Professional Documents
Culture Documents
A PROJECT REPORT
Submitted by
J.KARTHIK
421115103307
of
BACHELOR OF ENGINEERING
In
CIVIL ENGINEERING
OCT/NOV 2018
BONAFIDE CERTIFICATE
HALL” is the bonafide work of J. KARTHIK (421115103307) who carried out the
SIGNATURE SIGNATURE
Submitted for Project Work and Viva Voce Examination held on .....................
I thank all the staff members in our department for their cooperation they have
rendered to me and the sustained interests shown at every stage of my endeavour in
making project work a success.
Finally, I express heartfelt gratitude to my parents for their sacrifice and support
throughout the period of my study.
ABSTRACT
Now a days there are many functions are being organized in party halls. It is a multi
purpose hall in which all traditional functions and also corporate events can be hosted.
In this we have function area, place for kids to play and good dining area. So we have
planned and designed the construction of the main building of a party hall of approved
standards to fulfill the needs of the current situation.In our project, we have aimed to
satisfy the basic requirements of a party hall by allocating the sufficient space the
entire structure was developed. The structure was then analysed and designed in stadd
pro. The mathematical model is done using staad.pro v8i and the analysis results are
used for design .The design is done in compliance with IS 456-2000 using M20
concrete and Fe 415 grade steel.
This party hall is located at KARAYANCHAVADI and the total area is 7874.78sq
LIST OF SYMBOLS
The following symbols carrying the meaning noted against then which are used
in the project work
A : Area
P : Axial Load
αx & αy : Coefficients
: Minimum Reinforcement
Ast(min)
Mu : Moment
Vu : Ultimate shear
τv : Nominal Shear stress
ABSTRACT
OBJECTIVE
LIST OF SYMBOLS
LIST OF ABBREVATIONS
1. INTRODUCTION
1. GENERAL
2. STUDY AREA
2. REVIEW OF LITERATURE
3. METHODOLOGY
1. GENERAL
1. PLANNING
2. CADD DRAWINGS
4. SRUCTURAL ANALYSIS
1. CALCULATION OF LOADS
3. DESIGN OF BEAM
4. DESIGN OF COLUMN
5. DESIGN OF STAIRCASE
6. DESIGN OF LINTEL
7. DESIGN OF FOOTING
5. CONCLUSION
6. REFERENCE
CHAPTER – 1
INTRODUCTION
1.1GENERAL
Party hall is a place where functions can be organized. Now a days there are many
functions are being organized in party halls. It is a multi purpose hall in which all
traditional functions and also corporate events can be hosted. In this we have function
area, place for kids to play and good dining area.So we have planned and designed the
construction of the main building of a party hall of approved standards to fulfill the
needs of the current situation.
In our project, we have aimed to satisfy the basic requirements of a party hall by
allocating the sufficient space the entire structure was developed . The resultand
building should be aesthetically pleasing and reflect the care taken to produce a
quality facility capable of meeting the evolving needs of the party hall. Good
acoustic separation is essential and is achieved through careful planning and
specification of construction materials.
life of the average or low strata of people who happen to perform such personal
functions. An average man in the rising price conditions is even otherwise very
much troubled. These extraordinary events break the very backbones of normal
families whenever these occasions are celebrated. Party hall is the place where
all traditional and other parties can be organized. It is a small scale hall when
compared to marriage hall. In party halls generally 200 to 300 members can be
accommodated.
CHAPTER – 3
METHODOLOGY
3.1. GENERAL
CALCULATION OF LOADS
DESIGN OF SLAB
STRUCTURAL ANALYSIS STADD PRO V8i
DESIGN OF BEAM
DESIGN OF STRUCTURAL ELEMENTS
DESIGN OF COLUMN
`
REINFORCEMENT DETAILING AUTO CAD
DESIGN OF FOOTING
PROJECT REPORT
The changeover from traditional method to computer aided design has come to
stay as an important, fast and dependable method of designing. The building
drawing is prepared by using software like AUTOCAD and completely
analysed by “STADD PRO V81”. Powerful computer programs STADD are
available in market for analysis. STADD may be utilized for analysis
and designing practically all kind of structures bridges, towers,
transportation, industries and utility services.
CHAPTER 4
RESULTS AND DISCUSSION
1. PLANNING
GROUND FLOOR
When we design a party hall the main thing
to be noticed is parking area
because parking is the main problem in many areas. So in our design
ground floor is fully designed for parking. The areaof
parking is 731sqm.
FIRST FLOOR
First floor consist of party hall in which 240 members can be accomadated
and a separate dressing room and store room. The area of party hall is
371.94sqm.
SECOND FLOOR
The second floor consists of a dining area and kids play area. The area
of dining place is 371.94sqm.
2. CADD DRAWINGS
4.3 STADD ANALYSIS REPORT
4.4 STRUCTURAL DESIGN
This chapter deals with the design of structural elements (i.e. slab, beam,
column, staircase, lintel and footing)
1. Calculation of loads
For Truss and slab, load calculations are based on IS 875 part II.
This load calculations includes dead load, live load and wind load. Calculation
of loads for designing slab includes dead load and live load.
