You are on page 1of 21

TECHNICAL | TUNNELLING IMPACTS

TUNNELLING
AND GENERAL
CONSTRUCTION
IMPACTS ON UTILITY
PIPELINES
Dr Cheong Kin Gary Choy and Dr Barry New (both of Geotechnical Consulting Group, UK)
provide a broad guide and structure to assess the impacts on utility pipelines
from various tunnelling and construction activities

1 INTRODUCTION This paper develops and extends The paper cannot cover all types of utility assets
the content of the 2017 Harding Memorial lecture (New, and the various conditions encountered throughout
2019) and reflects the development of techniques used the world. However, it is intended to be as informative
on numerous recent projects including HS2 and Thames as possible so that assessors will be able to adapt
Tideway. It is inevitable that many construction works the presented principles and methods to suit local
will give rise to ground movements which can have conditions and construction methods.
adverse impacts on third party assets if these works
are not carefully designed, planned and carried out: 2 UTILITY REQUIREMENTS
the presence of sensitive, vulnerable or ageing assets There are generally three key utility requirements that
exacerbates this problem. The impact of construction will have to be considered by developers, designers
works on buildings throughout the world have been and contractors throughout the design and construction
well-documented but there is a lack of literature phases of new development schemes:
focusing on the impacts on utility assets. ● T
 he utility must be in compliance with its
Through the authors’ longstanding engagement with statutory and regulatory obligations. In particular,
the Research Working Group (WG2) of the International the serviceability to customers should not be
Tunnelling and Underground Space Association (ITA), it threatened in both short and long term. The failure to
has become apparent that the approaches adopted by protect an asset from any construction damage could
both utilities and developers in different countries vary result in serious health and safety issues, substantial
significantly and are influenced by the prevailing social third-party damages, and penalties from regulators.
and legal frameworks. ● W
 hole-life asset value should be maintained.
The objective of this paper is to provide a broad There should be no damage, loss of capacity or
guide to the assessment of utility pipelines which downgrade of an asset to ensure its value is retained
are subject to impact from various construction to protect stakeholders interests.
activities. It is intended to provide a structure to impact ● T
 he proposed works should not inhibit or prevent
assessment which includes utility requirements, any maintenance or repair works that are required
components of pipeline risk assessment, pipe failure for the asset.
mechanism, masonry, concept of impact strain, and
the staged assessment process. The presented methods In order to meet these key requirements, developers,
and strategies are based on the authors’ experience, designers and contractors are expected to undertake
particularly in London and the Thames Valley. The more pipeline risk assessments to inform utilities regarding
risk-based approach puts an emphasis on rationalising the likely risk to their assets posed by the proposed
the assessment process to reflect the uncertainties development, and how the risk might be eliminated,
about ground and asset conditions, consideration of the minimised or otherwise mitigated. The assessment
consequence of asset failures (see extent of damages cannot be completed without essential information
shown on Figure 1), and implementation of control and from the utility which includes asset maps (showing the
mitigation measures. ‘indicative’ alignment and material of the assets); repair

12 | February 2022
TUNNELLING IMPACTS | TECHNICAL

Left, figure 1:
Images showing extensive
damage caused by asset
failures

and maintenance records; criticality and vulnerability of


the assets; as well as the potential consequence to their
assets of failure.
The pipeline risk assessment prepared by the
Conditions
developer’s team will be reviewed by the utility
engineers and their consultants in order to provide a
high-level assurance to senior managers within the
utility business.
Conciliation Calculations
3 COMPONENTS OF PIPELINE
RISK ASSESSMENT
A pipeline risk assessment is often a complex process
and some of the required input information may PIPELINE RISK
be uncertain or unobtainable. On many occasions, ASSESSMENT
an assessor will have to make certain informed
assumptions in order to complete the assessment.
Figure 2 shows the six key components of pipeline risk
assessment and further details are summarised below: Consent Consequences
1 Conditions (properties) of assets
a Type
i Water, gas, electric, telecoms and others
b Location
Control
i It is important to confirm the line and level (and
material) of the asset via survey and exploratory
excavations because information provided
on utility asset maps may not be accurate or
complete. For instance, since the 2011 Transfer of Above. figure 2:
Private Sewer Regulations, sewage undertakers Components of pipeline
were required to become responsible for many risk assessment
unmapped private sewers. (The Six Cs’ Principles)

February 2022 | 13
TECHNICAL | TUNNELLING IMPACTS

c. Material b. Failure to meet statutory service obligations?


i Iron (grey or ductile); clayware; brick; concrete i There can be a substantial penalty to the utility
(unreinforced or reinforced); thermoplastic if it cannot restore its service to customers
(polyethylene (PE) or polyvinyl chloride (PVC)); within a pre-defined period.
glass reinforced plastic (GRP) c. Loss of whole-life asset value (e.g. damage, loss of
d. Size capacity or downgrade)?
i Outside and inside diameters; pipe section d. Damage to third-party assets and health and safety
length issues (e.g. possible flood zones, explosion)?
e. Jointing e. Financial and reputational impact to the utility’s
i Lead run; Cementitious; Flanged; Welded; business? The general public usually considers
Flexible; Age the utility is at fault even though the cause of pipe
f. Present conditions failure may be associated with other third-party
i Review of repair and maintenance (R&M) history activities.
and night line flow records held by the utility 4 Control (and preparedness)
will give a better indication of the condition of a. Mitigation
the pipe network than the occasional trial pit i Replacement, diversion or strengthening?
investigation. ii Temporary isolation? This will allow the asset
ii Internal survey of sewers allows identification to be inspected and/or tested upon completion
of existing defects which may require urgent of the proposed works before it can be safely
attention before commencement of the reopened for use.
proposed works. iii Pre- and post-condition survey (including
g. Exclusion zone additional inspection to be carried out at critical
i This is the minimum vertical and horizontal phases of the works, where necessary).
clearances required between the extrados of the iv Locate and exercise of valves controlling the
asset and the outer face of the proposed works. flows to minimise the extent of flooding/
ii This is to allow sufficient space for any repair/ damage associated with pipe failure.
maintenance/upgrade works required for the v Potential risk to workers (e.g. substantial
assets. periods of man entry to install structural lining
h. Ground conditions inside a sewer; collapse of brickwork during
i Geo-environment (e.g. chemical attack on pipe removal of temporary support)?
material) vi Potential risk/disruption to public (e.g. traffic
ii Problematic soil (e.g. alluvial deposits) diversion and intrusive traffic management,
iii Bedding (e.g. poor workmanship) traffic delays)?
i. Pre-existing strain (if known) vii Potential risk to projects (e.g. availability
i Strain arising from ground movements or other of materials, pipes and plants; speed of
loadings caused by historic works (e.g. cross construction; unforeseen additional costs and
trenching, tunnelling, basements) time to implement mitigation measures)?
2 Calculations (e.g. ground movements, changes in viii Feasibility of developing a strategy for doing the
loading) minimum to preserve serviceability of the assets
a. Tunnels, shafts, basements, boxes and foundations to reduce potential serious risks associated with
(including any demolition, piling, dewatering works mitigation works?
required and any use of heavy construction plant in ix ‘Do-nothing’ approach? This relies on a
the vicinity of the assets) and associated vibration robust emergency preparedness plan and
issues an undertaking from the developer that, on
b. Geometries and construction sequences/ completion of the works and stabilisation of the
methods (including both temporary and permanent ground movements, any damage will be either
works) repaired or the asset replaced.
c. Ground movement and utility damage assessments b. Monitoring
(e.g. strain, joint rotation and pullout) i Validation of design assumptions relied upon by
3 Consequence of damage the assessments
a. Strategic, trunk or distribution main? ii Type (e.g. ground/pipeline movements, leakage,
i Consequences of pipe failure are not necessarily vibration)
related to pipe size. For instance, a water supply iii Location of monitoring points
to a hospital or fire mains may be in a relatively iv Frequency of data collection
small diameter pipe (distribution main) but v Data interpretation method
nevertheless safety-critical in importance. vi  Trigger levels
ii Failure of a pipe within a resilient network vii Action plan (e.g. termination and/or modification
(i.e. there are sufficient alternative supply of the construction / mitigation processes;
routes) will have less impact on the supply to change in monitoring and data review
customers. frequency)

