GUGGENHEIM MUSEUM ABU DHABI

Activity ID Activity Name Original BL Project Start BL Project Finish Actual / Actual / Expected % Comp Total Var - BL Project 2023 2024
Duration Expected Start Finish Float Finish M A M J Jul A S Oct N D J F M Apr M JJul
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 1516
220 10-Oct-22 30-Sep-23 03-Jun-22 A 06-Aug-23 245 47
GALLERY 105 -Rev. 01_UPDT_17_04_23
SCAFFOLDING 11 27-Mar-23 17-Apr-23 29-Apr-23 12-May-23 15 -17

Scaffolding for Works on Roof 11 27-Mar-23 17-Apr-23 29-Apr-23 12-May-23 15 -17


G105-C-SC-230 Scaffolding Erection on roof [for MEP / Extrnal Facade & Glazing Packages] 11 27-Mar-23 17-Apr-23 29-Apr-23 12-May-23 0% 15 -17 Scaffolding Erection on roof [for MEP / Extrnal Facade & G
STRUCTURAL STEEL (EVS) 28 16-Mar-23 13-May-23 03-Apr-23 A 17-May-23 0 -2

Metal Decking & Casting 13 16-Mar-23 27-Mar-23 03-Apr-23 A 29-Apr-23 15 -17


Concrete Works 13 16-Mar-23 27-Mar-23 03-Apr-23 A 29-Apr-23 15 -17
Upstands & Eqpt Plinth 13 16-Mar-23 27-Mar-23 03-Apr-23 A 29-Apr-23 15 -17
G105-SS-CON-1850 Upstand casting by STJV 6 16-Mar-23 22-Mar-23 03-Apr-23 A 19-Apr-23 70% 18 -14 Upstand casting by STJV
G105-SS-CON-1630 Equipment plinth casting by STJV 6 18-Mar-23 27-Mar-23 17-Apr-23 29-Apr-23 0% 15 -17 Equipment plinth casting by STJV
SECONDARY STEEL FOR CATWALKS 21 25-Mar-23 13-May-23 17-Apr-23 17-May-23 0 -2
Design 21 25-Mar-23 13-May-23 17-Apr-23 17-May-23 0 -2
G105-SS-CON-1760 Submission of Design-Secondary Steel Structure for Architectural Lighting Catwalks 9 25-Mar-23 29-Apr-23 17-Apr-23 03-May-23 0% 0 -2
G105-SS-CON-1770 Approval of Design-Secondary Steel Structure for Architectural Lighting Catwalks 12 29-Apr-23 13-May-23 03-May-23 17-May-23 0% 0 -2
GFRC PACKAGE (FIBREX) 84 23-Feb-23 22-Jun-23 13-Feb-23 A 06-Jun-23 84 15

