You are on page 1of 1

SL NO. ZONE/ SEG.

POINT REMARKS

1 TEMPERATURE GAUGE (TG) NOT FITTED FOR COMPRESSOR


2 PRESSURE GAUGE (PG) NOT FITTED FOR COMPRESSOR
3 COMPRESSOR ALL FLANGE BOLTS NEED TO BE TIGHTENED PROPERLY FOUND LOOSE
4 HOUSE PIPE SUPPORTS NOT FITTED WHICH INCLUDE:
5 PS-18, 19, 19A, 20, 21, 22, 23, 24, 25,
PHYSICAL DIMENSIONS NOT MATHING AS PER DRG, NEED MODIFICATION IN
6 AS BUILT DRG.
7 ALL INSTRUMENTS NOT FITTED WHICH INCLUDE:
7a a. PRESSURE GAUGE WITH BALL VALVE
7b b. TEMPERATURE GAUGE
AIR RECEIVER
7c c. SAFETY RELIEF VALVE
AR-1
8 BALL VALVE FOR DRAIN
9 ALL FLANGE MUST BE TIGHTENED FOUND LOOSE BOLTS
10 GASKETS NEED TO BE CHANGED AS FOUND WORN OUT AT FEW LOCATION
11 ALL INSTRUMENTS NOT FITTED WHICH INCLUDE:
11a a. PRESSURE GAUGE WITH BALL VALVE
11b b. TEMPERATURE GAUGE
AIR RECEIVER
11c c. SAFETY RELIEF VALVE
AR-2
12 BALL VALVE FOR DRAIN
13 ALL FLANGE MUST BE TIGHTENED FOUND LOOSE BOLTS
14 GASKETS NEED TO BE CHANGED AS FOUND WORN OUT AT FEW LOCATION
15 FOLLOWING JOINTS NEED RECTIFICATION AS DEFECTS OBSERVED
JOINT NO: J-16, 24, 56, 53, 45, 25, 26, 27, 28, 29, 30
a. UNDERCUT
b. POROSITY
c.UNFILLED GROOVE
d. UNDRESSED WELD BEAD, SPATTERS
e. UNEVEN WELD BEAD, HIGH TOE
16 JOINT NO- 35 NOT ACCEPTABLE NEED TO RECTIFY
C/C DISTANCE BTWN COMPRESSED LINE AND OXYGEN LINE REQ- 400 mm
17 FOUND 280 mm
PIPE SUPPORTS NOT FITTED AS PER DRG, U BOLT MISSING, SUPPORTS MISSING
18 4.7 m FLOOR AT MULTIPLE LOCATION
PIPE SUPPORTS NOT FITTED AS PER DRG, U BOLT MISSING, SUPPORTS MISSING
19 AT MULTIPLE LOCATION
9.4 m FLOOR
ELEVATION OF PIPE NEED TO BE MAINTAINED NEAR D4'COLUMN, SUPPORT
20 TO BE MODIFIED.
21 13.9 m FLOOR ALL PIPE SUPPORT CLAMP MISSING, NEED TO FIX PROPERLY
PIPE PASSING IN CLOSE PROXIMITY OF STAIR OF 5' LINE NEED TO RE-ROUTE
22 19.1 m FLOOR FOR SAFETY POINT OF VIEW
PIPE SUPPORTS WITH CLAMP TO FITTED AS PER DRG, U BOLT MISSING AT
23 24.9 m FLOOR MULTIPLE LOCATION.
24 30 m FLOOR PIPE SUPPORTS REQ. AT FEW LOCATION WERE PIPE IS GETTING SAGGED.
FOR AR-02 MODIFIED DRAWING FOR OUTLET ORIENTATION CHANGE NEED TO
25 BE ATTACHED
EXTRA SUPPORT NEED TO BE PROVIDED BTWN DCA AND OXYGEN LINE NEAR
26 FD COOLER SIDE.
27 FOLLOWING POINTS NOT CHECKED
a. OUTLET DUCTING FOR COMPRESSOR
b. AR-03 ALONG WITH PIPE ROUTING FOR GCP
c. PIPING FOR +1.5 m FLOOR FOR CRAWLER BREAKER AS NOT READY
d. PIPING FOR BRIQUETTING PLANT