14 | February 2022
TUNNELLING IMPACTS | TECHNICAL

Left, figure 3:
Loss of mortar and
Missing brick
missing brick around the
Missing mortar arch of a masonry sewer

c. Network resilience 3 Operational overload (which is unlikely given a


i Alternative supply routes within the network? pipe in serviceable condition)
d. Emergency preparedness/contingency planning a. Over pressurisation; surge
i Review of impact models (possible flood zone
and other consequence) New (2019) illustrates typical failure mechanisms for
ii Emergency preparedness plan (EPP) should pipes made from brittle materials (e.g. cast iron, vitrified
include an incident recovery plan that will allow clay, unreinforced concrete) and they can be grouped
rapid repair of a pipe failure. R&M contractors into the following categories:
should be made aware of the works and have ● B earing fracture due to concentration of reaction or
emergency spares and equipment immediately load (which may occur in any size of pipe)
available for repairs. ● L ongitudinal cracking (splitting) due to overload (with
iii Local operations staff notified of the works. larger pipes tending to be more vulnerable)
5 Consent ● C ircumferential crack due to flexural bending (which
a. Has the appropriate level of analysis and checking is most common in metal pipes with diameters of
been carried out? 300mm or less; or unreinforced concrete/vitrified clay
b. Is the risk ALARP (As Low As Reasonably pipe with aspect ratio (pipe length/pipe diameter)
Practicable)? greater than two
c. Response from utility: ‘Approval in Principle’; ● B urst socket due to excessive joint rotation and/or
‘No further comments’, or ‘LONO’ (Letter of No shearing (which may occur in all pipe sizes)
Objection) ● S piral failure due to a combination of longitudinal
6 Conciliation flexural and transverse loading (which is commonly
a. Further negotiations with Developer found in pipes between 300 – 600mm diameter)
b. Court injunction (the last resort)
Experience has shown that the locations of pipe failures
4 PIPE FAILURE MECHANISMS rarely coincide with those pipe sections predicted to
Pipes do not fail randomly and there is always an have the most likely chance to fail. This is because pipe
explanation for pipe failure. Generally, the following failure depends on various factors which, when present
three groups of causes may be attributed to pipe in an unfavourable combination, are sufficient to cause
failures: the failure. Therefore, a probabilistic (rather than a
1 Third-party intervention strictly deterministic) approach is more appropriate for
a. road works; ground movements; compaction; pipeline assessment.
vibration; abnormal surface or other loads
2 Weakened pipe 5 MASONRY
a. Corrosion; casting defects (e.g. incorrect section, Many early trunk sewers were constructed in
wormholes, porosity, joint failure) brickwork and took various geometrical forms (e.g.

February 2022 | 15
TECHNICAL | TUNNELLING IMPACTS

⅓h

½d ½d ½d ½d ⅓d ⅓d ⅓d

(A) (B) (C) (D)

Above, figure 4: Stress distributions across a masonry arch (after Heyman (1982)) with the thrust line acting:
(a) at the centre (b) at slightly off-centre (c) at the limit of ‘middle-third’ (d) outside the ‘middle-third’ limit
(Note: h/3 is the location of the thrust line measured from the edge of the arch)

egg, circular, horseshoe, arched crown and invert with i Developed within the intrados-third of the
vertical sidewall). Analyses of such structures can be masonry arch thickness (see Figure 5a) – tension
analytically more difficult, more uncertain and highly will be developed at the extrados of the sewer.
condition dependant. A basic understanding of masonry However, the stability of the sewer could be
arch theory (see Heyman (1982 & 1995), Szechy (1970) for maintained if there is sufficient external ground
further reading) will assist in undertaking analyses for pressure to hold the arch in place.
assessment purposes. ii Developed within the middle-third of the
Transverse stability is usually the primary concern for masonry arch thickness (see Figure 5c) – tension
masonry arch. Some forms of structural overloading or will not be developed within the arch and the
asymmetrical loading often result in the development stability of the sewer is maintained.
of tension in the masonry. This can result in a loss of iii Developed within the extrados-third of the
mortar or bricks within the crown of the arch (see masonry arch thickness (see Figure 5e) – tension
Figure 3) or elsewhere between the springings, which will be developed at the intrados of the sewer
can subsequently result in collapse as the arch is no and this could result in the loss of mortar and/or
longer functioning because it becomes kinematically bricks around the crown of the sewer.
unstable.
Arch design seeks to resolve the loads upon the arch The ‘ULS envelopes’ shown on Figures 5b, 5d and 5f
into compressive stresses and thereby eliminate tension. indicate the minimum depths from the intrados and
Figure 4 illustrates the stress distributions across a extrados of the sewer at which the thrust line can be
masonry arch with the thrust line acting at various located without exceeding the ULS masonry compressive
locations. Compressive stress is developed across the strength (assuming it to be 2.5MPa in the analysis). For
whole arch thickness when the thrust line is retained stability, the thrust line should remain within the ‘ULS
within the ‘middle-third’ of the arch thickness. However, envelopes’ at all times and also cross the middle axis of
tension is developed when the thrust line is outside the arch at least twice.
the ‘middle-third’ limit. This results in the formation of The development of tension in the masonry can
cracks because masonry is assumed to have negligible also be caused by ground movements associated with
tensile strength for assessment purposes. various construction activities. Given sewer arches are
CIRIA C671 (2009) provides useful guidance for a considered to be semi-continuous linear structures, they
thrust line analysis of a circular masonry structure and are potentially vulnerable to the longitudinal ground
further details are provided in Appendix A. The aim for movement curvatures in a similar way to pipes (see
the thrust line analysis is to confirm if the line of thrust Section 6.3). Further details with regard to transverse
can be developed within an arch ring and equilibrate the strain analysis for masonry structures subject to
given loading. Figure 5 shows an example of a thrust external ground movements are presented in
line analysis of a 2m internal diameter and 0.6m-thick Section 6.8.
circular brick sewer located at a depth of 8m under Published test results on tensile and compressive
three different horizontal stress to vertical stress ratios strengths of masonry (see Backes (1985)) indicate that
(KT). maximum tensile strength can be less than 1% of
The location of the thrust line is one of the compressive strength whereas tensile modulus can
determining factors for masonry sewer transverse be significantly less than the compressive modulus.
stability: However, there is a common mistake by assessors to