Design and Engineering Works 55 23-Feb-23 07-May-23 13-Feb-23 A 09-May-23 84 -2


Structural / Design Calculations 27 23-Feb-23 17-Apr-23 13-Feb-23 A 01-May-23 83 -7
LOD350 27 23-Feb-23 17-Apr-23 13-Feb-23 A 01-May-23 83 -7
Gallery 105 27 23-Feb-23 17-Apr-23 13-Feb-23 A 01-May-23 83 -7
G105-GRC-ENG-114 Providing of Coordinated Interface Trade Models 12 23-Feb-23 09-Mar-23 13-Feb-23 A 18-Apr-23 90% 85 -34 Providing of Coordinated Interface Trade Models
G105-GRC-ENG-115 Preparation and Submission of LOD350 21 09-Mar-23 03-Apr-23 20-Feb-23 A 24-Apr-23 90% 86 -15 Preparation and Submission of LOD350
G105-GRC-ENG-118 Approval of LOD350/400 10 03-Apr-23 17-Apr-23 27-Feb-23 A 01-May-23 50% 70 -7 Approval of LOD350/400
Shop Drawings 14 17-Apr-23 07-May-23 05-Apr-23 A 09-May-23 85 -2
Coordinated Shop Drawings 14 17-Apr-23 07-May-23 05-Apr-23 A 09-May-23 85 -2
G105-GRC-ENG-155 Preparation and Submission of Shop Drawings 14 17-Apr-23 07-May-23 05-Apr-23 A 09-May-23 50% 85 -2 Preparation and Submission of Shop Drawings
Procurement 53 20-Mar-23 22-Jun-23 07-Mar-23 A 06-Jun-23 84 15
G105-GRC-PROC-02 Procurement of Material 12 20-Mar-23 31-Mar-23 07-Mar-23 A 22-Apr-23 80% 45 -20 Procurement of Material
Production and Delivery Works 62 27-Mar-23 22-Jun-23 07-Mar-23 A 06-Jun-23 84 15
Gallery 105 62 27-Mar-23 22-Jun-23 07-Mar-23 A 06-Jun-23 84 15
Elevation 01 51 27-Mar-23 09-Jun-23 07-Mar-23 A 05-Jun-23 84 5
ES1- Material Fabrication & Delivery (GFRC Works) 51 27-Mar-23 09-Jun-23 07-Mar-23 A 05-Jun-23 84 5
G105-GRC-FAB-40 Fabrication of Secondary Steel 8 27-Mar-23 04-Apr-23 07-Mar-23 A 17-Apr-23 90% 35 -11 Fabrication of Secondary Steel
G105-GRC-FAB-60 Delivery of Secondary Steel 6 05-Apr-23 11-Apr-23 15-Mar-23 A 19-Apr-23 75% 35 -7 Delivery of Secondary Steel
G105-GRC-FAB-50 Fabrication of GRC Material 18 20-May-23 09-Jun-23 08-Mar-23 A 05-Jun-23 42% 84 5 Fabrication of GRC Material
Elevation 02 46 31-Mar-23 13-Jun-23 07-Mar-23 A 03-Jun-23 84 9
ES1- Material Fabrication & Delivery (GFRC Works) 46 31-Mar-23 13-Jun-23 07-Mar-23 A 03-Jun-23 84 9
G105-GRC-FAB-90 Fabrication of Secondary Steel 8 31-Mar-23 10-Apr-23 07-Mar-23 A 24-Apr-23 90% 35 -9 Fabrication of Secondary Steel
G105-GRC-FAB-110 Delivery of Secondary Steel 6 10-Apr-23 17-Apr-23 21-Mar-23 A 26-Apr-23 75% 38 -5 Delivery of Secondary Steel
G105-GRC-FAB-100 Fabrication of GRC Material 18 24-May-23 13-Jun-23 08-Mar-23 A 03-Jun-23 45% 84 9 Fabrication of GRC Material
Elevation 03 29 10-Apr-23 17-Jun-23 10-Mar-23 A 06-Jun-23 84 11
ES1- Material Fabrication & Delivery (GFRC Works) 29 10-Apr-23 17-Jun-23 10-Mar-23 A 06-Jun-23 84 11
G105-GRC-FAB-140 Fabrication of Secondary Steel 8 10-Apr-23 19-Apr-23 10-Mar-23 A 25-Apr-23 90% 35 -2 Fabrication of Secondary Steel
G105-GRC-FAB-160 Delivery of Secondary Steel 6 19-Apr-23 29-Apr-23 21-Mar-23 A 27-Apr-23 75% 37 3 Delivery of Secondary Steel
G105-GRC-FAB-150 Fabrication of GRC Material 18 29-May-23 17-Jun-23 15-Mar-23 A 06-Jun-23 35% 84 11 Fabrication of GRC Material
Elevation 04 43 13-Apr-23 22-Jun-23 08-Mar-23 A 06-Jun-23 84 15
ES1- Material Fabrication & Delivery (GFRC Works) 43 13-Apr-23 22-Jun-23 08-Mar-23 A 06-Jun-23 84 15
G105-GRC-FAB-190 Fabrication of Secondary Steel 8 13-Apr-23 26-Apr-23 08-Mar-23 A 25-Apr-23 90% 35 1 Fabrication of Secondary Steel
G105-GRC-FAB-210 Delivery of Secondary Steel 6 26-Apr-23 03-May-23 21-Mar-23 A 27-Apr-23 75% 35 6 Delivery of Secondary Steel
G105-GRC-FAB-200 Fabrication of GRC Material 18 02-Jun-23 22-Jun-23 09-Mar-23 A 06-Jun-23 35% 84 15 Fabrication of GRC Material
IS1- Material Fabrication & Delivery 31 26-Apr-23 09-Jun-23 10-Mar-23 A 29-May-23 84 10
G105-GRC-FAB-230 Fabrication of Secondary Steel 7 26-Apr-23 04-May-23 16-Mar-23 A 26-Apr-23 80% 105 7 Fabrication of Secondary Steel
G105-GRC-FAB-260 Delivery of Secondary Steel 7 04-May-23 12-May-23 14-Apr-23 A 03-May-23 20% 105 8 Delivery of Secondary Steel
G105-GRC-FAB-240 Fabrication of GRC Material 7 02-Jun-23 09-Jun-23 10-Mar-23 A 29-May-23 25% 84 10 Fabrication of GRC Material
Installation Works 24 12-Apr-23 24-May-23 16-Mar-23 A 11-May-23 37 11

