Activity ID Activity Name Original Duration BL Proje ct Early Start BL Proje ct Early Finish Start Finish Total Float Activity % Variance - BL1 2022 2023 2024 2025
Complete Finish Date F M Apr M Jun Jul A S Oct N D Jan F M Apr M Jun Jul A S Oct N D Jan F M Apr M Jun Jul A S Oct N D Jan F M Apr M J Jul A
-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
GALLERY 103 MOCKUP - Rev. 01 issued to TIME (25OCT22) by email - Update 02-JAN-23 252 18-Oct-22 24-Aug-23 04-Mar-22 A 28-Aug-23 22 -3
MO-BMU-ENG-1500 Structural Design Resubmittal - Walk ways / Ladders 12 18-Oct-22 25-Oct-22 18-Oct-22 A 03-Jan-23 8 90% -56 Structural Design Resubmittal - Walk ways / Ladders
MO-BMU-ENG-1530 Structural Design Approval - Abseil/Safety Line 10 08-Nov-22 18-Nov-22 17-Nov-22 A 07-Jan-23 0 50% -39 Structural Design Approval - Abseil/Safety Line
MO-BMU-ENG-1510 Structural Design Approval - Walkways / Ladders 10 26-Oct-22 05-Nov-22 17-Nov-22 A 09-Jan-23 8 50% -51 Structural Design Approval - Walkways / Ladders
MO-BMU-PROC-1480 Fabrication and Delivery of Architectural Lighting Catwalk 20 19-Nov-22 15-Dec-22 12-Jan-23 04-Feb-23 2 0% -43 Fabrication and Delivery of Architectural Lighting Catwalk
MO-BMU-PROC-1490 Fabrication of Maintenance Walk ways 20 19-Nov-22 15-Dec-22 12-Jan-23 04-Feb-23 2 0% -43 Fabrication of Maintenance Walk ways
MO-BMU-PROC-1500 Fabrication of Maintenance Ladders 20 19-Nov-22 15-Dec-22 12-Jan-23 04-Feb-23 2 0% -43 Fabrication of Maintenance Ladders
MO-BMU-PROC-1510 Fabrication of Skylight Maintenance System Platform 20 19-Nov-22 15-Dec-22 12-Jan-23 04-Feb-23 2 0% -43 Fabrication of Skylight Maintenance System Platform
MO-BMU-PROC-1520 Fabrication of Abseil Deviation Bracket 20 26-Nov-22 22-Dec-22 14-Jan-23 07-Feb-23 0 0% -39 Fabrication of Abseil Deviation Bracket
MO-BMU-PROC-1530 Fabrication of Safety Line Bracket 20 26-Nov-22 22-Dec-22 14-Jan-23 07-Feb-23 0 0% -39 Fabrication of Safety Line Bracket
MO-BMU-CON-1570 Installation of Maintenance Walk ways 6 06-Feb-23 13-Feb-23 02-Mar-23 09-Mar-23 0 0% -21 Installation of Maintenance Walk ways
MO-BMU-CON-1580 Installation of Maintenance Ladders 6 13-Feb-23 20-Feb-23 09-Mar-23 16-Mar-23 0 0% -21 Installation of Maintenance Ladders
MO-BMU-CON-1590 Installation of Skylight Maintenance Platform 6 13-Feb-23 20-Feb-23 09-Mar-23 16-Mar-23 12 0% -21 Installation of Skylight Maintenance Platform
MO-EG-VMU-1180 VMU Fabrication 18 15-Nov-22 08-Dec-22 03-Jan-23 24-Jan-23 118 0% -39 VMU Fabrication
MO-EG-VMU-1190 VMU Construction 6 09-Dec-22 15-Dec-22 24-Jan-23 31-Jan-23 118 0% -39 VMU Construction
MO-EG-PMU-1190 PMU Fire Assembly Test 24 08-Nov-22 08-Dec-22 17-Nov-22 A 17-Jan-23 3 41.67% -34 PMU Fire Assembly Test
MO-EG-ENG-1050 System Design Approval ES9 12 25-Oct-22 07-Nov-22 26-Oct-22 A 04-Jan-23 4 80% -46 System Design Approval ES9
MO-EG-ENG-1030 System Design Approval EG11 10 12-Nov-22 23-Nov-22 15-Nov-22 A 06-Jan-23 0 80% -34
MO-EG-ENG-1080 Preparation and Submission of Shop Drawing EG11 6 24-Nov-22 03-Dec-22 07-Nov-22 A 04-Jan-23 0 90% -27