16 | February 2022
TUNNELLING IMPACTS | TECHNICAL

Below, figure 5 Example charts (all units in m) showing a thrust line analysis of a 2m ID circular masonry sewer
(0.6m thick, 8m depth to axis, 2.5MPa ULS masonry compressive strength) with various horizontal stresses to vertical stress ratios (KT)

2.0 2.0

1.5 1.5

1.0 1.0

0.5 0.5

0.0 0.0

-0.5 -0.5

-1.0 -1.0

-1.5 -1.5

-2.0 -2.0
-2.0 -1.5 -1.0 -0.5 0.0 0.5 1.0 1.5 2.0 -2.0 -1.5 -1.0 -0.5 0.0 0.5 1.0 1.5 2.0
Intrados Intrados 1/3 Extrados Extrados 1/3 Thrust line Intrados Intrados ULS Extrados Extrados ULS Thrust line

(a) KT = 0.5 (Middle-third Envelopes) (b) KT = 0.5 (ULS Envelopes)

2.0 2.0

1.5 1.5

1.0 1.0

0.5 0.5

0.0 0.0

-0.5 -0.5

-1.0 -1.0

-1.5 -1.5

-2.0 -2.0
-2.0 -1.5 -1.0 -0.5 0.0 0.5 1.0 1.5 2.0 -2.0 -1.5 -1.0 -0.5 0.0 0.5 1.0 1.5 2.0
Intrados Intrados 1/3 Extrados Extrados 1/3 Thrust line Intrados Intrados ULS Extrados Extrados ULS Thrust line

(c) KT = 0.7 (Middle-third Envelopes) (d) KT = 0.7 (ULS Envelopes)

2.0 2.0

1.5 1.5

1.0 1.0

0.5 0.5

0.0 0.0

-0.5 -0.5

-1.0 -1.0

-1.5 -1.5

-2.0 -2.0
-2.0 -1.5 -1.0 -0.5 0.0 0.5 1.0 1.5 2.0 -2.0 -1.5 -1.0 -0.5 0.0 0.5 1.0 1.5 2.0
Intrados Intrados 1/3 Extrados Extrados 1/3 Thrust line Intrados Intrados ULS Extrados Extrados ULS Thrust line

(e) KT = 1.1 (Middle-third Envelopes) (f) KT = 1.1 (ULS Envelopes)

February 2022 | 17
TECHNICAL | TUNNELLING IMPACTS

Original brickworks
around sewer crown

Right, figure 6:
Collapse of masonry sewer
caused by a storm event

Collapsed sewer section

adopt numerical models (finite element or similar) Masonry sewers were generally designed for
which assume masonry as linear elastic material with sustaining gravity flows without surcharge. However, the
‘unrestricted’ tensile strength and modulus of elasticity continuous expansion of population in cities has led to
equal in both tension and compression. It is important to a significant increase in volumes of sewage passing into
note that a numerical model must not assume tensile the network which can generate surcharge pressures.
properties that do not exist or cannot be justified. This can result in unacceptable hoop tension in the

Δσvo

CPRin-situ CPRexcavation
σvo / P > 1.33 (σvo - Δσvo) / P < 1.33 Collapse

Above, figure 7: Illustration of failure mechanism associated with CPR dropping below 1.33 as a result of excavation
(Note: σvo = existing soil overburden pressure, Δσvo = change in soil overburden pressure due to excavation,
h = head of surcharge pressure, γw = unit weight of water & P = surcharge pressure)

18 | February 2022
TUNNELLING IMPACTS | TECHNICAL

masonry which can lead to sewer collapse (see Figure 6). strain’ may be that predicted during the assessment
Stability of masonry sewers relies on sufficient process or back-calculated from field measurements
confinement during any surcharge events. The undertaken during the works.
consideration of the Confinement/Pressure Ratio (CPR) The calculated impact strain should be compared
gives an indication of the vulnerability of masonry with the assessment criteria advised by the relevant
sewers when subject to surcharge pressure. CPR is utility. This will provide an indication of the risk of
defined as the ratio of soil overburden pressure at the damage to the pipe associated with the proposed
sewer axis level (σvo) to the water pressure within the construction works.
sewer (P). For assessment purposes, the surcharge
pressure within a sewer is commonly taken as the 6.1 KEY ASSESSMENT ASSUMPTIONS
hydrostatic pressure to the levels of the controlling For Stages 1 and 2 of the assessment process (see
nearby manholes or other sources of pressure relief. Section 7) it is conservatively assumed that:
If a masonry sewer is in good condition and other 1 ‘Green field’ ground movement is adopted.
significant destabilising loadings are absent, a CPR in 2 Longitudinal flexural (bending) of the pipe follows
excess of 1.33 is generally considered to be acceptable. this ‘green field’ ground movement (i.e. stiffness of
This criterion is also applicable to sewers constructed the pipe is ignored).
using materials vulnerable to surcharge pressures such 3 The joints are stiff so that the pipe is assumed
as unreinforced concrete (see Figure 7). to be a continuous linear structure. This allows
CPR check is also a useful tool for assessing the calculation of maximum longitudinal flexural
potential vulnerability of unbolted water transmission (bending) stain.
tunnels. CPRs in excess of 1.33 under surge pressure 4 The joints are fully flexible so that the limiting
and 1.5 under operating pressure have been found to be condition is in joint rotation.
acceptable. 5 In the absence of site specific information, a 3.66m
Reduction in soil overburden pressure is usually (12ft) long pipe is used for the calculation of
caused by excavations for various structures (e.g. joint rotation for UK metal pipes. It is also useful
stations, basements) and can produce potentially to review dimensions provided in the Standards
damaging unload of confining compressive hoop loads and/or manufacturer specifications for other pipe
in both sewers and water tunnels. Therefore, this issue materials.
should be considered at the earliest planning stage for 6 Flexural strain is calculated at the pipe extrados.
infrastructure and buildings in order to avoid a design a Metal/plastic pipes – the neutral axis is at
which is unacceptable to the utilities. the geometric centre (i.e. lever arm equal to
Many masonry sewers are commonly subject to external pipe radius).
frequent cycles of large loadings from heavy traffic b Materials of low/negligible tensile strength (e.g.
and vibration. A fatigue-type racking motion within the masonry, vitrified clay, unreinforced concrete) –
masonry, caused by rotation of principal stresses and the neutral axis is at the pipe extrados (i.e. lever
such loadings from a rolling axle, can result in sewer arm equal to external pipe diameter).
failure. 7 Total ground movements are simply obtained by
superposition, as appropriate.
6 CONCEPT OF ‘IMPACT STRAIN’
For assessment purposes, the parameter ‘strain’ rather 6.2 SOURCES OF GROUND DISTURBANCES
than ‘stress’ is adopted as the damage criteria. This is 6.2.1 Tunnels
because it is displacements both in the ground and of Gaussian models (e.g. O’Reilly & New (1982) reprinted
the pipeline which are actually measured and used in 2015; New & O’Reilly (1991); Leca & New (2007)) have
to monitor and control the works. The conversion to been commonly used to calculate green field tunnelling
stress can be done but this introduces an unnecessary induced movements and associated slope, curvature
uncertainty in the choice of appropriate moduli. and strain because they are straightforward to apply
It is self-evident that a pipe will fail when the and have stood the test of time in their application.
movement/load imposed upon it exceeds its strain limit. The authors are not aware of any body of data that
In order to assess the impacts on the pipe as a result would contradict their general application for initial
of the proposed construction works, it is important to assessment of near surface pipelines with a depth to
understand the existing state of strain within the pipe axis of less than say, 3m.
which is unknowable in many circumstances. This leads The ‘ribbon sink’ model by New & Bowers (1994) is
to the introduction of the concept of ‘impact strain’ for useful for calculating ground movement in stiff cohesive
assessment purposes. materials at depth (especially for estimating movements
‘Impact strain’ is defined as the strain arising from in the vicinity of the tunnel under construction).
ground movements or other loadings caused by the Three dimensional movements from complex tunnel
proposed construction works. It does not include any geometries can be calculated using this model.
strains arising from any other causes (including pre- Volume loss (Vl) and trough width parameter (K)
existing ground movement, ground load, operating are the two key input parameters for the calculation of
pressures or normal vehicular loading). This ‘impact tunnelling-induced ground movements based on