Remaining Level of Effort Remaini... Date Revision Checked Approved


Page 1 of 4 Start Date: 04-Mar-22
Primary Baseline Critical R... Finish Date: 10-Jun-24
GALLERY 105 -Rev. 01_UPDT_17_04_23
Actual Work Milestone Data Date: 17-Apr-23
Three Weeks Lookahead
Activity ID Activity Name Original BL Project Start BL Project Finish Actual / Actual / Expected % Comp Total Var - BL Project 2023 2024
Duration Expected Start Finish Float Finish M A M J Jul A S Oct N D J F M Apr M JJul
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 1516
Main Scope 24 12-Apr-23 24-May-23 16-Mar-23 A 11-May-23 37 11
ES1 - GFRC Facade System 24 12-Apr-23 24-May-23 16-Mar-23 A 11-May-23 37 11
Elevation 01 (Near Entrance / Opposite Core Wall) 24 12-Apr-23 16-May-23 04-Apr-23 A 11-May-23 34 4
ES1 24 12-Apr-23 16-May-23 04-Apr-23 A 11-May-23 34 4
G105-ES-1060 Installation of Steel (Including Drilling holes & Fireproof coat) -Elevation -01 10 12-Apr-23 01-May-23 07-Apr-23 A 01-May-23 40% 34 0 Installation of Steel (Including Drilling holes & Fireproof coat)
G105-ES-1070 Installation of Unitized Panel ( Vapour Barrier, Insulation ) - From 6m to 20m -Elevation -01 8 01-May-23 10-May-23 01-May-23 10-May-23 0% 34 0 Installation of Unitized Panel ( Vapour Barrier, Insulation ) - F
G105-ES-1110 Application of Cementitious Fireproofing and paint touchup works at site up to 6m -Elevation -01 5 10-May-23 16-May-23 04-Apr-23 A 11-May-23 80% 34 4 Application of Cementitious Fireproofing and paint touchup
Elevation 02 (Towards Cone-07) 17 19-Apr-23 24-May-23 16-Mar-23 A 10-May-23 38 12
ES1 17 19-Apr-23 24-May-23 16-Mar-23 A 10-May-23 38 12
G105-ES-1000 Installation of Steel (Including Drilling holes & Fireproof coat) -Elevation -02 10 19-Apr-23 05-May-23 16-Mar-23 A 27-Apr-23 85% 38 7 Installation of Steel (Including Drilling holes & Fireproof coat)
G105-ES-1010 Installation of Unitized Panel ( Vapour Barrier, Insulation ) - From 6m to 20m -Elevation -02 8 05-May-23 15-May-23 27-Apr-23 06-May-23 0% 38 7 Installation of Unitized Panel ( Vapour Barrier, Insulation ) -
G105-ES-1040 Installation of Unitized Panel ( Vapour Barrier, Insulation ) - up to 6m Ht from Bottom -Elevation -02 3 20-May-23 24-May-23 06-May-23 10-May-23 0% 38 12 Installation of Unitized Panel ( Vapour Barrier, Insulation )
Elevation 03(Towards Sea) 12 29-Apr-23 20-May-23 16-Mar-23 A 08-May-23 37 11
ES1 12 29-Apr-23 20-May-23 16-Mar-23 A 08-May-23 37 11
G105-ES-1120 Installation of Steel (Including Drilling holes & Fireproof coat) -Elevation -03 10 29-Apr-23 11-May-23 16-Mar-23 A 28-Apr-23 80% 37 11 Installation of Steel (Including Drilling holes & Fireproof coat
G105-ES-1130 Installation of Unitized Panel ( Vapour Barrier, Insulation ) - From 6m to 20m -Elevation -03 8 11-May-23 20-May-23 29-Apr-23 08-May-23 0% 37 11 Installation of Unitized Panel ( Vapour Barrier, Insulation ) -
Elevation 04 (Near Shard 09) 20 03-May-23 24-May-23 30-Mar-23 A 09-May-23 35 13
ES1 20 03-May-23 24-May-23 30-Mar-23 A 09-May-23 35 13
G105-ES-1180 Installation of Steel (Including Drilling holes & Fireproof coat) -Elevation -04 10 03-May-23 15-May-23 30-Mar-23 A 29-Apr-23 70% 35 13 Installation of Steel (Including Drilling holes & Fireproof coa
G105-ES-1190 Installation of Unitized Panel ( Vapour Barrier, Insulation ) - From 6m to 20m -Elevation -04 8 15-May-23 24-May-23 01-May-23 09-May-23 0% 35 13 Installation of Unitized Panel ( Vapour Barrier, Insulation )
MEP WORKS 152 04-Feb-23 02-Aug-23 03-Jun-22 A 03-Aug-23 103 -1