MO-EG-ENG-1110 Approval of Shop Drawing ES9 10 15-Nov-22 25-Nov-22 02-Nov-22 A 05-Jan-23 4 90% -31 Approval of Shop Drawing ES9
MO-EG-ENG-1090 Approval of Shop Drawing EG11 10 05-Dec-22 15-Dec-22 15-Nov-22 A 06-Jan-23 0 80% -19
MO-EG-PRO-1200 Material Procurement - ES9 - Runners, Hardware & Accessories 40 16-Dec-22 31-Jan-23 24-Jan-23 11-Mar-23 118 0% -33 Material Procurement - ES9 - Runners, Hardware & Accessories
MO-EG-PRO-1220 Fabrication & Delivery of Brackets, Frames & Glass - EG11 20 14-Jan-23 06-Feb-23 23-Jan-23 14-Feb-23 0 0% -7
MO-EG-PRO-1230 Fabrication & Delivery of Bifolding Doors 20 14-Jan-23 06-Feb-23 02-Feb-23 25-Feb-23 4 0% -16 Fabrication & Delivery of Bifolding Doors
MO-EG-PRO-1240 Fabrication & Delivery of Brackets, Frames & Metal Panels Assembly - ES9 20 20-Jan-23 11-Feb-23 28-Feb-23 23-Mar-23 118 0% -33 Fabrication & Delivery of Brackets, Frames & Metal Panels Assembly - ES9
Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
Page 1 of 3 Start Date: 04-Mar-22
Actual Work Milestone Finish Date: 22-Sep-23
Remaining Work summary
GALLERY 103 MOCKUP Data Date: 02-Jan-23
GUGGENHEIM MUSEUM ABU DHABI
Activity ID Activity Name Original Duration BL Proje ct Early Start BL Proje ct Early Finish Start Finish Total Float Activity % Variance - BL1 2022 2023 2024 2025
Complete Finish Date F M Apr M Jun Jul A S Oct N D Jan F M Apr M Jun Jul A S Oct N D Jan F M Apr M Jun Jul A S Oct N D Jan F M Apr M J Jul A
-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
INSTALLATION 88 27-Dec-22 15-Mar-23 03-Jan-23 01-May-23 118 -26
EG2.2 44 27-Dec-22 09-Feb-23 03-Jan-23 22-Feb-23 0 -11
MO-EG-CON-1260 Survey and Setting out 6 27-Dec-22 02-Jan-23 03-Jan-23 09-Jan-23 5 0% -6 Survey and Setting out
MO-EG-CON-1270 Installation of Main Steel with Alignment 6 03-Jan-23 09-Jan-23 16-Jan-23 21-Jan-23 0 0% -11
MO-EG-CON-1280 Installation of Brackets & Frames 12 10-Jan-23 23-Jan-23 23-Jan-23 04-Feb-23 0 0% -11
MO-EG-CON-1320 Installation of Main Steel with Alignment 6 03-Jan-23 09-Jan-23 10-Jan-23 16-Jan-23 25 0% -6 Installation of Main Steel with Alignment
MO-EG-CON-1355 Installation of Bi-Folding Door 10 21-Feb-23 03-Mar-23 01-Mar-23 11-Mar-23 1 0% -7 Installation of Bi-Folding Door
MO-EG-CON-1390 Installation of Glass 20 20-Feb-23 15-Mar-23 23-Mar-23 01-May-23 118 0% -27 Installation of Glass
MO-EG-CON-1400 Finishing Work 20 20-Feb-23 15-Mar-23 23-Mar-23 01-May-23 118 0% -27 Finishing Work
MO-EG-VMU-1150 VMU Construction 6 10-Dec-22 16-Dec-22 07-Jan-23 14-Jan-23 13 0% -24 VMU Construction
A11500 Approval of Method Statement - Installation 8 28-Nov-22 09-Dec-22 19-Dec-22 A 03-Jan-23 23 80% -21 Approval of Method Statement - Installation
A11420 Review and Approval of Technical Data / Material Submissio n 12 14-Nov-22 26-Nov-22 22-Nov-22 A 04-Jan-23 0 82% -29
GYPSUM AND MEP WORKS 156 18-Oct-22 17-Mar-23 04-Mar-22 A 27-Mar-23 124 -7
GALLERY MOCKUP - 103 156 18-Oct-22 17-Mar-23 04-Mar-22 A 27-Mar-23 124 -7
Gallery 103- Mockup 156 18-Oct-22 17-Mar-23 04-Mar-22 A 27-Mar-23 124 -7