February 2022 | 19
TECHNICAL | TUNNELLING IMPACTS

the Gaussian models. Recent experience in London Dewatering (either route wide, local, short-term or
has confirmed that a volume loss of 1% for tunnelling long-term) is commonly required to facilitate excavation
in stiff cohesive materials (e.g. London Clay) has usually for shafts, basements and boxes, and this can give rise
not been exceeded by using Earth Pressure Balance to significant ground movements. Local dewatering
Machines (EPBMs) and this is generally considered as (especially in the presence of alluvial deposits) can
a ‘moderately conservative’ assumption for assessment result in damaging localised differential ground
purposes: this relates to a single tunnel driven in ground movements. Designers for the dewatering system should
undisturbed by other tunnels. Historically however, it is work with the assessors to minimise the risk of damage
clear from the literature that for twin tunnels the driving to the pipelines and other utility assets.
of a second tunnel parallel to the first yields larger
volume losses. 6.2.3 Foundation & heavy/abnormal loading
This is confirmed by recent measurements reported by The application of foundation loadings will result
Wan et al. (2017) during the construction of twin tunnels in ground movements and potential overloading of
(7.1m bore diameter, axis depth of 34.5m and 16.3m underlying utilities. The construction and use of piled
separation) below Hyde Park in London for Crossrail foundations in close proximity to a pipeline may result in
(now the Elizabeth Line). The surface volume loss during damage which can be caused by:
the excavations for the first tunnel being about 0.8% ● E xcessive pile loading onto the pipeline (e.g. shaft
but for the second tunnel increased to about 1.4%. This load shedding, end-bearing pressure)
increase is attributed to a softening of the clay caused ● U ncontrollable ground loss during pile boring within
by the first tunnel excavations. This would indicate that difficult ground conditions (e.g. water bearing gravels)
the impact assessment for the second of twin tunnels a ● E xcessive vibration during pile construction (e.g.
volume loss of greater than 1% should be considered by driven piles, encountering physical obstructions)
designers.
It is important to note that the predicted ground The use of temporary casings, sleeving, non-vibratory/
movements based on the Gaussian models cited above non-percussive piling methods (e.g. silent piling) and
are neither conservative nor un-conservative. It is the redesign of the foundation layout, backed-up by the
assessors’ responsibility to establish and justify the calculation of associated impacts, are the common ways
parameter values adopted in their analyses. Given the to mitigate the risks mentioned above.
uncertainties in the input parameters, more complex Construction works normally involve the use of
models are unlikely to be beneficial/necessary to Stages sizeable plant (e.g. cranes, piling rigs, load loaders,
1 and 2 of the assessment processes (see Section 7). self-propelled modular transporters (SPMTs)) which
can impose damaging loadings onto pipelines. The
6.2.2 Shafts, basements/boxes, dewatering ALARP risk approach is to ensure these heavy/abnormal
Tunnel construction often require construction of loads are positioned outside the zone of influence of the
shafts which are used for tunnel boring machine (TBM) pipeline, which is an area commonly defined by drawing
launching, access, and maintenance purposes and the 45 degree lines upward and away from the pipeline. This
shaft construction itself can lead to significant ground can also be achieved by using bridging structures to
movements. Based on the original predictive equations carry the load away from the pipeline.
proposed by New & Bowers (1994) and an extensive If it is not possible to position the loads outside the
database of measurements taken in London, New zone of influence, both longitudinal and transverse
(2017) has proposed a generic equation for predicting analyses for the pipeline will be required. Simple
settlement at a distance from the shaft wall: analytical solutions (e.g. Boussinesq approach) are
Sd = αH (1- d/nH)2 generally adopted for the assessment. It is unlikely to
where be beneficial to undertake soil-structure interaction
Sd is the settlement at a distance d from the shaft wall. analysis given the uncertainties regarding the ground
n is a simple multiple of the shaft depth H to a distance and pipe conditions.
d from the shaft wall where settlement becomes
zero. (Note: n = 1 for the original New & Bowers (1994) 6.2.4 Demolition
equation). Analysis should be undertaken to assess the potential
α is an empirical constant and αH is the settlement at ground movements and associated impacts on the
the shaft wall. pipeline due to demolition works. Careful control of
demolition operation is important to minimise the
The n and α values are dependent on shaft diameter, level of vibration and impact loads transmitted to the
ground conditions and construction method. The pipelines.
assessors will have to establish and justify their
parameter choices based on appropriate empirical data 6.2.5 Vibration
(e.g. case histories). Construction works may generate vibrations (dynamic
CIRIA C760 (2017) provides good guidance on ground ground strains) that can be damaging to local
movements associated with construction of basements structures, including utility apparatus. However, there
and boxes. are now non-vibratory methods available that can

20 | February 2022
TUNNELLING IMPACTS | TECHNICAL

Left, figure 8:
Calculation of longitudinal
radius of curvature based
Initial pipeline profile
on three consecutive
flexural displacement data
points

Flexural displacement
profile

build almost all structures without significant vibration of third-party asset owners in restricting PPVs (peak
impact. In order to mitigate this risk, it is common for particle velocities) to acceptable levels. Straightforward
major asset owners (e.g. Transport for London (TfL), predictive guidance is given in British Standard BS5228-
Thames Water Utilities Limited (TWUL)) to require an 2:2009 for piling and tunnelling works and the Highways
exclusion zone around their assets and this is typically Agency (Transport Research Laboratory TRL) has
15m from a vibratory source which is usually piling or published detailed predictive methods for a range of
vibratory compaction. vibratory sources caused by mechanised construction
Even at greater ranges, some piling works can present works (Hiller & Crabb, 2000).
difficulties but modern ‘city rigs’ and pre-augured Threshold values relating damage to transient and
vibratory methods can often meet the requirements continuous vibration levels for various structural

Material capable of sustaining tension under bending (e.g. cast iron, ductile iron, steel)

D
Bending (compression)

y = D/2
Left, figure 9:
Neutral axis Development of flexural
Bending (tension)
tensile strains for pipe
material either capable or
D incapable of sustaining
tension under bending
y=D