Engineering 152 04-Feb-23 02-Aug-23 03-Jun-22 A 03-Aug-23 103 -1


Shop Drawings 50 14-Feb-23 28-Apr-23 25-Aug-22 A 26-Apr-23 94 2
Approvals 50 14-Feb-23 28-Apr-23 25-Aug-22 A 26-Apr-23 94 2
G105-MEP-SD-1670 Review & Approval of Shop Drawings - Level 02M 24 06-Mar-23 08-Apr-23 28-Oct-22 A 17-Apr-23 98% 33 -4 Review & Approval of Shop Drawings - Level 02M
G105-MEP-SD-1610 Review & Approval of Shop Drawings - Level 01 24 14-Feb-23 14-Mar-23 25-Aug-22 A 19-Apr-23 94% 54 -22 Review & Approval of Shop Drawings - Level 01
G105-MEP-SD-1650 Review & Approval of Shop Drawings - Level 02 24 02-Mar-23 03-Apr-23 17-Oct-22 A 26-Apr-23 88% 94 -9 Review & Approval of Shop Drawings - Level 02
G105-MEP-SD-1690 Review & Approval of Shop Drawings - Level 03 24 16-Mar-23 28-Apr-23 22-Nov-22 A 26-Apr-23 87% 30 2 Review & Approval of Shop Drawings - Level 03
Procurement 152 04-Feb-23 02-Aug-23 03-Jun-22 A 03-Aug-23 103 -1
Material Submittals & Procurement 152 04-Feb-23 02-Aug-23 03-Jun-22 A 03-Aug-23 103 -1
MEP 1st & 2nd Fix 71 04-Feb-23 13-May-23 04-Feb-23 A 06-May-23 33 6
G105-MEP-PR-1800 Place Orders 36 04-Feb-23 17-Mar-23 04-Feb-23 A 26-Apr-23 90% 33 -20 Place Orders
G105-MEP-PR-1810 Manufacturing & Delivery to Site 48 03-Mar-23 13-May-23 11-Feb-23 A 06-May-23 75% 33 6 Manufacturing & Delivery to Site
MEP Final Fix 145 13-Feb-23 02-Aug-23 03-Jun-22 A 03-Aug-23 103 -1
G105-MEP-PR-1830 Review & Approvals 48 13-Feb-23 25-Apr-23 03-Jun-22 A 29-Apr-23 88% 103 -4 Review & Approvals
G105-MEP-PR-1860 Place Orders 21 27-Mar-23 04-May-23 06-Apr-23 A 18-May-23 25% 103 -12 Place Orders
G105-MEP-PR-1870 Manufacturing & Delivery to Site (Equipments / Final Fixes) 72 04-May-23 02-Aug-23 07-Apr-23 A 03-Aug-23 15% 103 -1 Manufacturing & Delivery to Site (Equipments /
Construction 57 17-Apr-23 02-Aug-23 24-Mar-23 A 07-Jul-23 65 21
MEP works below Decking Slab 57 17-Apr-23 02-Aug-23 24-Mar-23 A 07-Jul-23 65 21
G105-SS-CON-1650 Installation of MEP 1st Fix 36 17-Apr-23 03-Jun-23 24-Mar-23 A 03-Jun-23 15% 50 0 Installation of MEP 1st Fix
G105-SS-CON-1860 Installation of MEP 2nd Fix 48 13-May-23 13-Jul-23 06-May-23 06-Jul-23 0% 50 6 Installation of MEP 2nd Fix
G105-SS-CON-1660 Installation of MEP (Risers) 35 16-Jun-23 02-Aug-23 12-Apr-23 A 07-Jul-23 15% 65 21 Installation of MEP (Risers)
BMU WORKS (COX) 99 18-Jan-23 26-May-23 18-Jan-23 A 29-May-23 181 -2