Engineering MU-GL (Partition & Ceiling) 38 25-Oct-22 19-Nov-22 31-Aug-22 A 06-Jan-23 104 -38
MU-GL-ENG-1020 Materials - Review and Approval 12 25-Oct-22 03-Nov-22 31-Aug-22 A 03-Jan-23 55 90% -49 Materials - Review and Approval
MU-GL-ENG-1040 Method Statement - Preparation and Submission 12 25-Oct-22 03-Nov-22 11-Oct-22 A 03-Jan-23 105 85% -49 Method Statement - Preparation and Submission
MU-GL-ENG-1030 Shop drawings - Preparation and Submission 12 03-Nov-22 10-Nov-22 01-Oct-22 A 04-Jan-23 72 85% -45 Shop drawings - Preparation and Submission
MU-GL-ENG-1050 Method Statement - Review and Approval 12 04-Nov-22 17-Nov-22 29-Oct-22 A 05-Jan-23 105 85% -39 Method Statement - Review and Approval
MU-GL-ENG-1060 Shop drawings - Review and Approval 12 10-Nov-22 19-Nov-22 05-Oct-22 A 06-Jan-23 72 85% -38 Shop drawings - Review and Approval
MU-GL-ENG-1160 MEP - Material Submittals - Preparation & Submission 60 18-Oct-22 31-Oct-22 15-Mar-22 A 04-Jan-23 67 95% -53 MEP - Material Submittals - Preparation & Submission
MU-GL-ENG-1080 Method Statement - Review and Approval 24 22-Nov-22 06-Dec-22 11-Mar-22 A 11-Jan-23 67 78% -31 Method Statement - Review and Approval
MU-GL-ENG-1200 MEP - Shop drawings - Review and Approval 48 10-Nov-22 10-Dec-22 20-Jul-22 A 20-Jan-23 139 65% -35 MEP - Shop drawings - Review and Approval
MU-GL-ENG-1170 MEP - Material Submittals - Approvals 48 05-Nov-22 16-Nov-22 21-Mar-22 A 20-Jan-23 129 78% -53 MEP - Material Submittals - Approvals
Procurement MU-GL (Partition & Ceiling) 70 03-Nov-22 27-Jan-23 03-Jan-23 27-Mar-23 104 -49
MU-GL-PRO-LC-1000 Local Procurement 20 03-Nov-22 26-Nov-22 03-Jan-23 26-Jan-23 55 0% -49 Local Procurement
MU-GL-PRO-LC-1010 Long Lead Procurement (Acoustic Plaster) 70 03-Nov-22 27-Jan-23 03-Jan-23 27-Mar-23 104 0% -49 Long Lead Procurement (Acoustic Plaster)
Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
Page 2 of 3 Start Date: 04-Mar-22
Actual Work Milestone Finish Date: 22-Sep-23
Remaining Work summary
GALLERY 103 MOCKUP Data Date: 02-Jan-23
GUGGENHEIM MUSEUM ABU DHABI
Activity ID Activity Name Original Duration BL Proje ct Early Start BL Proje ct Early Finish Start Finish Total Float Activity % Variance - BL1 2022 2023 2024 2025
Complete Finish Date F M Apr M Jun Jul A S Oct N D Jan F M Apr M Jun Jul A S Oct N D Jan F M Apr M Jun Jul A S Oct N D Jan F M Apr M J Jul A
-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
SHADES PACKAGE 186 29-Dec-22 24-Aug-23 02-Jan-23 28-Aug-23 4 -3
GENERAL 12 29-Dec-22 11-Jan-23 02-Jan-23 14-Jan-23 4 -3
A14380 Subcontractor Mobilization 12 29-Dec-22 11-Jan-23 02-Jan-23 14-Jan-23 4 0% -3 Subcontractor Mobilization
A14400 Review and Approval of Engineering Documents / MAR / Samples 82 26-Jan-23 17-May-23 30-Jan-23 20-May-23 4 0% -3 Review and Approval of Engineering Documents / MAR / Samples
Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
Page 3 of 3 Start Date: 04-Mar-22
Actual Work Milestone Finish Date: 22-Sep-23
Remaining Work summary
GALLERY 103 MOCKUP Data Date: 02-Jan-23