Bending (tension)
Material incapable of sustaining tension under bending (e.g. masonry, vitrified clay, unreinforced concrete)

February 2022 | 21
TECHNICAL | TUNNELLING IMPACTS

Circumferential crack

Circumferential crack

Vitrified Clay Pipe Masonry Sewer

Above, figure 10: Examples of circumferential cracks caused by longitudinal flexure (bending)

types are given by British Standards BS7385-2:1993. where


An important factor often overlooked is the possibility dn is the flexural displacement predicted at the nth data
that vibration can increase the density of, and cause point along the assessment line and i is the interval
settlement, in some soils, which can put structures at between the data points (see Figure 8). An interval of 1m
risk (see BS5228-2:2009 Section B.3: Note 3). is generally adopted for assessment purposes. However,
a smaller interval may be required to capture any abrupt
6.3 Longitudinal flexural (bending) strain changes in curvature along the pipeline.
Longitudinal flexural (bending) strain (εb) along a The lever arm y is a function of the pipe extrados
pipeline is calculated from simple beam theory and is diameter (D) and is dependent on pipe material. Figure
given by: 9 illustrates the definition of lever arm for pipe material
εb = y / R either capable or incapable of sustaining tension under
where bending. Examples of circumferential cracks caused by
R is the longitudinal radius of curvature and y is the longitudinal flexure (bending) are shown in Figure 10.
lever arm to the neutral axis of a pipe.
6.4 Axial Strain
The calculation of longitudinal radius of curvature (R) is The calculation of axial strain (εa) along a pipeline is
given by: given by:
R = i2 / [2dn – (dn-1 + dn+1)] εa = [(S + ΔS) / S]

P1 P2

Initial positions

Right, figure 11: P1 P2


Development of axial
S - ∆S
tensile and compressive
strains along a pipeline
Axial compression

P1 P2

S + ∆S

Axial tension

22 | February 2022
TUNNELLING IMPACTS | TECHNICAL

Flexural
displacement
profile
D Left, figure 12:
Assessment of joint

rotation

where 6.5 Joint rotation


S is the initial distance between P1 and P2, and ΔS is the Assessment of joint rotation (ꞵ) is typically undertaken
change in the axial distance between P1 and P2. Axial by tracking two pipes along the predicted flexural
compression and tension are represented by negative displacement profile with the left and right end of
and positive ΔS values respectively (see Figure 11). the two pipes and the joint following the flexural
The bending strain (εb) and axial strain (εa) are usually displacement profile (see Figure 12) until the point of
combined together to calculate the total ‘impact strain’ maximum rotation has been established. The magnitude
for a pipeline when undertaking assessments. This of joint rotation is dependent on the pipe length L which
can sometimes result in very significant impact strain is usually assumed to be 12ft (3.66m) if as-built records
even after the axial strain reduction factor proposed by are not available.
Attewell et al. (1986) has been applied. Joint rotation is an important cause of failure in larger
Following review of field experience and various cast iron pipe (with diameter in excess of about 300mm
calculation methodologies, New (2019) concludes that or 12in) because of its higher bending stiffness. This
axial strain may be regarded as negligible for various allows the generation of very large bursting forces as
types of pipes at relatively shallow depths (say 2m) for the spigot rotates within the socket. Figure 13 shows an
the Stage 1 and Stage 2 assessment processes. However, image of a reconstructed cast iron pipe after suffering
assessors may still wish to include axial strain when from socket bursting caused by joint rotation.
assessing pipes of critical importance. It is important
to note that the potential axial compressive and tensile 6.6 Joint pullout
strains cannot be relied on to reduce flexural tensile and The axial ground strain may induce relative movement
compressive strains respectively (i.e. the beneficial axial between pipe lengths resulting in joint pullout (see Figure
strains are ignored) for assessment purposes. 14) which should be assessed because excessive joint

Left, figure 13:


Reconstructed cast iron
Zone of fracture associated pipe after suffering from
with socket bursting
socket bursting caused by
joint rotation

February 2022 | 23
TECHNICAL | TUNNELLING IMPACTS

J Initial spacing between mid-points


of adjacent pipe J

Initial Position

Right, figure 14:


Joint pullout
J + ΔJ Joint pullout ΔJ

Final Position

displacement can cause leakage. Assuming the is usually developed at the quarter points of the pipe
pipeline is rigid and the joint is free to accommodate wall. The maximum transverse bending strain (εt) at the
axial movement, the joint pullout will not be more than quarter points of the pipe wall is given by New (2019) as:
the differential ground movement between mid-points εt = 3 σv r2 (1 - K0) /2 E t 2
of adjacent pipes (see Attewell et al. (1986)). where
For an optimally aligned spigot and socket σv is the vertical stress at the pipe axis level. This can be
connection, a pullout limit of 3mm can be considered estimated by Boussinesq-based analyses.
for cast iron pipes as a joint leakage criterion for K0 is the ratio of horizontal to vertical ground stress.
assessment purposes. r is the mean radius of the pipe.
For non-flexible joints (e.g. bolted flanges), the E is the Young’s modulus of the pipe (typically 80GPa
pipelines should be considered as continuous linear for cast iron pipe).
structures with a check that the connections are not t is the pipe wall thickness.
overstressed.
6.8 Transverse strain for masonry sewer
6.7 Transverse (crushing) strain for pipe For assessment purposes, it is conservative to assume
The problem with large diameter pipe subject to load that masonry has negligible tensile strength and each
from concentrated sources from above is crushing. This part of the outer circumference of the masonry sewer
can result in longitudinal cracking (see Figure 15) which moves with the ground (full bond). The transverse sewer

Longitudinal crack Longitudinal crack

Vitrified Clay Pipe Cast Iron Pipe

Above, figure 15: Longitudinal cracks observed along vitrified clay pipe and cast iron pipe due to crushing failure

24 | February 2022
TUNNELLING IMPACTS | TECHNICAL

Vertical, z

α=90°

δz+
δT+

δN+
δy+

Int
ern
al r
adiu α+ Left, figure 16:
s
Notation for a transverse
α=180° α=0°
Lateral, y strain analysis of a circular
masonry sewer
s
iu
ad
lr
na
r
te
Ex

α=270°

movements are calculated around the periphery of the mode (i.e. decrease in vertical and increase in horizontal
brickwork at appropriate intervals. dimensions of the sewer) and both have to be
Figure 16 provides the nomenclature used in the considered during the analyses of the transverse strains
calculations of transverse strain of a circular masonry so as to ensure that the worst case is detected.
sewer. The vertical and horizontal movements derived Example charts showing the predicted distortion,
from the methods described in Section 6.2 are resolved displacement and tensile strain profiles of a circular
into movement in the radial (δN) and hoop (δT) masonry sewer, which runs normal to the tunnel
(circumferential) directions: direction including assumed parameters, are shown
δN = δy cos α + δz sin α in Figure 17. Note that the maximum transverse tensile
δT = -δy sin α + δz cos α strains are found to be in the crown/invert section and
springings, with the sewer under ‘squatting’ and
The sewer is divided into a number of segments ‘egging’ modes respectively. The hoop compressive
at appropriate intervals anticlockwise around the strain in the sewer due to the existing ground load is
circumference as shown. The axial strain in each to be considered and this reduces the maximum
segment is calculated from the change in length of transverse tensile strains currently shown on the
each segment indicated by δT and flexure is derived by charts.
analysis of a triplet based on δN (see Figure 8).
A similar assessment approach can be applied to 6.9 Assessment guidance and criteria
non-circular masonry sewers. Early consultation between the developers and the
The key to masonry sewer stability is to prevent relevant utilities (especially during the initial project
excessive tensile strains in the haunches and crown planning stage) is highly recommended. This will
so as to prevent bricks falling out giving rise to arch allow the developers to get a better understanding of
instability. Depending on the sewer position relative to the acceptable procedures and criteria which can be
the proposed construction works, the sewer may be applied for the impact assessment. This can reduce the
in either egging (i.e. increase in vertical and decrease risk of abortive work and the associated delays and
in horizontal dimensions of the sewer) or squatting unexpected costs to projects.

