Sea Fastenning Of Neptun Dock3 For Carrier Transfer - Trinidad & Tobago
2023 Projects
Neptun Dock3 Salvage Operation - Trinidat & Tobago
TOGG Electric Car Battery Factory Cooling Water Pipelines Engineering , Design , Consultancy
Eren Thermal Power Plant Zonguldak TR
DN3000 CRP Pipelines Interal Seal Application ( 16 Borinline Vertical & Horizontal )
2022 Projects
I.S.K.I
DN1200 HDPE Water Pipeline & DN1000 Steel Pipeline Flange Connection & Internal Seal Application
DP WORLD – Yarimca TR
Maintenance of Impressed Current Cathodic Protection System
COLAKOGLU METALURJI PORT– Dilovası
Cleaning/Maintenance Of Water Intake Structors of OP2 Power Plant DN2500 Pipelines
Cleaning /Maintanance Of fire Fighting Water Intake DN300 Pipeline Filters
936 MW ENERJISA BANDIRMA CCPP
Navigation Buoy Maintanence
4800 MW AKKUYU Nuclear Power Plant DN4000 Cooling Water Discharge Line Marine Construction
Marine Works Construction Subcontractor
Koruma Klor - Derince
Engineering & Diving Consultancy for Dredging Works
Removal of Wrecked Berth Concrete Piles ( Dredging,Demoliton of Burried 50x50 Concrete Piles, Pier Docks )
2021 Projects
2021 - Projects OPI MARINE WORK REFERANCES
BORTEK – I.S.K.I. - Prince Islands Istanbul
Drinking Water pipeline T joint Pipe Maintenance on Prince Islands Istanbul
Enerjisa BAN1 CCPP 840 MWatt
3 Year Contract Awarded- Bandirma CCPP 3 x DN2500 Cooling Water Pipeline Maintenance
KK – Oyak Port – Yarımca
Soft Cleaning Of Fenders with Cavitation Method
AKYATCH - Golcuk
Underwater Epoxy Painting (Maintenance Of Hull , Keel , etc ) Propeller & Shaft Cleaning
GYH KKC Metro Station – Istanbul
Contamination Dive to DN800 & DN1000 Sewage Pipelines , removal of sludge metarial
inside the pipelines.
MEADS / ISAT – Marmara Sea
Oil&Gas Jackup Platform ANADOLU-01
Well Abandonment – Removal Of Production Casings, ( internal cutting, internal Pile
Survey , Underwater Cutting, Guiding Casings)
Colakoglu Metallurgy Port – Dilovası
Diving Consultancy Services during Phase-1 : Berth Re-Construction For Facility Extension
- Removal Of Existing DN3000 GRP Pipeline and replacement with Steel DN3000 Pipeline
- Removal Of Pipe girders, and Replace with New Design.7
BORTEK – I.S.K.I. – Istanbul
Inspection Dive for Drinking water basin dam and WMS engineering for maintenance of the
HDPE DN1600 Pipelines.