2. SLAB
A slab is thin flexural member used in floors and roofs of the structure to
support imposed loads.
Slabs are primary member of a structure which support the imposed load
directly on them and transfer the and safely to the supporting elements such
as beam, columns etc therefore ,a slab should be safe and stable against the
applied loads and should have the required strength and stiffness to satisfy the
serviceability requirements.
The two main factors to be considered while designing a solid slab are
In this project the design of slabs are carried out in limit state method. The
grade of concrete and steel used in the project are M20 and Fe415 respectively.
A slab is called two way slab, when the load on it is distributed in both
the directions to all its four supports. In two way slabs, tension reinforcement
are provided in both the direction.
DESIGN OF TWO
* Width of support =
*0.3m
Live load =5kN/m2
* Floor finish =1kN/m2
* fck =20N/m2
* fy =415N/m2
CALCULATION
* assume overall depth=200mm
ly=3.18;lx=3.18
therefore ly/lx = 1
LOAD CALCULATION
* Self wt of slab=5kN/m2
* Floor finish
=1kN/m2
* Live load
=5kN/m2
* Total load
*Ultimate
=11kN/mload
2 = 1.5*total load
= 0.062*16.5*3.182
Mux & Muy =10.34KNm
Vu =WuL/2
= 26.24KN
10.34*10^6
max/d] bd2 =0.36 *0.48 [1-0.42*0.48] bd2 for Fe415( Xumax/d =0.48)
Hence safe
MAIN REINFORCEMENT
Ast=162 mm2
Provide 10mm diameter bars
Ast p=78.54mm2
Spacing = 200mm c/c in both the direction Distributors
τv =Vu/bd= 26.4*103/1000*180=0.146N/mm2
p=100Ast/bd=100*162/1000*180=0.09
τc=0.29N/mm2, τcmax=3.1N/mm2
τcmax>τc > τv
span/d =BV*Kt*Kc*Kv
Kt=1.6
Kc=1
Kv=1
d=93.75mm < 180mm
#10-200mm c/c
200
mm
#10-200mm c/c
Span = 3.2m
4.4.3 BEAM
the beam's axis. Its mode of deflection is primarily by bending . The loads
applied to the beam result in resultant forces at the beam's support points.
The total effect of all the forces acting on the beam is to product shear
forces and bending moments within the beam, that in turn induce internal
material.
In this project the design of beams are carried out in limit state method. The
grade of concrete and steel used in the project are M20 and Fe415
respectively.
Step 3: Calculation for area of reinforcement in mid span and decide number
and diameter of bars to be provided.
DESIGN OF BEAM
Length = 2770mm
Breadth = 300mm
Depth = 450mm
DESIGN:
CHARACTERISTIC STRENGTH:
fck = 20
N/mm2 fy = 415
N/mm2
EFFECTIVE SPAN:
=0.3x0.45x25
LOAD CALCULATION:
Total load=self weight of beam + live load + finishes + dead load(SW of
slab)
self wgt of
slab=0.2x3x25=15KN/m
= 3.375+15+0.75+15
total load, W
= F.O.S x W
= 1.5 x 34.125
Wu = 51.19 KN/m
MOMENT CALCULATION:
Mu = 51.19 x 32 / 8
Mu = 57.59 KNm
Vu =Wul/2=76.79KN
b =
300mm
d =
450mm
l = 6000mm
span / depth = l / d
=
3000
/ 500
=6>
Hence it is ok.
2.5
Section type,
Mu < Mu.lim.
DEPTH CHECK:
Ast = 396mm2
No. Of bars =
Therefore,
Ast / astproviding
= 1.96 (3 3nos.)
nos. Of 16mm dia. Bars Ast pro. = 603 mm2
τv =Vu/bd= 0.602N/mm2
P=100Ast/bd=0.473N/mm2
τc =0.291N/mm2
τc max=3.1N/mm2
vus = vu - τ c.b.d
= 76.79x103 - (0.291
x 300 x 425)
vus = 39.69 KN sv = (0.87.fy.asv.d) / vus
sv = 388.62mm
160
mm
300mm
450mm
3 nos of 16mm dia
4.4.4 COLUMN
The term column applies especially to a large round support (the shaft of the
column) with a capital and a base or pedestal which is made of stone, or
appearing to be so.
A small wooden or metal support is typically called a post, and supports with a
rectangular or other non-round section are usually called piers. For the purpose
of wind or earthquake engineering, columns may be designed to resist lateral
forces.
Columns are frequently used to support bemas or arches on which the upper
parts of walls or ceilings rest. In architecture, "column" refers to such a
structural element that also has certain proportional and decorative features.
All compression member must be designed for minimum eccentricity. when the
load does not exceed 0.005 times the lateral dimension, the load is assumed to
be axial.
cover = 40mm
bending) Pu = 1862 KN
Mx = 64 KNm
My = 51 KNm
interaction
ratio = 0.28
taking dI /D =
0.1
EQUIVALENT MOMENT
Mu = 1.15√(Muy2 + Muz2)
Mu = 94 KNm
p = 0.05 x 25
P = 1.25
AREA OF STEEL
Ast = 2500mm2
ast=491mm2
provide 6 no of bars
Mux1 = 0.0376 x 25 x
400 x 5002
Mux1 = 95 KNm
Puz = (0.45.fck.Ac) +
(0.75.Ast.fy)
= (0.45 x 25 x 400 x
500) + (0.75 x 2940 x
415)
= 3165KN
0.88 < 1
hence safe.