February 2022 | 25
TECHNICAL | TUNNELLING IMPACTS

Thames Water Utilities Limited (TWUL), the largest


water and wastewater services company in UK, offers
‘Guidance on piling, heavy loads, excavations, tunnelling
Brick Sewer (2m ID, 0.6m thick) z
and dewatering’ on their website (https://www.
Depth to axis (8m) =90°
thameswater.co.uk/developers). The assessment criteria
provided in that document are summarised in Tables
z+
1 and 2 and they assist developers in preparation of T+
N+
impact assessment reports. The criteria are for guidance y+
only, and it is based on early work by Attewell et al.
1m
(1986) and years of experience by TWUL. It is intended +

to represent a level of risk of damage which may be =180° =0° y


1.6m
reasonably regarded as negligible for a pipe in average
to good condition. It is a fact however that any pipe is
potentially vulnerable to any increase in strain and joint
rotation. The developers’ designers may adopt alternative
criteria values, provided they can justify that the risk of
damage remains negligible. =270°
Attewell et al. (1986) and Bracegirdle et al. (1996) also
offer useful guidance on the assessment of strain in
cast iron pipelines.

7 THE STAGED ASSESSMENT PROCESS 4


Position change in vertical (z) direction (mm)

A more risk based, three-stage approach for pipeline 2


assessment has been proposed by New (2019). The 0
aim is to demonstrate the risk balance between the -2
likelihood (based on evaluation of ground movement -4
and ‘impact strain’ presented in Section 6) and -6
consequences of an adverse event, and the ability to -8
recover (i.e. emergency preparedness and resilience) -10
during and after the works. -12
Details for this staged assessment approach will not -14
be repeated here. However, a comprehensive summary -16
of this staged assessment process is presented on Figure -18
18 and the key considerations are listed below: -20
Stage 1 (Assessment scope and information -16 -14 -12 -10 -8 -6 -4 -2 0 2 4 6 8 10 12 14 16
retrieval) Position change in lateral (y) direction (mm)
a. Identification of all utility assets which may be 10° Interval Original Prediction
affected by the proposed works:
i Calculation of likely green field ground
movements based on conservative assumptions.
ii Assets falling outside the 1mm settlement 4
Position change in vertical (z) direction (mm)

contour are likely to be excluded from further 2


analysis. 0
iii Contours indicating minimum radius of -2
curvature (R) or maximum curvature (1/R) can -4
assist in identifying those assets most likely to -6
need mitigation at this earliest stage. -8
b. Gathering of information needed for subsequent -10
stages of the risk assessment (see ‘Conditions -12
(properties) of assets’ and ‘Consequence of damage’ -14
in Section 3 for further details). -16
Stage 2 (More detailed analysis)
-18
a. Longitudinal and transverse analyses (based
-20
on moderately conservative assumptions and -16 -14 -12 -10 -8 -6 -4 -2 0 2 4 6 8 10 12 14 16
calculation methodologies as presented in Sections 5 Position change in lateral (y) direction (mm)
and 6) for those assets not eliminated by the Stage 10° Interval Original Prediction
1 preliminary assessment.
b. Produce charts showing (axial, lateral, vertical and
flexural) displacements, curvature, (axial, flexural,
combined tensile and compressive) strains, joint

26 | February 2022
TUNNELLING IMPACTS | TECHNICAL

Below, figure 17: Example charts showing distortion, displacement and tensile strain profiles of
a circular masonry sewer, which runs normal to the tunnel direction including assumed parameters

0.1
Excavated diameter (8m)
(%, -ve = squat; +ve = elongate)

Depth to axis (32m)


Diametrical distortion

0.05 Volume loss (1%)


K = 0.5

-0.05

-0.1
40 50 60 70 80 90 100 110 120 130 140 150 160
Distance along sewer (m)

Vertical (z) Lateral (y) Squatting Egging

Transverse Notation & Diametrical Distortion Profile

1.0 1500
0.8
1250
0.6
0.4
Displacement (mm)

1000
0.2
Strain (με)

0.0 750
-0.2
500
-0.4
-0.6
250
-0.8
-1.0 0
0 30 60 90 120 150 180 210 240 270 300 330 360 0 30 60 90 120 150 180 210 240 270 300 330 360
Degree α (°) Degree α (°)

δy δz δT δN Tensile (Intrados) Tensile (Extrados)

'Squatting Mode' - Distortion, Displacement & Tensile Strain Profiles

1.0 1500

0.8
1250
0.6
0.4
Displacement (mm)

1000
0.2
Strain (με)

0.0 750

-0.2
500
-0.4
-0.6
250
-0.8
-1.0 0
0 30 60 90 120 150 180 210 240 270 300 330 360 0 30 60 90 120 150 180 210 240 270 300 330 360
Degree α (°) Degree α (°)

δy δz δT δN Tensile (Intrados) Tensile (Extrados)

'Egging Mode' - Distortion, Displacement & Tensile Strain Profiles

February 2022 | 27
TECHNICAL | TUNNELLING IMPACTS

Table 1: Assessment criteria for existing TWUL pipeline and sewer assets
Allowable increase in strain (µε)
Pipe type Diameter (mm) Rotation (degree)
Tension Compression
Brick Sewer (red/yellow/blue brick) N/A 500 25% of the allowable stress N/A
Cast Iron (lead-yarn joints) N/A 100 1200 0.1
Ductile Iron (lead-yarn gasket joints) N/A 500 700 0.5
Ductile Iron (rubber gasket joints) N/A 500 700 2.0
Steel N/A 450 450 1.5
<125 80 400 0.5
Vitrified clay
>125 80 400 See Table 2
<225 20 400 0.5
Concrete (unreinforced) 225 – 750 40 400
See Table 2
>750 60 400