Engineering 96 18-Jan-23 18-May-23 18-Jan-23 A 11-May-23 182 6


Structural Design 81 18-Jan-23 03-Apr-23 18-Jan-23 A 28-Apr-23 90 -12
Design Calculations 81 18-Jan-23 03-Apr-23 18-Jan-23 A 28-Apr-23 90 -12
Submissions 69 18-Jan-23 15-Mar-23 18-Jan-23 A 25-Apr-23 90 -21
G105-BMU-ENG-2040 Resubmission of Design Calculation for Typical Abseiling points 12 18-Jan-23 31-Jan-23 18-Jan-23 A 25-Apr-23 80% 90 -58 Resubmission of Design Calculation for Typical Abseiling poin
G105-BMU-ENG-2060 Resubmission of Design Calculation for Typical Combined Cableline & Abseiling Systems 12 02-Mar-23 15-Mar-23 28-Mar-23 A 25-Apr-23 80% 90 -21 Resubmission of Design Calculation for Typical Combined Ca
Approvals 18 09-Mar-23 03-Apr-23 30-Mar-23 A 28-Apr-23 90 -12
G105-BMU-ENG-2050 Approval of Design Calculation for Typical Abseiling points 12 09-Mar-23 22-Mar-23 30-Mar-23 A 28-Apr-23 75% 90 -18 Approval of Design Calculation for Typical Abseiling points
G105-BMU-ENG-2070 Approval of Design Calculation for Typical Combined Cableline & Abseiling Systems 12 16-Mar-23 03-Apr-23 30-Mar-23 A 28-Apr-23 75% 90 -12 Approval of Design Calculation for Typical Combined Cablelin
Shop Drawings 19 26-Apr-23 18-May-23 01-Apr-23 A 11-May-23 182 6
Submissions 7 10-May-23 18-May-23 03-May-23 11-May-23 182 6
G105-BMU-ENG-2020 Resubmission of Shop Drawing -Rev-02 7 10-May-23 18-May-23 03-May-23 11-May-23 0% 182 6 Resubmission of Shop Drawing -Rev-02
Approvals 12 26-Apr-23 10-May-23 01-Apr-23 A 03-May-23 182 6
G105-BMU-ENG-1440 Approval of Shop Drawings -Rev-01 12 26-Apr-23 10-May-23 01-Apr-23 A 03-May-23 67% 182 6 Approval of Shop Drawings -Rev-01
Procurement 47 14-Mar-23 26-May-23 17-Feb-23 A 29-May-23 181 -2
Material Submittals & Approvals 19 12-Apr-23 17-May-23 17-Feb-23 A 06-May-23 201 10

Remaining Level of Effort Remaini... Date Revision Checked Approved


Page 2 of 4 Start Date: 04-Mar-22
Primary Baseline Critical R... Finish Date: 10-Jun-24
GALLERY 105 -Rev. 01_UPDT_17_04_23
Actual Work Milestone Data Date: 17-Apr-23
Three Weeks Lookahead
Activity ID Activity Name Original BL Project Start BL Project Finish Actual / Actual / Expected % Comp Total Var - BL Project 2023 2024
Duration Expected Start Finish Float Finish M A M J Jul A S Oct N D J F M Apr M JJul
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 1516
Submissions 12 12-Apr-23 03-May-23 17-Feb-23 A 29-Apr-23 201 4
G105-BMU-PROC-2170 Material & Sample Submission for Hatch-Rev-01 12 12-Apr-23 03-May-23 17-Feb-23 A 29-Apr-23 50% 201 4 Material & Sample Submission for Hatch-Rev-01
Approvals 12 03-May-23 17-May-23 23-Mar-23 A 06-May-23 201 10
G105-BMU-PROC-2180 Material & Sample Approval for Hatch-Rev-01 12 03-May-23 17-May-23 23-Mar-23 A 06-May-23 50% 201 10 Material & Sample Approval for Hatch-Rev-01
Material Fabrication & Deliveries 47 14-Mar-23 26-May-23 16-Mar-23 A 29-May-23 172 -2
G105-BMU-PROC-2140 Place Order & Material Delivery-Paints 22 20-Mar-23 29-Apr-23 20-Mar-23 A 29-Apr-23 71% 197 0 Place Order & Material Delivery-Paints
G105-BMU-PROC-2060 Raw Material Procurement 45 14-Mar-23 20-May-23 16-Mar-23 A 23-May-23 41% 69 -2 Raw Material Procurement
Platforms, Walkways & Ladders 38 30-Mar-23 26-May-23 30-Mar-23 A 29-May-23 172 -2
G105-BMU-PROC-3070 Fabrication & Delivery - Platforms @ Lvl 30.458 24 30-Mar-23 10-May-23 30-Mar-23 A 10-May-23 38% 87 1 Fabrication & Delivery - Platforms @ Lvl 30.458
G105-BMU-PROC-2070 Fabrication & Delivery - Platforms @ Lvl 37.646 24 11-Apr-23 17-May-23 13-Apr-23 A 17-May-23 13% 183 1 Fabrication & Delivery - Platforms @ Lvl 37.646
G105-BMU-PROC-3080 Fabrication & Delivery - Platforms @ Lvl 30.107 24 11-Apr-23 17-May-23 17-Apr-23 20-May-23 0% 87 -3 Fabrication & Delivery - Platforms @ Lvl 30.107
G105-BMU-PROC-3090 Fabrication & Delivery - Platforms @ Lvl 27.669 (Catwalk) 24 28-Apr-23 26-May-23 01-May-23 29-May-23 0% 69 -2 Fabrication & Delivery - Platforms @ Lvl 27.669 (Catwal
GYPSUM AND PARTITION WORKS (MAIS & OTHERS) 59 06-Mar-23 15-Jun-23 07-Mar-23 A 03-Jun-23 102 10

