Professional Documents
Culture Documents
Delay Analysis
Delay Analysis
1- IMPACTED AS-PLANNED
This method involves the insertion of delay events into a baseline or as-planned schedule to
determine the hypothetical impact of such events. It involves modifying the baseline or as-planned
schedule to include new activities and logic to represent delay events. The difference between the
project completion date in the impacted as-planned schedule and the original as-planned schedule
quantifies the delay. This methodology is simple and does not require an as-built schedule.
2- COLLAPSED AS-BUILT
This method is essentially the opposite of an impacted as-planned analysis. It involves removing
delay events from the as-built schedule to determine when the project should have been completed
‘but for’ the delay events. This methodology is easy to understand and does not require an as-
planned schedule or contemporaneous schedule updates.
3- AS-PLANNED VS AS-BUILT
This method is a simple technique used to compare the baseline or as-planned schedule to the as-
built schedule or a schedule update reflecting progress. It compares planned start and finish dates
with the actual start and finish dates of activities on the as-planned critical and near-critical paths.
This identifies delayed starts, extended durations, and late finishes. Its accuracy diminishes as the
actual critical path deviates from the planned schedule.
5- WINDOWS ANALYSIS
This method is a retrospective technique that divides the total project duration into smaller periods
(commonly referred to as “windows”) and quantifies the as-built critical path delays for each of
these periods. It compares the baseline or as-planned schedule’s forecasted critical path to the as-
built schedule, reflecting the as-built conditions for each selected period. It typically relies upon the
schedules in their contemporaneous state of submission (“as-is”). It identifies delays as well as
acceleration quantities and considers real-time conditions and actual construction progress.
However, it is time-consuming, requires complete project records, and depends on a reliable
baseline or as-planned schedule and as-built performance information.