Table 2: Maximum rotation for existing TWUL vitrified clay and concrete pipes
Diameter (mm) Rotation (degree)
<375 2.0
375 – 750 1.0
750 – 1400 0.5
>1400 0.3

rotation and pullout along the particular section ii Assessors should justify the necessity of
of the pipe under consideration. undertaking numerical analysis (finite
c. Identify those assets likely to be particularly element or similar) and the results should
vulnerable based on R&M history, night line flow be corroborated by closed form (analytical)
history and condition survey. solutions together with case history data
d. Identify those assets which are of critical where possible. Further guidance on the
importance and with high consequence of failure. management of advanced numerical modelling
e. Those assets which fail to meet the utility in geotechnical engineering can be found in
assessment criteria and/or with high criticality/ CIRIA C791 (2020).
vulnerability are further considered in the Stage 3 Mitigations
risk analyses. a. There are various engineering solutions to
Stage 3 (Evaluation of risk) mitigate risk to pipelines. However, there will
a. Risk/remedy based approach be risks associated with the implementation
i Acceptable level of risk? ALARP concept (i.e. the of the mitigation measures. Further details are
risk shall be ‘As Low As Reasonably Practicable’) summarised under ‘Control (and Preparedness)’ in
ii Importance of collaboration between developer Section 3.
and utility to develop a ‘reasonable and b. Pre- and post-work inspections of the assets
optimised’ solution which is acceptable to both are recommended. This can inform the assessors
parties regarding the current condition of the asset so that
iii Establish/justify the need for intrusive an appropriate set of criteria will be adopted in
diversionary or mitigation works (see ‘Control the impact assessment. Also, any damages/defects
(and Preparedness)’ in Section 3 for further identified after the completion of the proposed
details regarding inherent risks associated with works can then be repaired in order to restore the
these works and alternative options). whole-life asset value.
iv Consideration of consequential losses (in terms c. It is important to have an Emergency Preparedness
of ‘health and safety’, failure to meet statutory Plan (EPP) in place throughout various phases of
requirements, and ‘commercial’). the construction works. An incident recovery plan
v Risk of incorrect analysis or human errors should be included that will allow rapid repair
during the formal checking and approval of of a pipe failure and have provision of equipment
reports. and spares required to restore serviceability to
b. Need for soil-structure analysis? customers promptly while repair works are being
i Use of numerical models can be helpful undertaken (e.g. overpumping equipment covering
for certain applications but it is generally a sewer failure scenario).
considered to be unnecessary for pipeline d. It is important for developers to provide a RAMS
assessment, given the uncertainties about the (Risk Assessment and Method Statement) package
ground and pipe conditions and difficulties for early review by the utility to ensure the works
in establishing an appropriate set of input will be carried out within the constraints defined
parameters. by the utility and be ALARP.

28 | February 2022
TUNNELLING IMPACTS | TECHNICAL

Conservative Green field


assumptions settlement contour
Assessment scope

Limits of deviation Maximum curvature

STAGE 1
Current state
Location? Type? R&M History? Criticality? Exclusion zone?
of strain?
Information
retrieval
Consequence
Material? Size? Condition? Geo-environment?
of damage?
Asset not eliminated by
Stage 1 assessment

Curvature? Joint rotation?


Longitudinal
analysis
Moderately
conservative Strain? Pullout?
assumptions
More detailed
analysis
Green field analysis Distortion? CPR?

Transverse analysis

STAGE 2 Vulnerability? Strain? Middle-third rule?

Statutory or
Asset fails to meet the assessment criteria,

Health & Safety commercial


issues? obligations?
or high criticality/vulnerable asset

Consequence
of failures?
Financial impacts?

Collaboration Incorrect analysis/


ALARP Concept (Developer & Utility) human errors
Risk/remedy-
based approach
Risk to life and/or H&S risk to work Retain whole life Do nothing & repair
other third parties? around utilities? asset value? when required?
Need for
diversionary/
mitigation works?
Inconvenience Maintain
Network resilience?
to public? serviceability?
STAGE 3 Consequential losses
(H&S/Statutory
Requirements/
Commercial)?

Uncertainties
& Difficulties
Soil-structure
analysis?
Corroboration
(closed-form
solutions/case
history data)

Further considerations

Emergency
Type? Frequency? Trigger level? Preparedness Strengthening? Replacement?
Plan?
Monitoring, control Mitigation
& validation
Data Do minimum
Pre & Post work
Location? interpretation Action plan? Diversion? to maintain
inspection?
method? serviceability?

Review of
RAMS Package

Above, figure 18: Summary of staged assessment process

February 2022 | 29
TECHNICAL | TUNNELLING IMPACTS

Monitoring, Control, and Validation of Design 8 CONCLUSIONS


Assumptions This paper provides a guide to the assessment of
a. A well-thought-out and carefully planned pipelines subject to impact from various construction
monitoring system will provide useful information activities. In summary, a pipeline risk assessment
for validation of the design assumptions relied upon comprises six key components including ‘Conditions’,
by the assessors and provide ongoing assurance to ‘Calculations’, ‘Consequences’, ‘Control’, ‘Consent’ and
the utility. The monitoring results will also be used ‘Conciliation’, and these form the components of the
to confirm adequacy of the measures controlling three-stage assessment processes. The presented
the works. methods and strategies are drawn from the authors’
b. The Instrumentation and Monitoring (I&M) plan experience of the assessment processes developed
should include the type and location of monitoring through their works in London and the Thames Valley
points, frequency of data collection, data over the last two decades.
interpretation method, trigger levels and action This paper is intended to be as general and
plan. informative as possible so that the assessors will be
c. The action plan should include a strategy to cover equipped with appropriate tools to go through the
what to do in an event of a breached trigger impact assessment processes and have a positive
level (e.g. termination and/or modification of dialogue with the utility. The ultimate goal is to
the construction/mitigation processes; change in achieve a ‘reasonable and optimised’ solution which
monitoring and data review frequency). is acceptable to both parties, is truly ALARP and most
d. Continuation of post-work monitoring until importantly, takes a holistic view of risk.
cessation of significant ground movements has
become normal practice. For some recent major 9 ACKNOWLEDGEMENTS
infrastructure projects, the monitoring works have Any views expressed in this paper are those of the
been terminated when the settlement rate is less authors and not necessarily those of Thames Water
than 2mm/year. Utilities Limited or any other utility.

