Change Marble
SWI 1 20 Jan 2013 Employer
Fixation
2- Impact Discussion
Activity Estimated
New Activity Name Predecessor Notes
Id Duration
Demolish all fixed marble SWI1_1 3 SWI 1
Submit new method statement for mechanical
SWI1_2 3 SWI 1
fixation
Approved method statement for new method SWI1_3 3 SWI1_2
Material procurement order for new materials SWI1_4 7 SWI1_3
Activity Id Planned
Existing Activity Name Predecessor Notes
Duration
MARBLE WORKS VIP SEC. WALL'S CLADDING
Arch1110 20 SWI1_4
&FLOORING
3 Days
New Activity
SWI1_2 - Submit new method statement for
Existing Activity
mechanical fixation
Finished Work 3 Days
SWI1_3 - Approved method statement for new
method
3 Days SWI1_4 - Material procurement
order for new materials
7 Days
ARCH1110 - MARBLE WORKS VIP SEC. WALL'S CLADDING
&FLOORING
Change Painting
SWI2 15 March 2013 Employer
Color Code
2- Impact Discussion
Activity Estimated
New Activity Name Predecessor Notes
Id Duration
Submit new material for approved SWI 2_1 3 SWI 2
Approved new material SWI 2_2 3 SWI 2_1
Material Procurement SWI 2_3 15 SWI 2_2
Activity Id Planned
Existing Activity Name Predecessor Notes
Duration
Painting Site delivery date A2290 169 SWI 2_3
3 Days
SWI2_2 - Approved new material
3 Days
SWI2_3 - Material Procurement
15 Days
New Activity
Existing Activity ARCH1080 - Painting Site delivery date
Finished Work
15 Days
www.planningengineer.net DaARCH11 Course Link
10ys
Delay Event Project Team Discussion Meeting Result
2-Impact Discussion
Activity Id Estimated
New Activity Name Predecessor Notes
Duration
Response from Consultant RFI No.3-1 10 RFI No.3
Dewatering RFI No.3-2 10 RFI No.3-1
Soil Replacement RFI No.3-3 7 RFI No.3-2
Activity Id Planned
Existing Activity Name Predecessor Notes
Duration
COMPACTING WORKS UNDER THE P.C LAYER SUBZ100030 3
RFI No.3-3
10
RFI No.3-2 - Dewatering
Days
10 Days
RFI No.3-3 - Soil Replacement
7 Days
New Activity
Existing Activity
SUBZ100030 - COMPACTING WORKS
Finished Work
UNDER THE P.C LAYER
3 Days
www.planningengineer.net DaARCH11 Course Link
10ys
Delay Event Project Team Discussion Meeting Result
2- Impact Discussion
Activity Estimated
New Activity Name Predecessor Notes
Id Duration
Remove Fixed Lighting Fixture RFI-6- 1 20 RFI- 6
Modify cable and conducts RFI-6- 2 20 RFI-6- 1
Activity Id Planned
Existing Activity Name Predecessor Notes
Duration
0801EL000
LIGHTING FIXTURES& SWITCHS & OUTLETS 60 RFI-6- 2
5
RFI By Contractor
RFI- 6- 10-April-2012 - Clash between Lighting Unit
and Diffuser Response New Activity
Existing
Activity
Finished
RFI-6- 1 - Remove Fixed Lighting Fixture
Work
20
RFI-6- 2 - Modify cable and
conducts -
20
60
www.planningengineer.net Course Link
Delay Event Project Team Discussion Meeting Result
Local Authorities
Letter 1 25 March 2012 Employer
Permissions
4- Impact Discussion
Activity Id Estimated
New Activity Name Predecessor Notes
Duration
Authorities Permissions Letter 1 - 1 20 Letter 1
Activity Id Planned
Existing Activity Name Predecessor Notes
Duration
Excavation Activity SUBz100020 6 Letter 1 - 1
New Activity
Letter 1 – 1 - Authorities Permissions
Existing Activity
Finished Work 20
6- Impact Discussion
Activity Id Estimated
New Activity Name Predecessor Notes
Duration
Site Delivery Delay Letter 2 - 1 10 Letter 2
Activity Id Planned
Existing Activity Name Predecessor Notes
Duration
Mobilization SUBZ100010 26 Letter 2
New Activity
Letter 2 – 1 - Site Delivery Delay
Existing Activity
Finished Work 10
SUBZ100010 - Mobilization
26
8- Impact Discussion
Activity Estimated
New Activity Name Predecessor Notes
Id Duration
New Pumps Submittal MAR-20-1 5 MAR-20
Pumps Approval MAR-20-2 3 MAR-20-1
Pumps Procurement MAR-20-3 180 MAR-20-2
Activity Id Planned
Existing Activity Name Predecessor Notes
Duration
0801MW00
INSTALLATION OF WATER & FIRE PUMPS 17 MAR-20-3
11
New Activity
MAR-20-1 - New Pumps Submittal
Existing Activity
Finished Work 5
MAR-20-2 - Pumps Approval
180
17
Activity Estimated
New Activity Name Predecessor Notes
Id Duration
Delay of MAR response MAR 4-1 27 MAR 4
Activity Id Planned
Existing Activity Name Predecessor Notes
Duration
LIGHTING FIXTURES& SWITCHS Procurement A2250 47 MAR 4-1
MAR 4 -
New Activity
MAR 4-1 – Delay of MAR response
Existing Activity
Finished Work 27
Activity Estimated
New Activity Name Predecessor Notes
Id Duration
New Door Submittal SDF 2-1 5 SDF 2
New Door Approval SDF 2-2 3 SDF 2-1
Door Procurement SDF 2-3 280 SDF 2-2
Activity Id Planned
Existing Activity Name Predecessor Notes
Duration
WOODEN DOORS INSTALLING ARCH1150
14 SDF 2-3
New Activity
SDF 2-1 - New Door Submittal
Existing Activity
Finished Work 5
SDF 2-2 - New Door Approval
280
14
2- Impact Discussion
Activity Id Estimated
New Activity Name Predecessor Notes
Duration
MEETING
Delay of Utilities availability MOM-13-1 210
NO.13
Activity Id Planned
Existing Activity Name Predecessor Notes
Duration
Elevators TESTING AND COMMISSIONING A2450 22
MOM-13-1
Finishes Touch up & Commissioning Site 10090 14
MOM-13-1
Mechanical Testing & Commissioning Site 10100 23
MOM-13-1
Electrical Testing & Commissioning Site 10110 26
MOM-13-1
MEETING NO.13
MOM-13-1 - Delay of Utilities
availability
210
New Activity
Existing Activity
Finished Work A2450 - Elevators TESTING AND COMMISSIONING
22
Site 10090- Finishes Touch up & Commissioning
COMMISSIONING
14
Site 10100 - Mechanical Testing & Commissioning
4- Impact Discussion
Activity Estimated
New Activity Name Predecessor Notes
Id Duration
Safe Door Supplying Delay
MOM 9-1 60 MOM No.9
Activity Id Planned
Existing Activity Name Predecessor Notes
Duration
Wall Preparation for Painting Arch1070 21 MOM 9-1
60
New Activity
Existing Activity
Arch1070 - Wall Preparation for Painting
Finished Work
21