Engineering 43 06-Mar-23 11-May-23 07-Mar-23 A 16-May-23 35 -4


Calcluations 31 20-Mar-23 11-May-23 25-Mar-23 A 16-May-23 19 -4
G105-E-GP-110 Calculation for Gallery 105 - Review & Comments 14 20-Mar-23 08-Apr-23 25-Mar-23 A 17-Apr-23 95% 16 -5 Calculation for Gallery 105 - Review & Comments
G105-E-GP-120 Calculation for Gallery 105 - Revise & Resubmission 6 08-Apr-23 25-Apr-23 17-Apr-23 29-Apr-23 0% 19 -4 Calculation for Gallery 105 - Revise & Resubmission
G105-E-GP-130 Calculation for Gallery 105 - Review & Approval 12 25-Apr-23 11-May-23 01-May-23 16-May-23 0% 16 -4 Calculation for Gallery 105 - Review & Approval
Wall Section & 3D Isometric 39 06-Mar-23 08-Apr-23 07-Mar-23 A 11-May-23 25 -20
G105-E-GP-240 3D Isometric and Wall sections for Gallery 105 - Preparation and Submission 12 06-Mar-23 18-Mar-23 07-Mar-23 A 17-Apr-23 95% 25 -16 3D Isometric and Wall sections for Gallery 105 - Preparation an
G105-E-GP-250 3D Isometric and Wall sections for Gallery 105 - Review & Comments 14 20-Mar-23 08-Apr-23 18-Apr-23 11-May-23 0% 21 -20 3D Isometric and Wall sections for Gallery 105 - Review &
Shop Drawings 26 06-Mar-23 11-Apr-23 20-Mar-23 A 04-May-23 29 -13
G105-E-GP-280 Shop Drawings for Gallery 105 - Preparation and Submission 18 06-Mar-23 28-Mar-23 20-Mar-23 A 18-Apr-23 95% 28 -11 Shop Drawings for Gallery 105 - Preparation and Submission
G105-E-GP-290 Shop Drawings for G Gallery 105 - Review & Comments 9 29-Mar-23 11-Apr-23 18-Apr-23 04-May-23 0% 24 -13 Shop Drawings for G Gallery 105 - Review & Comments
Material Submittals &Approvals 14 10-Apr-23 04-May-23 30-Mar-23 A 17-Apr-23 46 9
G105-E-GP-530 Material Submittals for G Gallery 105 - Approval 14 10-Apr-23 04-May-23 30-Mar-23 A 17-Apr-23 95% 46 9 Material Submittals for G Gallery 105 - Approval
Procurement 36 04-May-23 15-Jun-23 17-Apr-23 03-Jun-23 102 10
Purchase Orders 36 04-May-23 15-Jun-23 17-Apr-23 03-Jun-23 102 10
G105-P-GP-120 Purchase Order for Acoustic Plaster 36 04-May-23 15-Jun-23 17-Apr-23 03-Jun-23 0% 102 10 Purchase Order for Acoustic Plaster
Production & Deliveries 20 12-May-23 01-Jun-23 01-May-23 21-May-23 67 11
G105-P-GP-110 Manufacturing & Delivery for Gypsum Gallery Walls 20 12-May-23 01-Jun-23 01-May-23 21-May-23 0% 67 11 Manufacturing & Delivery for Gypsum Gallery Walls
EXTERNAL GLAZING (ALICO) 151 10-Oct-22 06-May-23 12-Oct-22 A 29-May-23 11 -19