REFERENCES ● H
 iller, D. M. and Crabb, G. I. (2000). Groundbourne vibration
● A
 ttewell, P. B., Yeates, J. and Selby, A. R. (1986). Soil caused by mechanised construction works. TRL Report 429.
movements induced by tunnelling and their effects on pipelines Transport Research Laboratory (Highways Agency) Crowthorne.
and structures. Blackie. ● L
 eca, E. and New, B. M. (2007). Settlements induced by
● B
 ackes, H. P. (1985). Tensile strength of masonry. Proceeding tunnelling in soft ground. ITA Report. Tunnelling and
of the 7th International Brick Masonry Conference. Frank Underground Space Technology, Elsevier, 22, pp. 119-149.
Dnaiels Pty, Australia, pp. 779-789. ● N
 ew, B. M. (2017). Shaft settlements. Tunnels and Tunnelling
● B
 racegirdle, A., Mair, R. J., Nyren, R. J. and Taylor, R. N. International, September, pp. 16 -17.
(1996). A methodology for evaluating potential damage to cast ● N
 ew, B. M. (2019). The 2017 Harding Memorial Lecture (BTS/
iron pipes induced by tunnelling. Geotechnical aspects of ICE). Tunnel construction impacts on utility pipelines. Tunnels
underground construction in soft ground. Balkema, Amsterdam, and Tunnelling International, February, pp. 20-42.
pp. 659-664. ● N
 ew, B. M. and Bowers, K. H. (1994). Ground movement
● B
 ritish Standards Institution (1993) BS7385-2:1993. model validation at the Heathrow Express Trial Tunnel. Proc.
Evaluation and measurements for vibrations in buildings – Part Tunnelling ‘94, Inst. Mining & Metallurgy, Chapman & Hall,
2: Guide to damage levels from Groundbourne vibration. London.
● B
 ritish Standards Institution (2009) BS5228-2:2009. Code of ● N
 ew, B. M. and O’Reilly, M. P. (1991). Tunnelling induced
practice for noise and vibration control on construction and ground movements: predicting their magnitude and effects.
open sites – Part 2: Vibration. Invited review paper to: Int. Conf. Ground Movements and
● C
 IRIA (2009). C671 Tunnels: inspection, assessment and Structures, Univ. Wales, July (ICE, London).
maintenance. CIRIA, London. ● O
 ’Reilly, M. P. and New, B. M. (1982). Settlements above
● C
 IRIA (2017). C760 Guidance on embedded retaining wall tunnels in the United Kingdom – their magnitude and
design. CIRIA, London. prediction. Proc. Tunnelling 82, pp. 173-181. Instn. Min. and
● C
 IRIA (2020). C791 The management of advanced numerical Metal, London. (Reprinted in May 2015 Tunnels and Tunnelling
modelling in geotechnical engineering: good practice. CIRIA, International)
London. ● Szechy, K. (1970). The art of tunnelling. Akademiai Kiado,
● H
 eyman, J. (1982). The masonry arch. Ellis Horwood, Budapest.
Chichester. ● W
 an, M. S. P., Standing, J. R., Potts, D. M., and Burland, J. B.
● H
 eyman, J. (1995). The stone skeleton. Cambridge University (2017). Measured short-term ground surface response to EPBM
Press. tunnelling in London Clay. Geotechnique 67, No 5, 420-445.

30 | February 2022
TUNNELLING IMPACTS | TECHNICAL

A1 σv A2 σv

Y
Y Far left, figure A1:
External loading on the
t HH
masonry sewer
re
X σH
rc Left, figure A2:
M(θ) RX(θ) σH Consideration of ¼ of the
θ masonry sewer
RY(θ) AA(θ)
re
rc
X

APPENDIX A: dmin = 2 HH
THRUST LINE ANALYSIS OF A CIRCULAR 3 σm
MASONRY SEWER which is based on the compressive stress distribution
Background shown on Figure A.3
The thrust line analysis aims to confirm if the line where
of thrust can be developed within an arch ring and 1
equilibrate the given external loading (see Figure A.1) 3 h = dmin
without exceeding the masonry compressive strength. If
this is the case, the arch ring will not collapse under this This defines the locations of the ULS intrados and
loading in accordance with the lower bound theorem of extrados envelopes around the arch.
limit analysis. The following calculation is mainly based Within the bounds of the ULS envelopes, a further
on the methodology documented in CIRIA C671 (2009). check is undertaken to confirm if the thrust line can be
developed within the ‘middle-third’ of the arch thickness
Assumptions (i.e. dmin = t/3) so that there will be no tension within
The self-weight of the brickwork is ignored for the arch.
simplicity. Also, a quarter of the masonry sewer Bending moment at a given section located by the angle
is considered in the thrust line analysis because of (θ) is given by:

{ [ 2t – d [{
symmetry (see Figure A.2). The tensile strength of the
masonry is considered to be negligible for assessment M(θ) = HH × min + (1 – cosθ) × rc

[ [
purposes. r
+ – σv × rc – e × re × (sinθ) 2
2
Input parameters
re External radius of the sewer { [ r + r 2× cosθ
+ –σ ×H
e e
[
– rc × cosθ × re
rc Radius along centerline of the sewer
t Sewer thickness × (1 – cosθ) {
σm Masonry compressive strength
σH External horizontal pressure at sewer axis level Axial force at a given section located by the angle (θ) is
σV External vertical pressure at sewer axis level given by:
KT Ratio of external horizontal pressure to external AA (θ) = RX (θ) × cosθ + RY (θ) × sinθ
vertical pressure (σH/σV)
Eccentricity of the thrust line (i.e. offset from the
Calculations centerline of the arch) at a given section located by the
Thrust at crown is: angle (θ) is given by:
HH = σH × re M(θ)
ecc (θ) =
AA(θ)
Horizontal and vertical force components at a given
section located by the angle (θ) are: Worked example
RX(θ) = HH – σH × (1 - cosθ) × re Thrust line analysis of a 2m internal diameter masonry
RY(θ) = σV × re × sinθ sewer with an axis depth of 8m:
Step 1 Calculation of input parameters
The minimum depth from the intrados/extrados of the re External radius of the sewer = 1.6m
sewer at which the thrust line can be located (dmin) rc Radius along centerline of the masonry arch = 1.3m
without exceeding the masonry compressive strength is: t Sewer thickness = 0.6m

February 2022 | 31
TECHNICAL | TUNNELLING IMPACTS

2.0 2.0

1.5 1.5

1.0 1.0

0.5 0.5

0.0 0.0

-0.5 -0.5

-1.0 -1.0

-1.5 -1.5

-2.0 -2.0
-2.0 -1.5 -1.0 -0.5 0.0 0.5 1.0 1.5 2.0 -2.0 -1.5 -1.0 -0.5 0.0 0.5 1.0 1.5 2.0
Intrados Intrados ULS Extrados Extrados ULS Intrados Intrados 1/3 Extrados Extrados 1/3

Right: Step 2 (all units in m) Step 3 (all units in m)


Calculation results from 2.0 2.0
the thrust line analysis
1.5 1.5

1.0 1.0

0.5 0.5

0.0 0.0

-0.5 -0.5

-1.0 -1.0

-1.5 -1.5

-2.0 -2.0
-2.0 -1.5 -1.0 -0.5 0.0 0.5 1.0 1.5 2.0 -2.0 -1.5 -1.0 -0.5 0.0 0.5 1.0 1.5 2.0
Intrados Intrados 1/3 Extrados Extrados 1/3 Thrust line Intrados Intrados ULS Extrados Extrados ULS Thrust line

Step 4 (all units in m) Step 5 (all units in m)

HH KT Ratio of external horizontal pressure to external


A3
⅓h vertical pressure = 0.7
σV External vertical pressure at axis level =
20kN/m3 × 8m × 1.4 = 224kN/m2 (ULS, load factor
of 1.4 for overburden with soil unit weight of
20kN/m3)
σH External horizontal pressure at axis level =
KT σV = 156.8kN/m2 (ULS)
σm Masonry compressive strength = 2.5MPa (ULS)
Step 2 Calculation of ULS envelopes
h Step 3 Calculation of ‘middle-third’ envelopes
Step 4 Calculation of thrust line based on dmin = t/3
Step 5 Checking if the thrust line is compatible with
the masonry compressive strength
Step 6 Conclusions
The analysis indicates that the thrust line:
i Remains within the ‘middle-third’ of the
masonry arch thickness and no tension will be
developed within the arch.
ii Remains within the ULS envelopes at all times.
iii Crosses the middle of the arch at least twice.

σm
Therefore, the arch ring will not collapse under this
Above, figure A3: loading case in accordance with the lower bound
Stress distribution (after Heyman (1982)) theorem of limit analysis.

32 | February 2022

You might also like