Professional Documents
Culture Documents
Concrete For Lower Kihansi Dam
Concrete For Lower Kihansi Dam
Email: gerald.maregesi@aesl.co.tz
Concrete grade 25/25 [designated Mix 2 The dam was divided into 15 blocks in the
C25/25] was used in all intake structures, form of transversal joints. The specified
the downstream side of the overflow depth of one lift was 2.5 metres. The lift
section of the dam and at spillways. thickness of 2.5 metres was selected to
Concrete grade 25/64 [designated Mix 2 reduce the number of construction joints
C25/64] was used in locations where the which are likely to be a source of structural
concrete was in direct contact with weakness and seepage through the dam as
rock/soil or in unreinforced locations. the planes of weakness are likely to be
Concrete grade 30/64 [designated Mix 4] created between two successive concrete
was a massive dam concrete which was lifts.
used in the outer part of the dam [surface].
Concrete grade 25/90 [designated Mix 5] 2.0 AGGREGATES
was massive dam concrete which was used
in the inner part of the dam [core]. The The project specifications favoured the use
project specification called for Mix 2 and of natural aggregates for concrete
Mix 4 to be impermeable. production. They were several nearby
sources of natural sand which were
Advanced Engineering Solutions Journal, Vol 1/2021 2
Mineralogical analysis
Quartz 20-80%
Feldspar 15-55
Biotite 25-60
Muscovite Trace to 8%
The project specifications called for a low After blending OPC and GGBS, the
heat cement with the heat of hydration of characteristics of the resultant cement
less than 290kJ/g at seven days as blend like setting time, bleeding, the heat
measured using the heat of hydration of of hydration, fineness and compressive
hydraulic cement [heat of solution method] strength were modified. The summary of
as per ASTM C186. This requirement of the test results is shown in Table 4, from
limiting the heat of the cement hydration which it can be seen that the initial and
was specified to minimise the possibility of final setting time was extended. Due to
having cracks caused by thermal stress extensions of setting time, the bleeding
within the concrete. increased [Figure 2]. The 2,7 and 28 days
cube compressive strength were lower
Cement brands available locally were than that of OPC, but the cube compressive
tested, but none of them was found strength of blended cement was higher
suitable for dam construction. The most than that of OPC at 90 and 180 days
feasible solution was to use imported [Figure 3] while the heat of hydration was
Ground Granulated Blast Furnace Slag lowered as shown by test results in Table
[GGBS] which was site blended in the ratio 3.
of 1:1 with Portland cement CEM II 32.5R
sourced locally.
Table 3: The total heat under the adiabatic condition for OPC and a blend of OPC/GGBS
Age in days OPC OPC/GGBS (1:1)
1 200 120
3 240 210
5 250 240
7 260 245
Advanced Engineering Solutions Journal, Vol 1/2021 2
5.0 HEAT GENERATION AND cement. Due to this, it was found necessary
THERMAL TREATMENT to arrange a method of lowering the
MEASURES temperature of fresh concrete before
placing. The study carried out on-site
Crack resistance for the massive dam indicated that precooling the fresh concrete
concrete was considered as the most with chilled water-cooled using a
critical requirement. Therefore, the heat of containerised cooling plant using ammonia
hydration of concrete was considered as a as a cooling agent to 5 °C and sprinkling
crucial concrete design issue. The the aggregate with water would suffice
maximum cement content and maximum without additional measures of post-
heat of hydration were specified. The cooling. The average measured
maximum temperature of the fresh temperature of fresh concrete was 20oC.
concrete of 27oC and the maximum curing
temperature of 65oC was specified to limit The most critical thermal condition
the adverse effects of thermal stresses considered were the maximum curing
within the massive dam concrete. temperature attained and maximum
internal temperature differential which the
In most cases, the concrete class C25 and specified maximum was temperature 20 oC.
C30 pose no problem during mix design
and production. However, with poor The maximum temperature attained was
quality aggregate available within the measured using thermo-sensors positioned
project vicinity, led to concrete to be in the middle of the block. The maximum
proportioned with high cement content to internal differential was determined as the
compensate for the poor aggregate quality difference between the maximum curing
with an adverse effect of increasing the temperature and temperature at the
effect of the heat of hydration of the surface of the block measured about one
Advanced Engineering Solutions Journal, Vol 1/2021 2
centimetre from the concrete surface. The 5 MPa while that of the massive dam
maximum internal and surface temperature concrete was set to 3 MPa.
measurements are shown in Figure 5. 2) Blended OPC and GGBS in the ratio of
1:1 were used for concrete production
to lower the heat of hydration of
cement.
3) The water-reducing agent was used to
reduce the water demand and cement
content to achieve the desired targeted
compressive cube strength and
workability.
4) The coarse aggregates were sprinkled
with cold water so that some heat could
be lost through evaporation.
5) Managing the construction procedure
by fixing the formwork removal time to
5-7 days or more depending on the
curing temperature of the concrete
6) The temperature was monitored using
thermocouples in the inner part and the
Figure 5: The maximum internal, surface outer part so that the temperature
temperature and computed internal gradient within the concrete mass
differential temperature for mix 5 could be determined.
7) Testing the massive concrete at 90
days instead of 28 days
8) The cement silo was painted with white
reflective colour.
discharged into dump trucks and water sprinkler, allowing the concrete to
transported to a hopper feeding the 42 gain strength before being subjected to
metres crane with conveyor belt mounted tensile stress caused by shrinkage and
on a crane which was used to transport the volume changes.
fresh concrete. The concrete was The concrete lift was left for a minimum of
transported and placed in a plastic state four days before concreting the next lift.
with slump ranging from 20-50 mm for This ensured that heat of hydration of the
massive dam concrete. For structural previous layer had been dissipated through
concrete, the slump ranged from 50-90 the upper layer. The concreting time
mm. The concrete vibration was carried out between two adjacent blocks was set a
immediately after placing to ensure that minimum of ten days.
the concrete compaction was completed
before the concrete starts to stiffen. The weather condition at the dam site was
favourable, allowing the placement of
Curing of concrete commenced before concrete throughout the year. The weather
complete dry out to prevent surface cracks data, as measured from the site weather
caused by early drying of concrete. This station, is shown in Table 6.
operation was done continuously using
The removal of formwork depended on the The following amendments were done to
curing temperature of the concrete. the Technical Specifications to suit site
Generally, the formwork was left in place conditions:
for 5-7 days to reduce the possibility of • The structural concrete strength
having surface cracks caused by thermal requirements were relaxed by 5 MPa.
shock. • The age of testing for massive dam
concrete was increased from 28 to 90
9.0 CONCRETE TESTING days because of the poor quality of the
aggregates encountered within the
Several tests were specified in the contract project vicinity.
documents. The testing was carried out • The maximum aggregate size of
using the relevant BS, AASHTO or ASTM massive dam concrete Mix 5 was
reduced from 120 mm to 90 mm to
Advanced Engineering Solutions Journal, Vol 1/2021 2