I.S.K.I – Istanbul
Drinking Water Pipeline Leak Control - Maintenance Of DN 1600 HDPE Pipeline Project Engineering
Consultancy between Europe & Asia Bosphorus Connection
OPI MARINE WORK REFERANCES
2019 Projects
POLISAN/POLIPORT
Underwater NDT & UT, Thickness Measurement (As a subcontractor of Kuzey Sualtı
Hizmetleri)
Steel Piles Splash Zone DENSO SeaShield HD2000 Protection System Application Work (As
a subcontractor of Kuzey Sualtı Hizmetleri)
Scour Protection Of L WAlls ( Gap Filling Of Waterfront Structors )
KUWAIT AL JAHRA
7 lines DN2200 GRP Borinline Interna Seal Installations for Water Intake GRP Pipelines
2018 Projects
KUMCULAR PORT Construction
Dredging, Levelling and 80-Ton T-Wall Installation (As a subcontractor of Korfez Deniz
Insaat)
SEFINE SHIPYAR D
Underwater and Splashzone Oxy-Arc Cutting Diving Services - ( Korfez Deniz Construction)
BORUSAN PORT Gemlik Port East Pier (As a subcontractor of 2ER Muhendislik)
On water and Underwater Surveys:
2017 PREVIOUS EXPERIENCES OF BEHALF OF FOUNDER MEDIH OZAN EGEMEN & HIS TEAM
2016
UNIMAR ENERGY MARMARA EREGLISI CCPP ‐ GRP Intake and Outfall Pipelines Fall
Maintenance Works
SOCAR STAR REFINERY
- Cathodic Protection Underwater Installation
- Underwater Pile Removal by Thermal Cutting
- Underwater NDT‐ ACFM Inspection
(As a subcontractor of Dogus/Ayson)
ASSAN ISKENDERUN PORT – Jetty Piles Underwater NDT & UT
JAN DE NUL – Removal of the abandoned DN1000 discharge pipeline
PYRAMID ‐ YALOVA RO‐RO Terminal Construction – Inspection & Removal of Buried Piles
UNIMAR ENERGY MARMARA EREGLISI CCPP
- GRP Intake Pipelines Spring Maintenance
- Intake Pipelines Internal Seal Installation & Epoxy Application
- DN2100/DN2400 (BORINLINE INTERNAL SEAL)
JAN DE NUL – Istanbul New Airport DN1000 Discharge Pipeline Inspection
ASSAN PORT – Pier/Jetty Splash Zone Repair Works (PE Coating, Jetty Concrete)
Karadeniz Ereglisi Municipality – Water Front Dock Inspection
ENERJISA –Underwater Intake & Outfall Pipelines & Intake Structures Periodical Survey +
Buoy Maintenance
AYSON – GALATA PORT - Inspection of Jetty Piles
2015
Artı Muhendislik – Seafront Structors VT Inspection
THY&OPET ‐ jet fuel yesilkoy terminal – marine terminal services ( 2016 Full Year Service )
Istanbul Shıpyard – TSK HP Transfer Chamber ‐220mt Testing
Körfez Deniz – 2x Barge Underwater Turkish Lloyd VT Survey
Körfez Deniz – Split Barge Underwater Turkish LLOYD VT Survey
Evren Zincir – Gölcuk Navy Floating Barrier Project SeaBed Survey
Ambarlı TPP – Water Intake Structors Scour & Dredging Maintenance
ASF & BORDO – JET CHAMBER Demolition by WireCutting for Discharge Line Const.
ASSAN PORT ‐ SPLASH ZONE VT Inspection for Tendering ( Steel Piles & Concrete )
Artı Mühendislik –Dock Yard , PIER VT Inspection ( concrete ; Steel Piles)
HABAS Aliağa – Dock VT Inspection ( Old & New Pier ; Steel Piles & Concrete)
KORFEZ DENIZ – BORUSAN West & East Pier VT Inspection ( Steel Piles, Concrete )
KAPTAN DENIZ – 1300 MW EREN TPP Intake Pool Demolition by WireCutting
S&Q Mart – ASSAN PORT NDT UT Inspection of Steel Piles
TUPRAS – B DOCK – Demolition of Concrete Blocks after Dredging Project
STFA&KÖRFEZ\TÜPRAŞ ‐ AYGAZ 5x160 Ton ACBM Buoy Mooring System Removal