LATERAL TIES
= 0.25 x 25
= 6.25mm
pitch:
(iii)300mm
500
4.4.5 STAIRCASE
“A Stair is a series of steps with or without landings or platforms, which is
installed between two or more floors of a building to bridge a large vertical
distance”.
In this project the design of stair case are carried out in limit state method. The
grade of concrete and steel used in the project are M20 and Fe415 respectively.
DESIGN OF STAIRCASE
4m Size= 3mx4.5m
LL= 3.5KN/m
DIMENSIONS
2m
No of risers= 2000/150=
13.33= 14
No of treads= 14-1= 13
D= 210+20= 230mm
LOAD CALCULATION
W’=0.22*25=5.5KN/m
W=w’√
((R2+T2)/T)=7.38KN/m
DL of one step=
0.25*0.15*0.3*25=0.5
625KN/m
=0.5625/0.3=1.875KN/m
(ii)LL=3.5KN/m
(iv)Finis
hes=0.75KN/m TL=
13.51KN/m
Factored
load=20.27KN/m
Bending
moment
Mu=Wul2/8=33.19KN/m
d=98.1mm>dpro
Mu=0.87*fy*Astd(1-Astfy/bdfck)
=454mm2
Provide 10mm dia bars
ast=78.54mm2
Sv=173mm
spacing (ii)distributors:
Ast=0.12%bd=276mm2
ast=50.29mm2
Sv=182mm
230
A lintel or lintol is a structural horizontal block that spans the space or opening
between two vertical supports. It can be a decorative architectural element, or a
combined ornamented structural item. It is often found
over portals, doors, windows and fireplaces. In the case of windows, the bottom
span is instead referred to as a sill, but, unlike a lintel, does not serve to bear a
load to ensure the integrity of the wall.
Modern day lintels are made using prestressed concrete and are also referred
to as beams in beam and block slabs or ribs in rib and block slabs. These
prestressed concrete lintels and blocks are components that are packed together
and propped to form a suspended floor concrete slab.
In this project the design of lintel are carried out in limit state method. The
grade of concrete and steel used in the project are M20 and Fe415 respectively.
DESIGN OF LINTEL
DIMENSIONS:
thickness =150mm
depth =150-10/2-15
=130mm
LOAD CALCULATION
Wu=1.5*3.03 = 4.55 KN
MOMENT CALCULATION
M=0.125*Wu*L2
Mu=1.28KNm
DEPTH
CHECK
d=42<130 mm
Hence safe
AREA OF STEEL AND REINFORCEMENT
Mu=0.87*fy*Ast*d[1- (Ast*fy/b*d*fck)]
Ast=31 mm2
=(0.85*300*150)/415
=79mm2
=4.55*1.5/2
V=5.11KN
Tu=Vu/bd
Hence ok in shear
1.Transmitting the applied load effects (reaction in the form of vertical and
horizontal forces and moments) to the soil below, without exceeding the safe
bearing capacity.
2.Ensuring that the settlement of the structure is within tolerable limits and as
nearly uniform as possible.
In this project the design of footings are carried out in limit state method. The
grade of concrete and steel used in the project are M20 and Fe415 respectively.
PU = 1862KN.
Column no:60
Size of column=400mm *500mm
Fck = 25 N/mm2
FY = 415 N/mm2
Bearing
capacity of soil,
STEP qu
1: = 250KN/m
SIZE OF FOOTING
2
*Total load = load of column + self weight of footing (10% of the column load)
= 1862 + 150
= 2012 KN
A=LB,
L=1.2B
B=2.6m, L=3.12=3.2m
STEP 2: PROPORTIONING
= 223 KN/m2
Vu=quxB(0.5(L-a)-d)= 877.5-650d
V actual=0.33*2600*1100-d
VU = 136.675KN.
Ld=fs *dia/4Tbd
=0.87*415*16/4*1.6*1.2
=47(16)=750mm
Hence ok
Pu=1862 KN
A1=A2 thereforeA1/A2 =1
400
320
540
610
#16-140 #16-140
200
2600
#16-140
#16-140
As we entering into a new era of sustainable development, the need for projects
like this and their construction and implementation can change the whole
scenario of the human society. The planning of the project was done only
after having case studies and views of different such projects and also reference
and interviews with well known civil engineers, architects and professors.
By doing such a project, we have learnt to share our ideas and incorporate
them in the project, which we hope has given the means for a good design. We
worked as a team. Not dividing the work among each, but by doing each part
of the project together itself. On the lighter side, we have even learnt to
sacrifice our personal intersects and put forth more work hours, making small
sacrifice on each of our parts.
With the upcoming of many other challenging projects. We hope this hotel
stands out and becomes a landmark for the beautiful city of Chennai.
REFERENCE;