1 TEMPERATURE GAUGE (TG) NOT FITTED FOR COMPRESSOR
2 PRESSURE GAUGE (PG) NOT FITTED FOR COMPRESSOR 3 COMPRESSOR ALL FLANGE BOLTS NEED TO BE TIGHTENED PROPERLY FOUND LOOSE 4 HOUSE PIPE SUPPORTS NOT FITTED WHICH INCLUDE: 5 PS-18, 19, 19A, 20, 21, 22, 23, 24, 25, PHYSICAL DIMENSIONS NOT MATHING AS PER DRG, NEED MODIFICATION IN 6 AS BUILT DRG. 7 ALL INSTRUMENTS NOT FITTED WHICH INCLUDE: 7a a. PRESSURE GAUGE WITH BALL VALVE 7b b. TEMPERATURE GAUGE AIR RECEIVER 7c c. SAFETY RELIEF VALVE AR-1 8 BALL VALVE FOR DRAIN 9 ALL FLANGE MUST BE TIGHTENED FOUND LOOSE BOLTS 10 GASKETS NEED TO BE CHANGED AS FOUND WORN OUT AT FEW LOCATION 11 ALL INSTRUMENTS NOT FITTED WHICH INCLUDE: 11a a. PRESSURE GAUGE WITH BALL VALVE 11b b. TEMPERATURE GAUGE AIR RECEIVER 11c c. SAFETY RELIEF VALVE AR-2 12 BALL VALVE FOR DRAIN 13 ALL FLANGE MUST BE TIGHTENED FOUND LOOSE BOLTS 14 GASKETS NEED TO BE CHANGED AS FOUND WORN OUT AT FEW LOCATION 15 FOLLOWING JOINTS NEED RECTIFICATION AS DEFECTS OBSERVED JOINT NO: J-16, 24, 56, 53, 45, 25, 26, 27, 28, 29, 30 a. UNDERCUT b. POROSITY c.UNFILLED GROOVE d. UNDRESSED WELD BEAD, SPATTERS e. UNEVEN WELD BEAD, HIGH TOE 16 JOINT NO- 35 NOT ACCEPTABLE NEED TO RECTIFY C/C DISTANCE BTWN COMPRESSED LINE AND OXYGEN LINE REQ- 400 mm 17 FOUND 280 mm PIPE SUPPORTS NOT FITTED AS PER DRG, U BOLT MISSING, SUPPORTS MISSING 18 4.7 m FLOOR AT MULTIPLE LOCATION PIPE SUPPORTS NOT FITTED AS PER DRG, U BOLT MISSING, SUPPORTS MISSING 19 AT MULTIPLE LOCATION 9.4 m FLOOR ELEVATION OF PIPE NEED TO BE MAINTAINED NEAR D4'COLUMN, SUPPORT 20 TO BE MODIFIED. 21 13.9 m FLOOR ALL PIPE SUPPORT CLAMP MISSING, NEED TO FIX PROPERLY PIPE PASSING IN CLOSE PROXIMITY OF STAIR OF 5' LINE NEED TO RE-ROUTE 22 19.1 m FLOOR FOR SAFETY POINT OF VIEW PIPE SUPPORTS WITH CLAMP TO FITTED AS PER DRG, U BOLT MISSING AT 23 24.9 m FLOOR MULTIPLE LOCATION. 24 30 m FLOOR PIPE SUPPORTS REQ. AT FEW LOCATION WERE PIPE IS GETTING SAGGED. FOR AR-02 MODIFIED DRAWING FOR OUTLET ORIENTATION CHANGE NEED TO 25 BE ATTACHED EXTRA SUPPORT NEED TO BE PROVIDED BTWN DCA AND OXYGEN LINE NEAR 26 FD COOLER SIDE. 27 FOLLOWING POINTS NOT CHECKED a. OUTLET DUCTING FOR COMPRESSOR b. AR-03 ALONG WITH PIPE ROUTING FOR GCP c. PIPING FOR +1.5 m FLOOR FOR CRAWLER BREAKER AS NOT READY d. PIPING FOR BRIQUETTING PLANT