EREN CCPP‐ Marine Transportation Services ( 360 Ton Gas Turbines )
OPI MARINE WORK REFERANCES
2014
YMSK&JV–AVRASYATUNNELTBMExcavation–CutterHeadHyperbaricMaintenance-
Saturation Diving11,8Bar
HICC-Vlore-AlbaniaOilPlatformNDTSurvey,OilPipelinesVTSurvey
NORDSEETAUCHER – China Comminication SHENZEN & NANJİNG Metro Road Tunnels TBM
Excavation – Cutter Head Hyperbaric Maintenance Since 2013
ASELSAN – MARINE TESTS OF INNOVATIONS
BUTANGAZ A.Ş. Marmara Ereğli Terminal LPG Pipelines & ACBM Mooring Systems
Inspection & Maintenance – Since 2011
InstalSub – BP BTC Ceyhan Terminal – Diving Services
ISPARK\AQUAMARINE ‐ISTINYE MARINA Floating Pantoon & Mooring System Installation
GDF SUEZ ‐480 MW UNİMAR CCPP – DN2500/2400 Grp Cooling Water Pipeline Inspection
& Maintenance
GDF SUEZ ‐480 MW UNİMAR CCPP – DN2500/2400 Internal Seal Maintenance &
Replacement
SENTEZ ‐& KANDILLI Observatory and Earhquake Research Instute – Maintenance Of
Earthquake and Plate Motion Measurement Instruments Planting at -1600mt in Marmara
Sea Ridge
M\V MAGDA P MMA ‐ Cathodic Protection Replacement
DELTA RUBİS Oil & Gas Terminal – Berth Piles Maintenance ‐Underwater Habitat Welding
BAYRAKTAR INSAAT ‐ Tuzla Marina Precast Blok ‐ Berths Construction
METKA ‐ 870 MW OMV SAMSUNCCPP – Cooling Water Pipelines Inspection & Maintenance
( DN2100 Internal Seal Application )
TOTAL‐ Aliağa Terminal Cathodic Protection Works ( Anot Welding & Sea Shield Application
YMSK & JV – AVRASYA TUNNEL TBM Excavation – Cutter Head Hyperbaric Maintenance
STFA&KÖRFEZ\TÜPRAŞ ‐ AYGAZ 160 Ton ACBM Buoy Mooring System Removal
BUTANGAZ A.Ş. Marmara Ereğli Terminal ACBM Mooring Buoys / LPG Pipelines / Flexible
Hose Periodical Inspection & Maintenance – Since 2011
Intake Structures ‐ Periodical Inspection & Maintenance
2013
STFA&KÖRFEZ\TÜPRAŞ SECTION B –Removal Of Existing Berth & Pile Demolition
NORDSEETAUCHER – China Communication SHENZEN & NANJİNG Metro Road Tunnels TBM
Excavation – Cutter Head Hyperbaric Maintenance
940MW ENERJİSA BANDIRMA CCPP – DN2400/2200 Cooling Water Pipelines & Water
SENTEZ ‐& KANDILLI Observatory and Earhquake Research Instute – Planting Of Earthquake
and Plate Motion Measurement Instruments Planting at -1600mt in Marmara Sea Ridge
METKA ‐ 870 MW OMV SAMSUNCCPP Marine GRP Cooling Water Pipeline Construction
Marine Consultancy Since 2011
OPI MARINE WORK REFERANCES
METKA ‐ 870 MW OMV SAMSUNCCPP Marine GRP Cooling Water Pipelines ‐ Internal Seal
Application DN 3200/2400
METKA ‐ 870 MW OMV SAMSUNCCPP – Marine Operations ( Dive Support Vessel /
MultiCad Barge – Back Filling ACBM / GABION works , Mooring Systems )
KUTAY‐ DSI TURKEY‐ CYPRUS Drinking Water Pipelines Internal Seal Application – DN1500
Ductile Pipes
İKİHANLAR İNŞAAT‐ ARTVIN DN250 HDPE Discharge PipeLine Construction
EÜAŞ Ambarlı Oil Rig/Platform, Leg Inspection & Maintenance
2012
USTAOGLU SHIPYARD – MT MED PACIFIC Salvage with Balloon Method
ORDU Discharge Line Backfilling Marine Works and Free‐Span Inspection & Maintenance
ASELSAN – MARINE TESTS OF INNOVATIONS
METKA ‐ 870 MW OMV SAMSUN CCPP Marine GRP Cooling Water Intake & Outfall Pipeline
Construction Marine Consultancy Since 2011
2011 – 2009
2008-2007
GULERMAK & DOGUS – Basaksehir 6 - Atatürk Olympic Stadium Subway Construction (ACS)