Engineering 147 14-Nov-22 06-May-23 12-Oct-22 A 29-May-23 11 -19


BIM Model Finalization (ALICO) 138 14-Nov-22 02-Mar-23 14-Nov-22 A 15-May-23 11 -49
G105-E-GP-360 BIM model for Gallery 105 - Preparation and Submission 18 14-Nov-22 07-Dec-22 14-Nov-22 A 01-May-23 60% 11 -110 BIM model for Gallery 105 - Preparation and Submission
G105-E-GP-370 BIM model for Gallery 105 - Collaborations and Clash Detection 9 06-Dec-22 26-Dec-22 24-Mar-23 A 06-May-23 40% 11 -99 BIM model for Gallery 105 - Collaborations and Clash Detec
G105-E-GP-380 BIM model for Gallery 105 - Clash Resolutions and Resubmission 8 21-Feb-23 02-Mar-23 31-Mar-23 A 15-May-23 20% 11 -49 BIM model for Gallery 105 - Clash Resolutions and Resub
Shop Drawings 145 16-Nov-22 06-May-23 12-Oct-22 A 29-May-23 11 -19
EG2.2 (Skylight) 16 16-Nov-22 07-Dec-22 16-Nov-22 A 20-May-23 16 -127
G105-EG-ENG-1060 Preparation and Submission of Shop Drawing EG2.2 6 16-Nov-22 22-Nov-22 16-Nov-22 A 26-Apr-23 50% 32 -116 Preparation and Submission of Shop Drawing EG2.2
G105-EG-ENG-1070 Approval of Shop Drawing EG2.2 10 23-Nov-22 07-Dec-22 23-Nov-22 A 20-May-23 50% 16 -127 Approval of Shop Drawing EG2.2
ES9 (External Metal Cladding) 30 16-Mar-23 06-May-23 12-Oct-22 A 29-May-23 11 -19
G105-EG-ENG-1100 Preparation and Submission of Shop Drawing ES9 18 16-Mar-23 17-Apr-23 12-Oct-22 A 15-May-23 10% 11 -19 Preparation and Submission of Shop Drawing ES9
G105-EG-ENG-1110 Approval of Shop Drawing ES9 18 05-Apr-23 06-May-23 02-Nov-22 A 29-May-23 10% 11 -19 Approval of Shop Drawing ES9
Procurement 30 10-Oct-22 04-Mar-23 17-Apr-23 27-May-23 10 -58
EG2.2 (Skylight) 30 10-Oct-22 04-Mar-23 17-Apr-23 27-May-23 10 -58
G105-EG-PRO-1120 Material Procurment EG2.2 - Extrusion 30 10-Oct-22 16-Nov-22 17-Apr-23 27-May-23 0% 10 -148 Material Procurment EG2.2 - Extrusion
G105-EG-PRO-1130 Material Procurement - EG2.2 - Brackets, Frames & Glass 30 23-Jan-23 04-Mar-23 17-Apr-23 27-May-23 0% 10 -58 Material Procurement - EG2.2 - Brackets, Frames & Gla
G105-EG-PRO-1140 Material Procurement - EG2.2 - Hardware & Accessories 30 23-Jan-23 25-Feb-23 17-Apr-23 27-May-23 0% 10 -64 Material Procurement - EG2.2 - Hardware & Accessories
ROOFING ASSEMBLY (WP3+EP5) 62 20-Feb-23 23-May-23 20-Feb-23 A 31-May-23 176 -7

WP 3 SYSTEM (PROTECT MIDDLE EAST) 61 20-Feb-23 23-May-23 20-Feb-23 A 31-May-23 150 -7


BIM Model Finalization (PROTECT ME) 61 20-Feb-23 27-Apr-23 20-Feb-23 A 18-May-23 150 -18
G105-E-GP-470 BIM model for Gallery 105 - Preparation and Submission 18 20-Feb-23 11-Mar-23 20-Feb-23 A 03-May-23 50% 150 -31 BIM model for Gallery 105 - Preparation and Submission
G105-E-GP-480 BIM model for Gallery 105 - Collaborations and Clash Detection 18 13-Mar-23 08-Apr-23 01-Mar-23 A 13-May-23 50% 150 -22 BIM model for Gallery 105 - Collaborations and Clash Dete
G105-E-GP-490 BIM model for Gallery 105 - Clash Resolutions and Resubmission 8 10-Apr-23 27-Apr-23 20-Mar-23 A 18-May-23 50% 150 -18 BIM model for Gallery 105 - Clash Resolutions and Resub
Engineering 22 27-Apr-23 23-May-23 20-Mar-23 A 31-May-23 150 -7
G105-RW-CON-1000 Submission of Shop Drawings 22 27-Apr-23 23-May-23 20-Mar-23 A 31-May-23 50% 150 -7 Submission of Shop Drawings
EP5 ROOFING ASSEMBLY 22 13-Apr-23 16-May-23 17-Apr-23 18-May-23 187 -2
Engineering 22 13-Apr-23 16-May-23 17-Apr-23 18-May-23 187 -2

