INSTALLING ARCH1150
14 SDF 2-3

SDF 2 - Doors And Windows Response

New Activity
SDF 2-1 - New Door Submittal
Existing Activity
Finished Work 5
SDF 2-2 - New Door Approval

3 SDF 2-3 - Door Procurement

280

ARCH1150 - WOODEN DOORS INSTALLING

14

www.planningengineer.net Course Link


Delay Event Project Team Discussion Meeting Result

1- Delay Event Information

Event Title Event Source Event Date Event By Notes


Item no.1 ( Utilities
will be available on 1 MEETING NO.13 2-January 2013 Employer
July 2013 ).

2- Impact Discussion

2.1 – New Scope of Work

Activity Id Estimated
New Activity Name Predecessor Notes
Duration
MEETING
Delay of Utilities availability MOM-13-1 210
NO.13

2.1 – Existing Scope of Work

Activity Id Planned
Existing Activity Name Predecessor Notes
Duration
Elevators TESTING AND COMMISSIONING A2450 22
MOM-13-1
Finishes Touch up & Commissioning Site 10090 14
MOM-13-1
Mechanical Testing & Commissioning Site 10100 23
MOM-13-1
Electrical Testing & Commissioning Site 10110 26
MOM-13-1

MEETING NO.13
MOM-13-1 - Delay of Utilities
availability
210
New Activity
Existing Activity
Finished Work A2450 - Elevators TESTING AND COMMISSIONING
22
Site 10090- Finishes Touch up & Commissioning
COMMISSIONING
14
Site 10100 - Mechanical Testing & Commissioning

23 Site 10110 - Electrical Testing & Commissioning

www.planningengineer.net 26 Course Link


Delay Event Project Team Discussion Meeting Result

3- Delay Event Information

Event Title Event Source Event Date Event By Notes

Supplying Safe door MEETING NO.9 1-Septmber 2012 Employer

4- Impact Discussion

2.1 – New Scope of Work

Activity Estimated
New Activity Name Predecessor Notes
Id Duration
Safe Door Supplying Delay
MOM 9-1 60 MOM No.9

2.1 – Existing Scope of Work

Activity Id Planned
Existing Activity Name Predecessor Notes
Duration
Wall Preparation for Painting Arch1070 21 MOM 9-1

MEETING NO.9 - Supplying Safe door


MOM 9-1 - Safe Door Supplying Delay

60

New Activity
Existing Activity
Arch1070 - Wall Preparation for Painting
Finished Work

21