Remaining Level of Effort Remaini... Date Revision Checked Approved


Page 3 of 4 Start Date: 04-Mar-22
Primary Baseline Critical R... Finish Date: 10-Jun-24
GALLERY 105 -Rev. 01_UPDT_17_04_23
Actual Work Milestone Data Date: 17-Apr-23
Three Weeks Lookahead
Activity ID Activity Name Original BL Project Start BL Project Finish Actual / Actual / Expected % Comp Total Var - BL Project 2023 2024
Duration Expected Start Finish Float Finish M A M J Jul A S Oct N D J F M Apr M JJul
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 1516
G105-RW-CON-1070 Submission of Shop Drawings 10 13-Apr-23 02-May-23 17-Apr-23* 04-May-23 0% 187 -2 Submission of Shop Drawings
G105-RW-CON-1080 Shop Drawing Review & Comments 12 02-May-23 16-May-23 04-May-23 18-May-23 0% 187 -2 Shop Drawing Review & Comments
SHADES PACKAGE (MIMA) 88 15-Mar-23 30-Sep-23 11-Mar-23 A 06-Aug-23 195 47

Engineering 29 15-Mar-23 18-May-23 11-Mar-23 A 24-May-23 28 -5


Design 22 15-Mar-23 25-Apr-23 11-Mar-23 A 15-May-23 26 -17
G105-E-SHD-110 Review and Comments on Design - Shades Pkg. 12 15-Mar-23 03-Apr-23 11-Mar-23 A 04-May-23 10% 20 -17 Review and Comments on Design - Shades Pkg.
G105-E-SHD-120 Resubmission of Design (Post Comments) - Shades Pkg. 9 03-Apr-23 25-Apr-23 05-May-23 15-May-23 0% 26 -17 Resubmission of Design (Post Comments) - Shades Pkg.
Shop Drawings 20 03-Apr-23 08-May-23 17-Apr-23 16-May-23 34 -7
G105-E-SHD-140 Submission of Shop Drawings 6 03-Apr-23 14-Apr-23 17-Apr-23 29-Apr-23 0% 20 -7 Submission of Shop Drawings
G105-E-SHD-150 Review and Comments on Shop Drawings 14 14-Apr-23 08-May-23 29-Apr-23 16-May-23 0% 34 -7 Review and Comments on Shop Drawings
Method Statement 21 19-Apr-23 18-May-23 11-Mar-23 A 24-May-23 20 -5
G105-E-SHD-190 Review and Comments on Method Statement 21 19-Apr-23 18-May-23 11-Mar-23 A 24-May-23 10% 20 -5 Review and Comments on Method Statement
Procurement 112 06-May-23 30-Sep-23 17-Apr-23 06-Aug-23 243 55
G105-P-SHD-100 Procurement Works - Motors 56 06-May-23 01-Jul-23 17-Apr-23 11-Jun-23 0% 40 20 Procurement Works - Motors
G105-P-SHD-110 Procurement Works- Blind (Fabric) 112 10-Jun-23 30-Sep-23 17-Apr-23 06-Aug-23 0% 243 55 Procurement Works- Blind (Fabric)
GALLERY FLOOR FINISHES 52 09-Jun-23 14-Aug-23 13-Mar-23 A 22-Jun-23 279 41

Engineering 20 21-Jun-23 15-Jul-23 13-Mar-23 A 11-May-23 154 52


Material Submittals 20 21-Jun-23 15-Jul-23 13-Mar-23 A 11-May-23 154 52
G105-FF-CON-1210 Material Submittals- Review & Comments 12 21-Jun-23 08-Jul-23 13-Mar-23 A 04-May-23 10% 154 52 Material Submittals- Review & Comments
G105-FF-CON-1220 Submission of Material Submittals- Rev-01 6 10-Jul-23 15-Jul-23 05-May-23 11-May-23 0% 154 52 Submission of Material Submittals- Rev-01
Procurement 52 09-Jun-23 14-Aug-23 17-Apr-23 22-Jun-23 279 41
G105-FF-CON-1190 Delivery of Materials 52 09-Jun-23 14-Aug-23 17-Apr-23 22-Jun-23 0% 279 41 Delivery of Materials

Remaining Level of Effort Remaini... Date Revision Checked Approved


Page 4 of 4 Start Date: 04-Mar-22
Primary Baseline Critical R... Finish Date: 10-Jun-24
GALLERY 105 -Rev. 01_UPDT_17_04_23
Actual Work Milestone Data Date: 17-Apr-23
Three Weeks Lookahead